Other Canal Structures: Regulation Works
Other Canal Structures: Regulation Works
Other Canal Structures: Regulation Works
Regulation Works
Canal Falls
While canals are designed with a slope which is close to the regime slope, the
ground slope may differ from it considerably. Many a times, the ground slope is more
than the canal slope and this may result in a canal in heavy filling. To overcome this
situation, the canal has to be provided with falls (Fig.6.1) which require a masonary or
concrete work.
Fig.6.1
The drop in canal bed results in the potential energy of water being converted to
kinetic energy and this excess energy has to be dissipated before allowing the flow over
the unprotected canal bed. Also, the water surface upstream of the fall also needs to be
maintained at its normal level. The fall thus has to be provided with a crest and some
means of energy dissipation. The fall can be flumed or unflumed. In a flumed fall, the
trapezoidal canal section is contracted to a rectangular section having a width less than
the bed width of the canal and expanded back after the works. In unflumed falls, while
there is no reduction of the bed width, the section is however converted into a rectangular
one.
The energy dissipation in this case is by vertical impact of the water on the
downstream bed and a pool of water. A cistern of certain depth and length- known as the
cistern element is provided. There are many empirical formulae available to compute the
length and depth of the cistern such as the one given by UP Irrigation Research Institute
(UPIRI) as below is SI units.
49
Lc = 5 (E H L )
xc = 0.25(EH L )
2/3
in which Lc and xc are the length and the depth of the cistern respectively as shown in
Fig. 6.2. Neglecting velocity head, E can be taken equal to head H over the crest and HL
equal to drop in canal bed levels.
Glacis Fall
Fig.6.3
This type of fall is preferred for larger drops and utilizes the hydraulic jump for
energy dissipation (Fig.6.3). The crest is joined to the upstream floor at a slope of 1:1,
while the downstream glacis is generally at at slope of 2H:1V. The downstream floor
may be carried to a level lower than the canal bed for certain length to provide a cistern,
with the length and depth of the cistern being 1.25 E2 and 0.25 E2 respectively, where E2
is the downstream specific energy.
This is the work provided at the head of a branch canal or a distributary and
serves the purpose of controlling and regulating the flow into the offtake as well as
metering of the flow. The arrangement is more or less similar to that of a canal head
regulator, with a raised crest, upstream and downstream floors and cutoffs. The width of
the regulator and height of crest are fixed such that the offtake may be able to draw its
full supply discharge even if the water level in the parent channel is lower than the full
supply level. On smaller works, the control is in the form of wooden planks which can be
placed in grooves provided in piers for this purpose, while on larger works manually
operated gates are provided. Curved vanes or cantilever platform as discussed separately
are usually provided to control entry of excess sediment into the offtake
Cross Regulator
Cross regulators are structures constructed across a canal and spanning its entire
width. The width is divided into suitable number of spans and provided with gates so as
to regulate the flow in the canal downstream of the regulator. Cross regulators serve
many purposes such as
(i) If the canal downstream of the cross regulator has to be closed in an
emergency, the cross regulator gates can be closed and the discharge
diverted to any drain. This requires an escape to be constructed just
upstream of the cross regulator.
(ii) The canal water level upstream of the cross regulator can be regulated
depending upon the gate openings. This may be required if the canal is
carrying less than the full supply discharge and some offtake upstream has
to be supplied with its full supply discharge.
50
Cross Drainage Works
These are works provided at the crossing of a canal and a stream. Depending on
whether the canal crosses the stream at top, bottom or at the same level, these are divided
into three categories.
Fig.6.4
Siphon aqueducts are provided when the high flood level of the stream is higher
than the canal bed level. In such a case the flow in the stream becomes a pressure flow
through the siphon barrels (Fig.6.5)
Fig.6.5
The design of aqueducts and siphon aqueducts requires consideration of the
following factors:
Waterway of stream- The waterway provided in an aqueduct is generally close to
the Lacey’s regime perimeter. This helps in developing a stable channel upstream of the
works without much silting or scouring. The width is divided into suitable spans with the
help of piers. In a siphon aqueduct, the velocity in the barrels becomes one of the
considerations in deciding the waterway.
Headway i.e. the clearance between the downstream bed of the stream and the
bottom of the canal trough should be sufficient so as to prevent the blockage of the
barrels. While this may not present much of a problem in aqueducts, lowering of the
stream bed upstream of the siphon barrels may have to be resorted to at times (Fig.6.5).
Afflux will be caused by the flow of stream under the canal trough. This results
because of the head loss due to constriction, piers or siphon. Afflux can be computed
using appropriate formulae for the head loss and is used in determining the hydraulic
grade line specially in case of siphon aqueducts.
Fluming of the canal requires contraction as well as expansion transitions. While
the splay in contraction can be kept about 1:2, the expansion is generally provided with a
splay of 1:3 or more. Suitable design of transitions for contraction and expansion is
required and procedures for this design are available.
51
The considerations of uplift and exit gradient have also to be taken care of. The
worst condition for the stream bed being when the stream is dry and the canal is carrying
its full supply discharge. In case of siphon aqueducts, the canal trough is also subjected to
uplift when the canal is dry and the stream is in high flood.
Superpassages and Siphons
These are works where the stream crosses over the canal. In a superpassage the
canal full supply level is lower than the river bed level and the flow in canal is an open
channel flow. In a siphon the canal full supply level is higher than the stream bed level
and therefore the canal water flows under pressure through barrels under the stream
trough.
The design considerations for these works are similar to those for aqueducts and
siphon aqueducts. The stream however is not flumed and mostly carried with the original
section.
Level Crossing
In this work the canal and stream cross at nearly the same level (Fig.6.6). There is
intermixing of the canal and river water and the flow is controlled by regulator gates on
the canal as well as the stream. A sill with its top at the canal full supply level is provided
on the upstream side of the stream to prevent stagnant water pool in the stream during dry
season.
Fig.6.6
Level crossings have a problem with sediment getting deposited in the pool
formed at the crossing. This could lead to degradation in the river downstream. Also there
is need for constant watch and warning mechanism so that the stream gates could be
opened well in time in case a flood has to be passed. The canal may also have to be
closed during floods to prevent the river sediment from entering the canal.
Selection of Type
The selection of the type of cross drainage work depends on the relative bed
levels of the canal and the stream at the crossing and their discharge. Thus in case the
stream is carrying a large discharge, it may not be feasible to siphon it under the canal
even though the levels may dictate a siphon aqueduct. The type of crossing can be altered
by a suitable realignment of the canal if required, resulting in change in bed levels of both
the canal and the stream.
