P6 Manual PDF
P6 Manual PDF
Antony Selvaraj
BE MBA MIE
Version 8.2 and above
Project Planning and Scheduling
with Primavera P6
Antony Selvaraj
BE, MBA, MIE
Part-2
Section 4
Primavera P6 Basics
In this section:
Creating Resources
4.1 Introduction
Primavera Systems is the brand name Primavera Enterprise Suite Products include:
under which a range of software packages
that collectively form a comprehensive Primavera P6 Enterprise Project
enterprise project portfolio management Portfolio Management
(EPPM) solution are marketed. Primavera
was launched in 1983 by Primavera Primavera P6 Professional Project
Systems Inc. and was acquired by Oracle Management
Corporation in 2008. Primavera software
includes project management, Primavera P6 Analytics
collaboration, control capabilities, and
integrates with other enterprise software Primavera Portfolio Management
such as Oracle or SAP’s ERP systems
Primavera Unifier
Primavera Enterprise is a suite of
products/tools used for enterprise wide Primavera Contract Management,
project management. It provides Business Intelligence Publisher
comprehensive information on all the Edition
projects in the enterprise, from executive-
level summaries to detailed work Primavera Risk Analysis
assignments for each team member. It is
an integrated solution with Web-enabled, Primavera Inspire for SAP
client/server and desktop software that
provides role-specific tools to satisfy each Primavera Earned Value Management
team member’s needs, responsibilities,
and skills. The tools within the Primavera Primavera Contractor
Enterprise suite are multi-project and
multi-user. Planning and scheduling management
Easy to Use
Extensive wizards
Store and manage projects from a Team members see all supporting
central location information they need to coordinate
and perform their while communicating
directly with the central database.
Methodology Management
P6
Enterprise Data
Enterprise data provides the enterprise structure necessary for centralized project
structure needed to manage multiple and resource management. The data for
projects. It is available to all projects each type is listed below and shown in the
across the enterprise and provides the figure below.
Centralized Project Management Centralized Resource Management
This structure consists of the following: This structure consists of the following:
Project-Specific Data
Enterprise/Project-Specific Data
Calendars
Reports
Activity Codes
Enterprise/User-Specific Data
Layouts
Filters
Global Changes
User Rights
Rights are set at the Enterprise and Project levels. User rights may vary from project to
project. Enterprise rights are defined by Organization, and in general are set so only required
resources for the projects are available to the projects. Project level security can be
requested on a project by project basis if needed.
Project Management is the process of achieving set goals within the constraints of time,
budget, and staffing restrictions. The project management life cycle is made up of these
process groups:
Distribute information
Track work in progress and actual
costs
Once the application is loaded the bars as listed in the Table-2 below. A brief
following screen opens up. This is the description of the functionality of each bar
main window for Projects. Here you will is given in the table.
find a complete list of all projects already
existing in P6. The Projects main window
is the starting point for navigation through
other windows. You can see the following
Download eBooks at: www.industryfitengineer.com Page | 42
Project Planning and Scheduling with Primavera P6: Step by step guide Section-4
S No Item Functionality
Move between open windows, toggle the Directory bar and open
4 Navigation bar
Help
The Projects window, Figure 39, is used to All projects under the node will be
globally review the entire EPS and all the opened.
projects contained within that structure.
This view accesses and edits the project- Open multiple projects under the same
level data of individual schedules and the or different EPS nodes.
project default settings. Finally, it is Press Ctrl + click to select more
through the Projects window that an than one project.
individual project is navigated to and
opened.
Access Modes
Activities Window
S No Item Functionality
Icons that allow you to format the layout. Provides direct
1 Tool bar
access to several useful activity functions.
Options for editing data; contains icons (buttons) to
2 Command bar
add/delete activities, cut, copy, paste and move activities.
3 Gantt chart Graphical display of activities
4.2.2 Layout
You can choose from a number of layouts You can create your own layouts or
to present your project from different use global layouts provided by your
perspectives. This allows you to spend company.
more time managing projects instead of
repeatedly preparing the displays.
Steps:
P6 breaks data up into two categories; global Project level data is project-specific and not
level and project level (User-admin). Global shared across the entire P6 database. Project
level data is used across all project schedules, data includes:
while project level data is project specific. The
Directory Bar splits the global data from the Thresholds and Issues
project data. Risks
Activities
Global level data is available to all projects Dates
across the organization and provides the Expenses
structure necessary for centralized project and Work Products and Documents
resource management. Global level data Baselines
includes: Work Breakdown Structure (WBS)
4. If you click the Global button, the 5. If you click the User – admin button
following dialog box (figure – 43) the following dialog box (figure – 44)
opens. opens.
