General Conditions
General Conditions
INTRODUCTION
The Architect, in performance of his services to his Client, prepares the
“General Conditions” as one of the Contract Documents. The General Conditions define
the relationship among the Owner, the Architects and the contractor and stipulates the
norms by which the contractor shall perform his work.
The task for the compilation, review, editing and printing of the General
Conditions was given to the UAP committee on the Professional Practice and Ethics in
collaboration with the Inter-Professional Conference Committee whose membership is
composed of representatives from the United Architects of the Philippines (UAP), the
Philippines Institute of Civil Engineers (PICE), and the Philippine Contractors
Association (PCA).
MEMBERS:
Cesar V. Canchela, FUAP
Antonio S. Dimalanta, FUAP
Froilan L. Hong, FUAP
Norberio M. Nuke, FUAP
UNITED ARCHITECTS OF THE PHILIPPINES
THE DULY ACCREDITTED BONIFIDE PROFESSIONAL ORGANIZATION FOR ARCHITECTS
FOLK ARTS THEATER, CCP COMPLEX, ROXAS BLVD., PASAY CITY, METRO MANILA
Telephone; 832-78-50, 832-11-20 Loc. 09 fax: 832-37-11
RESOLUTION NO. 15
Series of 1984
WHEREAS, one of the projects of the United Architects of the Philippines is the preparation of standard
document that could be used by Architects as a means of the UAP to the members;
WHEREAS, the “General Condition” Document No. 301, as prepared by the UAP Committee on Professional
Practice & Ethics and the Inter-Professional Conference Committee in 1977 embodies provisions pertaining to the
responsibilities of the Architects to hid Client, and stipulations conditions for the implementation of the work by the
Contractor which are fair to both the Owner and the Contractor;
WHEREAS, the Inter-Professional Conference Committee (IPCC) tripartite group composed of the architects –
United Architects of the Philippines (UAP), engineers – Phil Institute of CMI Engineers (PICE) and contractors – Phil.
Contractors Association (PCA) have been reconvened in March 1983 to make revisions on the 1977 General Conditions to
meet the needs of the changing times.
WHEREAS, the revisions are: Art. 3; Paragraph 3.03, Sub-Paragraph “a. Should a conflict occur between
Drawings, or a conflict between Specifications, or between Specifications and Drawings, the Contractor shall be deemed
to have estimated a more expensive way of doing work unless he shall have asked for and obtained a decision. In writing,
from the Architect before submission of proposal as to which method or materials will be required. If, after award, the less
expensive work is done, the Contractor shall credit the Owner an amount equivalent to the difference between the more
expensive and the less expensive work”; “Art. 22.04 ARCHITECTS ACTON ON AV REQUEST FOE PAYMENT: Within fifteen
days after receipt of any Request for Payment by the Contractor, the Architect shall issue a certificate of payment or
withhold the Request for Payment. When the Architects decides to withhold the Request for Payment, he shall inform the
Contractor in writing the reasons for withholding it. IF THE CONTRACTOR AND ARCHITECT CANNOT AGREE ON A
REVISED AMOUNT, THE ARCHITECT WILL ISSUE A CERTIFICATE OF PAYMENT FOR THE AMOUNT FOR WHICH HE IS
ABLE TO MAKE REPRESENTATIONS TO THE OWNER.”; Art. 27: CONTRACTOR’S RIGHT TO SUSPEND WORK OR
TERMINATE CONTRACT: “If the Contractor is compelled to suspend work due to hardships or difficulties under b, c, and d
above then the contract sum shall be increased by the amount of the contractor’s reasonable costs of shut-down, delay
and start up, which shall be effected by appropriate change order.”;
WHEREAS, these revisions is in consonance with present trend of Architectural Practice in the Philippines and
the adoption of it as a standard document by the practicing architects will contribute to the maintenance of a high
standard of professionalism in the architectural professional and building industry;
NOW, THEREFORE, be it resolved as it is hereby resolved by the Board of Directors of the United Architects of
the Philippines the approval of the revised General Conditions and its adoption as UAP Document 301.
RESOLVED, FURTHER, that copies of this resolution and the General Conditions be furnished the Professional
Regulation Commission (PRC) and the Board of Architecture for their record, information and guidance, and enjoining
them to approve this revised General Conditions, as a standards document for all practicing Architects in the Philippines.
Unanimously, approved this 11th day of August in the year of our Lord Nineteen and Eighty Four.
HONORARY MEMBER – MADAME IMELDA ROMUALDEZ MARCOS Minister of Human Settlements and Governor of Metro Manila NATIONAL
BOARD OF DIRECTORS 1984 OFFICERS: MANUEL T. MANOSA JR. FUAP , National President NORBERTO M. NUKE, FUAP Vice President
for Private Practice; NATHANIEL VON EINSIEDEL, FUAP Vice President for Government Service; VICTOR N. TIOTUYCO FUAP, Vice
President for Privately Employed Professional & Allied Fields; RICARDO R. POBLETE, FUAP, National Secretary; LIBRADO M. MACALINAO,
FUAP, National Treasurer; COSTANTINO F. AGBAYANI, FUAP, Director, NCR; FELIPE M. MENDOZA, FUA, Director, NCR, MANUEL A
RESURRECCION, CUAP, Director, NCR; ROGER J. NAZ, CUAP, Director, N. Luzon; JOSE MACARIO B. DE LEON. CUAP Director, C. Luzon;
FIDEL J.R. SIAPNO, UAP Director, S. Luzon; SERVILLANO C. MAPESO, Director, E. Visayas; RAMIRO GARCIA, FUAP, Director, W. Visayas;
BOARD OF ARCHITECTURE
BOARD RESOLUTION NO. 24
SERIES OF 1984
WHEREAS, In UAP Resolution No. 108 dated September 7, 1977, the United Architects of the Philippines petitioned the
Professional Regulation Commission and the Board of Architecture to approve the General Conditions. UAP Document
No. 301, as a standard document for use by practicing architects in the Philippines;
WHEREAS, the “General Conditions”, UAP Document No. 301, whose provisions establish the relationship among the
owner, the Architect and the Contractor and stipulate the norms by which the contractor shall perform his work are in
consonance with the present trend of architectural practice in the Philippines;
WHEREAS, the UAP now proposes certain revisions in the said “General Conditions” UAP Document No. 301, as follows;
“Art. 3. Paragraph 3.03. Sub-Paragraph a. “ Should a conflict occur between Drawings, on a conflict between
Specifications and Drawings, the Contactor shall be deemed to have estimated a more expensive way of doing work
unless he shall have asked for and obtained a decision. In writing, from the Architect before submission of proposals as to
which method or materials will be required. If, after award, the less expensive work is done, the Contractor shall credit the
owner an amount equivalent to the difference to the more expensive and the less expensive work.”
“Art. 22.04. ARCHITECT’S ACTION ON A REQUEST FOR PAYMENT; Within fifteen days after receipt of any
request for Payment by the Contractor, the Architect shall either issue a Certificate of Payment or withhold the Request of
Payment. When the Architect decides to withhold the Request of Payment, he shall inform the Contractor in writing the
reasons for withholding it. IF THE CONTRACTOR AND THE ARCHITECT CANNOT AGREE ON A REVISED AMOUNT, THE
ARCHITECT WILL ISSUE A CERTIFICATE OF PAYMENT FOR THE AMOUNT FOR WHICH HE IS ABLE TO MAKE
REPRESENTATIONS TO THE OWNER.”
“Art 27. CONTRACTOR’S RIGHT TO SUSPEND WORK OR TERMINATE CONTRACT.: If the Contractor is
compelled to suspend work due to hardships or difficulties under b, c, and d above, then the Contract sum shall be
increased by the amount of the contractor’s reasonable cost of shut down, delay and startup, which shall be affected by
appropriate change order.”
WHEREAS, the Board of Architecture, after viewing said revisions, find them in order to maintain the high level of
professionalism in the implementation of infrastructure projects;
NOW, THEREFORE, BE IT RESOLVED, AS IT IS HEREBY RESOLVED, that the above stated revisions in the “General
Conditions”, UAP Document No. 301, are hereby approved and adopted.
RESOLVED FINALLY that the above take effect upon approval by the Commission and fifteen (15) days following it’s
publication in the Official Gazette.
Done in the City of Manila this 7th day of November, 1984.
ATTESTED:
(SGD.) SALUD M. SAHAGUN
SECRETARY
Approved and promulgated as part of the rules and regulations governing the practice of architecture in the Philippines
the 26th day of November, 19894
WHEREAS, one of the projects of the United Architects of the Philippines is the preparation of
standard documents that could be used by practicing Architects as a means of service of the UAP
to it’s members;
WHEREAS, the “General Conditions”, Document No. 301, as prepared by the UAP Committee on
Professional Practice and Ethics and the Inter-Professional Conference Committee embodies the
provisions pertaining to the responsibilities of the Architect to his Client, and stipulates
conditions for the implementation of the work by the Contractor which are fair to both the Owner
and the Contractor;
WHEREAS, the provisions of this document is in consonance with the present trend of
architectural practice in the Philippines and the adoption of it as a standard document by the
practicing architect will contribute to the maintenance of a high standard professionalism in the
architectural profession and the building industry;
NOW, THEREFORE, be it resolved as it is herby resolved by the Board of Directors of the United
Architects of the Philippines the approval of this General Conditions and its adoption as UAP
Document No. 301.
RESOLVED, FURTHER, that copies of this resolution and the General Conditions be furnished the
Professional Regulation Commission (PRC) and the Board of Architecture for their record,
information and guidance, and enjoining them to approve this General Conditions, as a standard
document for all practicing Architects in the Philippines.
Unanimously approved, this 7th day of September in the year of our Lord Nineteen Hundred and
Seventy Seven.
