Substructure: Basement Wall Basement Excavation & Wall Construction
Substructure: Basement Wall Basement Excavation & Wall Construction
Substructure: Basement Wall Basement Excavation & Wall Construction
4.5 4.5.1 4.5.2 The structure of each section of wall will vary in accordance with
the loads acting on it and which type of plant can access that
Basement Excavation & Wall Basement Wall location and install the wall within the site constraints.
Substructure Construction A stiff, embedded retaining wall will form the basement box,
Prior to construction the effect on the foundations of the
adjacent buildings will be calculated on a case by case basis to
resisting lateral pressures from groundwater, soil and surcharges determine what, if any mitigation measures are required. These
The existing basement condition varies across the site. Two
as well as vertical loads from the basement floor slabs and may include:
At this stage in design, an outline foundation design has been separate single storey basements sit beneath the Odeon, one
structure above. It will be designed to resist ultimate limit state
produced based on the Ground Engineering site investigation each under the north and south elevations. It is currently
forces and to remain within deflection limits determined on •• Reduced rate of construction and completion of shorter
factual report dated April 2007. This investigation characterised understood that the Post Office building and Whitlock House segments of wall during each construction phase
the basis of maximum acceptable ground movements (refer to
the ground conditions in detail, though it is anticipated that have no existing basements. Representative assumptions with
regard to surcharge loads and proposed retaining wall clearances
section 5.6 for further details). •• Injection grouting beneath adjacent foundations (with prior
further site investigation will be undertaken to verify details of agreement through the party wall process)
the existing foundations to the former Post Office building and have been applied in the design to date, which will be verified The proposed retaining wall solution will be robust and has have
the buildings along Earls Court Rd. This information will be used by site investigation in the next stage of design. been used successfully on similar projects in RBKC and London. •• Underpinning of adjacent foundations (with prior agreement
to refine the detailed design. To ensure the suitability and buildability of the wall, the design through the party wall process)
It is proposed that a new four storey basement covers almost
has been developed based on detailed input from two major
In addition, detailed discussions in relation to construction of the entirety of the site, with one and two storey basements
contractors with specialist experience of constructing deep
•• A stiff piling mat will be utilised to provide a stable working
the proposed basement wall were undertaken with specialist under blocks 3/5 and the northern part of block 2 respectively. platform for the plant ensuring accurate installation.
basements on confined sites within London. Based on this input
substructure contractors experienced in this type of project. The The maximum depth of excavation will be approximately 19m
a number of design refinements and construction processes •• Where required by the retaining wall type, screens will be
feedback received was used to establish a suitable wall zone depending on the exact location and the final foundation erected adjacent to the plant to protect adjacent buildings
have been identified:
accounting for construction tolerances, clearances to adjacent solution. It is proposed that the new basement wall will run and members of the public from ‘splashing’ of liquid
structures and feasible wall types based site spatial constraints. behind the Odeon retained facade, with the existing basement materials.
This information was preliminary and exact values will vary in that location being modified to incorporate the foundations
dependent of the final design details and contractor selected, for the new structure above. It is noted that the scheme calls for two new basement lifts
therefore full details will be confirmed at later stages of design. to be formed adjacent to the retained facade. A number of
Prior to excavation of the site, a new, stiff embedded retaining construction options have been investigated. It is proposed to
wall will be installed from ground level. Augmented with utilise sheet piling to form shafts, which will be lined with RC
temporary propping this will facilitate excavation of the walls to provide the permanent structure. Low-vibration, limited
basement without detriment to the adjacent structures and in clearance rigs will be utilised (eg Dawson silent piling press).
the permanent condition will form the basement wall and be Further details are provided in section 4.6.3.
propped by the basement floor slabs.
Extract from preliminary basement plan indicating extent of basement following line of
retained facade for the accommodation of lift shaft access
Image illustrating the basement volume with internal structure omitted for clarity
3256 - The Kensington 19
4.5.3
Foundations and basement
structure
The basement depth, ground conditions and irregular column
layout make The Kensington well suited to raft foundations
and this is the solution proposed beneath all blocks. Piled
foundations are also a viable option and may be suitable
for some parts of the development depending on the final
construction sequence selected (see below).
