11analysis of Shield Tunnel
11analysis of Shield Tunnel
11analysis of Shield Tunnel
SUMMARY
This paper proposes a two-dimensional finite element model for the analysis of shield tunnels by taking
into account the construction process which is divided into four stages. The soil is assumed to behave as an
elasto-plastic medium whereas the shield is simulated by beam–joint discontinuous model in which curved
beam elements and joint elements are used to model the segments and joints, respectively. As grout is
usually injected to fill the gap between the lining and the soil, the property parameters of the grout are
chosen in such a way that they can reflect the state of the grout at each stage. Furthermore, the contact
condition between the soil and lining will change with the construction stage, and therefore, different stress-
releasing coefficients are used to account for the changes. To assess the accuracy that can be attained by the
method in solving practical problems, the shield tunnelling in the No. 7 Subway Line Project in Osaka,
Japan, is used as a case history for our study. The numerical results are compared with those measured in
the field. The results presented in the paper show that the proposed numerical procedure can be used to
effectively estimate the deformation, stresses and moments experienced by the surrounding soils and the
concrete lining segments. The analysis and method presented in this paper can be considered to be useful
for other subway construction projects involving shield tunnelling in soft soils. Copyright # 2004 John
Wiley & Sons, Ltd.
KEY WORDS: subway construction; shield tunnelling; soil–structure interaction; numerical procedure;
finite element method; ground settlement; lining; soft soils
1. INTRODUCTION
Since 1950s, urban developments in many cities have experienced continuous growth and
expansion. Because of the large populations and shortage of land resources, these cities have
always had a strong demand for efficient, economic and environmental friendly urban civil
infrastructure systems to accommodate the daily and routine travels of thousands and millions
of commuters. The subway system is an obvious solution to meet the demand. To minimize the
n
Correspondence to: Dr. Q. Z. Q. Yue, Department of Civil Engineering, The University of Hong Kong, Pokfulam
Road, Hong Kong, China.
y
E-mail: [email protected]
Contract/grant sponsor: Research Grant Council of Hong Kong SAR Government
Contract/grant sponsor: Hong Kong Jockey Club Charities Trust
impact on the existing traffic during construction, tunnelling is usually adopted for the
construction of the subway. Because of its efficiency and safety, shield tunnelling is one of the
most popular tunnelling methods for the construction of subway tunnels in soft soil ground.
Over the last 30 years, the shield tunnelling method has experienced continuous improvement
and development. New shield tunnelling methods including the earth pressure balanced shield,
the slurry shield, the simultaneous backfill grouting as well as some improved grouting materials
have been introduced and developed in recent years [1].
Shield tunnelling will inevitably induce ground deformation and the surrounding soils will
also act on the shield lining segments. Quantitative and accurate prediction of such soil and
structure interaction will be of significant importance in many aspects including lining segment
design, construction safety, ground settlements, potential damage to existing structures and
facilities, and operation of the subway system.
Peck [2] developed an empirical method for the ground settlement associated with tunnelling
in soft soils by assuming the settlement trough to be a Gaussian distribution curve. The
actual ground settlement is predicted based on the estimation of the ground loss ratio. This
method was used and improved by many engineers and researchers such as Clough and
Schmidt [3] and Rowe et al. [4]. Recently, Schmidt [5] has proposed the semi-empirical
error function method for the estimation and prediction of ground settlement. Though these
empirical or semi-empirical methods are useful in the evaluation of the ground settlements
caused by shield tunnelling construction, they must be applied with caution as they may not be
applicable to situations significantly different from the cases on which they are based on
Wang [6].
Another important design parameter is the load acting on the lining. Such load can be
taken to be either the sum of the overburden pressure and water pressure or that determined
using Terzaghi’s formula, Schulze–Duddeck method or other empirical methods. It is noted
that such load only considers the final state that is after the completion of the shield tunnelling.
To provide a better simulation of the interaction between the lining and soil, beam–
spring models, in which the lining and soil are modelled by beam and spring, respectively,
can be adopted. As shield tunnel lining is composed of several concrete segments, a number of
researchers and engineers had also taken into consideration the effects of the segment ring
joints [7, 8] in their studies. Lee and Ge [9] suggested an equivalent method to determine
the correction factor for approximating a jointed shield-driven tunnel lining as a continuous
ring structure under a plane strain condition. The present literature review has revealed that
there are three widely accepted methods for modelling the effects of shield segment joints
[10, 11].
Furthermore, shield tunnelling usually adopts staged construction and supporting techniques.
Consequently, the responses such as soil displacements and lining forces induced by the
construction will be different at different stages. It is believed that an optimal construction
process can improve the safety and reduce the disturbance to the surrounding soils. Hence, it
becomes very important to take into account the actual construction process in the shield
tunnelling design [12, 13]. Due to the complex nature of the problems, one may have to resort to
numerical approach for analysing the problems. It is well known that the finite element method
is a powerful tool for the analysis of soil–structure interaction in geomechanics and it has been
applied to tunnel excavations by taking into account the construction process, the different soil
layers, complex geometries, various loading conditions and soil–lining interfaces [14]. Though
shield tunnelling, strictly speaking, is a three-dimensional and time-dependent soil–structure
Copyright # 2004 John Wiley & Sons, Ltd. Int. J. Numer. Anal. Meth. Geomech. 2004; 28:57–91
ANALYSIS OF SHIELD TUNNEL 59
interaction problem [15–18], many engineers and researchers have demonstrated that the two-
dimensional finite element models can still give a fairly accurate prediction on the behaviour of
the tunnel [12, 19, 20]. Benmebarek et al. [21] proposed two methods for taking into account the
three-dimensional effects in a two-dimensional model. Further assessment of two-dimensional
models in analysing shield tunnelling was reported in a recent publication by Negro and de
Queiroz [22].
In this paper, we propose a two-dimensional finite element method for analysing shield
tunnels during construction. The construction of each lining segment of a shield tunnel is
divided into four stages. To model the discontinuous displacements between segments, a beam–
joint discontinuous model is adopted for simulating the shield action. Moreover, the changes
from fluid and solid states of the backfill grout at different stages are also considered.
Furthermore, stress-releasing coefficients are used to account for the different contact conditions
between the soil and external lining surface. These coefficients are estimated based on field
measured settlements and professional experiences. The numerical results obtained by the
present model are compared with those measured during the construction of the No. 7 Subway
Line Project in Osaka, Japan. The comparison shows that the proposed model can be used to
estimate the deformation, stresses and moments experienced by the surrounding soils and the
concrete lining segments during tunnelling.