52
53
54
55
7. STORAGE SCHEMES
Storage schemes, as already mentioned, are those wherein the water is stored
when available (say monsoon months) and drawn from the storage during lean periods. A
reservoir created upstream of a dam constructed on a river provides the storage in such
schemes. The purposes for which such schemes are constructed include:
• Irrigation
• Power generation
• Water supply
• Flood control
• Navigation
• Recreation
A scheme which serves more than one of the above purposes is termed as a
multipurpose project. The extent to which the requirements of the various purposes can
be met depends on the compatibility of the purposes. Thus power generation is the most
compatible with other purposes in as much as it does not involve any consumptive use of
water. The water released for power generation can always be used for other purposes.
Likewise, flood control is the least compatible as this requires availability of empty
storage space in the reservoir, while other purposes require availability of water.
The main elements of a storage scheme are the dam, spillway, the reservoir. One
therefore has to decide the type of dam to be constructed, the type of spillway as well as
the reservoir storage capacity. The scheme may be for storing water during the wet
season and using it during the lean period in the same year or for using it during the next
year also. While the former is called “within year carryover storage”, the later is referred
to as “over year carryover storage”.
Planning for the elements of a storage scheme requires extensive data and
investigations to optimize the benefits. These include:
• Estimation of demand – The storage scheme The water these for different
purposes the project is supposed to fulfill has to be estimated separately.
Since the projects take a long time in completion and are supposed to
serve for a fairly long period, the projected population has to be estimated
while estimating the demand.
• Hydrologic studies including sedimentation – These include long term
data on stream flow, evaporation, water quality, sedimentation,
downstream water rights etc. The water availability can only be estimated
based on these investigations. Spillway capacity determination and
sedimentation of the reservoir is also based on these investigations.
56
• Geologic studies – The nature of foundations and abutment and the
availability of construction material near the site which determine to a
large extent the suitability of a given type of dam is a primary objective of
these investigations. Further determination of the suitability of the
reservoir site, stability of its rim and the possibility of landslides also
requires detailed geological investigations.
• Economic aspects – One of the major guiding principles in any project is
its cost effectiveness. Estimation of the costs and benefits of the project in
economic terms is required for any decision making. Both the capital and
recurring costs need to be considered. The benefits cannot always be
evaluated in monetary terms as these include the direct benefits as well as
called indirect ones. Some of the indirect costs and benefits can be
assessed by using a suitable metric wherever possible.
• Social aspects – The construction of a major project at any site is likely to
have significant social impact. This may include beneficial effects such as
the improved economic conditions, creation of employment opportunities
etc. Some adverse effects like submergence of land, increased noise and
other activity will also be a part of this. All these impacts need to be
evaluated.
• Environmental impact – The environmental impact assessment of any
major project has become one of the most important considerations
nowadays. The factors to be considered in carrying out an environmental
impact analysis are numerous and include things such as submergence of
agricultural land, submergence of forest land and its effect on flora and
fauna in the region, the loss of biodiversity, the impact of the project on
the overall water regime including downstream channel etc. A well carried
out study can at times result in some modification of the project plan
which minimizes any adverse environmental impact while keeping the
beneficial impacts nearly the same.
INVESTIGATIONS
Each of the aforesaid investigations requires a large amount of data and time. All
the data required will normally not be available to start with and needs to be collected –
an exercise which can be very costly and time consuming. Further, there are likely to be
many alternative schemes possible at or close to a given location, each requiring
additional data. In order to save time and expenses therefore, investigation for such
project are made in three stages.
Preliminary Investigations
These are investigations carried out considering all the abovementioned aspects
with the existing data. Some additional data may also be collected without spending
much time and with lesser accuracy. The purpose of this is to screen out some
alternatives which are considered poor and prepare a short list of promising alternatives
and decide upon the additional data to be collected.
57
Feasibility Investigations
This stage involves collecting data with the desired accuracy and analysis of the
alternatives shortlisted as a result of the preliminary investigations. This stage also will
cover all the pertinent aspects of the project and forms the basis of a provisional selection
of the project plan.
Detailed Investigations
Once the provisionally selected plan is approved, detailed investigations for the
same have to be carried out. Fixing up the size of various components of the project, their
design incorporating any additional information as well as collecting more data as
required are all part of this stage. The planning for construction is also part of the work to
be carried out.
The storage capacity required to support a given firm yield can be obtained using
the mass curve. Mass curve is a plot of the cumulative inflow into the reservoir – usually
in million hectare metres – over a period of time (Fig.7.1). The time is generally taken
over a period of years.
Fig.7.1
Flood control requires empty storage space in the reservoir and hence the
procedure for determination of such space is somewhat different. The major factor in
flood control projects is to limit the peak overflow from the reservoir, which is dictated
by considerations of the safe carrying capacity of the downstream channel and prevention
of flooding of downstream areas. The procedure used for this is of flood routing through
58
the reservoir. This has been discussed later alongwith the discussion on spillways. The
only point to be noted is that if empty space is available in the reservoir then it will be
filled up first and the outflow during this period will be zero. Once the water in the
reservoir attains the level of the spillway crest, the procedure is similar to that discussed
therein. The outflow hydrograph will thus start at a later time and its peak will be lower
compared to what it would have been if the reservoir was full to start with. The outflow
hydrograph with different values of empty space can be obtained and the one which has a
peak equal to that desired on the downstream side then gives the storage to be reserved
for flood control.
SEDIMENTATION OF RESERVOIRS
59
60
8. GRAVITY DAMS
Gravity dams are rigid dams which ensure stability against all loads by virtue of
their weight alone. They transfer all the loads to the foundation and hence are built when
the foundation is strong rock. A typical section of a gravity dam is shown in Fig.8.1
Fig.8.1
Uplift
There is always some seepage within the body of the dam as well as through the
foundations and this gives rise to an uplift force (U) acting vertically upwards. The uplift
pressure is assumed to be equal to the full water pressure at the upstream face and
varying linearly to the tail water pressure at the downstream face. Almost all gravity
dams are provided with internal drains which modify the uplift pressure distribution.
Studies indicate that the pressure at the drains drops to a value equal to the tail water
pressure plus one third the difference between the upstream and downstream pressures.
Silt Load
Earthquake Force
61
directions. Horizontal and vertical “seismic coefficients” are used to appropriately
modify these forces to account for the effect of earthquakes.
Other Forces
These include the force due to the impact of waves on the upstream face of the
dam, ice loads in case of dams in extremely cold regions where a sheet of ice may form
in the reservoir and thermal loads. Methods for estimation of these are available.
Overturning
If the moments of the destabilizing forces (such as water pressure on the upstream
face and uplift) about the toe of the dam exceed those of the stabilizing forces (mainly the
weight of the dam), the dam can overturn. This condition, however will not arise if the
condition (iii) discussed below is taken care of.
