Highway Asset Management Framework v1 PDF
Highway Asset Management Framework v1 PDF
Highway Asset Management Framework v1 PDF
Framework for
Highway Asset Management
Framework for Highway Asset Management
Framework for Highway Asset Management
FOREWORD BY THE PRESIDENT OF THE COUNTY SURVEYORS’ SOCIETY
I am very pleased that CSS has been instrumental in producing this Asset
Management framework for our highway infrastructure. This has come at an
opportune time for the future development of Local Transport Plans and funding
for transport in general.
The framework, I am sure, will help everyone setting out on the first step of
developing their highway Asset Management Plans and I am pleased to
commend the document to you.
Bob Wilkins
President of the County Surveyors’ Society
April 2004
Framework for Highway Asset Management
This framework has been produced by:
TAG
Welsh Cymdeithas
Association of Swyddogion
Technical Technegol
Officers Cymru
Framework for Highway Asset Management
Framework for Highway Asset Management
Acknowledgements
Project Board
Matthew Lugg (Chair) Cambridgeshire County Council
Alan Armson (Project Manager) Hertfordshire Highways
Chris Walker (Secretary) East Sussex County Council
Robert Biggs Derbyshire County Council
Technical Support
Rob Andrews Opus International Consultants (UK) Ltd
Paul Hardy Opus International Consultants (UK) Ltd
Framework for Highway Asset Management
Framework for Highway Asset Management
Preface
Introduction
The County Surveyors Society (CSS), together with the Local Authority Technical
Advisors Group (TAG) have produced the framework detailed in this document to
facilitate the meaningful exchange of knowledge and experience on the subject. It
is expected that the framework will be used to:
This document is the output from a project that comprises the following stages:
Stage One: Highway Asset Management: Worldwide Experience and Practice.
This framework document is the output from stage two of the project and
comprises two parts:
A definition of terms
Customers: Road users and the wider community served by the highway network
Network: A term used to describe the highway network inclusive of all its
elements i.e. the pavement, bridges, street lights, signs, drains, lines, street
furniture, verges etc.
Stakeholder: Any party who has an interest in the management, operation and
use of the highway. Stakeholders include customers, utility operators, e.g. gas,
electricity suppliers and interest groups.
i
Abbreviations
Framework for Highway Asset Management
ii
Framework for Highway Asset Management
1 Part One: Introduction
1.1 What is Asset Management?
1.1.1 Definition
1.1.2 Themes
The definition brings together themes that define an asset management approach:
1.1.3 Scope
Further Reading:
1
2
Framework for Highway Asset Management
Framework for Highway Asset Management
1.2 Why Asset Management?
Highway authorities exercise their duties to maintain, operate and improve their
highway assets under increasing pressures that include:
It is expected that the DfT will "strongly advise" highway authorities to prepare
highway asset management plans in the instructions for the next 5 year Local
Transport Plans. In Wales there is already a requirement to produce asset
management plans by 2006.
3
Whole of Government Accounts
Framework for Highway Asset Management
The valuation will be required to not only assess replacement value but also to
assess the level and rate of depreciation in order to record current value in their
accounts. Experience internationally and locally (with other government
departments) shows that meeting these accounting requirements demands a
detailed knowledge of the asset (including condition and maintenance backlog).
This in turn drives a need for robust processes, based around asset management
plans, backed by databases providing valid, relevant and up to date core data on
the assets. It is anticipated that the introduction of these requirements in this
country will provide a similar demand for improved asset information.
The code enables authorities to choose between revenue and capital intensive
options for service delivery, undertake ‘spend to save’ capital schemes and
undertake additional self-funded capital investment where they can afford to do so.
4
Framework for Highway Asset Management
General Drivers
It is a valid question to ask why a highway authority would not choose to adopt an
asset management approach i.e. why would an authority not want to:
Think strategically
Consider trade offs between alternatives
Establish performance goals and measure results
Consider the user
Be able to substantiate funding requests with facts
This is not to infer that these aspects are not routinely being undertaken. Most
authorities would however recognise that opportunity to improve their performance
exists under one or more of these areas. Asset management is a framework that
assists them to realise these improvements.
5
6
Framework for Highway Asset Management
Framework for Highway Asset Management
1.3 Benefits of Asset Management
A benefit occurs when the customer receives an improved level of service for the
resources available, i.e.:
The same or better level of service at a reduced cost,
A better level of service at the same or marginally increased cost or
Value = Performance
Cost of Service Delivery
7
8
Framework for Highway Asset Management
Framework for Highway Asset Management
1.4 Purpose of the Framework
1.4.3 Use
Assist with the Part two of the document has been structured in such a
preparation of an asset way that an authority that documents how it will
management plan address each section will have the basis of an asset
management plan.
Further Reading:
This project's stage one report details international highway asset management
and cross sector asset management experience. The report includes an extensive
literature search and includes references to many documents that are available
on-line. The report is a useful reference for those wishing to explore the
principles of the framework in more detail.
9
10
Framework for Highway Asset Management
Framework for Highway Asset Management
1.5 Regional Differences
Highway asset management is in its infancy in the UK. Each country in the UK is
approaching the issue in a subtly rather than fundamentally different way. This
framework can consequently be applied in each country by simply applying the
general principles identified.
1.5.1 England
1.5.2 Wales
All Welsh highway authorities are tasked with producing asset management plans
for their networks by 2006.
1.5.3 Scotland
While no specific timescale has been laid down in Scotland for the implementation
of asset management, guidance issued in regard to the “Local Government in
Scotland Act 2003” refers to the requirement for authorities to demonstrate that
assets are being used efficiently and
effectively.
The Northern Ireland Road Service has been valuing their assets for the last three
years but has only had the asset valuation part of their financial statements signed
off by the Northern Ireland Audit Office for the last financial year.
11
12
Framework for Highway Asset Management
Framework for Highway Asset Management
1.6 Implementing Asset Management
Current Practice
Desired Practice
Review
Gap Analysis
Implementation
Plan
Prepare Asset
Management Plan
It recognises that asset management is not entirely new and that each authority will
already be practising elements of the required processes. Implementation needs
therefore to result in a method, which complements current Practice.