Figure 4-23: Global layout dialog box Figure 4-24: User - admin layout dialog box
6. From the Global layout options, Select 7. You can see the dialog box as shown
a layout to apply to the project in figure-45.
<Classic WBS Layout>.
8. Click Open.
Gantt chart
Gantt chart is the default view in the are on the critical path (though these
Activities window. It can be customized colours can be edited).
both on the timescale and the information
shown. The bars can be customized to The Classic WBS layout displays a Gantt
show different colours, shapes, and chart in the Top layout and Activity details
patterns. Labels can easily be added to in the Bottom layout. The Gantt chart is
the right or left. Relationships between divided into two sections: Activity table
activities can also be shown. and Bar Area.
This spreadsheet displays unit, cost and The Activity usage spreadsheet covers
/or earned value data by activity over time. both the Top and Bottom layout.
Use this type of layout to review per period
and rolled up activity resource / cost data.
Activity Network
It shows the activity boxes and logic links. be known by reading the original duration
The activity network is a graphical field in the box itself.
representation of the logical network
behind the CPM schedule. Activity The Left pane displays the WBS hierarchy
information is contained in boxes, with and the right pane shows a graphical
logic links represented by arrows. display of activities and their relationships.
Activity Table
Activity table provides a listing of the This table enables to see the project data
activities in the schedule. These activities in spreadsheet format. One can modify the
can be grouped and sorted in a variety of columns display in the Table to meet your
ways, to suit the needs of the scheduler. needs. You can display the Activity Table
Additionally, the columns can be modified on the entire screen if you want to analyse
to provide detailed information about the data in a tabular format.
activity and its status. Specific information
about each activity can be seen and Steps:
modified from this page. 1. In the Layout options bar, click
Show on Top, Activity Table.
Selecting Columns
You can select the required columns to be displayed in the Activity Table, as well as the
order in which they appear from left to right.
Click Edit Title to edit the selected column’s title and choose its alignment in the display.
Steps:
4. Click the single right arrow key
1. From the Layout Options bar, to move the item into the Selected
click Columns. Alternatively you Options column.
can select the View in the
Standard Tool bar, Columns, 5. Click the single left arrow key to
Customize. remove the item from Selected
Options column.
2. Click on the Plus sign to see all
the options available under each 6. Use the up/down arrows to
head. position the order.
The display of information in the Activity The tabs in the Activity details help
window may be customized. Activity you to access various details related to
Details display detailed information for an the selected activity. Also
activity highlighted in the Activity Table or modifications of the activity details can
Activity Network. The width of the columns be done using these tabs. Use the
may be adjusted to accommodate the data tabs to enter and edit activity
being displayed. information.
6. Click OK.
Saving Layouts
Layouts can be saved and shared with a. Current User – only the user
other users to facilitate project creating the layout will have
communication. access to it in the future.
Layout, Save: saves changes to the b. All Users – all licensed users will
existing layout. have access to the layout. This
requires an enterprise security
Layout, Save As prompts you to save level.
the layout with a new name.
c. Another User – a specified user
Layouts can be global or user-specific. will have access to the layout.
The options for Save as are: The current user will not have
access to the layout.
Steps:
5. Click Save.
Use the Save layout dialog box to save a custom display format for the Activities, WBS,
Projects, Resource Assignments or Tracking windows.
Steps:
4. Click, Open.
Closing a Project
You should close the project when you are finished working with it. You will be prompted to
verify that you want to close the project. Data is saved automatically or when changes are
committed. There is no project save button or any undo button.
Steps:
Steps:
Here we will try to understand the organize projects. The EPS represents the
hierarchical framework that P6 uses to management and organization of projects
organize projects. The program is broken in your company. In the EPS the root is
into its constituent elements. Those the top level and can be subdivided into
elements are represented by Enterprise nodes. Each node represents a level in
Project Structure (EPS) nodes. Each EPS the project structure that can hold another
node can contain multiple projects. Each node or a project.
project can be further described and
organized by the work breakdown Project represents the lowest level in the
structure (WBS), and then by schedule hierarchy. The EPS allows you to access
activities. and view project data quickly and
accurately
The EPS is an organizational tool
to create a hierarchy for grouping and
organizing projects in a manner which
parallels the organization’s needs. With
the ability to create up to 50 EPS levels,
project storage structures can be
developed to accommodate multiple
complicated organization structures. In the
figure above, the overall program is
represented by multiple EPS levels.