BOARD OF ARCHITECTURE
BOARD RESOLUTION NO. 15
SERIES OF 1977
WHEREAS, in the UAP Resolution No. 108 dated September 7, 1977, the United
Architects of the Philippines have petitioned the Professional Regulation Commission
and the Board of Architecture to approve the “General Conditions”, UAP Document No.
301 as a standard document for use by practicing architects in the Philippines;
WHEREAS, the General Conditions – UAP Document No. 301 whose provisions
establish the relationship among the Owner, the Architect and the Contractor and
stipulate the norms by which the contractor shall perform his work are in consonance
with the present trend of architectural practice in the Philippines;
Unanimously approved, this 15th day of November in the year of our Lord Nineteen
Hundred and Seventy Seven
ANASTACIO R. BERNAL
Chairman
APPROVED:
1977
FORMER MEMBERS
INCUBENT MEMBERS
Chairman…………………………...………………………………… Felipe M. Mendoza, UAP
Vice-Chairman……………………………………………………… Ambrosio R. Flores, PICE
PERMANENT REPRESENTATIVES
ALTERNATIVE REPRESENTATIVES
1984
INTER-PROFESSIONAL CONFERENCE
COMMITTEE
Ernesto S. De Castro
Rosallo Q. Mallonga
Eluderio S. Salvo
Jesus R. Ferrer…………………………………………...............………….……Vice-Chairman
Andres V. Los Banos
Eustaquio T. Coronel, Jr.
Pastor B. Esguerra
UNITED ARCHITECTS OF THE PHILIPPINES
GENERAL CONDITIONS
UAP DOCUMENT 301
TABLE OF CONTENTS
ART. 8 GENERAL…………………………………………………….....page 11
ART. 19 LABOR……………………………………………………..……page 21
ART. 24 CONTRACTOR-SEPARATE
CONTRACTORS RELATONS………………………………..page 34
ART. 25 SUB-CONTRACTS…………………………………………..…page 35
25.01 General
25.02Competency of Sub-Contractor
25.03 Contractor’s Responsibility
33.01 Liens
33.02 Assignment
33.03 Damages
33.04 Disputes
33.05 Arbitration
GENERAL CONDITIONS
SECTION I
ART 1: DEFINITIONS
1.01 CONTRACT DOCUMENTS: The Contract consists of the following documents, including all
additions, deletions and modification incorporated therein before the execution of the Contract:
a. Agreement
b. General Conditions
c. Special Provisions
d. Specifications
e. Drawings
1.02 OWNER: The person or entity ordering the project for execution, including duly appointed
successors, or authorized representatives.
1.03 ARCHITECT: refers to the Architect commissioned by the Owner action personally or through
assistants duly authorized in writing by the Architect to act on his behalf
1.04 ENGINEER: The person so named n the Contract Documents or his representative duly
authorized in writing to act for the engineer.
1.05 PROJECT REPRESENTATIVE: The Full-time Construction Inspector hired by the Owner duly
authorized in writing to assist the Architect and the Engineer in the supervision of the work
1.06 CONTRACTORL The person or firm whose proposal has been accepted and to whom the
Contract was awarded.
1.07 SUB-CONTRACTOR: Anyone having a direct Contact with the Contractor who acts for or in behalf
of the Contractor in executing any art of the Contract, not including one who merely furnishes
materials without labor.
1.08 SURETY: is the person, firm or corporation who provides the guarantee for the Contractor’s
Bonds.
1.09 PROPOSAL: The offer of a Bidder to perform the work described by the Contract Documents
when made out and submitted on the prescribed Proposal Form, properly signed and guaranteed.
1.10 PROPOSAL BOND: the cashier’s check or surety bond accompanying the proposal submitted by
the bidder, as a guarantee that the bidder will enter into a contract with the owner for the
construction of the work, if the contract is awarded to him.
1.11 PERFORMANCE BOND: is the approved form of security furnished by the Contractor and his
Surety as a guarantee of good faith on the part of the contractor to execute the work in
accordance with the terms of the contract.
1.12 PAYMENT BOND: is the approved form of security furnished by the contractor and his surety as a
guarantee of good faith on the part of the Contractor to pay all obligations arising from the
contract.
1.13 GUARANTEED BONDL is the approved form of security furnished by the contractor and is surety
as a guarantee to the quality of materials and equipment installed and the workmanship
performed by the Contractor.
1.14 AGREEMENT: is the contract between the owner and the contractor undertaking the project
described in the Contract Documents including all supplemental agreements thereto and all
general and special provisions pertaining to the work or materials therefore.
1.15 ADVERTISEMENT or INVITATION TO BID: The notice published by the owner or the invitations
issue to perspective bidders, giving information to the nature of the proposed project, conditions
for the issuance of the contract documents date of bidding, and estimated cost or information that
would give the contractor a general idea of the magnitude and extent of the project.
1.16 BID BULLETIN: is additional information on contract documents issued to bidders before date of
bidding.
1.17 INSTRUCTIONS TO BIDDERS: The list of instructions stipulating the manner on how bids are to
be prepared and conditions for the award of contract.
1.18 DRAWINGS: are graphical presentations of the work involved in the project. They include all
supplementary details and shop drawings.
1.19 GENERAL CONDITIONS: as printed documents stipulating the procedural and the administrative
aspects of the contract.
1.20 SPECIAL PROVISIONS are instructions which may be issued prior to the bidding to supplement
and/or modify the drawings, specifications, and/or General Conditions of the contract.
1.21 SPECIFICATIONS: are written or printed description of work to e done describing qualities of
material and mode of construction.
1.22 SUPPLEMENTARY SPECIFICATIONS: are additional information which may be issued as an
addition or amendment to the provisions of the specifications.
1.23 SCHEDULE OF MATERIALS ND FINISHES: is an outline specification enumerating the type or
trade names of materials be used.
1.24 BREAKDOWN OF WORK AND CORRESPONDING VALUE: is a listing of the different parts of the
work indicating in each part of the corresponding value in materials and labor, including an
allowance for profit and overhead.
1.25 WRITTEN NOTICE: Written notice means information, advice a notification pertinent to the
project delivered in person or sent by registered mail to the individual, firm or corporation at the
last known business address of such individual, firm or corporation.
1.26 ACT OF GOD OR FORCE MAJEURE includes an earthquake, flood, typhoon, cyclone & other
cataclysmic phenomenon of nature and all misfortunes and accidents which human prudence
could not foresee or prevent, rain, wind, flood or other natural phenomenon of inconsequential
degree for the locality shall not be construed as an act of God or Force Majeure and no reparation
shall be made to the Contractor for the damages to the work resulting therefore.
1.27 TIME LIMITS: time limit is the duration of time allowed by the contract for the completion of the
project in any stipulated portions thereof.
1.28 LOCAL LAWS: applies to all laws, ordinances and other governmental regulations applicable to
the project and its undertaking.
1.29 WORK: The term “work” of the Contractor or Sub-contractor includes labor or materials or both
as well as equipment, transportation, or other facilities necessary to commence and complete the
construction called for in the Contract.
1.30 FURNISH: The work “furnish” shall be understood to mean “Purchase and/or fabricate and
deliver to the jobsite or other location when so designated.”
1.31 INSTALL: the word “install” shall mean to build in, mount positions, connect or apply any object
specified ready for the intended use.
1.32 PROVIDE: the word “provide” shall be understood to mean “furnish and install”
1.33 REQUIRED OR NECESSARY: The words “Required Or Necessary” shall mean as required or
necessary for the complete execution of that portion of the work.
1.34 APPROVED, DIRECTED AND ACCEPTABLE: The words “approved”, “directed” and “acceptable”,
or words of like import shall mean approved, directed by or acceptable to the architect unless
otherwise stipulated in the Contract.
1.35 SINGULAR OR PLURAL: in all cases where a device, item, or part of the equipment is referred to
in the singular number, it is intended that such reference shall apply to as many such device,
items, or parts as are required to complete work.
2.02 INTERNT OF CONTRACT DOCUMENTS: the Contract Documents are complementary, and
what is called for by anyone shall be as binding as if called for by all. The intent of the drawings
and the specifications is prescribed the complete work that the Contract is to undertake to comply
with the contract. The intention is to include all labor and materials, equipment and transportation
necessary for the proper execution of the work.
2.03 CONFORMITY TO THE CONTRACT DOCUMENTS: All work shall conform to the Contract
Documents.
a. If there be variance between drawings and the Specifications, the provisions of the specifications
shall control. In case of conflict between the General Conditions of the contract or any
modification thereof and the detailed specifications requirements shall control
b. Any discrepancies found between the Drawings and Specifications and site conditions or any
errors or omissions in the Drawing or Specifications shall be immediately reported to the
Architect or Engineer, who shall promptly correct such discrepancies, errors, omissions after his
discovery. Any work involving such discrepancies shall be done at the Contractor’s risk.
c. Responsibility for adequacy of the design and for sufficiency of the drawings and specifications
shall be borne by the owner. The complete requirements of the work to be performed under the
contract shall be set forth in drawings and specifications to be supplied by the owner through the
Architect or Engineer or by the Architect or Engineer as representative of the owner. Drawings
and specifications furnished shall be in accordance with the contract documents and shall be true
and accurate development thereof
d. The Architect or Engineer shall furnish from time to time all additional detail drawings and
instructions essential to the proper execution of the work. The Architect or the Engineer shall
furnish with reasonable promptness such additional detail drawings and instructions. All the
additional drawings and instructions shall be consistent with the Contract documents, true
development thereof, and reasonable inferable there from. All such additional drawings and
instruction are to be considered of equal force as those which originally accompany the
specifications.
e. The Contractor and the Architect or the Engineer if either one so requests shall jointly prepare a
schedule, subject to change from time to time in accordance with the progress of the work, fixing
dates at which the various detail drawings will be required and the Architect or Engineer shall
furnish then in accordance with that schedule. Under like conditions, a schedule shall be prepared
fixing the dates for the submission of shop drawings, for the beginning of manufacture and
installation of material, and for the completion of the various parts of the work.