2. BACKGROUND
During shield tunnelling, the shield will advance segment by segment with a balanced soil
pressure that supports the soil. After cutting through a length of a segment, the lining will
then be installed. The lining is essentially an assembly of concrete segments linked by bolts
which joints will be covered with waterproof flexible plates. Before the shield tail is
detached, grout will be injected into the gap between the surrounding soil and the lining.
After grouting, the shield will move forward. As the grout hardens and consolidates, the
surrounding soil will deform and induce pressures on the lining. Consequently, the ground will
settle gradually as well. All movements will cease only when a state of equilibrium state is
reached.
Field observations have confirmed that the ground movements and the earth pressure on the
lining segments have developed according to the construction process of the shield tunnelling
[1, 21, 23–25]. Factors affecting ground movements due to shield tunnelling have been
summarized in recent publications by Nomoto et al. [25] and Hashimoto et al. [1, 26]. The
construction process is one of the most important factors. Closer study of the field observations
has revealed that the construction process for a segment can be divided into four stages below:
Stage 1}Balanced cutting and shield supporting. This stage includes face cutting and
shield advancing. The existing soil pressure in the cutting face is balanced by pressure
from the machine behind the cutter. Consequently, the stress changes due to the cutting and
the balancing pressure will not result in significant soil movement. Furthermore, the
surrounding soil outside the shield will not be able to release its stress due to the rigid
support of the shield. However, one has to consider the possible disturbance on the surrounding
soil due to over-cutting, snaking and friction between the shield and the soil when the shield
advances.
Copyright # 2004 John Wiley & Sons, Ltd. Int. J. Numer. Anal. Meth. Geomech. 2004; 28:57–91
60 W. Q. DING ET AL.
Stage 2}Backfill grouting. The second stage is to install the lining segments and to backfill the
gap at the shield tail with grout. The lining will form a circular ring within the shield tail cover
plate. Once the shield moves forward, a gap between the soil and the lining segment will be
created. A grout must be simultaneously injected to backfill the gap space. The amount of grout
is usually equal to 1.2–1.3 times of the gap volume and the grout pressure is between 0.2 and
0:4 MPa: Such backfill grouting has three functions:
* preventing soil deformation immediately after the shield tail is detached,
* stabilizing lining segments, and
* improving tunnel water-proof performance.
The soil will start to interact with the lining although the grout is still in a fluid state. It is
noted that this backfill grouting serves a controlling measure to prevent soil deformation.
Excessive grout volume and pressure may lead to soil heave around the shield tail and must be
avoided.
Stage 3}Grout hardening. This stage is a transient stage. The grout will harden and consolidate,
and the soil deformation will also increase with time though its rate decreases. The lining
segments and ground soil interaction will increase with time until an equilibrium state is
reached. It is, therefore, necessary to assess the effects of the grout hardening and pressure
distribution on the response of the lining structure at this stage.
Stage 4}Hardened grout. In the final stage, the grout becomes hardened and gains its full
stiffness and strength. The settlement will almost cease to increase.
In this paper, a two-dimensional finite element model is developed for modelling shield
tunnelling process. As such process is a very complicated one, exact simulation is almost
impossible. Therefore, the model only tries to take into account major factors, namely the
complex properties of the soil materials, the snaking of the shield direction, the volume loss, the
grout properties and pressure, the joints of lining segment, and the construction process.
Following the standard finite element procedures, one has to obtain the initial stress before the
construction simulation can be carried out. The initial stresses at any point i is calculated by the
following equations:
P
sy0 ¼ gj Hj
ð1Þ
sx0 ¼ K0 ðsy0 Pw Þ þ Pw
where sy0 and sx0 are the vertical and horizontal initial earth stresses, respectively, gj is the unit
weight of the jth earth stratum above the point; Hj is the corresponding thickness; K0 is the
lateral earth pressure coefficient, and Pw is the water pressure at the point.
As pointed out in Section 2, the construction of a tunnel segment can be divided into
four stages. As the soils behave non-linearly during the construction, an elasto-plastic
model is adopted to model the soil. Similarly, the lining segment and the joints between
lining segment are modelled by adopting appropriate curved members. Different models
are adopted to simulate the grout as its behaviour is very much different at the various
Copyright # 2004 John Wiley & Sons, Ltd. Int. J. Numer. Anal. Meth. Geomech. 2004; 28:57–91
ANALYSIS OF SHIELD TUNNEL 61
Calculate initial or current earth stress and stress releasing equivalent nodal forces {∆F }rea
[K ]ini + ∑ [∆K ζ ]
j
Form element and global stiffness matrix:
ζ =1
j=j+1
Solve FEM equation, gain: ∆δ { jk
}
k=k+1
Nonlinear equivalent
Calculate incremental strain and stress: ∆ε { jk
}{
, ∆σ },
jk
{∆F } jk
non
Figure 1. Flow chart of the finite element simulation for shield tunnelling.
Copyright # 2004 John Wiley & Sons, Ltd. Int. J. Numer. Anal. Meth. Geomech. 2004; 28:57–91
62 W. Q. DING ET AL.
can be expressed as
!
X
j
½Kini þ ½DK z fDd jk g ¼ a j fDF grea þ fDF j gadd þ fDF jk gnon ð2Þ
B¼1
where j ¼ 1–4 and k ¼ 1–N ; N is the number of non-linear iterative steps; ½Kini is the initial
stiffness matrix of soil ground and structure (if it exists) before excavation; ½DK z is the
increment or decrement stiffness matrix of the soil ground excavated and the supporting
structure installed or removed at the construction stage z; fDF grea is the vector of the stress
releasing equivalent nodal forces due to the stress state of the previous construction process
acting along the currently excavated boundary. For one construction (excavation) process, it is
due to the initial stress state; fDF j gadd is the vector of newly added nodal load at construction
stage j; fDF jk gnon is the vector of P
current
R incremental equivalent excessive nodal forces caused
by non-linear stress. fDF jk gnon ¼ e Ve fBgT fDsa g dV where fBg is strain matrix and fDsa g is
the incremental non-linear stress vector; fDd jk g is the vector of incremental nodal displacement
at the stage j and iterative step k; a j is the stress releasing coefficient at construction stage j:
The iteration for each stage will cease after 10 iterative steps, that is N ¼ 10; or the prescribed
iterative precision is achieved. In the analysis, the iterative precision is chosen to be
Dse Dsp
jk jk
50:00001 ð3aÞ
sjðk1Þ Dspjk
where Dsejk and Dspjk are the elements of the vectors of incremental elastic stress matrix fDsejk g
and plastic stress matrix fDspjk g at the stage j and the iterative step k; respectively, and sjðk1Þ is
the corresponding total stress at the stage j and the iterative step k 1: Dsejk and Dspjk can be
estimated using the following equations:
fDsejk g ¼ ½D½BfDd jk g ð3bÞ
X
i X
N
fei g ¼ fe0 g þ fDe jk g
j¼1 k¼1
X
i X
N
fsi g ¼ fs0 g þ fDs jk g ð4Þ
j¼1 k¼1
where fd0 g and fe0 g are the initial displacement and strain respectively, they are usually set to
zero. fs0 g is the initial earth stress; fDe jk g and fDs jk g are the vectors of the incremental strain
and stress releasing step (construction stage) j and the iterative step k; respectively.
