Temp3 Elevating System
Temp3 Elevating System
3.1 Introduction
Elevating system is the group of units and components contributing in jacking the whole jack-up
unit up (to the operation height or preload height) and down (to the afloat / transit mode on water
surface).
3.2 Types
1. Pin & Yoke: The most basic type of elevating system, which allows for hull positioning
only at discrete leg positions. (Figure 1)
2. Rack & Pinion: This is the type which the majority of Jack up units in use today are
equipped with for continuous jacking operations.(Figure 2)
There are two basic jacking systems:
1. Floating: uses relatively soft pads to try to equalize chord loads. Floating jacking system
is one which is mounted to the jack house via flexible upper and lower shock pads. Under
environmental loading such a flexible system rotates and the guides come into contact with
legs and resist a considerable proportion of the leg bending moment.(Figure 4)
2. Fixed system: allows for unequal chord loading which is rigidly mounted to the jack house
and hence to the hull , ( welded to the hull )
There are two types of power sources for Fixed Jacking Systems:
i. Electric
ii. Hydraulic.
Both systems have the ability to equalize chord loads within each leg:
• Hydraulic-powered jacking system achieves this by maintaining the same pressure to each
elevating unit within a leg. Care must be taken, however, this can be a challenge because
piping lengths, bends, and other issues can cause a loss.
• Electric- powered jacking system, the speed/load characteristics of the electric induction
motors cause jacking motor speed changes resulting from pinion loads, such that if jacking
for a sufficiently long time, the loads on any one leg tend to equalize for all chords of that
leg.
Figure 1 Pin & Yoke
Figure 2 Rack & Pinion
Figure 5 Guides
3.6 Operations
1) Jacking up
A mat unit will jack the mat to the seabed in accordance with the ballasting procedure. Once the
mat has been lowered to the seabed, the hull will be jacked out of the water. The unit then
proceeds to Preload Operations (see related title below). All Independent leg units must perform
Preload Operations before they can jack to the design air gap. Most independent leg Units do not
have the capacity to elevate the Unit while the preload weight is on board. For these Units, the
next step is to jack the hull out of the water to a small air gap that just clears the wave crest
height. This air gap should be no more than five (5) feet. Once they reach this position, the Unit
may proceed with Preload Operations.
Some of the newer Independent Leg Units do have elevating systems capable of lifting the entire
weight of the hull with full preload weight. For these Units, preload is loaded on board while the
hull is still in the water. Once full preload is onboard, the Unit is slowly jacked out of the water
until the preload air gap is reached, no more than 5 feet.
3.7 Selected Topics on Sensitivities of Jack Ups related to Legs, Spud cans
& Elevating System
Jacking on existing footprints
Care must be taken when positioning a new jack up rig at a site previously occupied by another
jack up because of the tendency of the spud cans of the new rig to slip into the spud cans holes or
“foot prints” left on the sea floor by the previous rig. If there is an overlap of a spud can over an
old spud can hole, there is tendency for the spud can not to penetrate straight into the soil, but
instead to slip into the old spud can hole. This movement of a spud can, without a corresponding
movement of all the other spud cans in the same direction, will impose a bending moment on the
legs. This bending moment can be quite severe and may damage the leg in the preloading or
jacking up process or it may reduce the allowable storm environmental load of the rig due to the
resulting bend of the leg. (Figure 15 Effect of jacking on existing footprints)
When selecting a rig for a platform, it is always best to choose a rig with the same leg spacing as
a rig that previously drilled at the platform. However, the effect of previous spud can holes can
be mitigated if the new rig is positioned so that the centers of its spud cans are positioned either at
the center of the holes left by the previous rig or about 1.5 spud can diameters away for the edge
of the holes left by the previous rig.
If the rig selected for the platform does not have the same leg spacing as a rig previously at the
platform and it is not possible to position the new rig so that its legs either are centered over old
holes or 1.5 diameters away from old holes while still reaching all of the required drilling positions,
there are two techniques which can be used to minimize the effects of old holes. These techniques
are “Reaming” and “Swiss Cheesing”:
• “Reaming” is a technique by which the leg or legs are sequentially raising and lowering
the spud can in the hole left by the previous rig in an attempt to wear away the side of the
hole, thereby elongating the hole and creating a new hole center location at the spacing of
the legs of the new rig.
• “Swiss Cheesing” is a method in which a number of large diameter holes (24 to 30 inch
diameter) are drilled at the side of an existing can hole in order to degrade the strength of
soil at the side of the can hole, effectively enlarging the hole.
After all precautions have been taken to minimize the effect of previous can holes, care should be
taken in preloading and elevating the new jack up. The following should be observed:
a) The relative position of the rig to the platform should be monitored as a movement of a leg
into a previous can hole may cause an associated movement of the hull.
b) If the rig is of the type that exhibits visible deformation before failure, the Rack Phase
Differential (RPD) of the legsshould be monitored, as this is a good indication of an
external bending moment applied to a leg.
c) The noises made by the legs rubbing on the leg guides should be monitored, as an increase
in guide noise can be anindication of increased guide forces caused by an external bending
moment applied to a leg.
Figure 15 Effect of jacking on existing footprints
A preload that fails to achieve a punch through that occurs later during a storm spells potential
catastrophe. (Figure 17 Catastrophic Punch Through)
Figure 17 Catastrophic Punch Through
Jack Ups of all design types experience punch throughs and their resulting damages to braces,
chords and jacking units. The accidental loading resulting from a punch through can lead to several
types of leg damage including buckling of the braces, buckling or shearing of the chord, punching
shear and joint damage (Figure 18). The extent of possible damage is dependent on the magnitude
of the punch through and, more importantly, on the actions taken before, during, and immediately
after the punch through.
Punch through is an extreme event; therefore, proper management of this event is necessary.
Modern rigs with a better guide design along with a proper punch through management system,
can minimize some of the risks.