Sliding
A gravity dam may fail in sliding at any horizontal plane if the sum of the
actuating horizontal forces above that plane is more than the resistive forces. The
actuating forces are due to water pressure, silt load etc. while the resistive forces are due
to friction and the shear strength of the material of the dam. A measure of the stability
against sliding is the shear-friction factor of safety (SFF), defined as
Where C is the cohesion, A the area of the horizontal plane, µ the coefficient of
friction and ∑W and ∑H is the sum of the vertical and horizontal forces respectively.
The value of SFF should obviously be more than 1 and the actual value required
depends on the loading conditions considered in the analysis.
If a vertical load W acts on the base, the normal compressive stress at the base
will be W/A, A being the area of the base. This however is true only if the vertical load
acts through the centre of the base. In case the load W is eccentric, the maximum and
minimum stress will be given by (W/A) (1+6e/b) and (W/A) (1-6e/b) respectively, where
e is the eccentricity and b the base width. Thus while for e less than or equal to b/6 no
tension will develop, for e larger than this, there will be tension at the heel and even the
compressive stress at the toe may become quite large. This condition is to be avoided and
62
thus the design is made such that the resultant of all forces crosses the base within the
middle one third i.e. an eccentricity of less than or equal to b/6.
It can be shown that for a gravity dam subject only to the water pressure on the
upstream face, uplift and its own weight, a right angled triangular section with its apex at
the water level and adequate base width is a safe profile. Such a profile is called the
elementary profile of a gravity dam. The base width of the profile is determined from the
criteria of no tension at the heel and no sliding and the greater of the two is adopted.
Fig.8.2
No tension criteria
In the case of an elementary profile, if the reservoir is empty the only force acting
on the base will be the self weight (Wc) of the dam. This will act through the centre of
gravity of the section and thus intersect the base at a distance b/3 from the upstream face.
The eccentricity is thus b/2-b/3 i.e. b/6 and therefore satisfies the condition for no
tension. Since there is no horizontal force acting under these circumstances, there is no
question of overturning or sliding.
For the reservoir full case, the forces acting will be the water pressure (P) and
uplift (U) in addition to the self weight of the dam as shown in Fig.8.2 While the former
of these forces is horizontal, the later two are vertical and hence the resultant (R) will be
inclined to the vertical. In order to satisfy the criteria of no overturning this resultant must
intersect the base within itself and not pass out of the base. For no tension the resultant
must cut the base within the middle one third as this leads to an eccentricity of less than
or equal to b/6. In the limit the resultant must cut the base at the extremity of the middle
one third (point E in Fig.8.2). This automatically satisfies the no overturning criteria also.
The base width required for this can be worked out as below:
Wc =γsbh/2
P =γh2/2
U = γhb/2
Since R passes through E, taking moments about E gives
(γh2/2) h/3 + (γhb/2) b/3 = (γsbh/2) b/3
which yields
b = h/√(s-1)
No sliding criterion
For no sliding, the friction at the base must exceed the horizontal force acting on
the dam i.e. the water pressure. In the limit the two should be equal and thus one can
write
63
µ (Wc – U) = P
The preliminary design of a gravity dam starts with assuming its section. The
elementary profile can serve as a guide for the same with provision of freeboard, finite
crest width, batter near the bottom of the upstream face etc. The section thus obtained
needs to be analysed to determine the stresses in the section and other factors of safety.
This can be a simple two dimensional analysis which can be carried out using the gravity
method for different loading combinations. An actual dam however, will hardly exhibit
two-dimensional behaviour and will also have inspection and drainage galleries and
many other features which cannot be accounted for in the gravity analysis. One will then
have to resort to a much more complicated three dimensional analysis such as the trial
load method or a finite element analysis, before finalizing the design. The details of the
design procedure and methods of analysis are beyond the scope of the present discussion.
64
65
9. EMBANKMENT DAMS
Embankment dams are made of earth material and are suitable for situations where the
valley is wide and the foundation is weak rock or thick soil deposit and/or the abutments are
also weak. This type of dam is more flexible than the rigid dam and can withstand some
degree of foundation deformation more easily.
While earthfill dams or earth dams as they are generally called comprise primarily of
soil material, rocks form the bulk in a rockfill dam. The design principles of both these being
similar, only those for the earth dams are discussed here.
Earth dams can also have two types of sections viz. homogeneous or zoned.
Homogeneous earth dams are constructed of only one type of material and are used
only when the height of the dam is small and only one type of material is available
economically. In case the height of the dam exceeds about 6m, a modified homogeneous
section is used. The modified homogeneous section has some drainage arrangement provided
at the downstream side to provide stability as well as help in controlling the effects of
seepage. Typical sections of homogeneous dams are shown in Fig.9.1.
Fig.9.1
Zoned earth dams consist of an impervious core flanked by zones of more pervious
material called the shelll. The permeability of the material goes on increasing as one moves
away from the core. This is the most common type of earth dam and many high earth dams
such as Nurek (300m), Oroville (224m) and Ramganga (125m) are of this type. The
impervious core may be centrally placed or sloping. Both have their advantages or
disadvantages depending on the site conditions and availability of material. While the core
makes the section impervious thereby reducing seepage through the dam, the shell supports
and protects the core. Typical sections of zoned earth dams are shown in Fig.9.2 The top
width of the dam depends on the height and typically varies from about 2.5m to 6m but can be
much more for high dams.
Fig.9.2
66
CRITERIA FOR SAFETY OF EARTH DAMS
The design of earth dams is carried out to conform to the criteria of safety for the
same. These are based on observations on existing dams and study of failures. The main
criteria can be listed as below:
(i) No overtopping i.e. water must not flow over the dam under any circumstances
as this could lead to certain failure of the dam.
(ii) The slopes, both upstream and downstream must be stable under all conditions
(iii) The upstream face must be protected against the action of waves and the
downstream one against action of rain.
(iv) The seepage line must be well within the downstream face
(v) There should be no free flow of water through the dam body.
(vi) The seepage through the foundations must be controlled and not allowed to
cause piping
(vii) The foundation shear should be within permissible limits
Majority of the failures of earth dams have been a result of overtopping. In order to
avoid this, two steps are necessary. The first involves providing adequate spillway capacity.
Liberal provision of spillway capacity in earth dams as compared to rigid dams is mostly
resorted to in order to keep the maximum reservoir level within estimated limits. The second
step is to provide adequate freeboard – the vertical distance between the dam crest and the
still water level in the reservoir. Since the normal reservoir level will be less than the
maximum reservoir level i.e. the level when the design flood occurs, the freeboard with
respect to the former is termed as the normal freeboard while that with respect to the latter is
called the minimum freeboard. The freeboard is also supposed to take into account the safety
against overtopping due to the settlement of the dam and foundations. The parameters on
which the computation of freeboard is based are the wave height, wave run up and wind set
up with an additional margin added for uncertain effects such as settlement, earthquakes etc.