Furthermore, the lining internal forces (hoop force, shear force and bending moment) can
then be determined from the displacements.
Copyright # 2004 John Wiley & Sons, Ltd. Int. J. Numer. Anal. Meth. Geomech. 2004; 28:57–91
ANALYSIS OF SHIELD TUNNEL 63
Extensive monitoring was carried out during the construction of a tunnel of the Osaka Subway
Line. The results are readily available. This case history is used to assess the accuracy that can be
achieved by the present approach. For completeness, a brief of the relevant information will be
given and more detailed information can be found in the report prepared by the Japanese
Research Society of Construction Maintenance Techniques [27].
4.1. General
Figure 2 shows the general arrangement and longitudinal profile of the No. 7 Subway Line
Project in Osaka, Japan. The subway is between the Morinomiya Station and the Osaka
Business Park Station. Its east bound tunnel line is about 970:4 m long. Its west bound tunnel
line is about 974:5 m long. The tunnels are about 16–30 m below the soil ground surface. The
lining is of reinforced concrete and each segment is 1:2 m wide and 280 mm thick, and has the
outer diameter 5:3 m: Two 5:44 m in diameter earth pressure balanced shield machines with
synchronous grouting technique were used to construct the tunnels. In this paper, we will focus
on Section A of the west bound tunnel.
Figure 2. General layout of the Osaka No. 7 Subway Line: (a) line plan; and (b) tunnel profile.
Copyright # 2004 John Wiley & Sons, Ltd. Int. J. Numer. Anal. Meth. Geomech. 2004; 28:57–91
64 W. Q. DING ET AL.
0 50 Standard Penetration
Soil layer: Ac1 Test (SPT) value
Ac2
As1 -10
As2
Tunnel
-20
Ac3
As3 -30
Ac4
-40
Depth (m)
Figure 3. The soil layer of Section A.
and a clayey layer, AC3. The thicknesses of these layers are about 11 and 5 m; respectively.
Below the AC3 stratum, there are a sandy stratum, AS4, and a clayey stratum, AC4. The
permanent ground water level is at about 3 m below the ground surface. The standard
penetration test results revealed that the three upper clayey soil strata (AC1–AC3) had a SPT N -
values from 2.5 to 11.8 whereas the three sandy soil strata (AS1–AS3) had SPT N -values ranging
from 34 to 43.05 (Figure 3 and Table I).
Copyright # 2004 John Wiley & Sons, Ltd. Int. J. Numer. Anal. Meth. Geomech. 2004; 28:57–91
ANALYSIS OF SHIELD TUNNEL 65
depth (m) 0 y
S1 -0.25
S1 ~ S5 Measuring points
S2 -10.8
S3 -14.8
S4 -15.8
S5 -16.3 180°
Section A-A
Figure 4. The locations of the settlement gauges.
and lining structural performance. Figure 4 shows the arrangement of the five settlement
monitoring points in the soil right above the west bound tunnel. Figure 5(a) shows the
arrangement of eight earth pressure cells installed to measure the soil pressure acting on the
outer surface of the concrete lining segments. Gauges are installed to measure moment as well as
hoop forces. Their locations are shown in Figure 5(b) and 5(c), respectively.
K0 ¼ 1 sin j0 ð5cÞ
Copyright # 2004 John Wiley & Sons, Ltd. Int. J. Numer. Anal. Meth. Geomech. 2004; 28:57–91
66 W. Q. DING ET AL.
EP3(180°) 180°
EP4(224°) EP2(131°)
270° 90°
EP5(272°) EP1(90°)
EP8(58°)
EP6(310°)
EP7(355°) 0°
(a)
M04(188°) 180°
M05(214°) M03(151°)
M06(261°) M02(116°)
270° 90°
M07(288°) M01(75°)
M08(323°) M10(37°)
0° M09(5°)
(b)
AF04(188˚) 180˚
AF05(214˚) AF03(151˚)
AF02(116˚)
AF06(261˚)
270˚ 90˚
AF07(288˚) AF01(75˚)
AF08(323˚) AF10(37˚)
0° AF09(5˚)
(c)
Figure 5. The locations of: (a) earth pressure cells; (b) moment gauges; and (c) hoop force gauges.
K0
m¼ ð5dÞ
1 þ K0
where j is the internal friction angle, j0 is effective internal friction angle, K0 is the lateral
pressure coefficient, N is the number of standard penetration test (SPT) value.
Copyright # 2004 John Wiley & Sons, Ltd. Int. J. Numer. Anal. Meth. Geomech. 2004; 28:57–91
ANALYSIS OF SHIELD TUNNEL 67
joint
segment
Copyright # 2004 John Wiley & Sons, Ltd. Int. J. Numer. Anal. Meth. Geomech. 2004; 28:57–91
68 W. Q. DING ET AL.
Joint
n Beam
2 1
s
Figure 7. Beam–joint discontinuous model.
depends on the grout deformation modulus whereas the tangential stiffness Ks is related to the
sliding feature of the contact.
If the normal contact stress sn is compressive, i.e. it has positive value, one can assume that
the yield criterion of the contact element will follow the Mohr–Coulomb function, that is
f ¼ jts j ðcj þ sn tgjj Þ ð7Þ
where cj and jj are, respectively, the cohesion and internal friction angle of the contact element,
ts is the total shear stress on the contact element.
