Trench Excavation and Backfill Part 1 - General 1.01 Section Includes
Trench Excavation and Backfill Part 1 - General 1.01 Section Includes
PART 1 - GENERAL
1.03 SUBMITTALS
Follow the General Provisions (Requirements) and Covenants, as well as the following:
C. Dewatering plan.
1.04 SUBSTITUTIONS
None.
1 10/18/2011
SUDAS Standard Specifications Division 3 - Trench and Trenchless Construction
Section 3010 - Trench Excavation and Backfill
A. General: The following items are incidental to the underground utility being installed and will
not be paid for separately:
2. Removal and disposal of unsuitable backfill material encountered during standard trench
excavation.
6. Dewatering.
8. Adjusting the moisture content of excavated backfill material to the range specified for
placement and compaction.
9. Temporary support for existing water, sewer, gas, telephone, electric, and other utilities
or services that cross the trench.
B. Rock Excavation:
2. Payment: Payment will be at the unit price per cubic yard for the quantity of rock
removed.
C. Trench Foundation:
2. Payment: Payment will be at the unit price per ton for the quantity of stabilization
material furnished and placed.
3. Includes: Unit price includes, but is not limited to, removal and disposal of over-
excavated material required to stabilize trench foundation; and furnishing, hauling, and
placing stabilization material.
1. Measurement: Measurement will be in cubic yards for the quantity of backfill material
required to replace unsuitable backfill material removed during standard trench
excavation. Measurement will be based on compacted material in place.
2. Payment: Payment will be at the unit price per cubic yard for the quantity of backfill
material furnished.
3. Includes: Unit price includes, but is not limited to, furnishing, hauling, and placing
backfill material.
2 10/18/2011
SUDAS Standard Specifications Division 3 - Trench and Trenchless Construction
Section 3010 - Trench Excavation and Backfill
1. Measurement: Measurement will be by the linear foot along the centerline of pipe for
each type of special embedment or encasement.
2. Payment: Payment will be at the unit price per linear foot for each type of special pipe
embedment or encasement.
3. Includes: Unit price includes, but is not limited to, furnishing and placing all required
special pipe embedment or encasement materials.
1. The Contractor is not responsible for trench compaction testing unless otherwise
specified in the contract documents.
2. If the contract documents specify that the Contractor is responsible for trench compaction
testing performed by an independent testing laboratory hired by the Contractor,
measurement and payment will be as follows:
a. Measurement: Lump sum item; no measurement will be made.
b. Payment: Payment will be the contract lump sum price.
3. The Contractor will be responsible for payments associated with all retesting resulting
from failure of initial tests.
3 10/18/2011
SUDAS Standard Specifications Division 3 - Trench and Trenchless Construction
Section 3010 - Trench Excavation and Backfill
PART 2 - PRODUCTS
A. Standard Trench Excavation: All materials encountered during trench excavation, except
rock and over-excavation.
1. Suitable Backfill Material: Class II, Class III, Class IVA, or Class IVB as defined in
Section 3010, 2.02.
2. Unsuitable Backfill Material: Includes, but is not limited to, the following materials:
a. Soils not classified as suitable backfill material, as defined in Section 3010, 2.02.
b. Individual stones or concrete chunks larger than 6 inches and averaging more than
one per each cubic foot of soil.
c. Frozen materials.
d. Stumps, logs, branches, and brush.
e. Trash, metal, or construction waste.
f. Soil in clumps or clods larger than 6 inches, and without sufficient fine materials to fill
voids during placement.
g. Environmentally contaminated soils.
h. Materials removed as rock excavation or over-excavation.
A. Class I Material:
2. The Engineer may allow the use of gravel or authorize a change in gradation subject to
materials available locally at the time of construction.
3. The Engineer may authorize the use of crushed PCC for pipe sizes up to 12 inches.
4 10/18/2011
SUDAS Standard Specifications Division 3 - Trench and Trenchless Construction
Section 3010 - Trench Excavation and Backfill
Soil Group
1 1/2 in. No. 4 No. 200
Class Type Symbol Description
(40 mm) (4.75 mm) (0.075 mm)
D 2487
II Coarse-Grained Soils, GW Well-graded gravels and 100% <50% of < 5%
clean gravel-sand mixtures; little or "Coarse
no fines. Fraction"
Coarse-Grained Soils, e.g. Sands and gravels which are 100% Varies 5% to 12%
borderline clean to with GW-GC, borderline between clean
fines SP-SM and with fines.