The freeboard is given by:
Freeboard = Greater of design wave height or wave run up + wind set up + margin for
uncertain effects
The computation for design wave height requires determination of the effective fetch
fe and the wind velocity V for the reservoir. The wave height is then determined by:
in which Hw is the wave height in metres, V the wind velocity in m/s and fe the effective fetch
in metres, g being the acceleration due to gravity. The design wave height Hd is taken as 1.67
times the value Hw obtained from the above formula.
67
The wave run up R depends on the design wave height, the ratio of design wave height
to wave length and the embankment slope and roughness and can be determined from curves
relating the first three and correction factors available for roughness. The greater of Hd and R
is used in computing the freeboard with the proviso that it should not be less than 2.0m for
both the normal and minimum freeboard.
STABILITY OF SLOPES
Both the upstream and downstream slopes of an earth dam need to be tested for their
stability under different conditions. The conditions for which the testing is required are listed
below:
The pore spaces between the soil particles are filled with water and this exerts
a pressure called pore pressure. The effective intragranular stress is the total
stress minus the pore pressure. The shear strength of the soil can be given by:
s = c + (σ – u) tan φ
In which s is the shear strength, c the cohesion, σ the total stress, u the pore
water pressure and φ is the angle of internal friction for the soil.
During construction, soil is compacted after pouring water over it and therefore
large pore pressures develop, thereby reducing the effective stress and hence
the shear strength. The pore pressures dissipate with time and the shear
strength increases. In case of rapid mechanized construction, there is not
enough time for the pore pressures to get dissipated and hence it is important to
ensure the stability of slopes during construction as well as at the end of
construction.
68
(iv) Steady seepage
When t he reservoir is full and seepage is taking place through the dam, the
downstream slope is affected by the seepage. It therefore needs checking for
the case of steady seepage.
Besides the above, the stability of slopes also to be ensured for conditions such as
earthquake, heavy rainfall with seepage etc. These are however not included in the present
discussion.
There are many methods of analysis for determining the stability of slopes. However,
only the method of slices, also called the Swedish method will be discussed here. In this
method, like in many others also, a surface of failure of embankment is assumed and the
factor of safety for the same worked out. This process is repeated with a number of trial
surfaces and the one with the least factor of safety is called the critical slip surface. If the
factor of safety for the critical slip surface is more than one, the slope is taken to be stable.
The Swedish method assumes that the slip surface is an arc of a circle. Some guidelines for
getting the critical slip circle are also available, which serve to reduce the trials in as much as
one could assume slip circles in the vicinity of the one predicted by these guidelines and
choose the one with the smallest factor of safety.
Fig.9.3
The following procedure is adopted for analyzing the stability along an assumed slip
circle (Fig.9.3).:
(i) The assumed slip circle is divided into a number of slices. The arc at the
bottom of a slice should normally be contained wholly in one type of material.
(ii) For each slice, assuming unit length of the dam, the actuating and resisting
forces are computed. This is done as follows:
(a) The weight of the slice W is the volume multiplied by the appropriate unit
weight.
(b) The normal component of this weight N is given by W cosα, while the
tangential component T is W sinα.
(c) The uplift force U acts at the bottom of the slice and can be given by
ub/cosα, where u is the average unit pore pressure, b the width of the slice
and α is the angle that the normal to the bottom of the slice makes with the
vertical.
(d) The net normal force thus is (N-U) and results in a shear strength of (N-U)
tanφ.
(e) The shear strength due to cohesion C is cb/cosα and therefore the total
shear strength is C + (N-U) tanφ, where φ is the angle of internal friction.
(f) As is clear from the free body diagram of a slice as shown, the actuating
force i.e. one which tends to cause the sliding is T, while the resisting force
is C+(N-U) tanφ.
69
(g) There are also forces FL and FR acting on the left and right side of the slice.
It is difficult to estimate these and they are generally assumed to cancel
out.
(iii) The computations are carried out in a tabular form and the sum of the actuating
and resisting forces S and T is obtained.
(iv) The factor of safety is computed as
F.S. = ∑S/∑T
In case the pore water pressures are not directly taken into account in the analysis i.e.
if u is ignored, the same can be indirectly taken care of to some extent by using the submerged
unit weight of the soil for computation of the resisting forces and the saturated weight for
computing the actuating forces for the soil mass below the phreatic line. The moist weight is
used in computing these for the soil mass above the phreatic line.
The factor of safety for both the upstream and downstream slopes for all conditions
must be greater than one, though the actual acceptable value will depend on a number of
factors such as the condition under which the slope is being tested, the shape and size of the
dam, the site conditions etc.
In addition to being stable, the upstream slope of the dam has to be protected against
wave action. This is generally done by providing stone pitching on the upstream slope or
providing dumped rip rap over a suitable filter. Likewise, the downstream slope needs
protection against rain, which can cause deep gullies on this slope. The best protection against
rain is turfing – growing grass over this face. In situations where this is not feasible for one
reason or the other, the downstream face is also protected with pitching or dumped rip rap.
SEEPAGE CONSIDERATIONS
An earth dam being composed of earth material, water is bound to seep through it as
well as through the foundations. Though an impervious core is provided in the earth dams,
this is never truly impervious, but only has a low permeability compared to the shell. Certain
quantity of water thus will seep through the core also. Controlling the quantity of seepage and
the effects of seepage through the dam and its foundations is thus very important both from
the point of view of water conservation as well as the safety of the dam.
(∂2h/∂x2) + (∂2h/∂y2) = 0
70
analytical and numerical methods. The present discussion will be confined mainly to the
graphical method and results obtained therefrom.
The graphical method of solving the Laplace equation involves drawing the flownet
for given boundary conditions. In the case of an embankment dam, the topmost streamline,
also called the phreatic line is not known beforehand and hence the difficulty in drawing the
flownet. This is tackled by making use of the solution given by Kozeny, according to which,
the phreatic line for an embankment dam with a parabolic upstream face and a horizontal
drain as shown in Fig.9.4. will be a parabola with its focus F at the start of the horizontal drain
and vertex at V where
FV =
1
2
(d 2 + h2 − d )
And FG = 2 FV
The discharge per unit length of the dam will then be given by
q = K (√(d2 + h2) – d)
Fig.9.4
However, since the actual embankment dam sections do not have a parabolic upstream
face or may not have a filter which is horizontal, the phreatic line in such cases will not be
given by the Kozeny’s parabola (also referred to as the base parabola).
Fig.9.5
Casagrande obtained the flownets for a variety of sections of embankment dams and
found that the phreatic line by and large followed the base parabola with departures at the
entrance and exit points. Thus, while for a homogeneous section with no drains, the base
parabola will have its focus at the point D (Fig.9.5), it will start at a point H where EH is
equal to 0.3 EK. The actual phreatic line will however, start at the point E, normal to the face
AB and take a reverse curve to join the base parabola tangentially. At the exit end, the actual
phreatic line will join the face CD tangentially at I, while the base parabola cuts this face at J.
