0% found this document useful (0 votes)
66 views1 page

Ms Project Tutorial 66

This document provides instructions for entering fixed costs and recurring tasks in Microsoft Project 2013. To enter a fixed cost, go to the View tab, Data group, Tables menu, and Cost table to assign a fixed dollar amount to a task. To create a recurring task, go to the Task tab, Insert group, select Recurring Task from the dropdown, name the task, choose a recurrence pattern, and optionally specify a start time other than the default project start.

Uploaded by

John
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
66 views1 page

Ms Project Tutorial 66

This document provides instructions for entering fixed costs and recurring tasks in Microsoft Project 2013. To enter a fixed cost, go to the View tab, Data group, Tables menu, and Cost table to assign a fixed dollar amount to a task. To create a recurring task, go to the Task tab, Insert group, select Recurring Task from the dropdown, name the task, choose a recurrence pattern, and optionally specify a start time other than the default project start.

Uploaded by

John
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

MS Project 2013

Enter Fixed Cost


Fixed Cost is associated with a task that is not tied to any resources or amount of work.

Click View Tab -> Data group -> Tables -> Cost.

Enter the cost under the Fixed Cost column for the task of interest. In the following
example, we have assigned a fixed cost of $500 to Task 7.

Enter a Recurring Task


Status meetings, status reports, inspection dates can recur with a particular frequency. In
MS Project 2013, you can specify recurring tasks without having to assign tasks each time
separately. You can also assign resources to these task.

In Gantt Chart View -> Task Tab -> Insert group -> dropdown box for Task -> Recurring
Task.

Enter Task Name and choose Recurrence pattern.

You can also choose a specific time for the task to start as well. By default Project
schedules a recurring task to start on plan’s default start time. You can add time value in
the Start box for Recurring Task Information dialog box to change this. In the following
figure, start time of 10:00 AM is entered.