Asset management is a process that enables the people who manage the asset to do
so in a more informed manner. The structured approach it necessitates can require
amendment of established practices and a change of mindset. Implementation
plans therefore may need to address issues that include:
13
Framework for Highway Asset Management
People
14
Framework for Highway Asset Management
Processes
15
Asset Data
Framework for Highway Asset Management
What?
Where?
Size?
Type?
Age? etc
Condition Data:
Performance Data:
Most authorities will have existing data systems in place, for example UKPMS,
bridge management systems, street lighting, customer query systems etc. A review
of these in conjunction with any proposal to update internal processes is
recommended and should document:
Looking at processes prior to making any decisions about software systems allows an
understanding of whether existing business processes align with an asset
management approach; i.e. define desired process and purchase or develop
software where appropriate to assist in efficient delivery.
16
Framework for Highway Asset Management
1.6.2 Defining Desired Practice
This framework can be used as a tool to define desired practice. In defining desired
practice the issues to be considered are similar but subtly different to those used in
the review of the current practice. Instead of asking how things are done now the
question is; how would we like them to be in the future?
A gap analysis compares current and desired practice and quantifies the activities
required to change current practice to desired practice. The analysis should
consider:
Gap What are the differences between current and desired practice?
Cost What are the costs of closing the gaps?
Benefit How will the proposed changes benefit the customer?
Priorities Which items are most crucial to improving service delivery?
Resources Can resources be made available to action the desired changes?
There are a number of ways of carrying out a gap analysis and representing the
results. An example is included in Appendix C. The gap analysis focuses on
identifying the crucial tasks and making sure that they are given priority by
considering affordability and benefit. It may be desirable to have performance data
for all assets but can this be achieved at a reasonable cost? Would a sample of data
be sufficient for planning purposes? Are resources likely to be available to deliver?
17
1.6.4 Implementation Plan
Framework for Highway Asset Management
The gap analysis can then be used to create an implementation plan detailing:
Training
Collection of additional data
Reorganisation of responsibilities
Changes to practices
Investment in new software systems or
development of existing systems
Further Reading:
An example output from a gap analysis exercise is included in Appendix C.
An asset management plan is a document that states how a group of assets are to
be managed over a period of time. The plan provides a guiding reference for all
those engaged in delivering the highways service. This document is structured such
that, if an authority documents how they intend to deal with the issues covered in
each section in part two, they will have prepared a basic asset management plan.
Production Team
Ideally, the people tasked with delivering the service should produce the plan. This
will engender in them a sense of ownership of the plan and a greater incentive to
make sure that the tasks contained within it are delivered. It should however be
recognised that the existing team may not have the skills or the time required to
produce the plan and some assistance from other resources, internally or
externally, may be required.
Before embarking on production it is advisable to determine who will use the plan
and for what purpose. This will assist in defining the scope of the plan (e.g. what
asset will be covered by it, for example will winter maintenance facilities be
included?). Defining the structure and contents of the plan assists in gaining
confirmation of the scope of the plan.
18
Framework for Highway Asset Management
1.6.6 Implementation Recommendations
Case Study:
Hertfordshire County Council produced the first HAMP in the UK. Appendix C
contains a description of how Hertfordshire approached this task and the
structure of their plan.
19
20
Framework for Highway Asset Management
Framework for Highway Asset Management
2 Part Two: Framework
The framework is based on a generic asset management system. It is shown
diagrammatically below and described in more detail in the remainder of this
document. The framework illustrates how various activities are linked. It is the
linking of these activities into an overall management framework that is the
principal difference between asset management and current practice. The
remainder of this document follows this structure.
G oals,
O b je ctive s & Inven tory
Po licies
1. Startin g Poin t
Improvement Actions
C on d ition D em an d
A sse ssm en t A sp iration s
2. Le v els of Se rv ice
6 Reporting & Monitoring
3 . O p tio n Id e n tificatio n
Performance Measurement
4 . D e cisio n M ak in g
5 . Se rv ice D e liv e ry
21
22
Framework for Highway Asset Management
Framework for Highway Asset Management
2.1 Starting Point
Goals and objectives related to asset management aspirations must reflect those
that exist within other documentation that the authorities use to govern and drive
their works. If a highway asset management plan is being published it is important
to establish the context and scope of the plan and its relationship with these other
documents and their contents. Important considerations include:
What other standards are being applied that may effect the contents of the
plan?
- The Code of Practice for Highway Maintenance
- Local Maintenance Plans and standards
- Standards specified in works contracts
What is the desired relationship between the asset management plan and
other corporate documents?
Valuation
Resource Accounting and Budgeting is likely to affect the way in which funds are
allocated in the future. The value of the asset and the effect of any proposed
works programme upon that value will be an important consideration. Valuation
requires robust asset information to enable financial reporting requirements to be
met.
23
A replacement value for the asset is a common starting point for a valuation. This
Framework for Highway Asset Management
2.1.2 Inventory
The highway inventory is the asset register and is the starting point for any
valuation. In order to value the asset a valuer will need to know whether the
inventory is complete, accurate and up to date. A valuer will establish what level
of confidence exists in the data held and decide whether any omissions will
materially affect the valuation. Authorities will need to know, with some degree of
certainty, how good their asset inventory is, in order for their valuation to be
completed.
Data Review
All highway authorities hold inventory data. It is however typical for elements of
the inventory to be of unknown quality and not necessarily complete or up to date.
Before embarking on the adoption of asset management it is essential that the
quality and completeness of existing asset data be confirmed.
24
Framework for Highway Asset Management
A data review exercise should take into account:
A review of currently held inventory should cover what specific data is held on all
assets including:
Carriageway Earthworks, embankments
Bridges Footway/cycleways
Other highway structures Street lighting
Drainage Signs
Traffic Signals Road markings/studs
Safety fencing Verge and landscaped areas
This will enable an assessment to be made of the level of confidence in the data
held. In addition specific consideration should be given to noting any database
systems in use or planned and the minimum data needs for Best Value Performance
Indicators (BVPIs), for running UKPMS and for any other corporate information
systems e.g. a GIS.