The value of ∆a/(a+∆a) for different values of the angle α has been given by Casagrande.
αo 30 60 90 135
∆a
0.36 0.32 0.26 0.13
a + ∆a
Fig.9.6
In case the section has a drain other than horizontal such as a rock toe (Fig.9.6), the
focus of the base parabola will be at F and the starting point will be at H as for the case
71
discussed above. The corrections at the entry and exit will also be determined in a manner
similar to what has been discussed above.
Having drawn the phreatic line, the complete flownet can be drawn for the
embankment and the requisite information regarding seepage through the same obtained.
The discharge through the dam can still be determined by the equation
q=K ( (d 2
)
+ h2 − d )
with the value of d being taken as the horizontal distance between the point H and the focus of
the base parabola.
For a zoned embankment section, generally the shell is many times more permeable
than the core and hence the aforesaid analysis needs to be done for the core only, which can
be taken as homogeneous. Analysis on lines similar to the above can also be carried out if the
above condition is not satisfied or in cases where there is a variation of permeability in the
horizontal and vertical directions. These cases have, however not been discussed here.
As already mentioned, all earth dams are provided with some drainage at the
downstream end. This ensures that the phreatic line does not cut the downstream face thereby
preventing the chances of sloughing of the downstream slope. In addition, such a drain also
controls the outgoing seepage water such that it does not remove soil particles i.e. prevents
piping.
The seepage through the foundations can become an important parameter, specially if
the dam is founded on pervious material and can be analysed using a flownet. Reduction of
the quantity of water seeping through the foundations is important in such cases. This can be
done by use of cutoffs- partial or complete. These are shown in Fig.9.7. The cutoff can be a
rolled earth one, which is economical if the depth of the pervious foundation is relatively
small, with a partial cutoff being effective only to a limited extent. Other means such as a
slurry trench filled with clay and bentonite mixture, sheet piles or concrete cut off wall can
also be used for somewhat larger depths of pervious material.
Fig.9.7
In case the depth of the pervious strata is large, a horizontal impervious blanket can be
used to reduce the quantity of seepage through the foundations. The horizontal blanket is
provided on the upstream side (Fig.9.8) and consists of relatively impervious material with
thickness of the order of 0.75m to even 3m or more.
Fig.9.8
72
In the absence of the blanket, the seepage discharge through the foundation can be
given by
Q = Kf (H/xc)Df
where Kf and Df are the permeability and depth of the foundation respectively.
Qb = Kf ((H/(xc+xb))Df
p = Qb/Q = xc/(xc+xb)
It may however be mentioned that the above is a simplified analysis and the
effectiveness of the blanket will reduce with increasing length.
The seepage water should not get a free flow path through the body of the dam,
because in such a case the flowing water can dislodge soil particles and create a cavity within
the dam body by piping. This could ultimately lead to the failure of the dam. Such a free flow
path can generally be available along the outside of outlet pipes etc. embedded within the dam
and as such these are best avoided in an earth dam. In case it becomes necessary to embed the
same, extreme care has to be taken.
FOUNDATION SHEAR
The foundation of an embankment dam must be safe in shear. Thus the shear strength
of the foundation material should be more than the shear to which it is subjected. The
distribution of shear on the foundation is not uniform. The factor of safety being the ratio
between the shear strength and the shear intensity, it will vary with the distribution and should
be more than one at the location of maximum shear. Simplified procedures are available,
which can give a good idea of the shear as well as its distribution and should be used to check
the safety of the foundation.
Design Procedure
The design of an embankment dam starts with an assumed section based on the
availability of material, foundation conditions etc. and its modification based on the criterion
of safety as discussed above. Economy also plays a very important role in selecting from a
number of alternatives available before the section is finalised.
73
74
75
76
10. SPILLWAYS
Spillways are structures constructed to provide safe release of flood waters from a
dam to a downstream area - normally the river on which the dam has been constructed.
Every reservoir has a certain capacity to store water. If the reservoir is full and
flood waters enter the same, the reservoir level will go up and may eventually result in
overtopping of the dam. To avoid this situation, the flood has to be passed to the
downstream and this is done by providing a spillway which draws water from the top of
the reservoir. A spillway can be a part of the dam or separate from it.
When a reservoir is full, its water level will be the same as the crest level of the
spillway. This is the normal reservoir level. If a flood enters the reservoir at this time, the
water level will start going up and simultaneously water will start flowing out through the
spillway. The rise in water level in the reservoir will continue for some time and so will
the discharge over the spillway. After reaching a maximum, the reservoir level will come
down and eventually come back to the normal reservoir level. The top of the dam will
have to be higher than the maximum reservoir level corresponding to the design flood for
the spillway, while the effective storage available is only upto the normal reservoir level.
The storage available between the maximum reservoir level and the normal reservoir
level is called the surcharge storage and is only a temporary storage in uncontrolled
spillways. Thus for a given height of the dam, part of the storage – the surcharge storage
– is not being utilised. In a controlled spillway, water can be stored even above the
spillway crest level by keeping the gates closed. The gates can be opened when a flood
has to be passed. Thus controlled spillways allow more storage for the same height of the
dam.
For a given inflow flood hydrograph, the maximum rise in the reservoir level
depends on the discharge characteristics of the spillway crest and its size and can be
obtained by flood routing. Trial with different sizes can then help in getting the optimum
combination.
77
FLOOD ROUTING
Flood routing through a reservoir involves determination of the outflow over the
spillway and change in reservoir elevation corresponding to a given inflow hydrograph.
Any inflow into the reservoir causes a change in the reservoir elevation as well as in
outflow and the continuity equation dictates that the inflow must equal the outflow plus
the change in storage. This forms the basis for flood routing. The known quantities being
the inflow hydrograph, the reservoir elevation versus storage curve and the reservoir
elevation versus the spillway discharge curve (Fig.10.1).
Fig.10.1
( I1 + I2 ) ∆t/2 - ( O1 + O2 ) ∆t/2 = ( S2 – S1 )
where ∆t is a interval of time, I, O and S are the inflow, outflow and storages respectively
with the subscript 1 corresponding to the beginning and 2 to the end of the time period
respectively.
To carry out the process, a suitable time interval is chosen, beginning at the start
of the inflow hydrograph. The inflows at the beginning and end of this interval are
obtained from the inflow hydrograph. The initial reservoir level – usually the same as the
spillway crest level – being known, the outflow and storage corresponding to this is read
from the relevant curves. A value for the reservoir elevation at the end of the period is
then assumed and the outflow and storage corresponding to this are also read. If these
values satisfy the continuity equation as given above then this becomes the reservoir
elevation at the end of the period, otherwise the trial elevation is revised till the above
equation is satisfied. This value then gives the elevation and outflow at the end of the
time period. With these values as the initial values, the process is repeated for the next
time interval and so on till the whole of the outflow hydrograph has been obtained. This
computation also yields the maximum reservoir elevation.