2.04 CONTRACTOR DOCUMENTS AT SITE OF WORK: The Contractor shall keep at the site of
work. In good order one copy each of all drawings, specifications, Breakdown of work, Schedule
of Construction Work and including all instructions and graphs available to the Architect and his
representatives.
2.05 OWNERSHIP OF CONTRACT DOCUMENTS AND MODELS: The drawings, specifications, and
models, including all additional instructions, and copies thereof, furnished for this work by the
architect are the property of the Architect. They are not to be used on any other work and with the
exception of the signed contract set are to be returned to the Architect at the completion of the
work, before Final Payment to the Contractor is made.
ART. 3 DRAWING AND SPECIFICATIONS
3.01 COPIES OF DRWAINGS AND SPECIFICATIONS: The Owner shall furnish the contractor free
of charge three sets of drawings and specifications. All other copies of Drawings and
Specifications as required by the contractor will be furnished to him at cost of reproduction.
3.02 COORDINATION OF DRAWINGS AND SPECIFICATIONS: All drawings and models are
intended to cooperate with the Specifications, to form a part of the Contract Documents. Where
figures are given, they are to be followed in preference to measurements by scale. Anything
shown on the Drawing but not mentioned in the specifications, or vice versa, or anything not
expressly set forth in either but which is reasonably implied, shall be furnished as though
specifically shown and mentioned in both, without any extra charge.
1. Should a conflict occur between Drawings, or a conflict between specifications and Drawings, the
Contractor shall be deemed to have estimated a more expensive way of doing work unless he
shall gave asked for and obtained a decision, in writing from the architect before submission of
proposals as to which method or materials will be required. If, after award, the less expensive
work is done, the contractor shall credit the owner an amount equivalent to the difference
between the more expensive and the less expensive work.
2. If , in the Contractor’s opinion, any work indicated on the drawings, or specified in such manner
as will make impossible to produce a first-class work, he shall refer same to the Architect for
interpretation before proceeding with work if the contractor fails to make such reference; no
excuse will thereafter be entertained for failure to carry out work in the most satisfactory manner.
3.04 DISCREPANCIES IN DRAWINGS: In case of discrepancy in the figures or drawings, the matter
shall be submitted immediately to the Architect, before any adjustment shall be made by the
contractor save only at latter’s own risk and expense, the decision of the Architect on the
adjustment of discrepancies so as to conform to the real intent of the drawings and specifications
shall govern and shall be followed by the Contractor.
5.01 CONDITIONS IN THE PREPARATION OF SHOP DRAWING: the Contactor shall prepare at his own
expense and submit with such promptness as to cause no delay in his own work or in that of any
other contractor doing work on the same building, two copies of all shop or setting drawings,
templates, patterns and models as well as schedule required for the work of the various trades
and the Architect shall pass upon them with reasonable promptness, making desired corrections.
The Contractor shall make any corrections required by the Architect, file with him two corrected
copies and furnish such other copies as may be needed.
5.02 CHECKING DRAWINGS OF SUB- CONTACTORS: Before submitting shop drawings for approval,
the Contractor shall check drawings of all sub- contractors for accuracy. He shall see that all work
contiguous with and having bearing on work indicated on shop drawings is accurately and
distinctly illustrated and that work shown is in Conformity with Contract requirements
5.03 IDENTIFICATION: Shop drawings shall be numbered consecutively and represent:
a. All working and erection dimensions.
b. Arrangements and sectional views.
c. Necessary details, including complete information for making connections with other work.
d. Kinds of materials and finishes.
Shop drawing shall be dated and contain (a) name of project, (b) descriptive names of equipment,
materials, and classified item numbers, (c) location at which materials or equipment are to be
installed in work.
5.04 LETTER OF TRANSMITTAL: Submission of shop drawings shall be accompanied by a letter of
transmittal in duplicate, containing name of project. Contractor’s name, number of drawings,
titles, and other pertinent data.
5.05 CORRECTIONS, CHANGES AND VARIATIONS: The Contactor shall submit three sets of prints of
shop drawings to the Architect for approval. Satisfactory shop drawings will be so identified by
the Architect, dated and one copy thereof returned to the contractor. Should shop drawings be
disapproved by the Architect, one set of such shop drawings will be returned to the contractor
with necessary corrections and changes to be made as indicated.
a. The Contractor shall make required corrections and changes and resubmit shop drawings, in
duplicate until the Architect’s approval is obtained.
b. Upon receipt of approval the Contractor shall Insert date of approval on tracing and promptly
furnish the Architect with three additional prints of approved drawings.
c. No work called for by shop drawings shall be executed until the Architect’s approval is given.
d. If shop drawings show variations from Contract requirements because of standard shop
practice or other reasons, the Contractor shall make specific mention of such variations in his
letter of submittal.
5.06 RESPONSIBILITY OR ACCURACY: Approval of shop drawings will be general. It shall not relieve
the Contractor of responsibility for accuracy of such shop drawings, nor for Proper fitting and
construction of work, nor for furnishing of materials or work required by the Contract and not
indicated on shop drawings. The Architect’s approval of such drawings or schedule shall not
relieve Contractor from responsibility for deviations from Drawings or Specifications, unless he
has in writing, called the Architect’s attention to such deviations at the time of submission and
secure his written approval, nor shall it relieve him from responsibility for errors of any sort in
shop drawings or schedules
SECTION II
LAWS, REGULATION, SITE CONDITIONS, PERMITS AND TAXES
6.01 LAWS AND REGULATIONS: In general the contractor shall comply with all the laws, city and
municipal ordinances , and all building Codes, rules and regulations, In so far as they are binding
upon or affect the parties hereto, the work, or those engaged thereon. He shall also comply with
regulations of firms furnishing utilities such as water, gas, telephone and electricity for the
project.
IF the Contractor performs any work contrary to such laws, ordinances rules and regulations, and
without such notice to the Architect, he shall bear all costs arising there from.
6.02SITE CONDITIONS: Before the bidding and the awarding f the contract, the Contractor is expected
to have visited the locality of the work and made his own estimates of the facilities and difficulties
attending to the execution of the proposed contract, including local conditions and all other
contingencies. No extra compensation and extension of time will be given due to negligence or
inadvertence of the Contractor.
ART 8 GENERAL
Notwithstanding anything herein specified or provided that may be construed to the contrary, all
materials and equipment must conform to all laws, ordinances regulations and building codes
now or hereafter may be in force and applicable during the period of construction, and the
contractor shall obtain the necessary permits and pay the required fees therefore to the proper
authorities. The Contractor shall bear any and all damages by reason of ay delay in the work
arising from his failure to comply the provisions of his clause. Provided, however, that should any
revision or amendments to such laws, ordinances, regulations and building codes made during
the construction period affect the cost or time of completion of the contract, a corresponding
adjustment shall made.
ART 9 EQUIPMENT
9.01 QUALITY OF EQUIPMENT: In order to establish standards of quality, the Architect and the
Engineer have in the detailed Specifications, referred to certain equipment by name and catalog
number. This procedure is not to be construed as eliminating from competition other products of
equal or better quality by other manufacturers where fully suitable in design.
a. The Contractor shall furnish the complete list of proposed substitutions prior to the signing of
the Contract, together with such engineering and catalog data as the Architect and the Engineer
may require.
b. The Contractor shall by abide by the Architect’s and the Engineer’s judgments when proposed
substitute items of equipment are judged to be acceptable and shall furnish the specified item of
equipment in such case. All proposals for substitutions shall be submitted in writing by the
General Contractor and not by individual trades or material suppliers. The architect and the
Engineer will approve or disapprove proposed substitutions in writing within a reasonable time.
No substitute equipment shall be used unless approved in writing.
9.02 EQUIPMENT APPROVAL DATA: The Contractor shall furnish three copies of complete catalog
data for every manufactured item of equipment and all components to be used in the work,
Including specific performance data material description, rating, capacity, working pressure,
material gauge or thickness, brand name, catalog number, and general type.
a. This submission shall be complied by the Contractor and approved by the Architect and the
Engineer before any of the equipment is ordered.
b. Each data sheet or catalog in the submission shall be indexed according to
specification section and paragraph for easy reference.
c. After written approval, this submission shall become a part of the Contract, and may
not be deviated from except upon written approval of the Architect and Engineer.
d. Catalog data for equipment approved does not in any case supersede the Contract Documents.
The approval of the Architect and the Engineer shall not relieve the Contractor from responsibility
for deviations from Drawings or Specifications, unless he has in writing called their attention to
such deviations at the time of submission, nor shall it relieve him from responsibility for errors of
any sort in the items submitted. The Contractor shall check the work described by the Catalog
data with the Contract Documents for deviations and errors.
e. It shall be the responsibility of the Contractor to insure that Items to be furnished fit the space
available. He shall make necessary field measurements to ascertain space requirements,
including those for connections, and shall order such sizes and shapes of equipment that the final
Installation shall suit the true intent and meaning of the Drawings and Specifications.
f. Where equipment requiring different arrangement of connections from those shown is approved.
It shall be the responsibility of the Contractor to install equipment to operate properly, and in
harmony with the intent of the Drawing and Specifitations, and to make all changes in the work
required by the different arrangement of connections.