4.6
Construction STAGE 1: DEMOLITION OF EXISTING BUILDINGS
STAGE STAGE 5: RAFT C
INCLUDING BASEMENTS EXCEPT ODEAN STAGE1:1:DEMOLITION
DEMOLITIONOF
OFEXISTING
EXISTINGBUILDINGS
BUILDINGS WALLS AND COL
INCLUDING
INCLUDING BASEMENTS
BASEMENTS EXCEPT
EXCEPT ODEAN
ODEAN
FACADE AND LOCAL BASEMENT BENEATH
STAGE 1: DEMOLITION OFBASEMENT
EXISTING BUILDINGS REMOVAL AS CO
FACADE
STAGE
FACADE AND
AND LOCAL
1:BASEMENTS
DEMOLITION BENEATH
OF EXISTING
LOCALEXCEPT
BASEMENT BUILDINGS
BENEATH
WHICH ARE RETAINED USING TEMPORARY
INCLUDING ODEAN UPWARDS AS FL
WHICH ARE
INCLUDING RETAINED
BASEMENTS USING TEMPORARY
EXCEPT ODEAN
PROPPING WHICH
FACADE ANDARE RETAINED
LOCAL USINGBENEATH
BASEMENT TEMPORARY WALLS.
PROPPING
4.6.1 FACADE
PROPPING
WHICH
STAGE 1: DEMOLITION OF EXISTING BUILDINGS
AND LOCAL
ARE RETAINED BASEMENT
USING BENEATH
TEMPORARY
WHICH ARE RETAINED USING TEMPORARY
PROPPING
STAGE 5: RAFT C
INCLUDING BASEMENTS EXCEPT ODEAN WALLS AND COL
PROPPING
Demolition & Temporary Works FACADE AND LOCAL BASEMENT BENEATH
WHICH ARE RETAINED USING TEMPORARY
REMOVAL AS CO
UPWARDS AS FL
PROPPINGSTAGE 1: DEMOLITION OF EXISTING BUILDINGS STAGE 5: RAFT CONSTR
WALLS.
All buildings and substructure on site will be demolished, except INCLUDING BASEMENTS EXCEPT ODEAN WALLS AND COLUMN C
Stage 1 - Removal of Existing Basement Structure and advanced Stage 5 - Construct raft foundation and begin core walls and columns
for the retained facade and the basement and footings directly FACADE AND LOCAL BASEMENT BENEATH
works to form the lift shafts adjacent to the retained facade REMOVAL AS CONSTRU
shown overleaf WHICH ARESTAGE
RETAINED USING TEMPORARY
1: DEMOLITION OF EXISTING BUILDINGS UPWARDS
STAGE 5: RAFTASCONSTRUCT
FLOORS N
beneath. Based on the date of construction it is assumed that PROPPING INCLUDING BASEMENTS EXCEPT ODEAN WALLS AND COLUMN CONS
WALLS.
the Odeon sits on shallow foundations which would be removed FACADE AND LOCAL BASEMENT BENEATH REMOVAL AS CONSTRUCTIO
as part of the demolition and excavation. Similar construction is WHICH ARE RETAINED USING TEMPORARY UPWARDSSTAGE 6: SUBST
AS FLOORS NOW
assumed for the former Post Office building. PROPPING WALLS. COMPLETE. ALL
STRUCTURE CO
Whitlock is a newer construction that occupies the site of STAGE 2: MATERIAL ONSITE PLACED TO FORM2: MATERIAL ONSITE PLACED TO FORM
STAGE
previous building which incorporated a basement. No details PILING MAT FOR SECANT PILE AND D-WALL
STAGEMAT
PILING 2: MATERIAL ONSITE
FOR SECANT PILEPLACED TO FORM
AND D-WALL STAGE 6: SUBST
CONSTRUCTION STAGE 2: MATERIAL
PILING MAT FORONSITE
CONSTRUCTION SECANTPLACED TO FORM
PILE AND D-WALL COMPLETE. ALL
of the substructure are currently available. In discussions with STAGE
PILING MAT2:FOR
MATERIAL
CONSTRUCTION SECANTONSITE PLACED
PILE AND D-WALLTO FORM STRUCTURE COM
the current building manager it was noted that no basement STAGE 2: MATERIAL ONSITE PLACED TOPILING
FORM MAT FOR SECANT PILE AND D-WALL
CONSTRUCTION
existed for the building, this seems to be borne out by the PILING MAT FOR SECANT PILE AND D-WALL
CONSTRUCTION
CONSTRUCTION STAGE 6: SUBSTRUCTU
details indicated on the survey drawings. On this basis and COMPLETE. ALL LEVELS
having looked at adjacent buildings, it would seem likely that STRUCTURE COMPLETE
STAGE 2: MATERIAL ONSITE PLACED TO FORM STAGE 6: SUBSTRUCTURE C
made ground would exist under and around Whitlock house
PILING MAT FOR SECANT PILE AND D-WALL COMPLETE. ALL LEVELS AN
and this would in turn suggest that piled foundations would CONSTRUCTION STRUCTURE COMPLETED.