Attributes Benefits
The EPS consists of the following The EPS has the following benefits.
attributes.
View project priorities, scope, and
The EPS is a structure made of roots budgets across the enterprise or a
and nodes. single node.
The enterprise Project Structure is a EPS ID – Identifies the selected EPS node
global framework that should be
established by your system administrator. EPS Name - Describes the selected EPS
The EPS window is used to view and edit node
the EPS. One can use the EPS window to Responsible Manager – Use this field to
define the EPS. select an OBS (Organization Breakdown
The EPS has three fields, which are to be Structure) element to associate with the
entered while adding an EPS node. selected level of the EPS.
then place the new node under b. Click the arrow keys on
7. Click Next.
The Project Name dialog box will prompt Project Name: Type a new name into this
for Project ID and Project Name. The field. We shall use <Casanova> as our
default ID is “NEWPROJ” and the default Project name.
Project Name is “(New Project)”.
Steps:
We will be using Primavera to plan and
schedule a building project named as 1. Type PIBS001 in the ID field.
“Casanova”. You have to edit both the 2. Type Casanova in the name field.
field to create your project. 3. Click Next.
Steps:
Steps:
1. Click, Finish
Projects Window
Creating a Project and creating the Work breakdown structure will help you in defining the
scope of the project in the planning process group of the project lifecycle.
The WBS is a hierarchy arrangement of divide a project into meaningful and logical
the products and services produced during pieces for the purpose of planning, control
and by a project. WBS enables you to and reporting.
Attributes
To create a work breakdown structure level WBS element with the same ID and
(WBS) in an individual project, click WBS name as the project). Users cannot add
on the Directory Bar. This will open the additional parent level WBS values;
Work Breakdown Structure window as however, users can add values below this
shown in Figure 67. The top WBS level, parent. The WBS elements added after
the parent level, is automatically named the root level element are automatically
with the project name (When the project is indented to form the child levels of the
created, Primavera Enterprise adds a root hierarchy.
1. In the Directory bar, click WBS. 4. A new level entitled “<New WBS>”
The parent level WBS appears as will appear.
shown above.
Likewise you can add any number of WBS
2. Select the parent level WBS. depending upon your requirement. For our
example we will add four number of WBS
3. Click the Add button on the as shown in figure-68.
Command Toolbar.
Activities
Activities are the fundamental work Most detailed work unit that is tracked
elements of a project. They are the lowest in the project schedule.
level of the WBS and the smallest
functional area tracked in the project. It is They contain all information about the
the smallest subdivision of work that work to be performed.
directly concerns the project management.
Following are the attributes of activities. They are also known as a task (sub-
task in MSP), item, event, or work
package.
Activity Components
Activity Codes
Activity codes are like tags, assigned to database and each activity code (global or
each activity within a schedule, allowing project) may contain an unlimited number
customizing of data. They are ways to of activity code values.
classify and categorize activities according
to the organization and the project needs. Activity codes can be Global, i.e., they
They represent broad categories of are available to all projects in the
information, such as phase, division of database.
work, or location.
Create an unlimited number of
For each activity code, specific values global activity codes.
(activity code value) must be defined that Organize activities within a project
further describe that category. For or across the project structure.
example, if the project is occurring at
multiple locations, a Location code with Activity codes can be Project-specific,
values such as North, West, South, East i.e., they are available only in the
and so forth, should be created. Activities project in which they are created.
can then be associated with a specific
location, such as West, by assigning that Create up to 500 activity codes per
specific code value to the activity. project.
Filter and organize activities based
Use of activity codes provides a means to on unique project-specific
view, group, and summarize activities requirements.
within the schedule, create reports (in the
Report wizard or Report editor), select and Each Activity code (global, EPS or
summarize activities, and organize a project) may contain an unlimited
layout by grouping and filtering. number of activity code values.
Activity codes can be organized in a
hierarchy. They can be used on both the Activity codes values can be organized
global and project-specific level within the in a hierarchy.
EPS EPS in which code was created and EPS children Unlimited
Steps:
1. To create activity codes; on the Menu to open the Activity Codes popup
Bar, select Enterprise, Activity Codes window, Figure 71.
3. To Create Activity Code 3.5 Click the Close button and return
3.1 Click the Modify button. The to the Activity Codes window.
Activity Code Definitions Project
window (figure 73) will open. 3.6 The new activity code will be listed
in the pull-down box.