Desirable Data
The inventory data requirements for the adoption of a fully implemented asset
management approach can be determined from considering the purpose and
potential use of such data.
25
Typical desirable uses to consider are:
Framework for Highway Asset Management
Uses: Purpose:
Asset Condition To increase understanding of the condition both current
Modelling and future
Programming To enable a long term programme to be established
Fault Identification To capture faults such that they can be analysed
To report on BVPIs and other statutory reporting
Reporting
obligations
Contract Management To enable management of contracted arrangements
Valuation To enable the value of the asset to be calculated
To increase understanding of achievement of non-
Non-condition related
condition related levels of service e.g. accident reduction
performance
and congestion/availability indicators
The data can then be tabulated against the component detail as in the example
below.
Asset Condition
Fault Reporting
Inventory Attribute
Non-condition
Programming
performance
Management
Reporting
Modelling
Valuation
Contract
related
Carriageway
Section Id 9 9 9 9 9 9
Section Name 9 9 9 9 9 9
Road Name 9 9 9
Start point 9 9 9 9
End point 9 9 9
Length 9 9 9 9 9
Geometry 9
Lane width 9 9 9 9 9
Surface type 9 9 9 9 9
Surface Dates 9 9 9 9
Maintenance Category 9 9 9 9 9
Salting route 9 9 9
Owner 9 9
CVI 9 9 9
Analysis of this output enables a rational assessment of what data is missing and
how important it is.
26
Framework for Highway Asset Management
Network Referencing
Safety for road Data for structures, lighting, advisory or regulatory signage,
users traffic signals, safety fencing, and pedestrian crossings.
Pavement structure, surfacing, faults and repairs and
Integrity of the
drainage systems affect this function and include the data
network
necessary to process BVPIs, including UKPMS.
Other features on the highway network that have an impact
General service
on remaining levels of service for accessibility, financial
issues
performance, environmental impact etc.
27
Data Collection Advice
Framework for Highway Asset Management
28
Framework for Highway Asset Management
2.1.3 Starting Point Recommendations
Case Study:
The London Borough of Hammersmith and Fulham has undertaken an asset
inventory survey commission for TfL as part of the Road2000 project. The project
is an example of a structured approach to data collection. Details of this project
can be found in Appendix C.
29
30
Framework for Highway Asset Management
Framework for Highway Asset Management
2.2 Levels of Service
Levels of service describe the quality of services provided by the asset for the
benefit of the customers. They are composite indicators that reflect the social,
economic and environmental goals of the community. Levels of service are
therefore the manner by which the highway authority engages with the customer
and are about reflecting the customer’s interests in terms that can be measured
and evaluated.
Levels of service are a way in which a highway authority can determine whether or
not it is meeting customer expectations and its statutory obligations in the delivery
of its highway service. They enable the Highway Authority to:
Condition
Preservation of the physical integrity of the asset.
assessment
The service delivered by the asset in terms of its use,
Demand
generally expressed in terms of safety, availability,
Aspirations
accessibility, integration etc.
31
2.2.3 The Condition of the Asset
Framework for Highway Asset Management
The perceived condition of the asset as “measured” by public and road user
perception.
The condition of the asset as determined by measurement and analysis of
road condition data (less obvious to the public and road users).
This distinction is important as whilst this framework promotes a focus on the
customers needs there may be instances (particularly in relation to the structural
condition of the asset) when the customer is not in a position to hold an informed
opinion.
The development of measures that reflect performance against these aspects and in
particular the development of a relationship between the resources allocated to
tasks that support them is critical if the principles of asset management are to be
applied fully across all aspects of the highways service.
Once a suite of levels of service and performance measures are put in place to
support them, it will then be possible to obtain some understanding of the
relationship between the cost and the level of performance against each level of
service. This information can then ultimately be used to inform decisions on the
allocation of resources between competing demands.
In simple terms the requirements guide the development of the levels of service
into groups. These are a reflection of demands placed on the service.
Once the groupings are agreed, performance measures can then be developed that
enable the assessment of performance.
A series of performance measures then support each level of service, thus enabling
the level of service to be measured. For example by creating a means of weighting
each performance measure. Each authority will need to decide their own method
32
Framework for Highway Asset Management
and weighting to reflect the condition and use of their network and the desires of
local customers. The following section describes the requirements in more detail.
Legislative
Safety
Requirements
Customer Availability/
Expectations Accessability
Organisational
Condition
Objectives
Best Practice
Environmental
Guidelines
N.B. The above groupings of safety, availability etc. shown are purely for illustration and may vary
between authorities.
Legislative Requirements
Levels of service need to take due cognisance of the legislative framework that
applies to the business of highway management. Specifically the following types of
legislation should be considered when developing levels of service:
Highways Legislation: e.g. The Highways Act 1980, The Roads (Scotland) Act
1984, Road Traffic Act 1991, New Roads and Street Works Act 1991, Traffic
Management Bill etc.
Environmental Legislation: e.g. The Wildlife and Countryside Act 1981,
Weeds Act 1959, Ragwort Control Act 2003 etc.
Relevant General Legislation: e.g. Construction (Design and Management)
Regulations 1994
When developing levels of service, managers need to consider how relevant pieces
of legislation affect their network. For example, a network with areas of
exceptional natural beauty may require environmental considerations to be given
greater prominence than elsewhere.
33
Customer Expectations
Framework for Highway Asset Management
Highway networks are provided for the benefits of customers. The customer’s view
of the service being provided is, therefore, a highly important piece of information.
Which aspects of the service are of most importance to the customer e.g. is
street-lighting more important than snow clearing during the winter?
The degree of satisfaction with particular aspects of the service.
Combining these two elements can provide useful information to assist authorities
to focus their attention on the areas of greatest customer need.
34
Framework for Highway Asset Management
2.2.7 Organisational Objectives
Case Study:
Hertfordshire’s Highway Asset Management Plan contains levels of service
covering the whole service. A sample section covering safety is included in
Appendix C.
35
36
Framework for Highway Asset Management
Framework for Highway Asset Management
2.3 Option Identification
Highway budgets are allocated to a combination of services and assets. Gaps may
exist between desired and current performance for;
For the services a long-term programme is required that is linked to the anticipated
achievement of level of service targets. Generally the action to address service
area performance gaps is the advancement of the programme of works. This
inherently creates tension with other competing demands when funding is limited.