TYPES OF SPILLWAYS
There are different types of spillways that can be provided depending on the
suitability of site and other parameters. Generally a spillway consists of a control
structure, a conveyance channel and a terminal structure, but the former two may be
combined in the same for certain types. The more common types are briefly described
below.
Ogee Spillway
The Ogee spillway is generally provided in rigid dams and forms a part of the main
dam itself if sufficient length is available. The crest of the spillway is shaped to conform
78
to the lower nappe of a water sheet flowing over an aerated sharp crested weir. The
profile has been studied extensively by the United States Bureau of Reclamation (USBR)
(Fig.10.2).
Fig.10.2
y/Hd = -k ( x/HD ) n
where the value of k and n depends on the slope of the upstream face of the spillway and
is available in the form of curves, being 0.5 and 1.87 respectively for a vertical upstream
face. HD is the design head which is taken as 0.75 Hmax, being maximum expected head
over the spillway.
The profile to the left of the crest is given by a double circle as shown in the
figure. The values of the parameters defining these circles can also be read from curves
given by USBR.
The profile given by the above equation to the right is continued till a point at
which the tangent to the curve has a slope equal to the slope of the downstream face of
the dam. Thereafter it continues at the same slope and given a reverse curve near the
bottom.
Q = C L H3/2
Where L is the effective length of the crest, H the head over the crest and C is a
coefficient which depends- besides other factors – on the ratio of H to the design head
HD.
If the spillway is operated at heads less than the design head, the sheet of water
will have a tendency to press against the spillway surface resulting in positive pressures
over the surface and in reducing the value of C. At the design head, the pressures over the
surface will be atmospheric and at larger heads, these will be below atmospheric i.e.
negative. The negative pressures will result in increased value of C and thus are
advantageous from the discharging capacity point of view. Large negative pressures
could however cause stability problems. The operating head therefore is not allowed to
exceed the design head by more than a certain amount. This can be ensured by designing
the crest for a head which is about 75-80 % of the head expected for the design flood.
In this type of spillway, the water, after flowing over a short crest or other kind of
control structure, is carried by an open channel (called the “chute” or “trough”) to the
downstream side of the river (Fig.10.3). The control structure is generally normal to the
conveyance channel. The channel is constructed in excavation with stable side slopes and
79
invariably lined. The flow through the channel is supercritical. The spillway can be
provided close to the dam or at a suitable saddle away from the dam where site conditions
permit.
Fig.10.3
This type of spillway is ideally suited for embankment dams and for rigid dams in
narrow valleys where the river bed immediately downstream of the dam is of erodible
material.
Side channel spillways are located just upstream and to the side of the dam
(Fig.10.4). The water after flowing over a crest enters a side channel which is nearly
parallel to the crest. This is then carried by a chute to the downstream side. Sometimes a
tunnel may be used instead of a chute.
Fig.10.4
The crest is usually an ogee profile and generally straight in plan though shapes
like “L” or “U” have also been sometimes used.
This type of spillway utilizes a crest circular in plan, the flow over which is
carried by a vertical or sloping tunnel on to a horizontal tunnel nearly at the streambed
level and eventually to the downstream side (Fig.10.5). The diversion tunnels constructed
during the dam construction can be used as the horizontal conduit in many cases.
Fig.10.5
The crest can be a standard crest or a flat crest. While the former has a larger discharge
coefficient, the later requires smaller funnel diameter and hence economical if excavation
has to be carried out. The standard crest conforms to the lower nappe of flow over a
circular sharp crested weir. The ideal condition favouring this type of spillway is when
there is a rock outcrop in the reservoir somewhat upstream of the dam.
80
Siphon Spillway
As the name indicates, this spillway works on the principle of a siphon. A hood
provided over a conventional spillway forms a conduit (Fig.10.6). With the rise in
reservoir level water starts flowing over the crest as in an ogee spillway. The flowing
water however, entrains air and once all the air in the crest area is removed, siphon action
starts. Under this condition, the discharge takes place at a much larger head. The spillway
thus has a larger discharging capacity. The inlet end of the hood is generally kept below
the reservoir level to prevent floating debris from entering the conduit. This may cause
the reservoir to be drawn down below the normal level before the siphon action breaks
and therefore arrangement for depriming the siphon at the normal reservoir level is
provided.
Fig.10.6
One of the important aspects of the siphon spillway is its priming and therefore
priming devices such as a joggle or baby siphon are used to ensure early priming.
Cracking of the hood can lead to depriming by allowing entry of air. The spillway is
therefore provided in batteries so that the whole spillway does not get deprimed by the
cracking of one portion of the hood.
While this kind of spillway has a larger discharge for the same rise in reservoir
level, it has problems of vibration and noise. Cavitation can also be a problem in some
cases.
The water flowing over a spillway loses a large amount of its potential energy. A
good percentage of this is converted into kinetic energy and subsequently the flow at the
toe of the spillway is a high velocity flow. If allowed as such to flow in the river, it is
likely to cause considerable bed erosion and as such some sort of energy dissipation is
required before allowing this flow into the river. Generally two major types of energy
dissipating devices are used for spillways. These are the hydraulic jump type stilling
basin and the bucket type energy dissipators.
As the name indicates, these basins employ the hydraulic jump as the energy
dissipation mechanism. The characteristics of the jump- such as the length, efficiency in
energy dissipation etc.- depend on the initial Froude number and the tailwater conditions.
Appurtenances such as chute blocks, baffle blocks and end sill are also used to increase
the efficiency as well as to decrease the length of the basin (Fig.10.7).
Fig.10.7
A comprehensive study of this type of basins was carried out by the United States
Bureau of Reclamation and certain types of basins have been recommended by them for
81
various initial Froude numbers and inflow velocities. These basins- referred to as USBR
Type II, Type III etc.- are suitable for different ranges of initial Froude numbers. The
appurtenances to be used in each type are also specified. The dimensions of the basin as
well as of the appurtenances to be employed in each case are given in the form of curves,
which can be used to design the basin for a given set of conditions.
These are used when the tailwater depth is either too low or too high for the
formation of a hydraulic jump, rendering a jump type basin uneconomical. The bucket
can be a ski-jump bucket or a roller bucket.
Fig.10.8
This type of bucket is used when the tailwater depth is quite low for the formation
of a jump. The water leaves the bucket as an upturned jet (Fig.10.8) and strikes
the river bed somewhat downstream of the spillway. During its trajectory, the jet
splits into smaller jets and part of the energy is dissipated due to air friction. The
bulk of the energy dissipation however takes place due to the impact of the jet on
the water and river bed downstream. This also requires that the river bed be
comprised of hard rock to withstand the impact of the jet.
