API 570 Study Notes PDF
API 570 Study Notes PDF
1 SCOPE
Q – What activities are covered by API 570?
A – I.R.R.A
2. REFERENCES
3. DEFINITIONS
Alteration Mixing tee Rerating
Authorized inspection agency On-stream Secondary process piping
Authorized piping inspector Owner/user Small bore piping ≤ 2 NPS
Auxiliary piping Piping circuit Soil-to-air interface
Critical check valves Piping engineer Temper embrittlement
Deadlegs Piping system Temporary repairs
Design temperature Primary process piping Test point – 2” vs. 3”
Injection points Renewal Material verification program
Level bridle Repair Off-site piping
MAWP Repair organization On-site piping
4.1 GENERAL
Q – Who shall exercise control of piping system inspection program?
A – Owner/user
4.3 RESPONSIBILITIES
4.3.1 Owner/user
Q – Who is responsible for developing, documenting, implementing, executing, and assessing piping
inspection systems and procedures?
A – Owner/user
5.1 RBI
• All RBI assessments shall be thoroughly documented & clearly define factors contributing to both
likelihood and consequence of piping failure
5.2 Preparation
Q – What is extremely important when opening pipe for examining internal surfaces?
A – Safety precaution
• NDT equipment used is subject to operating facility’s requirements for electrical equipment
Q – Who should provide specific attention to the need for inspection of piping for various types of failure
mechanisms?
A – Owner/user
Q – What is the recommended upstream minimum limit for injection point circuit?
A – The greater of 12” or 3D
Q – What is the recommended downstream minimum limit for injection point circuit?
A – The lesser of 2nd change in flow direction or 25 feet after 1st change in flow direction. Or until next
vessel
Q – Where are the typical locations for measuring thickness within an injection point circuit, subject to
localized corrosion?
A – See Figure 5-1 – F.I.S.U.D. → Fittings, Impingement, Straight, Upstream, & Downstream
5.3.2 Deadlegs
Q – What should inspector monitor on deadlegs?
A – Wall thickness at stagnant section & connection to the active line
5.3.3 CUI
Q – What should be included in external inspection of insulated piping?
A – Inspect insulation for conditions that could lead to CUI
Q – Significant corrosion was found when inspecting soil-to-air interface. What next?
A – Perform UT measurement & excavate pipe to determine if corrosion is localized to S/A interface, or
more pervasive
Q – What to look for in concrete-to-air and asphalt-to-air interfaces, of buried piping without CP?
A – Evidence of caulking or seal deterioration, which will allow moisture ingress.
Q – What to do if found evidence of caulking or seal deterioration while inspecting concrete-to-air and
asphalt-to-air interfaces, of buried piping without CP, where piping system is older than 10 years?
A – Inspect corrosion beneath surface before resealing the joint
• Erosion damage can be increased by streams with large quantities of solid or liquid particles
flowing at high velocities
Q – If external or internal coatings, refractory linings, and corrosion-resistant linings are in good condition,
then what?
A – Corrosion is unlikely and no need to remove them to inspect piping
Q – What to consider if operating deposits such as coke, are present on piping surface?
A – Determine if such deposits have active corrosion beneath them. Larger areas may need to be
inspected.
Large lines – Remove deposits at selected critical areas for spot examination
Small lines – Remove selected spools or perform NDE e.g. RT in selected areas
• Inspector should examine piping for presence of any field modifications or temporary repairs not
recorded on piping drawings or records
• Inspector should be alert for presence of any components that may not be suitable for long term
operations e.g. improper flanges, temporary repairs (clamp), modifications (flexible hoses), valves
with improper specifications.
• Pay special attention to threaded components that are easily removed because they are easily
installed with improper components
Q – Who shall receive and assess the report of vibrating or swaying piping?
A – Engineering or inspection personnel
5.5.1 General
Q – What thickness shall be recorded and used to calculate corrosion rates, remaining life, and next
inspection date?
A – The thinnest reading or an average of several measurement readings taken within the area of that
test point
Q – How should TML be identified, to ensure repetitive measurements and accurate corrosion rate
determination?
A – Marked on drawings and on piping system
• For corrosion rate to be valid, measurement on thinnest point must be repeated as closely as
possible to the same location
• Alternatively, use the minimum reading or an average of several test point readings
Q – What are the requirements if fluid other than water is used for pressure testing?
A– Nontoxic
If flammable, flash point at least 120oF
No effect to the environment
Q – What precaution should be taken if pressure test takes a long time and subject to thermal expansion?
A – Avoid excessive pressure
• Remove all other attachments which are not capable of taking the pressure test e.g. gauge glasses,
pressure gauges, expansion joints.