The process of optimisation and the development of a forward works programme is
the tool used to manage the competing demands.
37
The Reasons for the Gaps
Framework for Highway Asset Management
It should be noted however that a performance gap could exist for a number of
reasons as follows:
Customer Expectations
Gap 1
Gap 2
Actual Performance
Gap 3
Communication to Customers
38
Framework for Highway Asset Management
2.3.2 Lifecycle Planning
39
Framework for Highway Asset Management
Non-Asset Options
There will also often be treatment options within the categories above. An
example of this is shown below.
40
Framework for Highway Asset Management
Using a pavement condition deficiency and structures condition as examples
Treatment Options
A lifecycle plan should document specific plans for how each phase of an asset’s life
is managed (i.e. from creation to disposal) and in doing so recognise the
interdependency of the phases. For example, it will recognise how the level of
investment in routine maintenance affects the renewals required, or how original
construction details affect the future demands for maintenance expenditure.
A lifecycle plan starts with the identification of options. It only however becomes
of significant value if the evaluation of those options is undertaken in a rigorous and
repeatable manner; i.e. if there is a process of optimisation.
41
Framework for Highway Asset Management
Case Study:
A working group within SCOTS is currently assessing the backlog of maintenance of
not just the carriageway, but of the network as a whole i.e. footways, signing &
lining, structures, drainage, ITS and car parking equipment etc. The intention is to
update the report produced by the body in 1997, and to input to the overall
backlog figure for the UK. Details of this project are given in Appendix C.
Case Study:
West Sussex County Council have studied the funding levels required to meet the
safety targets for reduction in KSI by calculating the inferred effectiveness of their
safety schemes. This study is an example of identification and analysis of a service
area gap. Details of this project are given in Appendix C.
42
Framework for Highway Asset Management
2.4 Decision Making
An improvement in decision-making is
one of the key benefits of asset
management. This section introduces Optimisation &
Risk
the concepts of optimisation and risk Budget
Assessment
management and states how budget Consideration
considerations are taken into account.
A full consideration of these advanced 4. Decision Making
topics is beyond the scope of this first
edition of the framework.
2.4.1 Optimisation
Optimisation is the process of identifying the optimal regime for the operation and
maintenance of the network. It requires analysis be carried out to find the most
cost effective means of providing for, or managing, the ongoing demands placed on
the asset. Optimisation is an advanced asset management technique and can only
be carried out if robust level of service information is available.
Levels of Optimisation
The outcome of optimisation is the selection of the “best” option out of a range of
acceptable options. It presupposes that options that are clearly unacceptable for
any reason (economic, social, environmental or political) are removed from the
analysis. Optimisation can be undertaken at two levels:
43
Single Asset/Service Optimisation
Framework for Highway Asset Management
This form of optimisation is then simply a mechanism to rank these options by some
predefined system (such as net present value or benefit to cost ratio), with the
selected option being that which shows the best return. Single asset/service
optimisation is a ranking mechanism often used to identify project to be put
forward for funding.
44
Framework for Highway Asset Management
Single Criterion Network Level Optimisation
Consider a simple network consisting of three single assets (A, B and C) each with
three options (A1, A2, A3 etc). In the absence of any financial constraint, and with
an objective of maximising the NPV, then the resulting selected strategies would be
A2, B2 and C1 as this combination would lead to the maximum NPV for the network
as a whole. The total cost of these three strategies is £62,000.
When more than one criterion is used to define the optimum solution the above
single criterion optimisation may be inappropriate and multiple criteria optimisation
(MCO) should be considered. MCO is a much more technically difficult concept to
explain than the single criterion optimisation discussed above. There are two main
methods of undertaking an MCO:
The first of the two above techniques requires the establishment of weighting
factors to enable combining reporting lines (e.g. economic, safety, image etc.) into
a single number. These weightings should be established for the geographic area of
45
interest, as different parts of society may have a diverse range of priorities. For
Framework for Highway Asset Management
instance, a large urban area with significant congestion issues may focus on the
economic and social issues, while a society based in a natural forest location may
be willing to forgo economic benefits for environmental protection.
The use of pure MCO techniques is a significant subject matter in its own right and
is not discussed further here. It is through the process of optimisation that the
greatest benefits of asset management can be gleaned. Optimisation can be aided
by the use of sophisticated analysis tools such as deterioration models and whole
life costing analyses.
Further Reading:
Birmingham City Council has developed a prioritisation process that combines
discrete data sets to enable identification and prioritisation of proposed projects.
This is an initial form of single asset optimisation. Appendix C includes a
description of this work.
Whilst the asset management approach advocates the identification of needs, these
must often be tempered by the reality of the available budget. Often management
decision must be taken within the context of limited budget availability. The
processes described above should lead to the ability to support funding applications
with rationalised decisions for splitting budgets across implementation programmes,
as well as within the programmes, in order to meet the levels of service.
Determining the funding demands for proposed levels of service needs to take into
account:
Requested Service
Reflecting customers stated desires
Level
Established Service
Current level of service
Level
Optimum Service Taking into account national and local policy, legislation,
Level projected use and engineering principles & requested level
Attainable Service A service level that re-interprets the optimum service level in
Level the light of available resources
46
Framework for Highway Asset Management
Budget considerations can determine the appropriate means of optimisation.
Consider the example given above, but with constraints of having a budget of only
£50,000, yet also having to do at least one option for each asset. In this case,
options A1, B2 and C3 are selected when optimising at a network level, despite
options A1 and C3 not being the optimal for that particular asset.
The above situation can be expanded to also consider the timing of expenditure
within an option, such that options that spend money in different years can be
considered.
Organisational Constraints
The process of risk management is widely applied in other asset sectors. This
section provides guidance on how risk management could be applied for a UK road
network.
47
Risk Identification
Framework for Highway Asset Management
Risk identification is the formal recognition and documenting of events that have
the potential to adversely affect the delivery of the service to the customer. The
type and relative importance of different risks will vary from authority to authority.