2. Roller Bucket
Fig.10.9
This type of bucket is used when the tailwater depth is too large for the formation
of a jump. The water entering the bucket forms a roller- called the bucket roller-
within the bucket and another one – called the ground roller- just downstream of
the bucket (Fig.10.9 a). While the former is anticlockwise, the latter moves in a
clockwise direction. Energy dissipation takes place because of the interaction
between the two rollers and the intermingling of the inflow with the same. The
ground roller has a tendency to pile up loose material against the bucket lip and if
some of this enters the bucket, it will keep moving with the bucket roller and can
cause objectionable abrasion in the concrete surface. To avoid this, a slotted
bucket is sometimes used instead of a solid bucket. The slotted bucket has teeth
and gaps (Fig.10.9 b) and leads to better flow conditions downstream, besides
allowing any material that may enter the bucket to leave through the gaps.
SPILLWAY GATES
There are three major types of gates provided in spillways. These are (Fig.10.10):
Fig.10.10
82
1. Vertical Lift Gates
These gates are made of steel plate and move in gate grooves provided in the
supporting piers. They move vertically in their own plane and are operated from a
hoist chamber, which has to be at a higher elevation than the raised position of the
gates.
2. Tainter Gates
Also called radial gates, these are segments of a cylinder made of steel plate and
connected to a trunnion at the centre of the arc. The hoist chamber is suitably
located and normally does not have to be as high as in case of vertical lift gates.
3. Drum Gates
These are in the form of a floating drum which is hinged at the top and sits in a
float chamber within the spillway crest. Raising of the gate is accomplished by
allowing water under pressure into the float chamber, while for lowering the same
another valve is used to empty the float chamber.
83
84
85
86
87
88
11. SOME SPECIAL PROBLEMS OF HILLY STREAMS
Hilly streams have many characteristics which are quite different from those in
the alluvial plains. Thus most of the hilly streams would have steep longitudinal slopes,
high velocity flow which generally does not follow the logarithmic distribution, large bed
roughness and narrow cross section with steep banks. Many of the techniques and
formulae used for alluvial rivers will not be applicable to such streams. This section is
intended to discuss very briefly some of these differences.
FLOW CHARACTERISTICS
The flow in hilly streams depends on the slope and bed material size. This would
vary from the origin of the stream to the foothills where the stream enters the plains, with
the slope and bed material size decreasing continuously. Thus while in the upper reaches
the bed will have predominance of boulders with very little finer material, further down
gravel will predominate till in the plain region it will mostly be sand.
Fig.11.1
Due to the low time of concentration, hilly streams generally have flash floods i.e.
the flood hydrograph has a small time base with rapid rise and fall. The estimation of
flood flows in the absence of data would require estimation of the bed resistance in
addition to the cross section, depth of flow and longitudinal slope. The estimation of bed
resistance using the procedures available for alluvial rivers is likely to result in
overestimation of the resistance and hence the flow.
RIVER TRAINING
There is hardly any possibility of a hilly stream changing its course. This is so
because of the type of cross section which is characterized by high banks. River training
works of the type already discussed therefore are not necessary for these streams. The
possibility of landslides is however always there, specially due to sloughing or by
89
undercutting in case one of the banks is being attacked by the stream. Bank protection
measures may be required in such situations. This is usually done by providing toe walls
at sites vulnerable to landslides. The toe walls have to be designed to withstand the
impact of boulders which will roll along during floods
DIVERSION STRUCTURES
The type of diversion structures discussed earlier i.e. weir with a raised crest or
barrage are not suitable for the boulder reaches. The boulders rolling along with the flow
during floods are likely to damage such structures or the gates. Alternative designs such
as the trench weir – discussed earlier – which are not likely to suffer major damage by
rolling boulders, are more suitable under such conditions. The canals also are contour
channels. Sediment exclusion is generally not a problem as most of the sediment is coarse
and moves along the bed. The traditional sediment exclusion devices are not suitable as
they can be blocked by large size particles or suffer damage by boulders. The use of
vortex chambers to exclude coarser material in case of power channels is possible in
gravel bed streams.
The waterway and scour in alluvial rivers is generally determined using the
Lacey’s theory. This theory is however not applicable to boulder or gravel beds. While
the determination of the waterway is not an issue in hilly streams because they do not
have wide flood plains, the determination of the likely scour may be needed. This could
be done by estimating the largest size of boulder that may get displaced during floods.
The size of such a boulder multiplied by an appropriate factor is likely to give an estimate
of the scour.
The loss of water by seepage underneath the structures is also likely to be more in
these streams because of the larger sediment size and hence increased permeability.
It may however be mentioned that the problems will vary depending upon the
topography, the bed material, the high flood discharge and many other parameters. No
single prescription can work for the boulder reach as well as the gravel reach equally and
a detailed discussion of all these is beyond the scope of the present work.
90
91
12. GROUND WATER
Ground water is the water occurring under the earth’s surface and fills the pores
and fractures of the subsurface medium. It can be divided into two zones viz. the
saturated or phreatic and the unsaturated or vadose zones. The saturated zone has all its
pores filled with water while in the unsaturated zone, pores contain gases alongwith water
(Fig.12.1).
Fig.12.1
Water Table: The top of the saturated zone, where the pressure is equal to the
atmospheric pressure, is known as the water table. It is however worth mentioning that
there is a capillary rise depending on the pore size and the medium can be saturated even
in the capillary zone but the pressure there is below atmospheric.
Fig.12.2
Ground water movement takes place both in unconfined and confined aquifers
depending on the hydraulic gradient. Thus an aquifer acts both as storage as well as a
conduit for ground water.
Some definitions, characterizing aquifers, useful in the study of ground water are
given below:
Porosity- is the ratio of the volume of pores to the total volume of the porous
medium.
Specific Yield – A saturated soil formation will yield certain amount of water
under gravity. The ratio of this volume to the total volume of the formation is called the
specific yield of the formation.
Specific Retention – This is the ratio of the volume of water retained by the
formation after it has been drained under gravity to the total volume of the formation. The
sum of the specific yield and the specific retention thus are equal to the porosity.
92
Storage Coefficient – is defined for confined aquifers and is the volume of water a
confined aquifer will release per unit surface area of the aquifer for a unit change in the
head.
Transmissivity (T) – is generally used for confined aquifers and is the product of
the hydraulic conductivity and the thickness of the saturated portion of the aquifer.
DARCY’S LAW
The flow of liquids through porous media is governed by the Darcy’s law, which
states that the rate of flow through a saturated medium is proportional to the hydraulic
gradient and the cross-sectional area of flow.