be the likely foundation system. This will need to be verified at STAGE 2: MATERIAL ONSITE PLACED TO FORM
Stage 2 - Secant and diaphragm wall construction PILING MAT FOR SECANT PILE AND D-WALL Stage 6 - Completion of substructure construction
a later stage. As the building is tightly hemmed in by existing (facade retention structure not shown for clarity)
CONSTRUCTION
buildings to the north and south it would seem likely that piled
foundations along these lines would have to be inset away
STAGE 7: SUPER
from the boundary location, and this would in turn suggest that EXCEPTION OF B
ground beams or a thick raft would be required to pick up the STAGE 7: SUPER
SITE ACCESS
EXCEPTION OF B
columns located on the N and S perimeter of the building. Since STAGE 3: EXCAVATION PROCEEEDS STAGE 3: EXCAVATION PROCEEEDS
SITE ACCESS
the building proposed to replace Block 3 has deep single storey DOWNWARDS WITH TEMPORARY PROPS DOWNWARDS
STAGE 3: EXCAVATION PROCEEEDS STAGESTAGE WITH TEMPORARY
3: EXCAVATION PROPS
PROCEEEDS
3: EXCAVATION PROCEEEDS
INSTALLED ABOVE FUTURE SLAB INSTALLED
LEVELS
STAGE ABOVE FUTURE
3: EXCAVATION
DOWNWARDS SLAB
PROCEEEDSLEVELS
basement (approx 4m) and raft foundation, it is likely that any DOWNWARDS WITH TEMPORARY PROPS DOWNWARDS WITHWITH TEMPORARY
TEMPORARY PROPSPROPS
piles in this location would need to broken down or extracted INSTALLED ABOVE FUTURE SLAB LEVELSDOWNWARDS
INSTALLED
INSTALLED ABOVE WITH
ABOVE TEMPORARY
FUTURE
FUTURE SLABSLABPROPS
LEVELS
LEVELS STAGE 7: SUPERSTRUC
to accommodate the new construction. This would need to be INSTALLED ABOVE FUTURE SLAB LEVELS EXCEPTION OF BLOCK 4
coordinated with installation of the new secant pile wall around SITE ACCESS
STAGE 7: SUPERSTRUCTUR
STAGE 3: EXCAVATION PROCEEEDS
the proposed basement and temporary propping of the adjacent EXCEPTION OF BLOCK 4 AS
DOWNWARDS WITH TEMPORARY PROPS
buildings and pavement vaults (if required) and underpinning. SITE ACCESS
INSTALLED ABOVE FUTURE SLAB LEVELS
STAGE 3: EXCAVATION PROCEEEDS
Temporary works to support the retained facade are covered in DOWNWARDS WITH TEMPORARY PROPS
the Block 1 superstructure section. INSTALLED ABOVE FUTURE SLAB LEVELS
Stage 3 - Begin excavation and install temporary props Stage 7 - Superstructure construction, except Block 4, to provide site
(shown indicatively) access
STAGE
STAGE 8:
8: BLOCK
BLOCK
4.6.2 SUPERSTRUCTU
SUPERSTRUCTU
THE KENSINGTON
THE KENSINGTONSCALE NTS
11/07/2014
PROJECT T
Stage 4 - Complete excavation and installation of piles Stage 8 - Completion of Block 4 superstructure fully constructed
DATE 11/07/2014 NTS 3256-S-SK-321
PROJECT
DATE
REV P1 DATE 11/07/2014 DESCRIPTION FOR INFORMATION BY CB CHECKED RH DRAWN CB CHECKED RH SCALE No.