3.2 Click the Add button to create a
new code.
4. To Create Activity Code Values 4.5 Click on the Code Value field to
4.1 Click the Select Activity Code pull- rename the code value. The example
down box and select the new code to is renamed to “1.”
add values to.
4.6 Click on the Description field to
rename the description. The example
is renamed to “Phase 1.”
The order of the codes can be managed The Cut, Copy, and Paste functions in the
by using the arrow keys (▲▼) in the Command Bar of the Activity Code popup
Command Bar. The order of the codes in window are used to quickly copy or move
this window determines the order of the sets of code values. Only the code values
grouping bands in a layout that uses will be deleted; and not the activity code
activity codes. Therefore, ordering the itself.
code values logically will lead to a logically
organized layout.
Steps:
Units of Measure tab - Admin Categories dialog box (P6 Professional Only)
Units of Measure table: Lists units of Shift down: Moves the selected unit of
measure abbreviations and descriptions. measure to a lower position in the display.
This changes the order in which the
Add: Adds a unit of measure abbreviation abbreviations display when you assign a
and description. unit of measure to an activity.
All project activities, at creation, have an original duration. The original duration is the
number of working days an activity needs to complete. Calendars can be assigned to
individual activities in order to show which days are allowable for progress to occur.
P6 uses calendars to account for the non-work periods, weekends, holidays and so forth, in
the CPM algorithm (forward and backward pass; see Section-3). P6 skips the non-work
periods to calculate the start and finish dates.
This is a simplified explanation of the represent the planned days for working, so
function that calendars serve in P6. P6 that the software can predict, with
actually calculates time in hours, not days reasonable accuracy and realism, the start
as in previous software versions. and finish dates for activities.
Therefore, it is necessary to accurately
Global Settings
Setting up the date formats is of utmost importance, since P6 calculates time in hours,
therefore all project calendars must have the same time formats. To select the basic date
format settings:
Steps:
8. Close box.
Types of Calendars
Steps:
Modify A Calendar
Section 5
In this section:
There are five different types of activities: in a given period, regardless of the
assigned resources’ availability. The
1. Task Dependent: activity’s resources are scheduled to work
This is the default activity type and is used according to the activity calendar and the
when the work needs to be accomplished duration is determined by the assigned
calendar’s workweek.
Steps:
1. In the Activities window, Top Layout, the activity code, its code values can
highlight an activity. be seen.
2. In the Activities window, Bottom 6. Assign a specific code value by either
Layout, select the Codes tab. See double clicking on the code value or by
Figure 105. highlighting the code value and
3. Click the Assign button to open the
Assign Activity Codes dialog box. clicking the (Assign) button. By
4. The activity codes are grouped, with following this method, activity code
the code values listed below them. values can be assigned to each newly
5. To expand the view, simply click the created activity.
―+” sign or double-click the activity
code bar. By expanding the view on
5.2 Relationships
In order to add, edit, or delete either window is the Assign button.
relationships to activities within the project Clicking the Assign button under
schedule, click on the Relationships tab in Predecessors will allow the user to assign
the Bottom Layout, Figure 106. On the left predecessor activities, while clicking the
side of the Relationships layout is the Assign button under Successors will allow
Predecessors window, and on the right the user to assign successor activities.
side is the Successors window. Within
Steps:
A lag, the delay between the start or finish 1. In the Activities window, Top Layout,
of one activity and the start or finish of highlight an activity.
another, can be specified between
2. In the Activities window, Bottom
activities. There are many uses for lags,
and some uses are not generally Layout, select the Relationships tab.
acceptable. Lags can be positive or 3. Click on the Lag field under the Lag
negative (lead).
column.
To add, delete or edit lags follow these 4. Click inside this field and type the
steps.
duration of the lag in work days.
5.3 Constraints
Attributes
Benefits
Build a schedule that more accurately reflects the real-world aspects of the project.
Provide added control to the project.
Use to impose a restriction on the entire project or an individual activity.
Types of Constraints
Constraints can be defined for the entire Primavera P6 provides one type of
project or for each and every activity. constraint for the entire project and nine
types of constraints for early start or early
finish dates when it becomes necessary to
impose restrictions on activities to meet
external requirements.
This is one of the most commonly used Used when an overall project deadline
Constraints in most of the projects. It is must be met.
used in the following circumstances and
its effects are:
Following are the effects of this type of Forces all activities in the project to
constraint: finish by the date (and time) specified.