• Rupture disks should be blanked or removed
• When HT is completed, re-install all of the above
• When block valves are used to isolate piping, do not exceed the permissible seat pressure as
described in ASME B16.34 or applicable manufacturer data
New work
• During repair or alteration of alloy material pressure retaining component, inspector shall ensure
the installation of new materials is consistent with selected material specification
• Material verification program as per API 578
Existing material
• When pipe failure occurs due to incorrect material use, inspector shall consider further verification
of existing piping materials
• Extent of further verification depends on consequence of failure & likelihood of further material
errors
Q – What is a key component of a material verification program, consistent with API 578?
A – Procedures for prioritization and risk ranking of piping circuits, which may lead to retroactive PMI
testing
Q – If a material verification program finds an operating pipe component with the wrong spec, what next?
A– Establish schedule for replacement – by owner/user & inspector, consulted by engineer
Periodically inspect using appropriate NDE – by authorized inspector
• Valve bodies exposed to thermal cycling → inspect for thermal fatigue cracks
• Gate valves operating in erosive/corrosive service → perform thickness gauging between the seats
• Control or throttling valves in high-pressure drop or slurry service are susceptible to localized
corrosion/erosion in the body downstream of the orifice → remove valve from line for internal
inspection. Inspect downstream mating flange and piping for local metal loss
• Critical check valves → inspect visually and internally to ensure they will stop flow reversal, which
may lead to over pressurizing of upstream piping
How?
→ Ensure flapper is free to move, without excessive looseness from wear
→ No excessive wear on flapper stop → or else flapper will move past top dead central
position and remain in open position if check valve is mounted in vertical position
→ Flapper nut is secured to flapper bolt to avoid backing off in service
API 570
• Use API 598 for valve body and/or pressure tests after servicing
Note: Acceptance criteria for random/spot RT in B31.3 apply to new construction, to assess the probable
quality of all welds/welders in the system. Do not use these criteria when assessing in-service welds.
• Fasteners should extend completely through their nuts → can still be accepted if lack of complete
engagement is not more than 1 thread
• Excessively bent flanges → check their markings and thicknesses against engineering requirements
before taking corrective actions
• Flange and valve bonnet, and fasteners → inspect visually for corrosion, evidence of leak such as
stains, deposits, drips. Leaks can cause environmental cracking
• Clamped flange & pumped with sealant → check for leak at bolts, which can cause corrosion or
cracking (caustic). Affected fasteners should be renewed before any further repumping
API 570
Q – What is the basis of the simplified piping classification scheme, as per Section 6.2?
A – Consequence of failure
Q – What is the purpose of the simplified piping classification scheme, as per Section 6.2?
A – Establish frequency & extent of inspection
• If RBI is used to increase inspection interval limits or extent of inspection → conduct RBI
assessment at intervals not to exceed limits as per Table 6-1
Q – Who shall maintain record of process piping fluids handled, including their classification?
A – Owner/user
6.2.1 Class 1
• Highest potential of emergency (safety or environmental) if leak
1. Flammable services that may auto-refrigerate and lead to brittle fracture
2. Pressurized services that may rapidly vaporize during release, creating vapors that may collect
and form explosive mixture e.g. C2, C3, C4 streams. These fluids have atmospheric boiling
temperature below 50oF
3. Hydrogen sulfide (> 3% weight) in gaseous stream
4. Anhydrous hydrogen chloride
5. Hydrofluoric acid
6. Piping affecting public – located in high-activity area
6.2.2 Class 2
• Those not in Class1 or Class 3
1. On-site hydrocarbons that will slowly vaporize during release such as those operating below the
flash point
2. Hydrogen, fuel gas, natural gas
3. On-site strong acids and caustics
API 570
6.2.3 Class 3
• Flammable services but do not significantly vaporize when leak & not located in high-activity area
• Services harmful to human tissue but located in remote areas
1. On-site hydrocarbons that do not significantly vaporize when leak such as those operating
below the flash point
2. Distillate and product lines connecting storage & loading
3. Off-site acids and caustics
Q – Who shall establish interval for thickness measurement, external visual inspection, internal &
supplemental inspections?
A – Owner/user
• Thickness measurement interval → the smaller of Table 6-1 or ½ pipe life, or even shorter when
appropriate
• Condition of insulating system or outer jacketing e.g. cold box shell, should be periodically
observed by operating personnel, such as;
A. Effectively insulated piping system → no moisture ingression
B. Jacketed cryogenic piping system
C. Piping system in cold box which atmosphere is purged with inert gas
D. Piping system with temperature too low or too high to preclude presence of water
• Use the lower value of short term CR or long term CR, for data assessment
• Authorized inspector, in consultation with corrosion specialist, will select CR that best reflects
current process
API 570
• Statistical treatment of data results must reflect actual condition of various pipe components
• Do not use statistical analysis employing point measurements on piping system with significant
localized unpredictable corrosion mechanisms
Q – How to calculate the probable CR for newly installed piping system or where service condition is
changed?