PROJECT 3256
PROJECT
CAD FILENAME
DRAWING No. S-SK-321
DATE 11/07/2014 NTS
11/07/2014
SCALE
REV DATE DESCRIPTION FOR INFORMATION THE KENSINGTON
PROJECTCHECKED DATE 11/07/2014
DATE
TITLE SUBSTRUCTURE CONSTRUCTION SCALE NTS
SCALE
BY
3256 - The Kensington 21
4.6.3
Formation of lift shafts adjacent EXTERNALEXTERNAL
SYSTEM TO
BALLASTED
SYSTEM
CUTTING BACK
STRUCTURE
CUTTING
BALLASTED
RETENTION
BE INSTALLED
EXISTING
STRUCTURE
EXTERNAL
BACK SUPPORT
EXISTING
RETENTION
TO BE INSTALLED
PRIOR
SYSTEM
BALLASTED RETENTION
TO PRIOR
CUTTING
TO BETO
SUPPORT
STRUCTURE
INSTALLED PRIOR TO
BACK EXISTING SUPPORT
Stage 1 - Assumed
LONDON CLAY FORMATION
existing condition based on record
LONDON CLAY FORMATION
Stage 2 - Installation of external retention system and Stage 3 - New sheet piled shaft constructed using limited clearance, low
information and visual inspection on site construction of new support structure for facade comprising FIGURE 1.2:
FIGURE
vibration rigs with propping installed ; main diaphragm wall constructed
1.2: INDICATIVE
INDICATIVE FIGURE INTERNAL
INTERNAL1.2: INDICATIVE INTERNAL
RC walls and strip footings, with load jacked into new structure TEMPORARY
TEMPORARY
PROPPING and
PROPPING tied
TEMPORARY
REQUIRED into sheet
REQUIRED
PROPPING REQUIREDpiles;
RC lining wall constructed and propping removed
WITHIN SHEET
WITHINPILED
SHEET SHAFT
PILED
WITHIN
SHAFT
SHEET PILED SHAFT
to minimise movement and packed tight; once resupported DURING DURING
CONSTRUCTION
CONSTRUCTION
DURING CONSTRUCTION
existing transfer beams may be cut back
FIGURE 1.2: INDICATIVE INTERNAL
TEMPORARY PROPPING REQUIRED
FIGURE SHEET
WITHIN 1.2: INDICATIVE INTERNAL
PILED SHAFT
TEMPORARY
DURING FIGURE
PROPPING
CONSTRUCTION 1.2: INDICATIVE INTERNAL
REQUIRED
WITHIN SHEET PILED TEMPORARY
SHAFT PROPPING REQUIRED
DURING CONSTRUCTION SHEET PILED SHAFT
WITHIN
DURING CONSTRUCTION
NB: SACRIFICIAL
NB: SACRIFICIAL NB:OF
LINE OF TEMPORARY
LINE SACRIFICIAL
TEMPORARY
SHEET LINESHEET
OF TEMPORARY SHEET
PILES SHOWN
PILES
TOSHOWN
FACILITATE
TO FACILITATE
PILES
EASIERSHOWN
PROPPING
EASIER
TO FACILITATE
PROPPING EASIER PROPPING
ARRANGEMENTS
ARRANGEMENTS
DURING CONSTRUCTION
DURING
ARRANGEMENTS
CONSTRUCTION
DURING CONSTRUCTION
(THRUSTS(THRUSTS
BALANCEDBALANCED
AGAINST(THRUSTS
GROUND)
AGAINSTBALANCED
GROUND) AGAINST GROUND)
INDICATES
INDICATES
NEW RC WALL
NEW RC
TIES
INDICATES
WALL
INTOTIES
EXISTING
NEW
INTO
RCEXISTING
WALL TIES INTO EXISTING
WITH NEWWITH
CONCRETE
NEW CONCRETE
STRIP
WITH
FOOTING
STRIP
NEW CONCRETE
FOOTING
UNDER UNDER
STRIP FOOTING UNDER
BEARING BEARING
IN THE NATURAL
IN THE NATURAL
BEARING
GRAVEL STRATA
GRAVEL
IN THE NATURAL
STRATA GRAVEL STRATA
NB: SACRIFICIAL LINE OF TEMPORARY SHEET
PILES SHOWN TO FACILITATE EASIER PROPPING
NB:ARRANGEMENTS
SACRIFICIAL LINEDURING CONSTRUCTION
OF TEMPORARY SHEET
(THRUSTS
PILES SHOWN BALANCEDNB:AGAINST
TO FACILITATE EASIER GROUND)
SACRIFICIAL LINE OF TEMPORARY SHEET
PROPPING
INDICATES NEW RC WALL TIES INTO EXISTING
ARRANGEMENTS PILES SHOWN
DURING TO FACILITATE EASIER PROPPING
CONSTRUCTION
WITH NEW CONCRETE STRIP FOOTING UNDER
(THRUSTS BALANCED ARRANGEMENTS
AGAINST GROUND) DURING CONSTRUCTION
INDICATESINNEW
BEARING THE RC WALL TIES
NATURAL INTOSTRATA
GRAVEL EXISTING (THRUSTS BALANCED AGAINST GROUND)
WITH NEW CONCRETE INDICATES NEW RC
STRIP FOOTING WALL TIES INTO EXISTING
UNDER
WITH NEW
BEARING IN THE NATURAL CONCRETE
GRAVEL STRATA STRIP FOOTING UNDER
BEARING IN THE NATURAL GRAVEL STRATA Fig: Part plan showing sheet piled wall with typical temporary propping
arrangement to be removed sequentially following construction of RC walls
RED ZONES
REDINDICATE
ZONES INDICATE
APPROXIMATE
RED ZONES
APPROXIMATE
INDICATE APPROXIMATE
EXTENT OF
EXTENT
DEMOLITION
OF DEMOLITION
FOLLOWING
EXTENTFOLLOWING
OF DEMOLITION FOLLOWING
RESUPPORT
RESUPPORT
OF FACADE
OF FACADE
RESUPPORT OF FACADE