Affects the total float of the entire
project.
Must be applied in the Project window
on the Dates tab.
Adding a Constraint
5. Scroll down to review the constraint 6. Next, click on the expand button by
types. Date to open a calendar, within which
to select a constraint date.
9. Click Select.
Steps:
5.4 Durations
This is used when resource availability is a Fixed Duration and Units are used
limiting factor. In other words, it is used when resources are variable. In
when the activity has fixed resources with other words, the duration remains
fixed along with the units, but the
fixed productivity output per time period.
When the activity duration or units are crew size increases or decreases
changed, resource units per time remain in order to complete the fixed
constant. This duration type is typically scope of work within a fixed time
used for resource dependent activities. frame.
This is used when the user intends on 3. Click on the pull-down menu for
holding the duration constant, because Duration Type.
time is the limiting factor. These duration
types are typically used for task
dependent activities, which are activities
whose duration remains constant
regardless of the number of resources
assigned. Figure 5-17: General tab, Duration type
accurately estimating the number of work represent progress for the activity. For
days remaining based on current example, if an activity originally had 10
information. tons of hot mix asphalt, and the contractor
has installed three tons, the activity is
2. Physical Percentage Complete estimated at 30 percentage complete.
This is used for activities whose progress To change the percentage complete type,
can most accurately be assessed based follow these steps:
on the judgment of a construction
inspector. This is useful for complicated 1. In the Activities window, Top Layout,
scopes of work involving more than one highlight an activity.
unit quantity, where an estimate of the
total work in place is the best way to judge 2. In the Activities window, Bottom
progress. Layout, select the General tab, Figure
118.
3. Units Percentage Complete
This is used when actual work effort 3. Click on the pull-down menu for ―%
accomplished and actual work effort Complete Type.‖
remaining can be used to accurately
4. Select and click the desired calculated by P6, and the use of different
percentage complete type to set it for types can impact the estimated remaining
that activity. duration. Therefore, take care to ensure
that the selected type of percentage
As with the duration type, the type of complete is appropriate to the way the
percentage complete selected for an schedule is being used.
activity can affect how that activity is
After the schedule is developed, all Within the Activities Toolbar, schedule
activities created and linked using calculation section there are three buttons;
appropriate logic links, it is necessary to however, the button needed for calculation
instruct P6 to calculate or run the is the Schedule button.
schedule. When the schedule is run, P6
applies the CPM algorithm, the forward To properly calculate the schedule;
and backward pass, in order to determine understanding of the concept of the data
a predicted completion date for the date and the P6 critical path options
schedule. (determines which activities are on the
critical path) is required.
6. Click Select.
To set the data date, follow these steps:
1. Open the Schedule dialog box. The calendar closes and Current Data
Date is now set to the date selected.
2. Click on the Expand button.
Before scheduling the project, it is important to explain how P6 will calculate criticality. P6
has two methods of defining which activities are critical.
In this method all activities with a total float This method sets the critical path equal to
value equal to or less than zero are on the the longest path, defined as the string of
critical path. This is a typical definition of directly related activities that comprise the
critical path and the default method for P6. longest path from the data date to the last
It is best applied to schedules using a activity in the schedule. This definition
limited number of calendars and does not use float value as the sole
constraints. When a schedule has multiple method of determining the longest logical
calendars or constraints, the total float chain of activities through the project, thus
values become complicated to interpret, avoiding the confusion of the presence of
and may become negative values. This activities with negative float.
creates a situation where negative float
could be called critical; however, a delay
to an activity with negative float does not
always result in a delay to the projected
completion date of the schedule.
4. The definition of critical path is now set Figure 5-24: Schedule options dialog box
and the schedule is ready for
calculation.
5.6.1 Layouts
6. The opened layout can be changed to Figure 5-25: Open Save layout
show a wide array of data for the
Figure 5-26: Save layout dialog box Figure 5-27: Save New layout
Columns
3. To condense the timescale, drag the Figure 5-31: Changing Timescale size
magnifying glass to the left.
To open a previously created layout, To this point, however, the layouts that
follow these steps: have been created do not have any
organization, grouping and sorting, and
1. In the Menu Bar, click Layout, Open. contain all the activities in the schedule,
since there are no filters applied.
2. When prompted to save changes to
the layout, click No. Organizing and filtering the schedule can
provide useful views of a project which
3. Highlight the name of the layout to be can help successfully evaluate the quality
opened. of the schedule and the status of progress
to date.