One can show readily that the elastic property matrix ½D and plastic property matrix ½Dp for
the ideal plastic and plane strain situation can be expressed as
" #
Ks 0
½D ¼ ð8aÞ
0 Kn
" 2 #
1 Ks Ks S1
½Dp ¼ ð8bÞ
S0 Ks S1 S12
where S0 ¼ Ks þ Kn tg2 jj ; S1 ¼ Kn tgjj :
The grout initially is in fluid state and it hardens gradually. Therefore, different parameters
should be used to simulate the behaviour of the grout. A brief description is given below to
explain how to adopt different grout parameters at the different construction stages.
In Stage 2, the grout is in the fluid state, and therefore, the tangential contact stiffness Ks is
close to zero. Although the liquid is incompressible, the trapped air voids can be compressed.
Assuming 15% of the total grout volume is occupied by air voids, the relation between the
grouting pressure and volumetric strain can be expressed as
Pa
ev ¼ 0:15 1 ð9Þ
Pa þ Pg
where Pa and Pg are the atmospheric pressure and the grouting pressure, respectively. In the
numerical calculations, we assumed Pa ¼ 0:1 MPa and Pg ¼ 0:15 MPa: The value of the normal
contact stiffness Kn can be estimated using the equation below
Pg
Kn ¼ ð10Þ
ev t 0
where t0 is the thickness of shield tail void and it equals to 0:07 m for the present shield tunnel.
Copyright # 2004 John Wiley & Sons, Ltd. Int. J. Numer. Anal. Meth. Geomech. 2004; 28:57–91
ANALYSIS OF SHIELD TUNNEL 69
In Stages 3 and 4, the grout hardens and its stiffness increases gradually. The tangential
contact stiffness is given as:
Kn
Ks ¼ ð11Þ
2ð1 þ nÞ
where n ¼ 0:3: The normal stiffness Kn can be estimated by using the following empirical
relation [12]:
E 150qu
Kn ¼ ¼ ð12Þ
t t
where qu is the unconfined compressive strength of grout, t is the thickness of contact element.
In this study, qu are taken to be 0.2 and 3:0 MPa for Stages 3 and 4, respectively. The normal
and tangential stiffnesses adopted at various stages are given in Table II.
(b) Distribution of grout pressure. Two models of grout pressure distribution (Figure 8) are
considered in the analysis. The first model (GP-A) assumes that the grout pressure is uniform
and such model has the advantage of being simplicity, but, it may not be able to model the
decrease in pressure as the grout flows away from the grout hole. To overcome the above
180°
Grouting hole
217°
170° GP-A GP-B
232° 143°
242°
270° 95°
90°
303° θ
19°
0° Segment joint
Grouting pressure (kPa)
180
160
140
120
100
80
60
40
20
0 30 60 90 120 150 180 210 240 270 300 330 360
θ (degree)
Figure 8. Grout pressure models.
Copyright # 2004 John Wiley & Sons, Ltd. Int. J. Numer. Anal. Meth. Geomech. 2004; 28:57–91
70 W. Q. DING ET AL.
Section A of the Osaka No. 7 subway line is analysed in this paper and the results are compared
with the field measurement data documented in the report prepared by the Japanese Research
Society of Construction Maintenance Technique [27].
Copyright # 2004 John Wiley & Sons, Ltd. Int. J. Numer. Anal. Meth. Geomech. 2004; 28:57–91
ANALYSIS OF SHIELD TUNNEL 71
tabulated. They are the results before grouting and after the completion of the Stage 4 using the
uniform grout pressure models. The settlement at the crown point A is about 7 mm: The
horizontal displacement at the points C and D are about 2–3 mm: The heave at the bottom
point B is about 11 mm: These results have shown that the soil displacements can gain
substantial increases with the progress of the construction stages.
The computed settlements above the tunnel after completion of Stage 4 are compared to the
measured values in Figure 11. The results show that the computed settlements agree fairly well
with the measured ones.
Copyright # 2004 John Wiley & Sons, Ltd. Int. J. Numer. Anal. Meth. Geomech. 2004; 28:57–91
72 W. Q. DING ET AL.
C D
C D
(b)
Figure 10. Deformed meshes of around the tunnel: (a) before grouting; and (b) after completion of Stage 4.
the completion of Stage 4 are generally less than those measured values, which could cause an
unsafe design.
From Figure 13, it can be observed that the variations of the measured and the present FEM
predicted hoop forces with respect to the hoop angle y and the construction stages are basically
similar although there are some significant discrepancies at the measurement locations AF01
ðy ¼ 758Þ: Basically, the hoop forces increased as the construction stage progressed, which
cannot be predicted using the conventional method. Furthermore, the measured hoop forces are
not symmetric about the vertical centre (y ¼ 0 or 1808), while the predicted results are symmetric
about the vertical axis. The percentage relative differences between each set of the measured and
FEM predicted hoop forces are between 113 and 35%. A majority of the relative differences
are within 20%: Furthermore, the predicted results using the conventional method at the
Stage 4 have the lowest variations with respect to the hoop angle y:
Copyright # 2004 John Wiley & Sons, Ltd. Int. J. Numer. Anal. Meth. Geomech. 2004; 28:57–91
ANALYSIS OF SHIELD TUNNEL 73
Settlement (mm)
0
0 1 2 3 4 5 6 7
-2
-4
Measured value
-6
GP-A
-8
-10
-12
-14
Depth (m)
-16
-18
Figure 11. Variation of settlement with depth.
Copyright # 2004 John Wiley & Sons, Ltd. Int. J. Numer. Anal. Meth. Geomech. 2004; 28:57–91
74 W. Q. DING ET AL.
110
Stage 2 & measured Stage 2 & GP model A
Stage 3 & measured Stage 3 & GP model A
90 Stage 4 & measured Stage 4 & GP model A
Conventional design method Location of joints
70
Bending moment (kN.m)
50
30
10
-10
-30
-50
-70
0 30 60 90 120 150 180 210 240 270 300 330 360
θ (degree)
Figure 12. Variation of measured and predicted bending moments with hoop angle at the
completion of construction stages 2, 3 or 4.
900
Stage 2 & measured Stage 2 & GP model A
Stage 3 & measured Stage 3 & GP model A
800 Stage 4 & measured Stage 4 & GP model A
Conventional design method Location of joints
700
Lining ring hoop force (kN)
600
500
400
300
200
100
0 30 60 90 120 150 180 210 240 270 300 330 360
θ (degree)
Figure 13. Variation of measured and predicted hoop forces with hoop angle at the
completion of construction stages 2, 3 or 4.