1. Natural coarse-grained soils with fines. Class III materials are further described in Table
3010.02.
Soil Group
Class Type Symbol Description
D 2487
III Coarse-Grained Soils, with GM Silty gravels, gravel-sand-silt
fines mixtures.
GC Clayey gravels, gravel-sand-
clay mixtures.
SM Silty sands, sand-silt
mixtures.
SC Clayey sands, sand-clay
mixtures.
1. Natural fine-grained inorganic soils. Class IVA materials are further described in Table
3010.03.
2. The Engineer will determine if material is not suitable for use as backfill material under
deep fills, surface applied wheel loads, heavy vibratory compactors, tampers, or other
conditions.
5 10/18/2011
SUDAS Standard Specifications Division 3 - Trench and Trenchless Construction
Section 3010 - Trench Excavation and Backfill
Soil Group
Class Type Symbol Description
D 2487
IVA Fine-Grained Soils ML
Inorganic silts and very fine
(inorganic)
sands, rock flour, silty or
clayey fine sands, silts with
slight plasticity.
CL Inorganic clays of low to
medium plasticity, gravelly
clays, sandy clays, silty clay,
lean clay.
1. Natural fine-grained inorganic (high elastic silts and plastic clays - fat clay) with a liquid
limit greater than 50%. Class IVA materials are further described in Table 3010.04.
2. When approved by the Engineer, material may be used as final trench backfill in a dry
trench.
Soil Group
Class Type Symbol Description
D 2487
IVB Fine-Grained Soils MH
(inorganic) Inorganic silts, micaceous or
diatomaceous fine sandy or
silty soils, elastic silts.
2.04 TOPSOIL
A. Class V Material:
2. Use only as topsoil outside of the pavement, unless otherwise specified or allowed by the
Engineer.
6 10/18/2011
SUDAS Standard Specifications Division 3 - Trench and Trenchless Construction
Section 3010 - Trench Excavation and Backfill
Soil Group
Class Type Symbol Description
D 2487
V Organic Soils OL
(Unsuitable for backfill) Organic silts and organic
silty clays of low plasticity.
OH
Organic clays of medium to
high plasticity, organic silts.
B. The Engineer may authorize a change in gradation depending on materials available locally
at time of construction.
C. CLSM:
7 10/18/2011
SUDAS Standard Specifications Division 3 - Trench and Trenchless Construction
Section 3010 - Trench Excavation and Backfill
PART 3 - EXECUTION
C. Excavate trench to required elevations and dimensions. Comply with Figure 3010.101.
3. Grade spoil piles to drain. Do not allow spoil piles to obstruct drainage.
2. Remove rock, rubbish, boulders, debris, and other unsuitable backfill materials at least 6
inches below and on each side of the pipe.
3. Keep unsuitable backfill material separated from suitable backfill material and topsoil.
B. The Engineer will determine the need for over-excavation and trench foundation stabilization
prior to installation of pipes and structures.
C. Comply with Figure 3010.101 for over-excavation of rock and wet or soft foundations.
A. Install adequate trench protection (sheeting, shoring, and bracing) to prevent ground
movement or damage to adjacent structures, pipelines, and utilities.
B. Move trench boxes carefully to avoid disturbing pipe, bedding, or trench wall.
3.04 DEWATERING
B. Perform the dewatering operation according to the dewatering plan approved by the
Engineer. The dewatering plan may be modified to meet actual field conditions, with approval
of the Engineer.
C. Ensure operation of the dewatering system does not damage adjoining structures and
facilities. Cease dewatering operations and notify the Engineer if damage is observed.
8 10/18/2011
SUDAS Standard Specifications Division 3 - Trench and Trenchless Construction
Section 3010 - Trench Excavation and Backfill
D. Discharged Water:
3. Obtain permission of adjacent property owner prior to discharging water onto their
property.
4. Maintain and control water discharge as necessary to prevent a safety hazard for
vehicular and pedestrian traffic.
6. Use dewatering equipment that will minimize disturbance from noise and fumes.
7. Protect discharge points from erosion. Provide sediment control for sediment
contaminated water discharged directly from trench.
1. Bedding and backfill used for pipe installation will depend on:
a. Type of installation (water main, sanitary sewer gravity main, sanitary sewer force
main, or storm sewer).
b. Pipe material.
c. Depth of bury.
d. Pipe diameter.