4. Click Open.
5.6.2 Organization
Grouping Activities
Grouping activities pulls together activities the layout, P6 displays a coloured title
that share some common aspect, in an band to distinguish each group.
effort to present activities in format that is
more useful to the audience. P6 allows the On the Activities Toolbar, click on the
activities to be organized in a variety of (Group and Sort) button to open the Group
ways, but the most common groupings are and Sort window
made by WBS code or by activity code. In
The Group and Sort window contains: b. Group By (middle section, primary
options)
a. Display Options (top section) i. Group By—creates grouping
i. Show Grand Totals—check to
bands by providing a list of activity
display a grand total row at the top
data used to group the current
of the layout.
display.
ii. Show Summaries Only—check to
ii. Indent—check to layer the levels of
hide the activities within each
grouping bands within a single
group title band.
code. Typically unchecked for
iii. Shrink vertical grouping bands—
activity codes, but useful for WBS
check to make the width of the
organization.
grouped summary bands smaller in
iii. To Level—indicates the number of
the Activities window.
levels to display when grouping by
Sorting Activities
Sorting determines the sequence that P6 2. Click Sort to open the Sort dialog box.
lists activities in the Activity Table and
Gantt Chart. Almost any data item can be 3. The current data item which is being
sorted on; however, sorting by start and used to sort this schedule is the
finish dates, or by total float, are some of Activity ID field. This can also be seen
the more common sorts. in the Activity Table.
1. On the Activities Toolbar, click on the When a single field is being used to sort a
layout, and that field’s column is displayed
(Group and Sort) button to open
in the layout, there is an arrow which
the Group and Sort window.
designates that as the sorted field.
The most common and useful sorting 7. Scroll down the list and click on total
order for a typical schedule layout is to Float.
sort activities first by Start, then Finish,
and then by Total Float. Sorting the 8. Click OK to close the Sort dialog box.
schedule in this way (in ascending order) Click OK to close the Group and Sort
will give the layout the typical left-to-right window.
look for the bars in the Gantt Chart.
4. Click Add to add a second field. Click Figure 5-39: Sorting field selection
on the pull down tab on the second
field under Field Name, below Start.
The schedule will now be sorted by these data items. These data items can be altered as
necessary to create layouts which are most useful for a given project.
5.6.3 Filters
A filter is a set of selection criteria that 1. On the Activities Toolbar, click on the
determines which activities P6 displays in
(Filter) button to open the Filters
the layout. By default, layouts display all of
window.
the activities in a project. Filters can be
created and then applied to focus on
2. To select an existing filter (such as a
specific areas of a project.
default filter):
They allow the creation of customized
layouts by limiting the number of activities 3. Scroll through the filter list to find the
displayed. Pre-defined filters are provided desired filter.
in P6, as well as the ability to create user-
defined filters. 4. Check the Select box corresponding to
the desired filter.
Filters are divided into the following
groupings: 5. Click Apply to apply the selected filter
and keep the Filters window open.
1. Default Filters
These are available to all users, and 6. Click OK to apply the selected filter
cannot be deleted or modified. There are and close the Filters window.
13 default filters, including the Longest
Path filter.
2. Global Filters
Benefits
Allows the user to focus on specific data by limiting the number of activities in the layout.
Facilitates updating
Creating Filters
To create a new filter, follow these steps: inclusion in the layout, or if meeting
any of the conditions is acceptable.
1. In the Filters window, click New from For the example, set the Parameters
the Command bar to open the Filter field to (All of the Following). Now, the
window in which to create a new filter. filter conditions can be set.
Now you will execute the new filter to 1. From the Layout Options bar, choose
display all activities scheduled to occur Filters.
within the next month. You will save the
2. Mark the All Activities checkbox.
Layout with a new name, One Month look
ahead. 3. Click OK to execute the filter.
P6 will allow printing or plotting to any on the Print Setup button to open the Print
installed printer or plotter. The printers Setup dialog box. From this dialog box, a
installed on the computer will printer can be selected; print properties
automatically show in the list of available can be set and paper size and orientation
printers. In the Print Preview window click chosen.
To change the way a particular layout will across the top (Page, Margins, Header,
print out, click on the Page Setup button to Footer, and Options). All five of these tabs
open the Page Setup dialogue box. The have useful features for customizing a
Page Setup dialogue box has five tabs printout.
Page
To create a printout that will fit onto one 5. If the number of pages tall is left at
page width (landscaped) and A3 size, zero, P6 will not scale the height of the
follow these steps: schedule, and it will print out as many
pages long as necessary to show the
1. Click on the Page tab in the Page active layout’s activities.
Setup dialogue box.