From Figure 14, it is clear that the present FEM predicted earth pressure values are very close
to those measured results at the cell Nos. EP8 ðy ¼ 588Þ; EP1 ðy ¼ 908Þ and EP7 ðy ¼ 3558Þ and
are about two times greater than those measured results at the other cell Nos. EP2 to EP6.
Furthermore, the present FEM predicted result generally decreases as the hoop angle y increases
Copyright # 2004 John Wiley & Sons, Ltd. Int. J. Numer. Anal. Meth. Geomech. 2004; 28:57–91
ANALYSIS OF SHIELD TUNNEL 75
340
310
280
220
190
160
130
Measured Present method
100 Conventional Location of joints
70
40
0 30 60 90 120 150 180 210 240 270 300 330 360
θ (degree)
Figure 14. Variation of earth pressure after completion of Stage 4.
from 0 to 1808 and then increases as the hoop angle y increases from 180 to 3608; which is
considered to be reasonable. However, the results predicted with the conventional method have
four cycles of increasing and decreasing. The four cycles correspond to the hoop angle intervals
04y5908; 9084y51808; 18084y52708 and 27084y53608; which are evidently caused by the
basic assumptions associated with the semi-analytical formation of the conventional method
(see Appendix B). Moreover, the predicted results using the conventional method are close to
those predicted using the present FEM method. The predicted results do not have significant
differences.
From the above analysis and discussions, one can have the following general findings:
(a) The present method can be used to make a best prediction on the hoop forces and a
good prediction on the earth pressures and a reasonable prediction on the bending
moment. The predicted results can be used for a safe design for each of the three
construction stages.
(b) The in situ measurements have a best performance for the hoop forces, a good
performance for the earth pressure and a reasonable performance for the bending
moments. There seems a need to develop more reliable senses for in situ measurement of
the bending moment in the lining.
(c) The conventional method could give a reasonably good prediction on the hoop forces,
an adequate estimation on the earth pressure and an under-estimation on the bending
moment after the completion of the Stage 4. The use of this conventional method in
design estimation of the bending moment needs a great care.
(d) These results have also shown that the mechanical responses of the shield tunnel
construction at the construction stages can be predicted by the numerical procedure
presented above. It is noted that it is very important to select correct soil parameters in
the numerical prediction.
Copyright # 2004 John Wiley & Sons, Ltd. Int. J. Numer. Anal. Meth. Geomech. 2004; 28:57–91
76 W. Q. DING ET AL.
Table IV. The relative displacements at joints of lining segment at the completion
of construction stage No. 4.
y 198 958 1708 2328 2428 3038
2 2 2 2 2
GP-A Du ðmmÞ 1.91 10 2.19 10 1.60 10 1.79 10 1.91 10 2.13 102
4 4 4 5 5
Dv ðmmÞ 1.62 10 9.60 10 8.54 10 1.22 10 6.15 10 1.35 103
DW ð8Þ 8.83 106 1.12 105 9.51 106 3.05 107 3.87 106 5.08 106
GP-B Du ðmmÞ 1.80 102 2.12 102 1.53 102 1.72 102 1.84 102 2.03 102
4 4 4 5 5
Dv ðmmÞ 1.46 10 9.01 10 8.55 10 1.66 10 5.09 10 1.42 103
DW ð8Þ 9.31 106 1.23 105 1.06 105 1.23 107 4.62 106 4.81 106
Note: Du; Dv and DW are relative normal displacement, relative shearing displacement and relative rotational angular
displacement between two nodes of joint element, respectively.
340
310
GP-A GP-B
Normal earth pressure (kPa)
280
250
220
190
160
130
100
0 30 60 90 120 150 180 210 240 270 300 330 360
θ (degree)
Figure 15. Effect of grout pressure models: earth pressure.
Copyright # 2004 John Wiley & Sons, Ltd. Int. J. Numer. Anal. Meth. Geomech. 2004; 28:57–91
ANALYSIS OF SHIELD TUNNEL 77
100
80
GP-A GP-B
60
900
800 GP-A GP-B
Lining ring hoop force (kN)
700
600
500
400
300
200
100
0 30 60 90 120 150 180 210 240 270 300 330 360
θ (degree)
Figure 17. Effect of grout pressure models: hoop force.
Copyright # 2004 John Wiley & Sons, Ltd. Int. J. Numer. Anal. Meth. Geomech. 2004; 28:57–91
78 W. Q. DING ET AL.
(b) The two grout pressure models can produce very close results in the beam bending
moments although it is interesting to note that the GP-B model has slightly higher earth
pressure values around y ¼ 908; y ¼ 1808 or y ¼ 2708 (see Figure 16).
(c) The lining ring hoop forces predicted with the GP-A model is uniformly slightly (about
7%) greater than those predicted with the GP-B model over the entire hoop angle ð04
y53608Þ (see Figure 17).
6. CONCLUSIONS
Based on the main characteristics of the tunnel construction process, the properties of the grout
and the stiffness of the lining and its joints, we have presented a two-dimensional finite element
model for shield tunnels. In the analysing, we pay special attentions to the contact factors
between the soil and the lining structure. These factors include the gap closing, the grout
pressure distribution and hardening. Based on the analysis, we may have the following
conclusions:
* The results obtained by the present FEM method, in particular, the settlements, the earth
pressures and the hoop forces, are very close to the values measured on site. The measured
values are well within the ranges of the numerical results. Furthermore, although the
present predicted lining bending moment values are generally greater than those measured
on site, they can be used for a safe design. These findings have shown that the numerical
procedure presented in this paper is practical and reliable for evaluation, design and
displacement prediction for shield tunnel construction.
* The hardening of the grout materials with the process of shield tunnelling can be simulated
by varying parameters such as the stiffness, the internal friction angle and cohesion at
different construction stages.
* The two grouting pressure models give similar results for the displacements, moments and
forces. It may be concluded that the grouting pressure models do not have a significant
effect on the behaviour of the tunnelling in soil ground.
* Although the conventional method have been used for prediction of the lining bending
moment, hoop forces and earth pressures after the completion of the construction stages,
the predicted values could be lower and the method could not take into account many
complex factors and construction stages that the present FEM method can accommodate
in the design calculations.
* The above FEM analysis has further shown that numerical procedures can make adequate
predictions on the mechanical behaviour of complex soil–structure interaction system such
as shield tunnelling during and after construction. Such numerical predictions can enhance
the design and construction measures of geotechnical works in soft soils. It is noted that it
is also critical to select correct values for the mechanical parameters of soils in the
theoretical predictions. Good knowledge and experience of the local soft soil conditions
and properties are always assets in selection of the parameter values for prediction.