10.01 MANUFATURERS AND DEALERS: Names of proposed manufacturers, material men, and
dealers who are to furnish materials, fixtures, appliances or other fittings shall be submitted to the
Architect for approval as early as possible, to afford proper investigation and checking.
a. No manufacturer will approved for any materials to be furnished under this Contract unless he
shall be of good reputation, shall have a plant of ample capacity and adequate quality control and
shall have successfully produced similar products.
b. All transactions with manufacturers, or sub-contractor, shall be through the Contractor.
c. In asking for prices on materials, the Contractor shall provide manufacturer or dealer with
complete information from specifications and Drawings, and shall inform manufacturer or dealer
of all pertinent contract requirements.
d. The manufacturer or dealer shall have the materials, equipment, fixtures, appliances or their
fittings supplied by him properly coded or identified in accordance with the existing standards for
same to indicate class grade or quality.
10.02 SAMPLES OF MATERIALS: The Contractor shall furnish for approval, with such promptness as
to cause no delay in work, samples as specified or required. Work shall be in accordance with
approved samples.
a. Unless otherwise specified, three samples shall be submitted, and of adequate size to show
quality, type, colour, range, finish, and texture if material.
b. Each sample shall be labeled, bearing material name and quality, the Contractor’s name, date
project name, and other pertinent data.
c. Where specifications require manufacturer’s printed installation directions, such directions
shall accompany samples submitted for approval.
d. A letter of transmittal in triplicate from the Contractor requesting approval shall accompany all
sets of samples.
e. Transportation charges to the Architect’s office must be prepaid on all samples forwarded.
f. Materials shall not be ordered until approval is received in writing from the Architect. All
materials shall be furnished substantially equal in every respect to approved samples.
10.04 TESTING SAMPLES OF MATERIALS: The Contractor shall submit to the Architect as many
samples as may be needed for purposes of testing. Testing of all samples shall comply with the
Specifications and government standards and shall be performed by competent entity or testing
laboratory approved by the Architect. All cost for shipment, delivery, handling, and testing of
samples are to be paid by the Contractor.
10.05 QUARLITY OF MATERIALS: Unless otherwise specified, all material shall be new. The quality of
materials shall be the best grade of their respective kinds for the purpose. The work shall be
performed in the best and most acceptable manner in strict accordance with the requirements of
the Drawings and Specifications.
The decision of the Architect as to quality and quantity of work and material shall be final and
precedent to the Contractor’s right to receive any money hereunder.
10.07 DEFECTIVE MATERIALS: All materials not conforming to the requirements of these
specifications shall be considered as defective. No defective materials, the defects of which have
subsequently corrected, shall be used until approval has been given. Upon failure on the part of
the Contractor to comply forthwith with any order of the Architect made pursuant to the
provisions of this article, the architect shall have authority to remove and replace defective
materials and to deduct the cost of removal and replacement from any money due or to become
due the Contractor.
a. The apparent silence of the Specifications, Drawings, Special Provisions and supplementary
Specifications, as to any detail or description concerning any point shall be regarded as meaning
that only the best general practice is to prevail and that only materials and workmanship of first
class quality are to be used.
B, Failure or neglect on the Architect, or any of his agents to condemn or reject bad or interior
materials shall not be construed to imply an acceptance of the materials if said bad or inferior
materials are discovered at any time prior to the final acceptance f the work by the Owner and the
release of the Contractor.
10.08 IMPORTED MATERIALS, FIXTURES AND EQUIPMENT: The Contractor shall take cognizance of
the in element of the Contract. He shall make early arrangements for the purchase and delivery of
all specified imported materials, fixtures, appliances and equipment in order to avoid delay in the
completion of the work.
No extension of time or substitution of materials shall be allowed due to negligence or
inadvertence of the Contractor.
Materials, equipment, fixtures, appliances and fittings specifically indicated shall be furnished by
the Owner in accordance with schedule of delivery agreed upon between the Owner and the
Contractor. The fact that the Owner is to furnish material is conclusive evidence of its
acceptability for the purpose intended and the Contractor may continue to use it until other
directed. If the Contractor discovers any defect in material furnished by the Owner, he shall notify
the Architect. The Contractor shall be responsible for material loss or damage after receipt of any
material, equipment, fixture, and appliance or fitting unless the same has been installed and
accepted for safe keeping by the Owner or his representative.
SECTION IV
PREMISES AND TEMPORARY STRUCTURES
14.01 LIMITATION OF USE: The Contractor shall confine his apparatus, the storage of
materials, and the operations of his workmen to limits indicated by the law, ordinances, permits,
or directions of the Architect and shall not unreasonably encumber the premises with his
materials.
14.02 SAFEGUARD FOR STRUCTURE: The Contractor shall not load or permit any part of the structure
to be loaded with a weight that will endanger its safety. The Contractor shall enforce the
Architect’s Instructions regarding signs, advertisements, fires and smoking.
15.01 TEMPORARY OFFICE AND CONTRACTOR’S BUILDING: The Contractor shall at all times provide
and maintain adequate weather tight temporary office with water, light, telephone, and toilet
facilities for the use of the Architect, resident engineers, Inspectors, contractor, and sub-
contractors. This office shall be provided with wooden floor raised above the ground, windows,
doors and locks, tables, closet, blackboard, tack board, benches and racks for drawings. One
room of approximately 12 square meters shall be provided for the Architect’s use.
15.02 TEMPORARY HOUSING FOR WORKERS: The temporary buildings for housing men, or the
erection of tents or other forms of protection will be permitted only at such places as the owner or
Architect shall designate: and the sanitary condition of the grounds I or about such structures
shall at all times be maintained in a manner satisfactory to the owner and the Architect. Nobody
shall be allowed to sleep or cook within the building line of the project under construction.
15.03 TEMPORARY SANITARY FACILITIES AND FIRST AID STATION: The Contractor shall provide
construct and maintain for the duration of the contract, ample sanitary toilet accommodation and
other necessary conveniences including water connections for the use of personnel and laborers
on the work, properly secluded from public observation. In such manner and at such points as
shall be approved by the Architect, and their use shall be strictly enforced. He shall keep such
places clean and free from flies: remove all connections and appliances connected therewith prior
to the completion of the contract and leave the premises perfectly clean.
15.04 TEMPORARY BARRICAES AND GUARD LIGHTS: The Contractor shall furnish and put up all
temporary barricades and guard light necessary for the, proper prosecution and completion of
work. The guard lights at the top to the false work tower, barricades, railing, ET, shall be provided
and maintained by the Contractor throughout the prosecution of the project.
15.05 TEMPORARY WATER, POWER AND TELEPHONE FACILITIES: The
Contractor shall make all necessary arrangements with the local utility companies in order that
temporary facilities for water, power, and telephone are sufficiently provided till the completion of
the work. All expenses incurred in connections therewith shall be paid by the Contractor
15.06 TEMPORARY SIGNS: No signs advertisements will allowed to be displayed
without the Architect’s approval. The Contractor may erect one painted sign as approved by the
Architect, giving names and addresses of the Architect. Contractor and various sub-contractors.
The Architect shall approve size, colour, lettering, and sign locations.
15.07 TEMPORARY ROADWAYS: The Contractor shall construct and properly maintain temporary
roadways within and adjacent to site in order to provide proper access to the building. Temporary
roadways shall adequately sustain loads to be carried on them and be so constructed as not to
endanger existing or newly installed underground structures.
15.08 TEMPORARY STAIRS, LADDERS, RAMPS, and RUNWAYS: The Contractor shall furnish and
maintain all equipment such as temporary stairs, ladders, ramps, scaffolds, runways, derricks,
chutes, and the like as required for proper execution of work by all trades. All such apparatus,
equipment, and construction shall meet all requirements of Labor Law and other laws applicable
thereto.
15.09 TEMPORARY ELEVATORS AND HOISTS: The Contractor shall install and operate an adequate
number of hoists and elevators. No hoists shall be constructed at such locations as will interfere
with or affect construction of floor arches (or work of other Contractors). They may be located at
exterior sides of structure and extend upward adjacent to line of window openings. They shall be
located at a sufficient distance from exterior walls and be so protected as to prevent damage,
staining or marring the permanent work.
15.10 TEMPORARY ENCLOSURES: The Contractor shall provide temporary weather tight enclosure for
all exterior openings as son as walls and roof are built so as to protect all work from. All exterior
doors shall be equipped with self-closing hardware and padlocks. All exterior windows shall be
provided with temporary sash frames securely fastened in place buy removable when required.
Such sash frames shall be covered in approved manner.
15.11 TEPORARY OR TRIAL USAGE: Temporary or trial usage by the Owner of any mechanical device,
machinery, apparatus, equipment, or any work or materials supplied under Contract before final
completion and written acceptance y the Architect shall not be construed as evidence of the
Architect’s acceptance of same.
The Owner shall have privilege of such temporary or trial usage, for such reasonable length of
time as the Architect shall deem to e proper. No claim for damage shall be made by the Contractor
for injury to or breaking of any parts of such work which may be caused by weakness or
inaccuracy of structural parts or by defective material or workmanship.
If the Contractor so elects, he may, at his on expense, place persons satisfactory to the
Architect to make such trial usage.
15.12 REMOVAL OF EMPORARY STRUCTURE: The contractor shall remove all temporary work from
premises, erected by him and shall clean the premises as a condition for completing the work and
before acceptance of the work by the Owner.
Section V
PROTETION OF WORK AND PROPERTY
16.01 SAFEGAURD MEASURES: The Contractor shall put up ad continuously maintain adequate
protection of all his work from damage and shall protect the Owner’s property, as well as all
materials furnished and delivered to him by the Owner. He shall make good any such damage,
injury or loss, except such as may caused by agents or employees of the Owner, or due to causes
considered as Act of God.
a. The Contractor shall provide reliable and competent watchmen to guard the site and
premises, from commencement of operation until building is fully completed. Provide all
doorways with locks under control of the Contractor, who shall lock doors at the close of each
day’s work. In the event that the Architect at any time deems watchmen service inadequate or
incompetent, the contractor shall increase or change the watchmen personnel to the Architect’s
satisfaction.
b. Smoking on premises shall be prohibited except in designated places and signs to this
effect shall be posted conspicuously. Fires shall not be built on premises except by express
consent of the Architect.
c. The Contractor shall provide and maintain barrels of water and fire buckets on premises
for fire protection. Such equipment shall not be used for other purpose.
d. The Contractor shall provide and maintain in good working order and adequate number
of fire extinguishers.