6. Keep the Fit Timescale to as 1 page
2. Under Orientation, select Landscape. wide.
3. Under Scaling, click on the box next to 7. Select the A3 Paper size from the pull
Fit To: and change the number of down menu.
pages wide to 1.
8. Click OK.
4. Do not alter the number of pages tall.
Options
The Options tab provides key features for customizing the printout.
In the Options tab, in the Print area, there printout will only show those columns
are a series of check boxes corresponding which are visible in the layout. So, if some
to different elements of the layout. These of the columns are hidden by the split
boxes can be toggled in order to show between the Activity Table and the Gantt
only the elements that are relevant. For Chart, the hidden columns will not display.
instance, to only show the Gantt Chart,
then un-check all other boxes except for When the Gantt Chart appears in the
Gantt Chart. The layout would then only printout, it is often expanded beyond the
be a Gantt chart view, without the Activity point where it will appear on only one
Table. page. The layout has already been set to
show the entire timescale on only one
page; however, it is also necessary to
ensure that the software knows what
duration of the timescale to display.
Headers and footers are optional ways to Headers and footers can appear at the top
add descriptive information to printed and at the bottom, respectively, of the first
layouts. The content of a header or footer or last page of a printed layout or on all
is selected or entered, including items pages, or on no pages.
such as the project titles, important dates,
Gantt Chart or Activity Network legend, a The settings for headers and footers are
drawing, or a company logo. defined in the Header and Footer tab of
the Page Setup dialogue box.
Headers and footers are as wide as the To edit the type of information contained in
page, but their height can be defined. The a section, follow these steps:
default height is 0.25 inches.
1. Under the section number, click on the
To alter this height, pull-down tab.
use the up and down arrow keys next to
the height field. We will use 0.5 inches 2. A menu will appear with choices for
high header. elements to place in the section.
Headers and footers are also divided into 3. Choose the desired element by
sections. Each section can contain a clicking on it.
different piece of information. Section 1 is
the left side of the paper, Section 2 is the 4. Use the text formatting buttons to
middle, and Section 3 is the right side of customize the font, font size, colour,
the paper. The default setting for the and layout of each section.
number of sections is three.
Margins
The Margins tab allows you to adjust the margins for the paper size selected. You can adjust
the margins on all four sides for better presentation.
Section 6
Resources
In this section:
Roles can be defined as job titles or skill sets. They represent o type of resource with a
certain proficiency level rather than an individual. Roles are assigned to resources to
describe the skill capabilities of a resource. Typically the primary role for a resource is
defined. Examples of roles are Software Engineer, Project Manager, Trainer and Database
Administrator.
Roles Dictionary
The Roles dictionary is an enterprise data item; and it is applicable to all projects in the EPS.
Each Role has skill sets/responsibilities defined and resources have been assigned to the
appropriate roles.
General Tab
It lists the Role ID and the Role Name. The Responsibilities field lists the skills required to
perform the Role.
Resources Tab
Lists the resources that are capable of performing the responsibilities associated with this
role; as well as their proficiency.
Prices Tab
There are five available price per unit values. The title of these values can be defined in the
Rates tab in Admin Preferences.
Limits Tab
This tab helps you to assign a limit on the availability of a particular resource on a specified
date. For example equipment may be available only for few hours on a particular day.
Steps:
resource. windows:
3.1.1. Use a resource profile to
2. Assign resources view resource quantity/cost
2.1. In the Activity window: graphically, displaying when
2.1.1. Enter the resource name and how much of the
and amount of work planned resource will be used.
for the activity. 3.1.2. Use columns to view total
2.1.2. P6 calculates the cost costs.
based on the resource
Resource Dictionary
You can use the Resource Details to add, view and edit detailed information about the
selected resource.
1. General Tab
This Tab enables you to enter general information about the selected resource, including the
resource ID, Name, Employee ID, Title, e-mail address, phone number and status.
2. Codes Tab
This Tab enables you to assign resource code values to further categorize the selected
resource for grouping and organizing. When you click “Assign” button, the “Assign Resource
Codes window” will open.
3. Details Tab
This Tab enables you to enter the selected resource’s labour classification, currency and
overtime settings and profile.
This tab enables you to set prices and h/d (100%) = full time and 4h/d (50%) =
availability according to time. part time. Setting this limit allows you to
quickly identify areas of resource over
Effective Date: the effective start date for allocation in resource
price and availability. profiles/spreadsheets.