Q = - K A (dh/ds)
In which, Q is the rate of flow, A the cross-sectional area and dh/ds represents the
hydraulic gradient which is negative as h decreases in the direction of flow, K being a
constant of proportionality which is equal to the hydraulic conductivity of the medium.
The aforesaid relationship applies so long as the flow is laminar, which is the case
most of the times as far as ground water is concerned. This law is considered to be valid
in a Reynold’s number range from 1 to 10, with the Reynold’s number Re being defined
as
Re = V d ρ/µ
In which V is the velocity, d the average grain diameter, ρ and µ are the density
and viscosity of fluid respectively.
V = - K (dh/ds)
93
u = -Kx (∂h/∂x )
v = -Ky (∂h/∂y)
w = -Kz (∂h/∂z )
in which Kx, Ky and Kz are the coefficients of permeability in the x, y and z directions
respectively.
For an unconfined aquifer, one obtains the Dupuit’s equation, which is based on
the assumption that the free surface curvature is small enough so as to make the w
component of the velocity negligible. This equation has the following form
(∂2H2/∂x2) + (∂2H2/∂y2) = 0
Well Hydraulics
Wells are structures used to pump water from an aquifer. They consist of an
intake which is a slotted pipe with screen to prevent fine sediment from entering the well
and a vertical casing pipe to convey the water to the surface.
94
Fig.12.3
As the pumping from a well starts, the radius of influence and drawdown for an
extensive aquifer start increasing with time and attain a constant value once the rate of
pumping becomes equal to the rate of recharge. The well is then said to have attained
equilibrium conditions.
An expression for the discharge through a well can be obtained by writing the
Boussinesq/Dupuit equations for confined/unconfined aquifers in the radial coordinate
system and integrating them with the appropriate boundary and initial conditions. For
equilibrium conditions, this results in the following equations:
d = Q W(u)/(4πT)
u = r2 S/(4Tt)
For a fully penetrating well in an unconfined aquifer, the solution was given by
Boulton and can be expressed as
Ck being a correction factor which depends on t’ and V(t’, r’) is the Boulton’s
well function the values of the same being available as a function of t’ and r’, which are
defined as
t’ = Kt / (SH0)
and
r’ = r / H0
95
Pumping Tests
T = Q ln (r2 / r1 ) / (2(h2 – h1 ))
96
97
98
13. DECISION SUPPORT SYSTEMS IN WATER
RESOURCES
It is being increasingly realised that water resources related decisions cannot be
taken in isolation. While surface water and ground water have to be dealt with together
because of the strong interaction between these components, there are a number of other
interacting parameters that need to be considered in planning and managing water
resources. These range from the water quality, environmental, economical and socio-
economical, land use and stakeholder perceptions to sustainability and the like. It is also
being realised that water related decisions have to be taken with the basin as a unit rather
than an isolated catchment, as any intervention somewhere is likely to have an impact
elsewhere.
Decision Support Systems traditionally have three major components viz. a user
interface, a database and a model base, besides the management tools necessary for the
intended purpose.
The user interface component is to present and receive information from a user
and various types of interfaces have been developed for the same. The database
component manages data while the model base keeps track of the various models and
methods that may be needed in any given Decision Support System.
99
USER INTERFACE
MANAGEMENT
TOOLS
ENVIRONMENT
Some of the issues connected with the various components are briefly discussed
below:
DATA MANAGEMENT
In addition to collection, analysis and presentation is necessary to transform data
to information, which can be used by the decision-maker.
Data Types
Data can be temporal, spatial or attribute data. Attribute data generally record
information about the other two data types. While temporal data may reside in different
formats in a database, spatial data is mostly in a GIS platform.
100
Data Storage
Data Warehouse and Data Mart are the basic architectural options to interface
with the Decision Support Systems. The data in a Data Warehouse contains multiple
subject areas while Data Marts are a scaled down version of Data Warehouse and usually
subject specific.
Data Retrieval
Data Interchange
Any DSS may use a number of models, which require data from different types of
sources such as time series database systems, relational database management systems,
GIS or data synthesis systems. Sometimes these sources may be with different
organisations and all the data in one particular type of source may also not always be in
the same format. The data along with information about the data- metadata as it is
referred to- has to be exchanged between what are called the Information Providers and
Information Consumers and therefore a standard data exchange system is a necessity.
MODELLING ISSUES
Modelling has come a long way from the early computational models and
simulation. Five generations of models have been identified. The first three were
concerned with performing numerical tasks, custom models for a particular region or
system and generalisation of these custom models respectively. The fourth generation
models built on the work of the first three generations and combined codes and products
from several third generation products. Another important development was to establish
the distinction between tool-maker and tool-user.
The fifth generation models combined the tools of computational hydraulics with
the tools of artificial intelligence and incorporated sophisticated visualisation tools to
allow the non-experts to better comprehend the results.
101
Soft Computing Techniques
It may not be out of place to mention here some of the Artificial Intelligence (Soft
Computing) techniques, which have emerged in recent years as a complement tool to
mathematical approaches and are being increasingly used in water resources applications.
Expert Systems- These are knowledge-based or rule-based systems, which use the
knowledge base and inference engines to solve problems. These however do not have the
ability to learn or adapt to new situations. A schematic of a knowledge-based expert
system is shown in Fig.13.2.
EXPERT SYSTEM
EXPLANATION CASE
MODULE INFERENCE HISTORY
ENGINE FILE
USER
I/O
INTERFACE KNOWLEDGE
BASE WORKING
MEMORY
EDITOR LEARNING
MODULE
X Y
102
Agents- an agent is something that perceives and acts in an environment. It is a
self contained software program specialised in obtaining a set of goals by autonomously
performing tasks. Agents could be simple reflex; model-based reflex, goal-based or
utility based. All the types can improve their performance through learning. Fig. 13.4
shows a schematic of learning agents.
PERFORMANCE STANDARD
CRITIC SENSOR
ENVIRONMENT
LEARNING PERFORMANCE
ELEMENT CHANGES ELEMENT
KNOWLEDGE
PROBLEM
GENERATOR
ACTUATORS
Model Integration
1. Integrating the model implementations for a given set of packages. This however
does not seem to be very useful as such an exercise will have to be carried out
separately for all combinations of packages.
103
2. Providing shells for pre- and post-processing to generate configurations for a range of
models. This is also considered as a partial solution only.
3. Developing integration frameworks and integrating models with the framework. Most
of the current effort is directed primarily towards this approach.
USER INTERFACE
The user interface is the component of the system, which facilitates the interaction
between the user and the system, the major types being:
The growing complexity of interfaces and the need for flexibility has given rise to
the development of “intelligent interfaces” which can anticipate and adapt to the needs of
different users, can learn new techniques and concepts and provide explanation of their
actions.
104