It is recommended that highway authorities carry out a risk identification exercise
considering the following areas as a minimum:
Safety: in the context of both the road user and the safety of those involved
in delivering the service (e.g. road workers)
Natural Events: predominantly the weather and its effects,
- Snow and Ice,
- Flooding,
- Extreme wind, Fog, etc
Physical Risks: where the failure
of the asset could lead to failure.
For example:
- The collapse of a structure
- Street-lighting failures
- Collapse of drains leading to
flooding
Economic: the potential for economic changes to affect the ability to deliver
the service could include such potential changes as:
- Oil price rises affecting the cost of bituminous materials
- Dramatic increases in inflation increasing costs
Legislative:
- Changes to key pieces of legislation
- Changes in government policy
Resources: the potential future availability
Public Liability: claims
In addition a number of other potential risks with less obvious relevance include:
Reliance on key personnel for service delivery (i.e. the risk of loss of
institutional knowledge)
Systems: the potential loss of key information if information systems fail
Politics: the potential for unexpected policy changes as a result of a change
in the relevant local politicians
The lists above are not exhaustive. They are intended as a prompt to assist an
authority to identify the risks that apply in their locality.
48
Framework for Highway Asset Management
Risk Analysis
Risk analysis is a process by which an authority determines which events are the
most critical to them. Determining the level of risk involves:
One method of assessing risk is to place a monetary value on the risks by pricing the
“consequence of failure”. By doing this it then becomes possible to evaluate the
cost benefit ratios of differing risk reduction actions.
Risk Reduction
49
Ongoing Monitoring and Review
Framework for Highway Asset Management
50
Framework for Highway Asset Management
2.5 Service Delivery
A forward work programme should cover the maximum period possible. A minimum
period of 10 year is recommended. Only by projecting forward the anticipated need
can the best whole life options be identified.
When good quality condition data is available for analysis it is possible to predict
the likely future major maintenance schemes and their locations. The timing of
non-condition related work can then be reviewed to ensure situations don’t arise
where new work is destroyed by subsequent tasks.
Long-term programmes are built on projections using currently available data and
knowledge. As such there are limitations on the reliability of these projections, in
particular in terms of the precise location and nature of individual projects in the
later years of the programme. Aggregating anticipated needs is however a valid
method of predicting future funding requirements.
51
Typical levels of confidence that may be achieved in a long-term programme are
Framework for Highway Asset Management
shown below;
The later years of the forward works programme are essentially a planning tool. As
the projects in the later years may only be speculative, care should be taken over
how widely available this documentation is made so as not to create unreasonable
expectations.
All authorities use some form of supply chain to deliver the service. An array of
different arrangements exists. None of these arrangements preclude the use of
asset management but some may have elements within them that may make the
adoption of an asset management approach more difficult. This will particularly be
the case if a supplier’s commercial needs are not aligned with what is best for the
asset. Some existing term contracts may include terms that encourage suppliers to
spend budgets fully rather than allocate them based on need. It is advisable to
review contracted arrangements in the light of asset management requirements to
determine if they present a hindrance to progress.
The delivery of physical works and service delivery should recognise the need for
information. There are often cost effective solutions for data capture that can be
incorporated into the works at a minimal additional cost. Combining inspection
regimes with condition rating and monitoring is one of the more obvious examples.
Other opportunities may include collection of missing inventory data by teams
carrying out routine repairs.
52
Framework for Highway Asset Management
2.6 Reporting and Monitoring
53
Types of Performance Monitoring
Framework for Highway Asset Management
54
Framework for Highway Asset Management
2.6.2 Developing Performance Measures
Many authorities have published vision, mission and goal statements, as well as
objectives. In these instances the objectives form a logical starting point for the
development of performance measures and specifically to identify what aspect of
performance is being measured.
Objectives are often grouped. For example, into areas such as safety, availability,
customer service, asset preservation and environmental. This is the approach
recommended, by grouping proposed performance measures to support levels of
service.
Consideration should also be given to other existing documents. For example the
Local Transport Plans can also provide a starting point and often a number of
existing developed measures.
It is advisable to start with data that is readily available or can be easily obtained.
Do not assume that new data sources are required. It is likely that much of the
data needed to support desired performance measures is already being collected.
It may simply not be being collated and provided to others. Maintenance history
records for example can provide the input for maintenance cost analysis, which can
provide intervention triggers for treatments.
55
Framework for Highway Asset Management
Using historical figures if possible, run tests on the proposed measures to determine
if they are practical to measure and compute.
Data is gathered as an integral part of carrying out the work, rather than as
a separate task
Data is collected by the people who need to use it to make decisions
Check the validity of the result to ensure that they genuinely reflect current
performance. The precision of the performance measures and the ability to
measure to an appropriate level of accuracy is a critical issue when performance
measures are established and target values set. Problems are likely to occur when
the difference between the target level and the measured condition is small and
the accuracy of the measuring method could be the reason for non-achievement
rather than the actual performance provided.
There are a number of ways in which performance measures can be summarised and
reported. In deciding upon a reporting format considerations should be given to:
Balanced Scorecard
Increasingly there is a demand for organisations to report on not only the financial
performance of their assets but also on the social and environmental effects of
their actions. Under such a regime the outcomes of their actions are reported
against the social, economic and environmental outcomes. This means a move
away from a purely financial reporting to being able to demonstrate to stakeholders
that they are also managing their social and environmental responsibilities. Clearly
there is an inherent tension between these competing demands.
56
Framework for Highway Asset Management
represents comparative importance and the radial measure shows current
performance.
0 Ministerial Indicators
format that can be quickly
Operational Targets
understood. Numerous
SCORE alternative methods of
96.7
presenting such results
exist and it is for each
authority to decide
whether such reporting is
important for them and to determine an appropriate presentational format.
Review
Improvement Plan
57
Framework for Highway Asset Management
58
Framework for Highway Asset Management
Appendix A: References
1. CSS/TAG, Preparation of a Model Framework for Asset Management (Plans) for a
Highway Network in the UK: Stage One Report: Review of International and Cross-
Sector Experience, May 2004.