Fig: Part plan showing final as built condition with RC liner wall and
additional front wall to lift shaft constructed
3256 - The Kensington 22
4.7 4.7.1 •• Stage 2a: Short term settlement due to construction before
application of brittle finishes
Proposed building
Impact Assessment •• Stage 2b: Short term settlement due to construction after
Load from proposed building at end of construction Ref:
application of brittle finishes
EN1990:2002 Quasi-permanent combination (6.16a)
•• Stage 3a: Consolidation settlement due to building occurring
4.7.1.1 during 100 year design life
Case 1: 1.00ψ2Gk, proposed + 1.00ψ2Qk, proposed
Detailed assessments as outlined below will generally be Soil parameters and design approach •• Stage 3b: Consolidation settlement due to building occurring
Case 2: 0.90ψ2Gk
undertaken at the appropriate stage of design by AKTII Limited. after 100 year design life Where Qk,proposed is determined considering live load reduction
AKTII have extensive experience in the development of designs A detailed assessment of ground movements for comparison by factor αn (Ref: EN 1991-1-1:2002 eq. NA.2)
for deep basements in London and throughout the world. Given against relevant acceptance criteria will be undertaken •• Stage 4a: Long term heave due to gross unload occurring
the size and importance of the project, construction will be during 100 year design life Long term effects
during the detailed design stage to ensure that there is not a
undertaken by an established main contractor and associated detrimental impact on adjacent buildings in the short and long •• Stage 4b: Long term heave due to gross unload occurring Load from proposed building
supply chain with significant experience of such ground works. term. The procedure for implementing this analysis is outlined after 100 year design life
Comprehensive calculation packages will be prepared by AKTII Ref: EN1990:2002 Quasi-permanent combination eq. 6.16a
below.
Limited for Building Control approval at the relevant stage of Through the use of superposition the relevant design conditions
Case 1: 1.00ψ2Gk,proposed + 0.30ψ2Qk, proposed
Preliminary assessments of likely ground movements have been for the affected structures may be determined.
design.
made on the basis of the site investigation results obtained to Case 2: 0.90ψ2Gk
date bench-marked against typical stiffness parameters for the
where Qk,proposed is determined considering live load reduction
London Clay deposits. These preliminary analyses have formed 4.7.1.3 by factor αn (Ref: EN 1991-1-1:2002 eq. NA.2)
the basis of the assessment of the viability of a raft foundation
and retaining wall proposals, which are to be verified in the next
Time dependency effects
stage of design. A detailed design philosophy shall be developed ii. Material factors
With reference to Tomlinson (2001) and Brien & Sharp (2001),
in preparing the Geotechnical Design Report as required
relevant apportioning of the total ground movement into short- Soil parameters
under the provisions of Eurocode 7. Ground modelling for the
and long-term response has been determined.
assessment of ground movements shall principally comprise For the purpose of ultimate limit state design using Type 1
the following analyses addressing both vertical and lateral With reference to Tomlinson (2001), the rate of consolidation combinations (which encompasses the structural design of the
movements: settlement will been assumed to conform to drainage raft, retaining walls and assessment of any secondary effects
model type 1 using the coefficient of consolidation (Cv) generated from tilt of cores, etc.) the undrained shear strength
•• Elastic halfspace analysis of the proposed raft foundation
value as determined by relevant soil tests to be undertaken. will be modified in accordance with EN1997-1:2004 Annex A.
