Plant Layout Design
Plant Layout Design
The plant layout designer must develop layout documents during the
conceptual and study phases of a project. The skills needed include:
∙Common sense and the ability to reason.
∙Knowledge of what a particular plant is designed to do.
3.Principal Functions
The principal functions of the plant layout designer include the conceptual and
preliminary development of process unit plot plans , sometimes referred to as
equipment arrangements ; the routing of major above and below-grade piping
systems ; and the layout of equipment and its associated infrastructure. Plot
plans show the positions of major units and equipment within units and their
associated infrastructure. Creating a well-designed facility involves meeting
all client specifications and local government codes and regulations and
adhering to design engineering practices with the planning plot plan as a basis
, the following functions are a standard part of the plant layout designer’s
activities :
These activities must be closely coordinated all the plant design and
construction participant volved in the engineering and construction phase
project to reduce costly rework and enable the layout designer to generate the
optimum design schedule.
Although there is a vast amount of input data throughout the life of a project ,
the data basically follow three distinct categories :
∙Project design data – Is supplied by the client or project engineering.
∙Vendor data – Pertains to equipment and specialty bulk items.
∙Internally generated engineering data.
These are discussed in the following sections.
Project design data This includes the geographic location of the plant ; its
proximity to roads , railways and waterways ; local codes and regulations .
Topography ; and climatic conditions. The project design data also specifies
whether the project is within an existing facility or is a new site. This
information is generally required during the project’s plot plan development
phase.
Vendor data All purchased equipment and specially bulk items (e.g. , pumps ,
compressors , air coolers , furnaces , control and safety valves , level
instruments , strainers , and silencers) require preliminary vendor drawings for
the development of piping layouts . Final certified drawings are usually not
required until the detail phase.
Internally generated engineering data This data is typically generated by the
supporting disciplines within the designer’s organization. An example of such
information is shown in Fig.LPP 1. This information is eventually superseded
by certified vendor drawings but is of sufficient quality and definition to use
during the study phase of the project.
The major activities of the plant layout designer to achieve an optimum plant
configuration taken place during the study phase of a project. Although project
schedules often dictate variations in this approach, it is intended to be an
optimum condition for the most effective use of staff time. The study phase
can make or break a project. Working out of sequence is acceptable within
reason, but if it is overdone, a project will never recover during the detail
phase. The ideal situation for speed and quality is to do the job right the first
time.
11.Use of Space
The effective use of plant real estate provides plant operations and
maintenance personnel with the maximum amount of room in a plant. Which
in most cases can be very congested Fig.LPP 6 shows some typical misuses of
valuable real estate.
For example, the steam trap assembly shown on the left is commonly designed
in the engineering office. This arrangement for a thermodynamic steam trap is
spread out over an area of approximately 27 in (690 mm) in length. Although
this area may not seem excessive for one trap assembly, it can be avoided
completely by installing the trap and strainer in the vertical leg of the piping,
as shown on the right. An additional drain may be required, but this
arrangement should be considered as a space-saving alternative. The steam
tracing manifold in the left-hand sketch is another common engineering office
approach that wastes valuable plant space. If a vertical manifold that is
supported from the column is used, additional space is available for other
piping systems or operator access.
The client must live with the plant long after the engineering and construction
phases are over. The operators will be walking through the facility each day
and will be continually reminded of who took the time and effort to plan the
project thoroughly, and they will keep that in mind when the next expansion
planned.