2. After pipe installation, place remaining bedding material and immediately place backfill in
trench.
3. Adjust the moisture content of excessively wet, but otherwise suitable, backfill material by
spreading, turning, aerating, and otherwise working material as necessary to achieve
required moisture range.
4. Adjust the moisture content of excessively dry, but otherwise suitable, backfill material by
adding water, then turning, mixing, and otherwise blending the water uniformly
throughout the material until the required moisture range is achieved.
5. Hydraulic compaction (flooding with water) is not allowed unless authorized by the
Engineer.
B. Pipe Bedding:
1. Granular Material:
a. Class I granular bedding material is required for all gravity mains. Use when
specified for pressure pipes.
b. Comply with Figures 3010.101 through 3010.105.
c. Place bedding material in the bottom of the trench in lifts no greater than 6 inches
thick. Consolidate and moderately compact bedding material.
d. Shape bedding material to evenly support pipe at the proper line and grade, with full
contact under the bottom of the pipe. Excavate for pipe bells.
e. Install pipe and system components.
f. Place, consolidate, and moderately compact additional bedding material adjacent to
the pipe to a depth equal to 1/6 the outside diameter of the pipe.
9 10/18/2011
SUDAS Standard Specifications Division 3 - Trench and Trenchless Construction
Section 3010 - Trench Excavation and Backfill
C. Haunch Support: Place from the top of the pipe bedding to the springline of the pipe.
1. Granular Material:
a. Place Class I material in lifts no greater than 6 inches thick.
b. Consolidate and moderately compact by slicing with a shovel or using other approved
techniques.
1. General:
a. For primary backfill, place from the springline of the pipe to the top of the pipe.
b. For secondary backfill, place from the top of the pipe to 1 foot above the top of the
pipe.
2. Granular Material:
a. Place in lifts no greater than 6 inches thick.
b. Compact to at least 65% relative density.
10 10/18/2011
SUDAS Standard Specifications Division 3 - Trench and Trenchless Construction
Section 3010 - Trench Excavation and Backfill
1. Place suitable backfill material from 1 foot above the top of the pipe to the top of the
trench.
a. Use no more than 8 inch thick lifts for backfill areas more than 3 feet below the
bottom of pavement.
b. Use no more than 6 inch thick lifts for backfill areas less than or equal to 3 feet below
the bottom of pavement.
5. In areas to remain unpaved, terminate backfill material 8 inches below finished grade.
Use topsoil for the final 8 inches above trench backfill material.
A. General: When trench compaction testing is specified in the contract documents as the
Contractor’s responsibility, provide testing of trench backfill material using the services of an
independent testing laboratory approved by the Engineer.
B. Soil Testing:
1. Cohesive Soils:
a. Determine moisture-density relationships by ASTM D 698 (Standard Proctor).
Perform at least one test for each type of cohesive soil used.
b. Determine in-place density and moisture content. Use ASTM D 1556 (sand-cone
method) and ASTM D 2216 (laboratory moisture content), or use ASTM D 6938
(nuclear methods for density and moisture content).
11 10/18/2011
SUDAS Standard Specifications Division 3 - Trench and Trenchless Construction
Section 3010 - Trench Excavation and Backfill
2. Cohesionless Soils:
a. Determine maximum and minimum index density and calculate relative density using
ASTM D 4253 and ASTM D 4254.
b. For Class I granular bedding material, determine gradation according to ASTM C
136.
C. Field Testing:
1. Testing Frequency and Locations: Perform testing of the final trench backfill,
beginning at a depth of 2 feet above the top of the pipe, as follows:
a. Coordinate the timing of testing with the Engineer.
b. The Engineer will determine the location of testing.
c. For each 2 vertical feet of consolidated fill, provide tests at a maximum horizontal
spacing of 200 feet and at all street crossings.
d. Additional testing may be required by the Engineer in the event of non-compliance or
if conditions change.
e. If necessary, excavate to the depth and size as required by the Engineer to allow
compaction tests. Place backfill material and recompact.
2. Test Failure and Retesting: Rework, recompact, and retest as necessary until specified
compaction and moisture content is achieved in all areas of the trench. In the event of
failed tests, the Engineer may require retesting as deemed necessary.
END OF SECTION
12 10/18/2011