Additional experience on the selection of the soil parameters can be gained from the
comparisons between the predicted and measured mechanical responses that have been
presented in this paper.
Copyright # 2004 John Wiley & Sons, Ltd. Int. J. Numer. Anal. Meth. Geomech. 2004; 28:57–91
ANALYSIS OF SHIELD TUNNEL 79
As shown in Figure 7, the beam–joint discontinuous model uses several curved beam elements
for a segments and a joint element for a joint. Figure A1 depicts a curved beam element and
Figure A2 shows a joint element in the forms of a double node.
By using the Castigliano’s second theorem [12] we can establish the relation of the nodal
forces Fi ¼ fNi Qi Mi gT with the nodal displacements di ¼ fui vi Wi gT ði ¼ 1; 2Þ in a local co-
ordinate system ðn; sÞ: It can be shown readily that:
( ) " #( ) ( )
F1 K11 BK11 d1 d1
¼ ¼ ½K ðA1Þ
F2 BK11 K22 d2 d2
where ½K is the stiffness matrix and ½B is the correlative matrix between the two nodal forces of
the beam element.
Q2 v2
M2 2
N2 u2 2 P
M1 1
1
Q1 v1
β ϕ
N1 u1
z o′
o x
Figure A1. Nodal forces and displacements of curved beam model.
α2
γ
2
z 1
s
o x
α1
Figure A2. Double nodes of joint and nodal direction angles in global co-ordinates.
Copyright # 2004 John Wiley & Sons, Ltd. Int. J. Numer. Anal. Meth. Geomech. 2004; 28:57–91
80 W. Q. DING ET AL.
R R3
d111 ¼ ð0:5b þ 0:25 sin 2bÞ þ ð1:5b 2 sin b þ 0:25 sin 2bÞ ¼ d211 ðA5Þ
EA EI
R R3
d112 ¼ sin2 b þ ðcos b þ 0:5 sin2 b 1Þ ¼ d212 ðA6Þ
2EA EI
R2
d113 ¼ ðb sin bÞ ¼ d213 ðA7Þ
EI
R R3
d122 ¼ ð0:5b 0:25 sin 2bÞ þ ð0:5b 0:25 sin 2bÞ ¼ d222 ðA8Þ
EA EI
R2
d123 ¼ ðcos b 1Þ ¼ d223 ðA9Þ
EI
R
d133 ¼
b ¼ d233 ðA10Þ
EI
In Equations (A4)–(A10), E; A and I are the elastic modulus, cross-sectional area and moment
of inertia of the curved beam, respectively.
The local stiffness ½K can be assembled into the global stiffness ½KG in a global co-ordinate
system as follows:
½KG ¼ ½T ½K ½T T ðA11Þ
where ½T is a transformation matrix between the local co-ordinate system and the global
co-ordinate system; and ½T T is the transpose of the matrix ½T :
The discontinuity of the two adjacent segments is described by the following relative
displacements with three variables between the two nodes 1 and 2 in the local co-ordinate
system ðn; sÞ
Du ¼ u1 u2
Dv ¼ v1 v2 ðA12Þ
DW ¼ W1 W2
where s is defined as the direction of the bisecting angle between the two beams with a positive
direction inward to opening; n is the direction perpendicular to s with a positive direction as
counterclockwise. Accordingly, Du is the relative normal displacement of the joint along the n
Copyright # 2004 John Wiley & Sons, Ltd. Int. J. Numer. Anal. Meth. Geomech. 2004; 28:57–91
ANALYSIS OF SHIELD TUNNEL 81
k
kn
ks
Figure A3. The stiffness kn ; ks ; kW in normal, shearing and rotational directions of joint.
direction, Dv is the relative shearing displacement along the s direction, and DW is the relative
rotational angular displacement; ðui ; vi ; Wi Þ; where i ¼ 1; 2; are the displacement components at
the node i along the local co-ordinate directions respectively.
Furthermore, the force–deformation relationship of the joint element can be expressed as
follows:
fF g ¼ ½KfDdg ðA13Þ
where
2 3
kn 0 0
6 7
fF g ¼ fN Q MgT ; fDdg ¼ fDu Dv DWgT ; ½K ¼ 6
40 ks 07 5
0 0 kW
(Figure A3), and N ; Q; M are the two forces along the n and s directions and the moment of the
joint element, respectively.
Expressing ðui ; vi ; Wi Þ as fdg ¼ fu1 v1 W1 u2 v2 W2 gT ; we can have the following equation:
fDdg ¼ ½C fdg
2 3
1 0 0 1 0 0
6 7
½C ¼ 6
40 1 0 0 1 0 7
5 ðA14Þ
0 0 1 0 0 1
where ½KJ is the stiffness matrix of the joint element in the local co-ordinates, ½T is a co-ordinate
transformation matrix, ½KG is the stiffness matrix of the joint element in the global co-ordinates
Copyright # 2004 John Wiley & Sons, Ltd. Int. J. Numer. Anal. Meth. Geomech. 2004; 28:57–91
82 W. Q. DING ET AL.
where kW1 ; kW2 ; l are constants that can be determined from the bending test for the segment
joint.
For comparisons, we also present an analysis using the semi-analytical method [10, 11, 29] for
shielding tunnelling. As the details are already document in the reference, we only provide a
highlight of the key points of the method.
The loads acting on the shield lining is shown in Figure B1. In the figure, P0 is overload, and
usually equal to 10 kN=m2 ; R0 is external radius of shield lining; Rc is radius of middle line of
shield lining; g is gravity of lining; Pe1 and Pw1 are, respectively, the vertical earth pressure and
water pressure, respectively, acted on the up side of shield lining. The lateral earth pressure and
water pressure vary linearly and act on both sides of the shield lining. They are equal to qe1 and
qw1 at the top of shield lining and qe2 and qw2 at the bottom of shield lining; Pe2 and Pw2 are
respectively the vertical earth pressure and water pressure respectively acted on the bottom side
of shield lining; Pg is the vertical resistance of lining weight acted on the bottom side of shield
lining.