16.02 OLD MATERIALS: All old materials of value found the Contractor upon the work, shall be
carefully piled where designated by Owner or the Architect and the Contractor shall be
responsible for the same until final acceptance of the work.
16.03 TREES AND OTHER PLANTS: Existing trees, plants, shrub, etc., which are to remain shall be
boxed and otherwise protected from damage. No trees within site or located outside building lines
shall be cut or removed without specific approval from the Owner and the Architect.
a. all trees and other plants that need to be transplanted elsewhere within fifty(50) meters
from the building lines shall be done by the contractor at his own expense in accordance with
instructions from the Architect or from the authorities concerned.
b. undue damage to trees, plants, shrub, streets, sidewalks, etc., resulting from and in
connection with construction work shall be made good and /or replaced b the Contractor his own
expense to the satisfaction of the Owner and the architect.
16.04 DRAINAGE: If it is necessary in the prosecution of the work to interrupt or obstruct the natural
flow of rivers or streams, the drainage of the surface, or flow of artificial drains, the Contractor
shall provide for the same during the progress of the work in such a way that no damage shall
result to either public or private interest. For any neglect to provide for other natural or artificial
drainage which he may have interrupted, he shall solely be held liable for all damages which may
result there from during the progress of work.
19.01 CHARACTER OR WORKMEN: The Contractor shall employ only competent and efficient
engineers, superintendents, foremen, mechanics, laborers, or artisans. Whenever, in the opinion
of the Architect, any employee is careless or incompetent or obstructs the progress of the work or
acts contrary to instructions or conducts himself improperly, the Contractor shall, upon written
request of the Architect, discharge or otherwise remove him from work and not employ him again
upon it.
Should the Contractor fail to remove unsatisfactory workmen or fail to furnish suitable and
sufficient equipment or personnel for the proper prosecution of the work, the Architect may
withhold payment which are or may become due, or may suspend the work until such orders are
complied with.
19.02. SUPERINTENDENCE AND SUPERVISION: The Contractor, if supervises the work personally,
must be a licensed engineer or architect acceptable to the Architect who will supervise the work
personally and inspect at least once a week.
The Contractor shall keep in his project site, during the work’s progress, a competent engineer or
Superintendent and any necessary assistants, all satisfactory to the Architect.
The Project engineer or Superintendent shall represent the Contractor in his absence and all
directions given to him shall be as binding as if given to the Contractor. He shall have full
authority to execute the orders or directions of the Architect without delay and to prompt supply
such materials, tools, paints, equipment, and labor as may be required.
20.01 METHODS AND APPLIANCES: The Contractor shall use such methods and appliances for the
performance of all the operations connected with the work embraced under this Contract as will
produce a satisfactory quality of work and rate of progress which, in the opinion of the Architect,
will ensure the completion of the work within the contract time.
a. If, at any time before the commencement or during the progress of the work, such methods or
appliances appear to the Architect to be inefficient or inappropriate for producing the quality of
the work required, or insuring the required rate of progress, the Architect may order the
Contractor to increase the rate of their efficiency or to improve their system of operation. The
Contractor must comply with such order. Failure, however, of the Architect to demand such
increase of efficiency or improvement of character of methods and appliances shall not relieve the
Contractor from his obligation to turn out such quality of work and rate of progress as are called
for in t his contract.
b. The Contractor shall, if required, furnish to the Architect for approval full information and
satisfactory evidence as to the name of the manufacturer of machinery, or mechanical or other
equipment which he contemplates using together with the performance capacities and other
pertinent information.
20.02 LAYING OUT THE WORK: The Contractor shall lay out the lines and grades of the work as per
conditions set forth under Article 7.03 (Construction Stakes and Reference Mark) of the General
Conditions.
All stakes benchmarks, etc., placed by the Contractor in laying out the work, approve by the
Architect, shall be carefully guarded and preserved by the Contractor. In case such stakes or
marks are displaced or rendered useless through the carelessness or neglect of the Contractor or
of his agents, employees, or workmen, they should be replaced by the Contractor at his own
expense.
20.03 INSPECTION OF WORK: The Owner, Architect and their representatives shall at all times have
access to the work wherever it is in preparation or progress and the Contractor shall provide
proper facilities for such access and for inspection.
a. If the specifications, the Architect’s Instructions, laws, ordinances or any public authority require any work
to be specifically tested or approved, the Contractor shall give the Architect and other parties required to
make the inspection, timely notice of its readiness for inspection, and the date fixed for such inspection.
Inspections by the Architect shall be promptly made and were practicable, at the source of supply. If any
work should be covered up without approval or consent of the Architect, it must, if required by the Architect,
be uncovered for examination at the Contractor’s expense.
b. Re-examination of questioned work may be ordered by the Architect and is so ordered; the work must be
uncovered by the Contractor. If such work be found not in accordance with the Contract Documents, the
Contractor shall pay the cost.
c. The Contractor shall furnish promptly without additional charge all reasonable facilities, labor, and
materials necessary for the safe and convenient inspection and tests that may be required by the inspectors.
All inspection and tests shall be performed in such manner as not to unnecessarily delay the work.
d. If there are indications that the work done are not in accordance with plans and specification, the Architect
may at any time before final acceptance of the entire work make an examination of the work already
completed. By removing or tearing out same, the Contractor shall, on request, promptly furnish all necessary
facilities, labor, and materials. If such work is found to be defective in any material respect due to fault of the
Contractor, or his subcontractors, he shall defray all the expenses of such examination and of satisfactory
reconstructions. If, however, such work is found to meet the requirements of the Contract, the actual cost of
labor and materials necessary involved in the examination and replacement plus 15 percent, shall be allowed
the Contractor and shall in addition, if completion o the work has been delayed hereby, be granted a suitable
extension of time on account of the additional work involved.
20.04 DEFECTIVE WORK: Defective work may be condemned by the Architect at any time before the
final acceptance of the work, and when such work has been condemned it shall be taken out
immediately by the Contractor and rebuilt in accordance with the Drawings and
Specifications. Failure or neglect on the part of the Architect or any of his agents to condemn or
reject bad or inferior work, shall not be construed to imply an acceptance of the work of the same
if such bad or inferior work is discovered at any time prior to the final acceptance of the work by
the Owner and the release of the Contractor.
20.05 WORK DURING EMERGENCY: The Contractor shall perform any work and shall furnish and
install all materials and equipment necessary during an emergency endangering life or property.
In all cases he shall notify the Architect and the Engineer of the emergency as soon as
practicable, but he shall not wait for instructions before proceeding to properly protect both life
and property.
20.06 INCREASED OR DECREASED QUANTITIES OF WORK: Adjustments of Drawings to suit field
conditions which cannot be foreseen at the time of calling for bids may be necessary during
construction. It is the essence of the Contract to recognize such changes in Drawings as
constituting a normal and expected margin of adjustment, and not involving nor permitting
change or modification of Contract Prices, provided only, that resulting overruns or under runs
from the quantities in the Proposal do not exceed five percent. In case of discrepancy, the matter
shall be submitted immediately to the Architect, before any adjustment shall be made by the
Contractor, otherwise it shall be at his own risk and expense.
b. CHANGE OF SUB-SURFACE CONDITIONS: If, during the progress of the work, sub-surface conditions
at the site materially different from those shown on the Drawings or indicated in the Specifications are
discovered or encountered, the attention of the Architect shall be called immediately to such conditions before
they are disturbed. The Architect shall thereupon promptly investigate the conditions, and if he finds that
they materially differ from those shown on the Drawings or indicated in the Specifications, he shall at once,
with the approval of the Owner, make such changes I the Drawings and Specifications as he may find
necessary.
c. ADJUSMENTS OF CONTRACT: All such work shall be executed under the conditions of the original
contract. If such changes cause an increase or decrease in the amount due under this Contract, or in the time
required for its performance, an equitable adjustment shall be made and the contract shall be modified I
writing accordingly. The express consent of the sureties shall be obtained in writing. In the event that the
work involved is increased y such changes, the Contractor shall furnish proportionate additional
performance bond.
d. VALUE OF EXTRA WORK: The value of extra work or change shall be determined in any one or more of
the following ways:
1) By estimate and acceptance in a lump sum
2) By unit price stipulated I the Contract or subsequently agreed upon, provided the extra or credit does not
exceed 25% of original contract of the particular work involved.
3) By actual direct cost plus Fifteen Percent for contractor’s profit, overhead and contractor’s tax.
Under case (3), he shall keep and present such formats the Architect may direct, a correct account of the cost,
together with vouchers. In any case, the Architect shall certify to the amount including the Fifteen Percent
allowance for overhead and profit due the Contractor.
e. PERIOD OF WHICH CLAIM FOR ADJUSTMENT HAS TO BE ASSERTED: Any claim for adjustment
involving questions of fact must be asserted fifteen days from the date of charge is ordered unless the
Architect shall for proper cause extend such time. Except as otherwise specifically provided in this Contract,
all disputes concerning questions of act arising under this Contract shall be decided by the Architect or his
duly authorized representative. Nothing, however, as provided for in Article 20.07 shall excuse the
Contractor for proceeding with the prosecution of the work so changed.
f. CHANGES ORDERED BY THE ARCHITECT: In giving instructions, the Architect shall have the authority
to make minor changes in the work, not involving extra cost, and not inconsistent with the design concept of
the building.
g. AWARD OF EXTRA WORK TO OTHER CONTRACTORS: Incase any extra work shall be required in the
proper performance of the work contemplated under this Contract, it is understood that if the Contractor
and the Owner fail to arrive at any agreement as to the price of such extra work, the Owner reserves the right
to have such extra work done by any other person, firm, or corporation that said Contractor.