considering short and long term conditions accounting
Consolidation curves shall be derived for the London Clay It follows that the Young’s modulus values derived from the
for variation in pore water pressure and considering time
deposits. It will be assumed that the rate of long term heave undrained shear strength will be subject to the same partial
dependency of movements; use of halfspace model to
development follows the same progression through time. safety factor. When considering serviceability effects the soil
assess vertical ground movements below and adjacent to
parameters will be utilised without the application of partial
the excavation with consideration of rebound heave effects
safety factors.
in both short and long term conditions
4.7.1.4
Concrete
•• Elastic plane-strain 2D section cut analyses for assessment Design standards
of lateral and vertical ground movements in regions adjacent To account for cracking in concrete elements in the short-
to the excavation including the effects of basal heave Design will be undertaken in accordance with Eurocode 7 with term the Young’s modulus for the concrete will be modified
load factors taken from Eurocode 1. All relevant ULS and SLS to 0.75Ecm. To account for the combined effects of creep,
•• Review of predicted ground movements against empirical
derivations and case study data (eg CIRIA C580 data). The cases shall be considered, which in the case of this design are shrinkage and cracking in concrete elements in the long-term
results will be assessed against relevant acceptance criteria likely to comprise structural (STR), geotechnical (GEO) and uplift the Young’s modulus will be modified to 0.60Ecm.
as outlined below in order to secure the relevant formal (UPL) cases. The partial safety factors to be utilised in design
approvals for the works to be undertaken. Any resulting together with the relevant load case combinations are listed
requirements with regard to the Contractors’ methodology below:
will be detailed and enforced through the project
specifications and preliminaries. i. Load factors
Demolition
Construction phasing Where all loads are assumed to be uniformly distributed over
the site and the weight of buildings and imposed loads are
The construction phasing shall be considered in the assessment estimated from record information
of time dependency effects. At this stage of design development
the following stages have been identified as critical to one Excavation
or all of the structures that may be affected by the proposed Case 1: 1.00ψ2Gk,soil
development.
Where Gk,soil is equal to the weight of soil in accordance with
•• Stage 1a: Short term heave due to demolition the recommendations of the SI report
•• Stage 1b: Short term heave due to excavation
3256 - The Kensington 23
4.7.2 In summary:
mitigation measures. It is noted however that the impact adopted in design as the only variation to the Eurocode 7 design
of the proposed development is not anticipated to be procedure, with the exception that the accidental groundwater
significant due to the isolated nature of the proposed level will be taken as 1m below ground level as per BS8102,
basement, the low flow rates in the terrace gravels and which has been the adopted figure in UK construction for many
the background of fluctuating groundwater levels. Any years. It is considered that taking the accidental level at the
NO SHADING INDICATES NO
significant effect which is isolated will be mitigated through the ground surface would be unduly conservative. SIGNIFICANT BELOW GROUND
OBSTRUCTION
construction of a free draining layer to the north of the proposed
basement which will drain any elevated peak groundwater and
return it to the downstream perched water table in a controlled
manner. 4.7.3 DARKER RED INDICATES BASEMENT
LIKELY TO SEVERLY IMPEDE
SURFACE AQUIFER FLOW IE
BS EN1997-1:2004 & National Annex hard-standing over the site is proposed. New surface drainage
will be installed in areas of hardstanding within the proposed
The Kensington project will be designed to Eurocode 7 (BS development discharging to the public sewer with consent via
PROPOSED SITE
BOUNDARY
EN1997-1:2004 & National Annex) and as such the following new below ground drainage installations. Given the surrounding
limit states shall be considered: public sewer invert levels it is anticipated that the surface water
can be disharged by gravity through the basement at high level
1. Ultimate Limit State (ULS): Design values shall be the most into the public sewers.
unfavourable design conditions that could occur during the
lifetime of a structure during an extreme or accidental event. In order to meet BREEAM requirements, predicted increases
in peak rainwater due to climate change must be attenuated.
2. Serviceability Limit State (SLS): Design (characteristic) values Storage tanks are being located within the site boundary to
shall be the most unfavourable design conditions that could attenuate surface water prior to being discharged into existing
occur in normal circumstances. The option is given to the sewers. A. EXISTING GROUND LEVEL