For sandy clay, the earth pressure and water pressure are assumed to act on the lining
separately. If the overburden thickness is two times larger than the external diameter D of shield
lining, an effective overburden thickness h0 ðh0 52DÞ should be used and it is determined by
following Terzaghi’s formula (Figure B2) below:
B1 ð1 ðc=B1 gÞÞ P0
h0 ¼ ð1 eK0 tan fðH =B1 Þ Þ þ ðeK0 tan fðH =B1 Þ Þ ðB1Þ
K0 tan f g
Copyright # 2004 John Wiley & Sons, Ltd. Int. J. Numer. Anal. Meth. Geomech. 2004; 28:57–91
ANALYSIS OF SHIELD TUNNEL 83
ðp=4Þ þ ðf=2Þ
B1 ¼ R0 cot ðB2Þ
2
where c; f and g are cohesion, internal friction angle and unit weight of soil layer respectively;
K0 is lateral pressure coefficient; H is overburden thickness. For many soil layers condition, the
average parameter values with a weighting factor of the layer thickness will be used in Equations
(B1) and (B2).
Copyright # 2004 John Wiley & Sons, Ltd. Int. J. Numer. Anal. Meth. Geomech. 2004; 28:57–91
84 W. Q. DING ET AL.
The distribution of earth resistance is triangular in shape and its acting range is shown in
Figure B1. The magnitude of the earth resistance qk is determined by following equation:
qk ¼ k d ðB3Þ
where k is the soil resistance coefficient, d is the deformation at the horizontal quadrant point of
shield lining, and d can be calculated by following formula:
½2ðpe1 þ pw1 Þ ðqe1 þ qw1 Þ ðqe2 þ qw2 ÞR4c
d¼ ðB4Þ
24ðEI þ 0:0454 k R4c Þ
Having these parameters determined, the internal forces of the shield lining can be easily
computed. The formulae for the calculation of the beam bending moment and lining ring hoop
force are given in Table B1.
Copyright # 2004 John Wiley & Sons, Ltd. Int. J. Numer. Anal. Meth. Geomech. 2004; 28:57–91
ANALYSIS OF SHIELD TUNNEL 85
Note: The values beyond the expressed range can be easily obtained as the loads and lining are symmetric.
Copyright # 2004 John Wiley & Sons, Ltd. Int. J. Numer. Anal. Meth. Geomech. 2004; 28:57–91
86 W. Q. DING ET AL.
B1 1B g
c H
1 K tan fB
2 h0 ¼ K0 tan f 1e 0 1 þ h0 ¼ 2D ¼ 10:6 m
H
P0 K0 tan fB
g e
1 ¼ 9:708 m52D
Table B2 gives the values of the design parameters adopted in the present study and
Table B3 tabulate the parameters computed by using these equations. These parameters are
then used to determine the beam bending moment and lining ring hoop force in the tunnel
lining.
APPENDIX C: NOMENCLATURE
Symbols in Main Text
Copyright # 2004 John Wiley & Sons, Ltd. Int. J. Numer. Anal. Meth. Geomech. 2004; 28:57–91
ANALYSIS OF SHIELD TUNNEL 87
Copyright # 2004 John Wiley & Sons, Ltd. Int. J. Numer. Anal. Meth. Geomech. 2004; 28:57–91
88 W. Q. DING ET AL.
Symbols in Appendix A
Symbols in Appendix B
P0 overload
Copyright # 2004 John Wiley & Sons, Ltd. Int. J. Numer. Anal. Meth. Geomech. 2004; 28:57–91
ANALYSIS OF SHIELD TUNNEL 89
ACKNOWLEDGEMENTS
The authors are indebted to Mr. Junichi Nagaya in Geo Research Institute, Osaka Soil Test Laboratory,
Osaka, Japan for his kind assistance during this investigation. The work presented in this paper is
supported by the Research Grants Council of Hong Kong SAR Government and the Hong Kong Jockey
Club Charities Trust. The authors would also like to thank the three reviewers and Editor, Professor Stein
Sture, for their invaluable comments that have enhanced the paper presentation.
REFERENCES
1. Hashimoto T, Nagaya J, Konda T. Geotechnical aspects of ground movement during shield tunneling in Japan.
One-day Seminar Geotechnical Aspect of Underground Structure, vol. 1/III–6/III. Indonesia, Jakarta. Himpunan
Ahliteknik Tanah: Indonesia, 1996 (Hatti).
2. Peck RB. Deep excavation and tunneling in soft ground. In Proceedings of 7th International Conference Soil
Mechanics and Foundation Engineering. Mexico, State of the Art Volume, 1969; 225–290.
3. Clough GW, Schmidt B. Design and Performance of Excavations and Tunnels in Soft Clay. Soft Clay Engineering.
Elsevier: Amsterdam, 1981; 569–634.
Copyright # 2004 John Wiley & Sons, Ltd. Int. J. Numer. Anal. Meth. Geomech. 2004; 28:57–91
90 W. Q. DING ET AL.
4. Rowe RK, Lo KY, Kack GJ. A method of estimating surface settlement above tunnels constructed in soft ground.
Canadian Geotechnical Journal 1983; 20(8):11–22.
5. Schmidt B. Tunneling in soft ground in the United States}National report. In Proceedings of the International
Symposium on Underground Construction in Soft Ground, Underground Construction in Soft Ground, Fujita K,
Kusakabe O (eds), New Delhi, India. A.A. Balkema: Rotterdam, 1995; 119–122.
6. Wang JY. Tunneling and technological progress in tunneling in China. In Proceedings of the International
Conference on Tunnels and Underground Structures, Tunnels and Underground Structures, Zhao J, Shirlaw JN,
Krishnan R (eds), Singapore. A.A. Balkema: Rotterdam, 2000; 97–106.
7. Zhu HH, Yang LD, Chen QJ. Two kinds of design model for joint of segment and lining in shield tunnel.
Engineering Mechanics 1994; (Suppl.):395–399 (in Chinese).
8. Hudoba I. Contribution to static analysis of load-bearing concrete tunnel lining built by shield-driven technology.
Tunneling and Underground Space Technology 1997; 12(1):55–58.
9. Lee KM, Ge XW. The equivalence of a jointed shield-driven tunnel lining to a continuous ring structure. Canadian
Geotechnical Journal 2001; 38(3):461–476.
10. Koyama Y, Kishio T, Kobayashi T. Design of linings for shield driven tunnels}a survey on Japanese shield
tunneling. In Proceedings of the International Symposium on Underground Construction in Soft Ground, Underground
Construction in Soft Ground, Fujita K, Kusakabe O (eds), New Delhi, India. A.A. Balkema: Rotterdam, 1995;
359–366.
11. Kurihara K. Report on current shield tunneling methods in Japan. In Proceedings of the International Symposium on
Underground Construction in Soft Ground, Underground Construction in Soft Ground, Fujita K, Kusakabe O (eds),
New Delhi, India. A.A. Balkema: Rotterdam, 1995; 111–114.