59
60
Framework for Highway Asset Management
Framework for Highway Asset Management
Appendix B: Definitions of Asset
Management
A myriad of definitions exist for asset management. A selection of these is given
below:
61
62
Framework for Highway Asset Management
Framework for Highway Asset Management
Appendix C: Case Studies
C1 Implementation: Gap Analysis
The following chart shows the result of one method of gap analysis.
Gap Analysis
100
90
80
70
60
50
40
30
20
10
0
Per f or mance
Cor por ate Buy-In Data Management Ser vi ce Expectati on For war d Pl anni ng Wor k Achi evement Asset Condi ti on
Measur ement
2-Year Tar get 40.0 45.0 60.0 42.0 35.0 50.0 55.0
5-Year Tar get 82.0 77.0 91.0 71.0 79.0 70.0 89.0
Contact Details:
Paul Hardy. Opus International Consultants (UK) Ltd.
T: 0115-959-9611 E: [email protected]
W: http://www.opusinternational.co.uk
63
64
Framework for Highway Asset Management
Framework for Highway Asset Management
C2 Implementation: Hertfordshire’s Highway Asset Management
Plan
An external consultant was appointed to facilitate the process of producing the first
draft of the asset management plan. People from all aspects of the highway service
have been involved in the production of the plan to ensure that it is a plan that is
“owned” by appropriate personnel.
The plan took approximately 9 months to produce and contains the following
sections:
Contact Details:
Alan Armson
T: 01707-356552 E: [email protected]
65
66
Framework for Highway Asset Management
Framework for Highway Asset Management
C3 Inventory: Road2000 Asset Inventory Collection Project
Purpose: The Transport Commissioner's asked for an asset survey to be carried out
of both the Transport for London Road Network TLRN and the Borough Principal
Road Network (BPRN). Through the ROAD2000 project London Borough of
Hammersmith & Fulham (LBHF) as lead borough are managing a project on behalf of
Transport for London (TfL) to collect asset inventory information on London's
Principal Road Network.
Scope: The project involved the collection of inventory data for the borough
principal road network in the 33 London boroughs. The survey collects map based
inventory data and assigns every inventory item with a coarse/lay person’s
condition rating.
Cost: Phase 1 cost approximately £740 k. This cost includes project setup, the
identification, procurement, and delivery of hardware (12 tablet PC's, 2 GPS
stations, 1 server), the identification, procurement, and delivery of purpose built
software, licensing, external technical support, a management team, and field
survey staff. The cost of phase 2 is £716k. The lower per item cost is anticipated
due to establishment costs being taken up in phase 1.
Benefits: The condition rating will enable an initial rational assessment of the
condition of these assets to be made. If future surveys were to collect information
in a consistent manner the data could be used to predict future deterioration and
thus future funding needs. The survey will enable TfL and the boroughs to compare
the number and condition of assets across London on a consistent basis.
Contact Details:
Gordon Prangnell, London Borough of Hammersmith and Fulham
T: 0208-753-3002 E: [email protected]
67
68
Framework for Highway Asset Management
Framework for Highway Asset Management
C4 Levels of Service: Hertfordshire’s Safety Levels of Service
Scope: Hertfordshire’s plan contains levels of service grouped into the following
categories:
69
Framework for Highway Asset Management
Outcome: Safety
Level of Service: Safety Related Defects
Performance Measure Method of Calculation
Percentage of killed and seriously injured Number of accidents with road asset
accidents in which asset condition is condition mentioned as a contributor
reported as a contributing factor. divided by the total number of
(qualifying) accidents, expressed as a
percentage.
Percentage of potholes repaired within 24 Number of potholes repaired within 24
hours of alert hours divided by the number reported
faulty, for publicly reported faults,
expressed as a percentage
Percentage of unauthorised objects on the Percentage of hazardous objects
network removed removed from the road corridor within
2hrs (contract response time) of
notification, expressed as a
percentage
Percentage of signs missing Number of signs missing/dirty divided
by the total number of signs observed
on an audit/scouting route, expressed
as a percentage.
Number of accidents where snow and ice Number of accidents reported as a
are identified as contributing factor number
Number of traffic signals not operating as Number of traffic signals not working
planned properly divided by the number
reviewed, expressed as a percentage.
It should be noted that it is important the performance measures include items that
are measured on an ongoing basis, so that actions can be taken to address
performance deficiencies progressively as opposed to waiting for annual reporting
figures. This issue is covered in more detail in the section on performance
measures.
Contact Details:
Alan Armson
T: 01707-356552 E: [email protected]
70
Framework for Highway Asset Management
C5 Performance Gaps: SCOTS Maintenance Backlog Study
Purpose: The purpose of the study is to evaluate the maintenance backlog using
factual data and a consistent method across all Scottish Authorities.
In order to use available data, authorities have been grouped on the basis of the
proportion of urban/rural network. Five groupings, cities, urban (> 60% urban
network), semi urban (< 60% but >30% urban network), rural (< 30% urban network)
and island authorities have been established. Both of the cities and islands were
established as it was considered that they had particular issues either relating to
the usage of roads or the costs of maintenance which were different to the other
groupings.
Progress: Each group is now gathering information on the wide range of categories
of infrastructure, using the available data from any authority in the group e.g. if
only one authority has detailed information or costs for footways then that
information will be used as a proxy for the group with pro–rata costs based on
comparable length of network. Indeed if detailed information and costs are only
available for part of an authorities network then this can also be factored to cover
the network as a whole.
Benefits: This approach is aimed at using the available statistical and condition
information to the maximum effect, allowing all authorities in the group to input
data and to gain an impression of the position in their authority even if the
information they have is limited.
Contact Details:
Hugh Murdoch
T: 01224 522420 E: [email protected]
71
72
Framework for Highway Asset Management
Framework for Highway Asset Management
C6 Optimisation: Birmingham City Council
Birmingham had been using the Maintenance Assessment Rating and Costing for
Highways (MARCH) condition assessment system to gain knowledge of its Network’s
condition and requirements since the early seventies. It was used to produce
suggested treatments, priority listings, and an annual maintenance backlog figure.
The MARCH system’s drawback was that it was working in isolation without access
to other condition data on which to base its calculations. When UKPMS came along
we recognised an ideal opportunity to store all our condition data in one location.