A – SEPI 3
→ S - Similar material
→ E – Experience
→ P – Published data
→ I 3 – Inspection after no more than 3 months. Can use corrosion coupons or probes
• For known material – MAWP computations can be made if the following essential details of the
material comply with code spec:
A. Upper and/or lower temperature limits
B. Quality of materials & workmanship
C. Inspection requirements
D. Reinforcements of openings
E. Any cyclical service requirements
• For unknown materials – MAWP computations will use lowest grade material & joint efficiency
8.1.1 Authorization
8.1.2 Approval
Q – Who shall approve methods of design, execution, materials, WPS, examination, and testing?
A – Authorized inspector or engineer
Q – Who shall approve repair of cracks that occurred while in-service e.g. vibration, thermal cycling,
expansion, environmental cracking?
A – Engineer
API 570
Q – What are possible options while doing on-stream welding repair on corroded or damaged area?
A– Full encirclement welded split sleeve
Box-type enclosure
• Do not use these options for longitudinal crack unless engineer says it will not propagate from
under sleeve
Q – How to repair localized problem e.g. pinholes, pitting, on material with SMYS not more than 40 ksi?
A – Fillet welding of split coupling or patch plate over pitted area. Use same material as base metal,
unless approved by engineer
• Temporary repair should be removed and replaced with suitable permanent repair at next
opportunity unless approved and documented by piping engineer
• During TA or other opportunities, remove temporary leak seal and leak dissipating devices,
including valves. After that, restore original integrity of piping system.
Q – Who shall review repair procedure that includes leak sealing fluids?
A – Authorized inspector or engineer
Q – What should be considered when doing repair that includes leak sealing fluids?
A – Compatibility of sealant with leaking material, pumping pressure, risk of sealant affecting downflow
meters, PSV, etc.
API 570
8.2.2.1 Preheating
• As per original code & WPS
• Any exceptions – get engineer’s approval
8.2.2.2 PWHT
• As per original code & B31.3
Q – When can local PWHT be substituted for 360-degree banding on local repairs on all materials?
A – When the following are met:
A. Reviewed and approved by engineer
B. Give consideration to base metal thickness, thermal gradients, material properties, changes
resulting from PWHT, need for full penetration welds, overall and local strains and distortions due
to heating of local restrained area
C. Minimum preheat of 300oF is maintained during welding
D. Maintain PWHT temperature at distance at least 2 times base metal thickness from weld
E. Monitor PWHT temperature using at lest 2 thermocouples
F. Apply controlled heat to any branch connection or attachment within PWHT area
G. PWHT is for code compliance, not for environmental cracking resistance
8.2.3 Design
• Butt joint shall be full penetration
8.2.4 Materials
Q – What are the material requirements?
A- Have known weldable quality
Conform to applicable code
Compatible with original material
8.2.5 NDE
• Acceptance as per applicable code or owner/user spec, unless otherwise specified in API 570
Q – Who shall perform UT on welds that have not been pressure tested or welds repair?
A – Industry qualified UT shear wave examiner, as specified by owner/user
8.3 Rerating
• Nonmandatory references for buried piping → NACE documents RP0169, RP0274, RP0275, and API
651
API 570
1. Intelligent pigging → Ensure five diameter bends or else pig will get stuck
2. Video cameras
3. Excavation → Last few inches of soil should be manually removed to prevent damaging pipe.
When line is too deep, shore the trench to prevent collapse, as per OSHA requirements. If
coating is damaged, it should be removed in that area to inspect condition of underlying metal.
9.4 Records
• As per Section 7.6 + include date and location of installation of temporary clamps
C.1 Repairs
• May use gas metal-arc or shielded metal-arc processes (GMAW or SMAW)
• If temperature < 50oF, use low-hydrogen electrodes AWS E-XX16 or E-XX18 for materials
conforming to;
A-53 Grades A & B
A-106 Grades A & B
A-333
A-334
API 5L
• If temperature < 32oF, use these electrodes for all lower grade materials
• When different materials are used → consult engineer
• All repair and welding procedures must be as per API Publication 2201
• When welding sleeve-to-pipe fillet weld (as per Figure C-1: Encirclement repair sleeve) using low-
hydrogen electrodes AWS E-XX16 or E-XX18
Weld upward i.e. start from bottom to top
Electrode diameter should not exceed 5/32”
• When welding sleeve-to-sleeve butt joint (as per Figure C-1: Encirclement repair sleeve) using
low-hydrogen electrodes AWS E-XX16 or E-XX18
Electrode diameter should not exceed 3/16”
Fit the sleeve with suitable tape or backing strip to prevent fusing weld to the pipe side wall.
This may be omitted if pipe thickness along this weld has sufficient thickness as determined
by UT