12. Zhu HH, Ding WQ. The analysis of the segment internal forces in the construction process of shield tunnel. Recent
Development of Theory and Practice in Geotechnology, China–Japan Joint Symposium, October 29–30, 1997; 257–266.
13. Bernat S, Cambou B. Soil–structure interaction in shield tunneling in soft soil. Computers and Geotechnics 1998;
22(3/4):221–242.
14. Oreste PP, Peila D, Poma A. Numerical study of low depth tunnel behaviour. In Proceedings of the World Tunnel
Congress’99, Challenges for the 21st Century, Alten T et al. (eds), Oslo, Norway. A.A. Balkema: Rotterdam, 1999;
155–162.
15. Soliman E, Duddeck H, Ahrens H. Effects of development of shotcrete stiffness on stresses and displacements
of single and double tunnels. In Proceedings of the International Congress on Tunneling and Ground
Conditions, Tunneling and Ground Conditions, Abdel Salam ME (ed.), Cairo, Egypt. A.A. Balkema: Rotterdam,
1994; 549–556.
16. Swoboda G, Abu-krisha A. Three-dimensional numerical modeling for TBM tunneling in consolidated clay.
Tunneling and Underground Space Technology 1999; 14(3):327–333.
17. Dias D, Kastner R, Maghazi M. Three reducing settlement caused by shield dimensional simulation of slurry shield
tunneling. In Geotechnical Aspects of Underground Construction in Soft Ground}Is}Tokyo’99, Kusakabe O, Fujita
K, Miyazaki Y (eds), Tokyo, Japan. A.A. Balkema: Rotterdam, 2000; 351–356.
18. Zhou XJ, Gao B, Hu S, Li DC. Three dimensional finite element analysis on construction process of large span
tunnel of Guangzhou Metro. In Proceedings of the International Conference on Tunnels and Underground Structures,
Tunnels and Underground Structures, Zhao J, Shirlaw JN, Krishnan R (eds), Singapore. A.A. Balkema: Rotterdam,
2000; 335–342.
19. Negro Jr AN. Design of shallow tunnels in soft ground. Ph.D. Thesis, University of Alberta: Edmonton, 1988.
20. Katano S. Behavior of cohesive soil ground during shield tunneling. In Proceedings of the International Symposium
on Underground Construction in Soft Ground, Underground Construction in Soft Ground, Fujita K, Kusakabe O (eds),
New Delhi, India. A.A. Balkema: Rotterdam, 1995; 269–272.
21. Benmebarek S, Kastner R, Ollier C. Reducing settlement caused by shield tunneling in alluvial soils. In Geotechnical
Aspects of Underground Construction in Soft Ground}Is}Tokyo’99, Kusakabe O, Fujita K, Miyazaki Y (eds),
Tokyo, Japan. A.A. Balkema: Rotterdam, 2000; 203–208.
22. Negro A, de Queiroz PIB. Prediction and performance: a review of numerical analysis for tunnels. In Geotechnical
Aspects of Underground Construction in Soft Ground}Is}Tokyo’99, Kusakabe O, Fujita K, Miyazaki Y (eds),
Tokyo, Japan. A.A. Balkema: Rotterdam, 2000; 409–418.
23. Lee KM, Ji HW, Shen CK, Liu JH, Bai TH. A case study of ground control mechanisms of EPB shield tunneling in
soft clay. In Geotechnical Aspects of Underground Construction in Soft Ground}Is}Tokyo’99, Kusakabe O, Fujita
K, Miyazaki Y (eds), Tokyo, Japan. A.A. Balkema: Rotterdam, 2000; 251–256.
24. Mair RJ. Geotechnical aspects of design criteria for bored tunneling in soft ground. In Proceedings of the World
Tunnel Congress’98 on Tunnels and Metropolises, Tunnels and Metropolises, Negro Jr A, Ferreira AA (eds), Brazil.
A.A. Balkema: Rotterdam, 1998; 183–199.
25. Nomoto T, Mori H, Matsumoto M. Overview on ground movements during shield tunneling}a survey on Japanese
shield tunneling. In Proceedings of the International Symposium on Underground Construction in Soft Ground,
Underground Construction in Soft Ground, Fujita K, Kusakabe O (eds), New Delhi, India. A.A. Balkema:
Rotterdam, 1995; 345–351.
Copyright # 2004 John Wiley & Sons, Ltd. Int. J. Numer. Anal. Meth. Geomech. 2004; 28:57–91
ANALYSIS OF SHIELD TUNNEL 91
26. Hashimoto T, Hayakawa K, Mizuhara K, Konda T. Investigation on successive settlement due to shield tunneling.
In Geotechnical Aspects of Underground Construction in Soft Ground}Is}Tokyo’99, Kusakabe O, Fujita K,
Miyazaki Y (eds), Tokyo, Japan. A.A. Balkema: Rotterdam, 2000; 233–238.
27. Japanese Research Society of Construction Maintenance Technique (Shield Branch). The in-situ measuring results
of the soil pressure etc. on the segment of the Osaka No. 7 subway line from Morinonomiya to Osaka Business Park.
The Sixth Conference of Shield Branch SC-6-1, 1995 (in Japanese).
28. Zheng YR, Dong YF, Xu ZY et al. The design instruction for rock bolt and shotcrete of underground structure. China
Railway Press: Beijing, China 1988 (in Chinese).
29. Nakajima S. New technology of shield tunnel (8). III. design and construction section. Tunnel and Underground
1991; 22(1):69–78 (in Japanese).
30. van Empel WHNC, de Waal RGA, van der Veen C. Segmental tunnel lining behavior in axial direction. In
Geotechnical Aspects of Underground Construction in Soft Ground}Is}Tokyo’99, Kusakabe O, Fujita K, Miyazaki
Y (eds), Tokyo, Japan. A.A. Balkema: Rotterdam, 2000; 357–362.
31. Ding WQ, Yang LD, Zhu HH. Simulation of the material behavior in shield tunnel construction. Journal of Tongji
University 1999; 27(4):297–302 (in Chinese).
32. Zhu HH, Tao LB. Study on two beam–spring models for the numerical analysis of segments in shield tunnel. Rock
and Soil Mechanics, 1998; 18(2):26–32 (in Chinese).
Copyright # 2004 John Wiley & Sons, Ltd. Int. J. Numer. Anal. Meth. Geomech. 2004; 28:57–91