20.08 CLAIMS FOR EXTRA COST: I f the Contractor claims that any Instructions by drawing or
otherwise involve extra cost under this Contract, he shall give the Architect written notice thereof
within fifteen days after the receipt of such instruction, and, in any event, before proceeding to
execute the work, except I emergency endangering life or property, and the procedure shall be as
provided for in Article 20.05 (Work During an Emergency) of the General Conditions. No such
claim shall b e valid unless so made.
In like manner, if the Contractor incurs a delay in the mobilization and/or in the progress of his
work for reasons attributable to the Owner, e.g., Owner-supplied materials not arriving on time,
movements or work executed by the Owner which interfere with the progress of the Contractor’s
work, delay decisions and other matters related thereto, he shall give the Architect written notice
thereof within fifteen days after recognition of such delays. No such claim shall be valid unless
such written notice has been executed.
20.09 CLEANNGUP AT COMLETION OF ORK: The Contractor shall at all times keep the premises free
from accumulations of waste materials or rubbish caused by his employees or work. At the
completion of the work, he shall remove all his rubbish from and about the building and all his
tools, scaffolding and surplus materials and turn over the work for occupancy with:
a. All dirt, stains and the like on all finishing of floors, walls and ceiling, decorative work, finishing hardware
and fixtures, removed;
b. All woodwork, finishing hardware and all metal works, cleaned and polished.
c. All glazing marble and tile work washed and polished. The Contractor shall so clean the building site as
shown in the Drawings and all areas which the Contractor used in the operation of the project.
At no time shall any rubbish be thrown from windows or other parts of the building without the
use of rubbish chutes.
20.10 USE OF COMPLETED PORTIONS OF WORK: The Owner shall have the right to take possession
of and use any completed or partially completed portions of the work, notwithstanding that the
time for completing the entire work or such portions may not have expired; but such taking
possessions and use shall not be deemed an acceptance of any work not completed in
accordance with the Contract Documents.
Neither shall it be deemed a waiver by the Owner of the rights to claim for damages due to delays
in the completion of the work. If such prior use increase the cost of or delays the completion of
uncompleted work, the Contractor shall be entitled to such extra compensation, or extension of
time or both, as agreed upon prior to the occupancy.
20.11 CERTIFICATE OF COMPLETION OF WORK: Upon due notice from the Contractor that he has
substantially completed the work; the Architect shall make an inspection of the project.
Substantial completion shall mean that the value of the work completed shall not be less than 98%
of the contract amount and that the remaining unfinished work shall be of a minor nature only. If
the contract covers the furnishing and/or installation of equipment, fixtures and utilities, said
equipment, fixtures and utilities, shall be fully tested and test- run in order that the work can be
considered as substantially complete. However, should the Contractor, through no fault of his, be
unable to test run in order that the work can be considered as substantially completed. However,
should the Contractor, through no fault of his be unable to test run the equipment at the time of
substantial completion, he shall be given the necessary time extension for that portion of the
work. As soon as, in the opinion of the Architect, the work shall have been substantial completed
and shall have satisfactorily passed any final test of materials that may be prescribed by the
Contract, the Architect shall issue a Certificate of Completion in respect to the work. Even before
the completion other whole work, upon written application of the Contractor, the Architect may
likewise issue such a Certificate of Completion with respect to any substantial part of the work
which has been completed to the satisfaction of the Architect and occupied or used by the Owner.
In all cases, prior to the issue of sold Certificate of Completion, the Contractor shall execute a
written undertaking to finish any outstanding work during the Period off making Good of Known
Defects or Faults as defined in Article 20.12 hereof.
20.12 PERIOD OF MAKING GOOD OF KNOWN DEFECTS OR FAULTS: The expression “Period of
Making Good off Known Defects or Faults” shall mean a period of not more than sixty calendar
days, unless otherwise expressly named in the contract, calculated from the date of issue of the
Certificate of Completion of the whole work or of any part thereof, in accordance with Article
20.11.
20.13 MAKING GOOD OF KNOWN DEFECTS OR FAULTS : The Contractor shall execute at his own
expense all work necessary for making good of known defect, Imperfections or faults ( fair, wear
and tear expected) within fifteen days after its expiration as a result of an inspection made by or
on behalf or the Architect prior to its expiration.
If, in the opinion of the Architect, the defect or fault is due to the owner or Owner’s representative,
the value of such work shall be ascertained and paid for as it were additional work. If the
Contractor shall fail to do any work as aforesaid, the Owner shall upon written notice to the
contractor be entitled o carry out such work u his own workmen or but other contractors, and if
such work which the contractor should have carried out is at the Contractor’s cost, the Owner
shall be entitled to recover from the Contractor the cost thereof, or may deduct the same from any
monies due or may become due to the Contractor.
20.14 SEARCH FOR CAUSES OF DEFECTS OR FAULTS: The Contractor shall, if required by the
Architect in writing, search for the cause of any defect, imperfection or fault under the directions
of the Architect. Unless such defect, imperfection or fault shall be one for which the Contractor is
not liable under the Contract, the cost of the work is carried out by the Contractor in searching for
said defect shall be borne by the Owner. But if such defect, imperfection, or fault shall be one for
which the Contractor is liable, the costs of the work carried out in searching said defects shall be
borne by the contractor and he shall in such case, repair, rectify and make good such defect,
imperfection or fault at his own expense, in accordance with the provisions of Article 20.13 hereof.
21.01 NOTICE TO PROCEED: Following the execution of the Contract Agreement but the Owner,
written Notice to Proceed with the work shall be given to the contractor. The Contractor shall
begin and shall prosecute the work regularly and uninterruptedly, thereafter (unless otherwise
directed in writing by the owner) with such force as to secure the completion of the work within
the time stated in the contract. If the Contractor undertakes actual construction on the proposed
work including the delivery of equipment or materials (In the case for furnishing materials) or the
performance of any other kind of work whatsoever, before he receives a copy of the duly executed
Contract or Notice to Proceed, he does so in his own risk,
21.02 The Contractor shall complete, in an acceptable manner, all of the work contracted for in the time
stated in the Contract. Computation of Contract Time shall commence on the seventh (7 th) day
from receipt of Notice to proceed, unless otherwise stipulated in the contract, and every calendar
following, shall be counted as a working day.
21.03 SCHEDULE OF COMPLETION: The Contractor shall submit, for approval, the Schedule of
Construction Work in Critical Path Method form or any other form acceptable to the Architect
indicating the approximate date each item will be started and completed, the equipment to be
used and number of men to be employed to complete it, in accordance with his schedule. The
progress of the work shall be at a rate sufficient to complete the Contract in an acceptable manner
within the period of time specified. If it appears that the rate of progress is such that the Contract
will not be completed within the time limit, the Architect may order the Contractor to take such
steps as he considers necessary to complete the Contract within the period provided.
21.04 EXTENSION OF TIME: The Contractor will be allowed an extension of time based on the following
conditions:
a. Should the Contractor be obstructed or delayed in the prosecution or completion of the work by
the act, neglect, delay, or default the owner or any contractor employed by the Owner on the work;
by strikes or lockouts, by and Act of God or Force Majeure as defined in Article 1.26; by delay
authorized by the Architect pending arbitration; then the Contractor shall within fifteen (15) days
from the occurrence of such delay file the necessary request for extension. The Architect may
grant the request for extension for such period of time as he considers reasonable.
However, no such extension of time shall be granted for any alleged failure of the Owner to
furnish materials or information unless they be required in the proper prosecution of the work in
the order prescribed by the Architect and unless the Contractor shall have made written request
for them at ten (10) days before they are actually needed.
b. The WRITTEN CONSENT OF THE BONDSMEN must be attached to any request of the
Contractor for an extension of time and submitted to the Owner for consideration.
c. If the satisfactory fulfillment of the Contract shall require the performance of work in greater
quantities than those set forth in the Contract, the time allowed for performance shall be
increased in the same ratio that the total cost of work actually performed shall be the total cost in
Contract. However, if in the opinion of the Architect, the nature of the increased work is such that
the new Con tract Time as computed approve is unreasonably short, the time allowance for any
extension and increases shall be as agreed upon writing.
d. If no schedule or agreement stating the dates upon which drawing shall be furnished is made,
then no claim for delay shall be allowed on account of failure to furnish drawings until two weeks
after demand for such drawings and unless such claim be reasonable.
e. If the work is interrupted for any reason, it must be promptly resumed on the removal or
cessation of the cause of delay.
f. The Contractor shall give written notice to the Architect at least ten (10) days prior to beginning,
suspending (Except in case of accident), or resuming the work to the end that the Architect may
make the necessary preparations for inspection without delaying the work. All delays or losses
resulting from failure of the Contractor to give such notice will be at the Contractor’s risk; and all
extra costs to the Owner for such delay (said costs to be determined by the Architect) shall be
deducted from the Final Payment.
21.05 LIQUIDATED DAMAGES: It is understood that time is an essential feature of this contract and
that upon failure to complete the said contract within the contract time, the Contractor shall be
required to pay the Owner the liquidated damages in the amount stipulated in the Contract
Agreement, the said payment to be made as liquidated damages, and not by way of penalty. The
Owner may deduct from any sum due or to become due the Contractor any sums accruing for
liquidated damages as herein stated. For purposes of calculating, the actual completion date shall
be the date certified by the Architect under Article 20.11 hereof.