Currently Birmingham’s UKPMS system holds CVI, DVI, Deflectograph, and SCRIM
data with TTS data being loaded shortly.
All this data is useless however if it does not correspond accurately to your
Network. Birmingham decided to digitise its Network with each Highway section
being accurately measured against OSCAR centre line data with start and end nodes
marked and their coordinates noted. The benefits from this is a confidence in the
accuracy of the Network allowing easy audit of raw condition data and also an
ability to supply Condition Survey Contractors accurate and clear mapping prior to
survey.
Once the data has been inputted and processed Condition Indices are allocated to
defective sections. These indices together with the findings from Deflectograph,
SCRIM, and BVPI reports are then used to produce the annual Highway Maintenance
Priority Listing. In addition, using the digitised network, thematic maps are then
produced with the poorest sections of highway highlighted for easy identification
out on site.
Birmingham has recently completed a project undertaken with Marsh Associates Ltd
where SCRIM data has been analysed automatically and linked to the latest accident
data and works records. The result is a priority listing specifically designed to treat
sites with poor skidding characteristics based on the principal of treating those sites
with the greatest risk first. Once again these sites are displayed thematically giving
each site a ranking. A picture paints a thousand words, and that is certainly true
when you are trying to display the condition of your network. Once the network is
accurately linked to a GIS system then the possibilities are numerous.
Birmingham will soon commence the installation of an asset management system
and envisage the UKPMS network forming the framework on which to hang the rest
of our asset data.
It is anticipated that GIS will play a major part in providing the full benefits of an
asset management system to both the client and the customer. With the future
requirements of public access to Local Government data, a GIS mapped framework
could be easily displayed on the internet and, with the correct security features, be
available to all.
Contact Details:
Barry Wilcox. Condition Survey Project Leader. Birmingham City Council
T: 0121 303 1111 E: [email protected]
73
74
Framework for Highway Asset Management
Framework for Highway Asset Management
C7 Performance Gaps: Dorset’s Study of Pavement Maintenance
Backlog
The Dorset PMS was used in support of evidence to the Transport Select Committee
Inquiry into Road and Pathway Maintenance, the recommendations from which were
published in June 2003, and has been used more recently to inform the DCC Local
Public Service Agreement (LPSA) targets for highway condition having regard to
likely budget availability from the Local Transport Plan settlement for structural
maintenance. The methodology developed for Dorset was also used by WDM Ltd for
their Project Report to the UK Roads Board on “Estimating Budgets to achieve the
Government Targets for Highway Maintenance in England” published in November
2003.
Purpose: To identify and repair local roads, ensuring that the most defective roads
are prioritised appropriately, in order to halt overall deterioration and meet agreed
LPSA targets by 2005/06. Then to aim to reduce the proportion of defective roads
to a preset level of 8% for principal (A) and non-principal (B) roads and 12% for
minor/non-principal (C and D) roads.
Scope: For principal (A) and non-principal (B) roads, DCC assess the local road
network in terms of structural (deflection), functional (roughness, rutting) and
safety, (skid resistance and texture) condition. For minor roads, the UKPMS
condition indices for structural, edge and wearing course are used. This data is
collected, processed, referenced and stored on the County Council’s PMS.
The asset information in the PMS is used to assess need, prioritise pavement
treatments and produce predictive models. For principal (A) and non-principal (B)
roads the information is also used with predicted deterioration rates to obtain
future budget requirements using preset defect targets. Budgets can also be
estimated for minor roads.
75
The budget required to treat defects can be estimated from the length of road that
Framework for Highway Asset Management
requires treatment, a unit cost of maintenance treatment for each class of road and
treatment type and an assumed return maintenance period and hence design life of
20 years for principal and non-principal (B) roads and 30 years for non-principal (C
and D) roads. The 30-year design life assumption for minor roads was derived from a
long-term research project (10 years) carried out in Cornwall.
Progress: The PMS has enabled DCC to predict that percentage reductions of 0.5%,
2% and 3% in the defectiveness of A, B and C, and unclassified roads respectively (as
measured by BVPIs 96 and 97) should be achievable as “stretch” targets by 2005/06
if current LTP allocations for structural maintenance are maintained. Progress
towards these targets is now monitored on a regular basis.
Benefits: The principal benefits that have been gained are in the ability to advise
elected members and government departments of the budgetary implications of
meeting condition targets and in consequently being able to set realistic targets
having regard to budget availability.
Ability to anticipate the cost of meeting the agreed LPSA condition targets has
increased confidence in allocating the structural maintenance budget between
works aimed specifically at reducing carriageway defectiveness as measured by
BVPIs 96 and 97 and other works (eg, bridge maintenance, footpath maintenance
and drainage).
Contact Details:
Mike White
Head of Highways and Transportation, Dorset County Council
T: 01305-224233 E: [email protected]
Richard Bastow
Highways Manager, Dorset County Council
T: 01305-225335 E: [email protected]
76
Framework for Highway Asset Management
C8 Performance Gaps: Surrey’s Funding for Bridge Management
Purpose: The purpose of the report is to establish the funding required to maintain
the standard of the Council’s bridge stock at an acceptable level.
This information is used to draw conclusions on the condition of the asset currently,
its expected future condition and the funding implications. It also highlights that a
risk management approach is already in place on some bridges where they have
failed assessments and are now under a regime of special inspections. The report is
update on an annual basis. It is recognised in the report that improvement should
be sought in:
The accuracy of some of the data used in the analysis
77
Despite this the key finding in relation to future funding needs are clearly identified
Framework for Highway Asset Management
Benefits: The report establishes a rational basis for the evaluation of funding needs
for highway structure maintenance in Surrey.
Contact Details:
Graham Cole, Structures Group Manager, Surrey County Council
T: 020-8541-7317 E: [email protected]
78
Framework for Highway Asset Management
C9 Optimisation: Transport for London’s Maintenance Funding
Model
Framework: This project illustrates the use of condition data to identify and
quantify performance gaps (in this instance a backlog of maintenance works) and
the development of a model to aid decision making and to thus optimise resource
allocation.
