0% found this document useful (0 votes)
115 views1 page

Earned Value Gold Card

Earned value management (EVM) is a project management technique for measuring project performance and progress. It integrates the measurement of scope, schedule, and resources with dollar metrics to forecast project performance problems. Key terms include budget at completion, actual cost of work performed, schedule variance, and cost variance. EVM requires contractors over $20 million to use an Earned Value Management System to plan, measure, and forecast contract performance.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
115 views1 page

Earned Value Gold Card

Earned value management (EVM) is a project management technique for measuring project performance and progress. It integrates the measurement of scope, schedule, and resources with dollar metrics to forecast project performance problems. Key terms include budget at completion, actual cost of work performed, schedule variance, and cost variance. EVM requires contractors over $20 million to use an Earned Value Management System to plan, measure, and forecast contract performance.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

EARNED VALUE MANAGEMENT Contract Price

‘GOLD CARD’ NCC


TAB Profit / Fees
CBB
AUW OTB
EAC OVERRUN

TAB PMB Management


Management Reserve BAC Reserve (MR)
PMB Undistributed Control Summary Level
Budget (UB) Accounts (CA) Planning Packages (SLPP)

Projected Slip ?
Work Packages (WP) Planning Packages (PP)
Schedule Variance
Cost Variance ACRONYMS
$ ACWPCum ACWP Actual Cost of Work Performed Cost actually incurred in accomplishing work performed = ACTUAL COST
AUW Authorized Unpriced Work Work contractually approved, but not yet negotiated / definitized
BAC Budget At Completion The sum of all budgets for the contract thru any given WBS/OBS level
BCWP Budgeted Cost for Work Performed
Value of completed work in terms of the work’s assigned budget = EARNED VALUE
BCWSCum
BCWS Budgeted Cost for Work Scheduled
Time-phased Budget Plan for work scheduled = PLANNED VALUE
BCWPCum CA Control Account Lowest CWBS element assigned to a single focal point to plan & control
scope / schedule / budget
CBB Contract Budget Base Sum of NCC & AUW
Time Time
Now
Completion
Date
EAC Estimate At Completion Estimate of total Cost for the contract thru any given level generated by
Ktr, PMO, DCMA, etc. = EACKtr / PMO / DCMA
ETC Estimate to Complete Estimate of the cost of remaining work
LRE Latest Revised Estimate Ktr’s EAC or EACKtr
VARIANCES Positive is Favorable, Negative is Unfavorable OVERALL STATUS MR Management Reserve Budget withheld by Ktr PM for unknowns / risk management
Cost Variance CV = BCWP – ACWP % Schedule = (BCWSCUM / BAC) * 100 NCC Negotiated Contract Cost Contract Price Minus profit or fee(s)
CV % = (CV / BCWP) * 100 % Complete = (BCWPCUM / BAC) * 100 OTB Over Target Baseline Sum of CBB + additional budget approved for remaining work
Schedule Variance SV = BCWP – BCWS PAC Price At Completion EAC Plus Adjusted Profit or Fee(s)
% Spent = (ACWPCUM / BAC) * 100
PMB Performance Measurement Baseline Contract time-phased budget plan
SV % = (SV / BCWS) * 100
PP Planning Package Far-term CA activities not yet defined into WPs
Variance at Completion VAC = BAC – EAC SLPP Summary Level Planning Package Far-term contract activities not yet assigned to a CA
VAC % = (VAC / BAC) * 100 TAB Total Allocated Budget Sum of all budgets for work on contract = NCC, CBB, or OTB
TCPI To Complete Performance Index Efficiency needed from ‘time now’ to achieve a Cost Target = BAC, LRE, or EAC
EFFICIENCIES UB Undistributed Budget Broadly defined activities not yet time-phased for distribution to CAs or SLPPs
Cost Efficiency CPI = BCWP / ACWP Favorable is > 1.0, Unfavorable is < 1.0 WP Work Package Near-term, detail-planned activities within a CA
Schedule Efficiency SPI = BCWP / BCWS Favorable is > 1.0, Unfavorable is < 1.0 EVM POLICY: DoDI 5000.02, Enclosure 1. Table 8.
EVMS in accordance with EIA-748 is required for cost or incentive contracts, subcontracts, intra-government work
SCHEDULE METRICS (Selected) agreements, & other agreements valued > $20M (TY $). Contracts > $100M# (TY $) require that the EVMS be formally
BEI = Total Tasks Completed / (Total Tasks with Baseline Finish On or Prior to Current Report Period + validated by the cognizant contracting officer. # Class Deviation-Earned Value Management System Threshold (9/1/15)
EVM is discouraged on Firm-Fixed Price, Time & Material Contracts, & LOE activities regardless of cost.
Tasks without baseline finish dates) Refer to the IPMR Implementation Guide for IPMR Tailoring Guidance.
Hit Task % = 100 * (Tasks in Denominator that Completed ON or Before Baseline Finish /
DoD’s EVM CONTRACTING REQUIREMENTS:
Tasks Baselined to Finish within Current Report Period)
DFARS CLAUSES 252.234-7001 “NOTICE OF EVMS” FOR SOLICITATIONS
ESTIMATE @ COMPLETION = ACTUALS TO DATE + [(REMAINING WORK) / (PERFORMANCE FACTOR)] 252.234-7002 “EVMS” FOR SOLICITATIONS & CONTRACTS
EACCPI = ACWPCUM + [(BAC – BCWPCUM) / CPICUM] 252.242-7005 “CONTRACTOR BUSINESS SYSTEMS” FOR SOLICITATIONS & CONTRACTS
EACComposite = ACWPCUM + [(BAC – BCWPCUM) / (CPICUM * SPICUM)] Integrated Program Mngt Report DI-MGMT-81861A * 7 FORMATS = WBS, OBS / IPT, BASELINE, STAFFING, EXPLANATIONS & PROB ANALYSES,
IMS, HISTORY / FORECAST COST
TO COMPLETE PERFORMANCE INDEX (TCPI) § # INTEGRATED BASELINE REVIEW MANDATORY FOR ALL CONTRACTS THAT HAVE EVM INVOKED ON THE CONTRACT
TCPITarget = Work Remaining / Cost Remaining = (BAC – BCWPCUM) / (Target – ACWPCUM) WBS For Defense Materiel Items MIL-STD-881D
* Combines & Supersedes DI-MGMT-81466A (CPR) & DI-MGMT-81650 (IMS); Effective July 1, 2012
§ To Determine the TCPI for BAC, LRE, or EAC Substitute TARGET with BAC, LRE, or EAC
# To Determine the Contract Level TCPI for EAC, You May Replace BAC with TAB
EVM CoP: https://www.dau.mil/cop/evm
eMail Address: [email protected]
Revised SEP 2018

You might also like