ART. 22 PAYMENTS
22.01 DETAILED BREAKDOWN OF CONTRACT AMOUNT: Except in cases where unit prices from the
basis for payment under the Contract the Contractor shall, within fifteen (15) days from the receipt
of Notice to Proceed, submit a complete Breakdown of Work and Corresponding value of the
Contract Amount showing the value assigned to each part of work, including the allowance for
profit and overhead. Upon approval of the Breakdown of Work and Corresponding Value by the
Architect, it shall be used as the bass for all Requests for Payment.
22.02 REQUEST FOR PAYMENTS: the Contractor may submit periodically but not more than once each
month a Request of Payment for work done. The Contractor shall furnish the Architect all
reasonable facilities required for obtaining the necessary information relative to the progress and
execution of the work. Each Request for Payment shall be computed from the work completed on
all items listed in the Breakdown of Work and Corresponding Value, less the 10% retention unless
otherwise agreed upon and less previous payments. When 50% of the Contract has been
accomplished, no further retention shall be made on the balance of the Contract.
a. In general, no payment shall be made for materials or items not incorporated in the work.
However, exception to this condition may be made in the case of materials or items which may
require immediate acquisition and compensation du to shortages or import or transportation
difficulties. In the event of such exceptions, payment shall be conditioned upon the submission
by the Contractor of bills of sale or such other procedures as will establish the Owner’s title to
such material or item or otherwise adequately protect the Owner’s Interest.
22.03 PROGRESS PHOTOGRAPHS TO ACCOMPANY REQUEST FOR PAYMENT: The Contractor at his
own expense shall furnish the Architect progress photographs which shall be taken monthly,
starting when the work begins and continuing so long as the work is in progress in the outside of
the building, from station points designated by the Architect.
a. The photographs shall be 6”x8”. At each period four exposures shall be taken, one on each side
of the building. Eight (8) prints dull finish, (2 copies for each exposure) shall be delivered to the
Architect and all negatives shall bear the date of exposure and name of the work.
b. No partial payment shall be considered for approval without the above mentioned prints
accompanying the Request for Payment.
22.04 ARCHITECT’S ACTION ON A REQUEST FOR PAYMENT: Within fifteen days after receipt of any
Request for Payment by the Contractor, the Architect shall either issue a Certificate of Payment or
withhold the Request of Payment. When the Architect decides to withhold the Request for
Payment, he shall inform the contractor in writing the reasons for withholding it. If the Contractor
and Architect cannot agree on a revised amount, the Architect will issue a certificate of payment
for the amount for which he is able to make representations to the owner.
The Certificate of Payment shall include the value of work accomplished by the Contractor during
the period covered buy the certificate and recommendation to the Owner for payment in an
amount the Architect decides to be properly due.
22.05 APPROVAL WITHHELD: The Architect may recommend withholding of payment in whole or in
part on any approved Request for Payment on account of any of the following reasons:
When the above grounds are removed, payment shall be made for amounts withheld.
Owner’s failure to pay the amount involved would be subject to payment based on banking loan
rates prevailing at the time of the signing of the contracts
22.08 PAYMENT OF CONTRACTOR’S OBLIGATIONS: the Contractor shall pay workmen employed by
him on his project such rates as are provided by existing laws. He shall also pay promptly all
materials and equipment used by him on his project, and all taxes due from him. He shall remit as
required by law all amount withheld from the salaries or wages of his employees or workmen.
If required he shall furnish the Owner with a statement sworn to before an officer duly authorized
to administer oath that all persons who have done work or furnished materials under this Contract
have been duly paid. If such written evidence is not furnished before the final payment in under
the Contract falls due, said Owner may after due notice to and clearance by the Contractor pay
such lawful claims in whole or in part to any person, firm, or corporation claiming the same, and
charge the amount thus paid to said Contractor, who will accept the same as payment from the
amount due on the Contract.
22.09 PAYMENTS OVER 65 PERCENT: No payment shall be made on contracts in excess sixty five
percent (65%) of the Contract Price, unless a statement sworn before an officer duly authorized to
administer oath is submitted by the Contractor to the effect that the bills for labor other than
current wages, and all bills for materials have been duly paid by the Contractor and his Sub-
contractor, if any, excepting only such bills as may be enumerated in such sworn statement.
Provided however, that should such sworn statement turn out false, the Owner and the work
cover whereby shall not be liable for any claim or lien arising from the failure to pay and other
causes, provided for in this clause the Contractor does hereby bind itself society answerable for
any such lien should the same arise.
22.10 CORRECTION OF WORK BEFORE FINAL PAYMENT: The Contractor shall promptly remove the
premises all work condemned by the Architect as failing to conform to the Contract, whether
incorporated or not, and the Contractor shall promptly replace and re-execute his own work in
accordance with the Contract and without expense to the owner and shall bear the expenses of
making good all work of other contractors destroyed or damaged by such removal or
replacement.
If the Contractor does not remove such condemned work within a reasonable time, fixed by
written notice, the Owner may remove them and may store the material at the expense of the
Contractor. If the Contractor does not ay the expenses of such removal within ten days time
thereafter, the Owner may, upon ten days written notice, soil such materials at auction or at
private sale and shall account for the net proceeds thereof, after deducting all the costs and
expenses that should have been borne by the Contractor.
20.11 OTHER REQUIREMENTS BEFORE FINAL PAYMENT: The Contractor shall submit (aside from
those provided in the Contract Document) the following before the final payment if made.
a. Certificate of Final Building Occupancy unless such certificate cannot be obtained through no
fault of the Contractor
b. Certificate of Final Inspection of electrical, telephone, sanitary, mechanical, gas, safety and other
utilities unless such certificate cannot be obtained through fault no Contractor.
c. Original and three (3) sets of prints of “As-Built Drawings” if electrical, sanitary, gas, telephone
and mechanical works, if such works are within the scope of the contract “As-Built Drawings” are
the working drawings showing the system and actual locations of outlets, fixtures, services, and
equipment that were installed.
d. Three (3) copies of Directory of Panel Boards and list of circuits
e. Three (3) copies of instructions and manual for operating and maintaining of fixtures and
equipment.
f. Three (3) copies of keying Schedule
g. Guarantee bond equivalent to 30% of the Contract Price covering a period of one year after the
final acceptance of the work which guarantees the quality if the contract works and materials
installed. The Guaranteed bond shall be in the form of securities as approved by the Owner, The
Guarantee Bond will be required only if the Owner, upon acceptance of the building, releases to
the Contractor the Performance Bond and Payment Bond.
20.12 ACCEPTANCE AND FINAL PAYMENT: Whenever this Contract, in the opinion of the Architect,
shall be completely performed on the part of the Contractor, the Architect shall proceed to verify
the work, shall make the final estimates, shall certify as to the completion of the work, and accept
the same.
a. The Owner shall then, excepting for causes herein specified, pay to the Contractor promptly,
after the execution of said certificate, the remainder which shall be bound due, excepting there
from such sum or sums as may be lawfully retained under any of the provision of this Contract
PROVIDED THAT FINAL PAYMENT ON THE CONTRACT SHALL NOT BE MADE UNTIL THE
CONTRACTOR HAS SUBMITTED A STATEMENT SWORN TO BEFORE AN OFFICER DULY
AUTHORIZED TO ADMINISTER OATH, SHOWING THAT ALL TAZES DUE FROM HIM, AND ALL
OBLIGATIONS FOR MATERIALS USED AND LABOR EMPLOYED IN CONNECTION WITH THIS
CONTRACT HAVE BEEN DULY PAID; AND PROVIDED, FURTHER that nothing here in contained
shall be construes to waive the right of the Architect hereby reserved to reject the whole or any
portion of the aforesaid work, should the same be found to have been constructed in violation of
the drawings and specifications or of any of the conditions or covenants of this Contract within
the guarantee period.
b. The making and acceptance of the final payment shall constitute a waiver of all claims by the
Contractor
a. Neither the final certificate nor payment nor any provision in the Contract Documents shall
relieve the Contractor of responsibility for faulty materials or workmanship and, he shall remedy
any defects due thereto and pay for any damage to other work resulting there from, which shall
appear within a period of one year from the date of acceptance of work.
b. Neither the foregoing nor any provision in the contract documents, nor any special guarantee
limit, shall be held to limit the Contractor’s liability for defects and damages and the right of the
Owner under the provisions of the New Civil Code, and all laws, regulations and ordinance
applicable to the plans and construction of the building.
c. The Owner shall give notice of observed defects with reasonable promptness. All questions
arising under this article shall be decided by the Architect whose decision shall be subject to
arbitration.
22.14. RELEASE OF RETENTION: the amount retained by the Owner under the provision of the contract
shall be released within three months after the date of final payment.
SECTION VII
CONTRACTOR-SEPARATE CONTRACTORS-
SUB-CONTRACTORS RELATIONS
23.01: OWNERS RIGHT TO LET OTHER CONTRACTS: The Owner reserves the right to let other
contracts in connection with this work.
24.01: STORAGE OF MATERIALS AND WORK COORDINATION: The Contractor under this
Contract shall afford other contractors reasonable opportunity for the introduction and storage of
their materials and the execution of their work, and shall property connect and coordinate his
work with theirs so as to minimize interferences or obstruction in the progress of the work.
24.02: CUTTING, PATCHING AND DIGGING: The Contractor shall do all cutting, fitting or
patching of his work that may be required to make its several parts come together property and fit
it to receive or be received by work of other contractors shown upon, or reasonably implied by,
the Drawings and Specifications for the completed structure, and he shall make good after them
as the Architect may direct.
Any cost caused by defective or ill-timed work shall be borne by the party responsible therefore.
The Contractor shall not endanger any work by cutting, digging or otherwise and shall not cut or
alter the work of any other contractor save with the consent to the Architect.