Max Units/Time: a numeric value or % Price/Unit: set the resource’s price for a
the resource can perform in a single work single work unit, according to the effective
period, according to effective date, i.e., 8 date.
5. Roles Tab
This tab enables you to assign resources from the Roles dialog box and displays the ID,
Name, Proficiency level and Primary role. This tab displays the roles who can perform
responsibilities associated with the selected role.
6. Notes Tab
This tab enables you to add descriptive notes about the Resources which will be self-
explanatory and easily understandable.
This Tab enables you to assign the users login credentials for creating reports or printing
reports. Click the expand button to display the available User details.
Rate types can be assigned to Roles in 6. Assign Rate Type in Price/unit to the
the Resources tab in the Activity details Role
tab on bottom layout. Follow the below
procedure to assign a rate type on a role. 7. You will see a prompt for
confirmation.
Steps:
5. Click OK.
Steps:
4. Click to assign the resource.
1. Press Ctrl + click to select multiple
activities. In our example we shall 5. Close the dialog box.
select A1010 Excavation, A1020
Footings and A1030 Plinth beam. 6. View the Resources column or select
each activity to verify the resource
assignments.
The person responsible for the Only the Primary resource can send
coordination of the activity’s work is called feedback via Primavera to the Project
as the Primary resource. An activity can manager, to let him know the status of
have one or no primary resource. The an activity.
attributes of the Primary resource are:
A Primary resource can be assigned to
a milestone activity to allow the
milestone to be updated through
timesheets. This assignment is made
on the Activity Details general tab.
Steps:
(If you don’t have the Primary resource
1. Mark the Primary Resource checkbox column you can add it from the
for a rsource, Karthick. Columns editing options.)
Resource
Expense
Expenses are the non-resource costs Expenses can be accrued at the start,
associated with a project. They are end or uniformly over the duration of
normally the one-time expenditures for an activity.
non-reusable items. Examples include A unit of measure can be used to label
facilities charges, travel expenses, the quantity like each, kilos, and
overhead costs and training expenses. square feet.
Expenses are assigned manually at the
activity level. You can enter a single lump- Steps:
sum expense or can enter the number of 1. Click the Expenses tab
units and price/unit. Following are the
attributes of expense: 2. Click Add
3. Type an Expense Item <Petrol>
Expense categories can be assigned
to classify the expense.
Summary Tab
You can use the Summary tab to display 3. Select Display units to see the
unit, cost or date information for a selected information on units.
activity. 4. Select Display cost to see the
information on variuos costs.
Steps: 5. Select Display dates to see the
1. Select an activity A1030 Plinth information on Start and Finish
beams. dates.
2. Click the Summary tab.
Resource curves are used to better the an activity. Selected users can build their
projection of the distribution of resource own Resource Curves. Resource Curves
units or costs over a long activity. Several are not protected at the user level;
standard Resource Curves are pre-built therefore, users must be responsible not
into the system. By default Primavera to modify other user’s curves.
distributes units and cost linearly across
6.4.1 Settings
The Resource usage profiles provide a graphical view of unit/cost distribution over time.
They display the amount of effort needed from each resource/role on the project during each
time period. Following is the attributes and benefits of Usage profiles.
Attributes
Benefits
You can determine how many hours You can track expenditures per time
each resource/role is scheduled to period.
work.
You can display a “banana” curve to
You can identify overallocated compare early and late dates.
resources.
Item Functionality
1. Right Pane Display Displays a menu of the formatting options available for the
Options bar resource/role usage profile.
Displays a legend for the profile’s bars and /or lines. This will
2. Legend
change depending on the data/formatting options selected.
4. Display Activities for When viewing Open Projects only, you can mark Time period or
selected Resource to filter the activities in the Top layout.
6. Left Pane Display Displays a menu of the formatting options available for the
Options bar resource/role hierarchy.
All aspects of the resource usage profile can be modified by adjusting the settings in the
Resource Usage Profile Options dialog box.
Data Setting
Graph Setting
Date Interval – choose the units of the 3. You can select the date from the
timescale in years, quarters, months, options in the drop down menu or
weeks, days, hours, and shifts. enter a custom date from the pop-up
You can also format the timescale by using click and drag in the timescale onscreen.
Place your mouse on the minor date interval on the timescale. Click and drag to expand
or contract the timescale.
Place your mouse on the major date interval on the timescale (the cursor will change to a
hand). Click and drag to move the entire timescale.