Purpose: TfL and the London Boroughs have completed condition assessments for
all London’s principal roads and have developed a co-ordinated programme to clear
the road maintenance backlog using TfL’s Asset and Inventory Management (AIMS)
system. A model has been developed as part of AIMS to target funding where it is
needed over time and on an equitable basis.
Scope: TfL utilise United Kingdom Pavement Management System (UKPMS). UKPMS
is used by Highway Authorities to obtain condition index (CI) ratings of the
carriageways and footways. The condition of the carriageways and footways is rated
from 0 to 100. The higher the indicator, the worse the condition of the road.
Roads with CI ratings of 70 and above are in poor condition, with structural
degradation that may cause a safety hazard to road users. The percentage of
carriageway with CI ratings of 70+ is the National best value performance indicator
(BVPI) and the carriageways with CI ratings of 70+ can be considered to be the
backlog. Condition information enables prioritisation of spend on maintenance to
take place.
Model
The model evaluates the following:
If the level of funding is not adequate then the backlog will increase as will
the pressure on revenue maintenance funding.
Treating the roads with a condition index of 50-70 is the most economical
way of maintaining the road network.
79
Assumptions
Framework for Highway Asset Management
The model utilises UKPMS road condition survey data and treatment
recommendations. The costs are the current non-discounted average rates
for carriageways and footways, including TM, design, supervision and
premium time allowances.
A 15-year life cycle of the carriageways and footways.
Further development
Benefits
Contact:
Dana Skelley, Chief Engineer, Transport for London, Street Management Services
T: 020 7941 7061 E: [email protected]
80
Framework for Highway Asset Management
C10 Performance Gaps: West Sussex’s Road Safety Funding
Effectiveness
Purpose: The new national (and local) road safety targets set in 2000 required a
reduction of 40% in numbers of KSI by 2010 compared with the average for 1994-98.
The project was seeking to determine the appropriate level and distribution of
investment required in a range of different programmes to meet the 2010 targets
with a degree of confidence.
Scope: The performance of existing scheme types was assessed from historic data
on scheme costs and benefits (i.e. terms of casualty reduction). Information on
existing levels of budget provision, programme content and potential additional
funding was collated and analysed in a spreadsheet, together with a gap analysis
model linked to a forecast of casualty reduction outcomes.
Progress: The first iteration was completed in 2003 to support the general
performance review of road safety and bidding for supplementary funding. In 2004
the analysis was refined with more data to show the effect of more or less
additional resources.
The initial work showed that trend based forecasting combined with the analysis of
the relative benefits derived from each type of programme enabled options for
influencing the desired outcome to be modelled. For example, programme type A
has a higher benefit/cost ratio than type B, so transferring investment from B to A
improves the outcomes for casualty reduction.
Optimise the appropriate levels of spend for each programme type whilst
demonstrating the overall outcome for forecast casualty reduction.
Enable flexible analysis to show the effects of modifying rates of investment
in connection with other asset management priorities.
Provide a basis for arguing the case when bidding for additional funding and
determination of programme priorities.
Help define more explicit links between investment levels of services and
outcomes.
81
Cost/benefits: This is an inherent part of the project so, for example, the benefit
Framework for Highway Asset Management
is in the enabling of better outcomes for the same level of overall investment. It is
estimated that an outcome improvement of up to 20% can be achieved using this
methodology within an asset management framework.
Contact Details:
Rob Salmon
T: 01243-777504 E: [email protected]
82
Framework for Highway Asset Management
C11 Valuation: Northern Ireland Road Service’s Valuation
Framework: The Northern Ireland Road Service are one of the first authorities
within the UK to tackle the valuation of their assets. Their experience illustrates
that this is not an easy task and that a number of iterations may be required before
an acceptable set of accounts are produced.
Progress: The first infrastructure valuation was produced for the Agency Annual
Accounts for the year 1998/99 however, difficulties with the process and the
underlying assumptions used to produce the valuation led to the Northern Ireland
Audit Office disclaiming the accounts in 1999/2000. By the year 2002/03 many
issues were resolved and a clear audit opinion obtained. The infrastructure
valuation has a very significant impact on the Agency’s Accounts and the
Department’s Resource Accounts because of its scale:
Gross Value £m
Trunk Roads 3,941
Non Trunk Roads 7,508
Footways 269
Land 7,992
Structures 932
Special Features 158
Communications 18
Total 20,878
Roads Service considers that the reliability of the valuation is dependant on the
quality of data captured from operational systems, very high-level quality assurance
standards and a project planning methodology.
However, the outputs of the depreciation figures that have the greatest impact on
the Agency’s budgets still depend on unrepeatable and unpredictable road condition
83
survey techniques. Depreciation on the trunk roads is based on the output of the
Framework for Highway Asset Management
deflectograph surveys and that on the non-trunk roads on the output from the
Coarse Visual Inspection regime.
Roads Service is content to continue to rely on its operational systems and its
valuation model and has no plans to convert to an asset management approach.
Copies of the annual report and accounts for 2002/03 can be downloaded from:
http://www.roadsni.gov.uk/Publications/corp_docs/AnnualReport0203.pdf
Contact Details:
Jean McKay Financial Accountant
T: 028 8676 6980
E: [email protected]
84
Framework for Highway Asset Management
C12 Service Delivery: Rotherham’s Integrated Inspection Regime
Purpose: The purpose of the project was to improve the efficiency of highway
inspection at the same time improving the data available to support decisions on
maintenance works. It resulted from concerns over the quality of early CVI data
obtained from contracted surveys.
Progress: The new regime was implemented in August 2001 and proved to be very
flexible in accommodating ad hoc inspections resulting from reports because of the
limited geographical area covered by each inspector. The Council in 2003 developed
its community strategy for service delivery through the creation of Streetpride.
Integrated inspections are still undertaken but to accommodate the need for the
inspectors to spend more of their time interacting with local groups the task of CVI
inspection is now undertaken by two dedicated inspection staff. Further progress is
being made in the use of hand held PCs with the acquisition of iPAQs for all
inspectors.
Contact Details:
Robert Stock
Street-pride Network Principal Engineer - Network Management Group
T: 01709 822928 E: [email protected]
85
86
Framework for Highway Asset Management