24.03 DEFECTIVE WORK BY SEPARATE CONTRACTORS: If any part of the Contractor’s work
depends for proper execution or results upon the work of any other contractor shall inspect and
promptly report to the Architect any defect in such work that renders it unsuitable for such proper
execution and result. His failure to inspect and report shall constitute an acceptance of the other
contractors work as fit and proper for the reception of his work, except as to defect which may
develop in the other contractor’s work after the execution of his work.
To insure the proper execution of his subsequent work the contractor shall verify work already in
place and shall at once report to the Architect any discrepancy between the executed work and
drawings.
25.01 GENERAL: It is understood and agreed that the entire work called for by this Contract
shall not be sublet or sub-contracted. However, any part thereof or any specialty work therein,
may be sublet or sub-contracted. Subject to the provision of Article 25.02. Nothing contained in
the Contract Documents shall create any contractual relation between any sub-contractor and the
Owner.
25.02 COMPETECY OF SUB-CONTRACTOR: At least fifteen (15) days prior to the date of
bidding, the Contractor shall seek the Architects clarification as to the particular areas or parts of
the work for which the competence of the sub-contractor shall be subject to evaluation by the
Architect. Immediately thereafter, the Contractor shall submit to the Architect a list of his
prospective sub-contractors for approval.
26.03 THE CONTRACTOR AND THE SUB-CONTRACTOR AGREE THAT: In the matter
arbitration, their rights and obligations and all procedure shall be analogous to those set forth in
the contract; provided, however that a decision by the Architect shall not be a condition precedent
to arbitration.
SECTION VII
SUSPENSION OF WORK AND TERMINATION OF CONTRACT
The contractor may suspend work or terminate contract upon fifteen (15) days’ written notice to
the owner and the Architect for any of the following reasons:
a. If an order of any court or other public authority caused the work to be stopped or suspended for a period of
ninety (90) days through no act or fault of the contractor or his employees.
b. If the Architect should fall to act upon any Request for payment within (15) days after it is presented in
accordance with the general Conditions of the Contract.
c. If the owner should fall to act upon any request for payment or certificate of payment within (15) days after
its certification by the Architect.
d. If the Owner should fail to pay the contractor any sum within (30) days after its award by arbitration.
If the Contractor is compelled you suspend work due to hardships or difficulties under b, c, and d above, then
the contract sum shall be increased by the amount of the contractor’s reasonable costs of shutdown delay and
start up, which shall be effected by appropriate change order.
The Owner, upon the certificate of the Architect that sufficient cause exists to justify his action,
may without prejudice to any other right or remedy and after giving the Contractor and his surely
if any, fifteen (15) days’ written notice, terminate the contract with the Contractor and take
possession of the premises and of all materials, tools and appliances thereon and finish work by
whatever method he may, deem expedient. Sufficient cause to justify termination of the contract
shall deem to exist whenever the Contractor does any of the following:
a. Declare bankruptcy become insolvent or assign his assets for the benefit of his creditors.
b. Disregard or violate provisions of the Contract Documents or Architect’s Instructions, or fail to prosecute
the work according to the agreed schedule of Completion, Including extensions thereof.
c. Fail to provide a qualified superintendent, competent workmen or sub-contractors, or proper materials.
d. fail to make prompt payment to sub-contractors, workmen or material dealers.
29.01 USE OF MATERIALS AND EQUIPMENT AT SITE: The Contractor, upon receiving notice of the
termination of contract, shall vacate possession and deliver the said work, or the parts thereof specified in
said notice, peaceable to the owner. All materials, plant, appliances and other essential equipment as may be
needed by the construction of the project shall, at the option of the Architect, remain on the work until
completed, at such rental as may be considered reasonable.
In case such materials and/or equipment do not belong to the contractor, then the Architect shall have the
option to retain them for use in the project at the cost of the failing Contractor, or pay reasonable rent for the
use, chargeable against the Contractor.
29.02 OWNER TO COMPLETE WORK: The Owner shall then take over the work and proceed to complete
the same by administration or otherwise, and use such tools, appliances and materials of every description as
may be found upon the line of said work, or at point where materials are built or framed for the work and
also procure such other tools and materials for the completion of the work as may be required.
29.03 EVALUATION OF COST OF WORK: It is agreed and understood that, upon such termination of this
Contract, the Architect will ascertain and fix the value of the work completed by the Conductor and not paid
for by the owner and of all usable materials on the line of the work taken over by the Owner at the time of
said termination.
a. In the event that the total expenditures of the Owner on completion of the work, Including all charges against
the project prior to termination of the contract and compensation for additional architectural managerial
and administrative services, are not in excess of the Contract Price, then the difference between the said total
expenditures of the Owner and the Contract price may be applied to settle claims filed, and the balance, If
any, may be paid to the Contractor.
b. No amount in excess of the combined value of the unpaid completed work, retained percentage and usable
materials taken over by the Owner at the time of the Termination of the Contract shall be paid, nor shall any
claim for prospective profits on the work done after termination of the Contract be considered or allowed.
c. In case of suspension of work, all unpaid work executed including expenses incurred during suspension shall
be evaluated by the architect and charged to the owner.
29.04 OWNER’S RIGHT TO RECOVER LIQUIDATED DAMAGES: Neither the taking over by the
Owner of the work for completion by administration nor the re-letting of the same to another
Contractor shall be construed as a waiver of the Owner’s rights to recover damages against the
original Contractor and/or his sureties for the failure to complete the work as stipulated.
In such case, the full extent of the damages for which the Contractor and/or his sureties shall be
liable shall be:
a. The total daily liquidated damages up to and including the day immediately before the date the Owner
effectively takes over the work.
b. The excess cost incurred by the Owner in the completion of the project over the Contract Price. This excess
cost includes cost of architectural managerial and administrative services, supervision and inspection from
the time the owner effectively took over the work by administration or by re-letting same.
SECTION IX
RESPONSIBILITIES AND LIABILITIES OF CONTRACTOR AND OF OWNER
30.02 CONTRACTOR’S RESPONSIBILITY: The owner shall not be responsible for the death of
disease contracted, or injury received by the Contractor or any employee or laborers of the
Contractor; for the contractor’s plant or materials, for any damage done by or to them from any
source or cause; and damages caused by the Contractor or his employees to any property of the
Owner and adjoining property. All damages shall be the responsibility of the Contractor
30.03 INDEMNITY: The Contractor shall indemnify and save harmless the Owner from and against
all losses and all claims, demands, payments, suits, actions, recoveries, and judgment of every
nature and description brought or recovered against him, by reason of any act or omission of said
Contractor, his agents or employees, in the execution of the work or the guarding of it.
Claims for payment and repairs for damages shall be settled by the Contractor at his own expense
and to the satisfaction of the Architect and the parties concerned. In the event of failure of the
Contractor to repair at once such damages, and pay other claims, the owner may repair the same
and pay the claims, and deduct the entire cost of such repairs and claims from the payments due
the contractor.
ART 31: CONTRACTOR’S INSURANCE AND BONDS
31.01 CONTRACTOR’S LIABILITY INSURANCE: The Contractor shall secure and maintain such
Insurance from an Insurance company acceptable to the Owner as will protect himself, his sub-
contractors, and the Owner from claims for bodily Injury, death or properly damage which may
arise from operations under his Contract. The Contractor shall not commence work under his
Contract until he has obtained all insurance required under this section and shall have filed the
certificate of Insurance or the certified copy of the insurance policy with the Owner. Such
insurance policy shall contain a clause providing that it shall not be cancelled by the insurance
company without ten (10) days’ written notice to the Owner of intention to cancel. The amounts of
such shall be as agreed-upon.
31.02 CONTRACTOR’S FIRE INSURANCE: In addition to such fire insurance as the Contractor
elects to carry for his work protection, he shall secure and maintain in the name of the Owner
policies upon such structures and materials and in such amount as shall be designated. These
policies shall be secured from a company which is satisfactory to the Owner and delivered to the
Owner.
31.03 CONTRACTOR’S PERFORMANCE AND PAYMENT BONDS: The Contractor, prior to signing
the Contract, shall furnish a Performance Bond equal to 15% of the Contract amount for the
faithful performance of his work and 15% Payment Bond covering payments and obligations
arising from his Contract. Such bonds shall be in the forms of sureties as approved by the Owner.
Such bonds shall remain in effect untill replaced by the Contractor’s Guarantee Bond.
31.04 CONTRACTOR’S GUARANTEE BOND: The performance and Payment Bonds will be
released by the Owner after the expiration of two (2) months from the final acceptance of the work
and only after the Contractor has furnished the Owner, a Guarantee Bond In the amount of 30% of
the total Contract cost. The Guarantee Bond shall be for a period of one (1) year commencing
from the date of acceptance as a guarantee that all materials and workmanship installed under
Contract are of good quality.
32.02 OWNER’S OPTIONAL INSURANCE: The Owner at his option may maintain such Insurance
as will protect him from his contingent liability for damages, for personal injury, including death,
which may arise from the operations under this contract, and any other liability for damages
which the contractor is required to insure under any provision of this contract.
33.01 LIENS: Neither the final payment nor any part of the retained percentage shall become due
until the Contractor, if required, shall deliver to the Owner a complete release of all liens arising
out of this Contract, or receipts in full in lieu thereof and, if required in either case of affidavit that
so far as he has knowledge or information the release and receipts include all the labor and
materials for which a lien could be filed; but the Contractor may, if any sub-contractor refuses to
furnish a release or receipt in full, furnish a bond satisfactory to the Owner, to indemnity him
against any lien. If any lien remain unsatisfied after all payments are made, the Contractor shall
refund to the Owner all monies that the latter may be compelled to pay in discharging such lien,
including all cost and a reasonable attorney’s fee.
33.02 ASSIGNMENT
a. This Contract shall not be assigned In whole or in part by the contractor nor shall any part of the work be
sublet by the Contractor without the prior written consent of the Owner and such consent shall not relieve
the Contractor from full responsibility and liability for the work hereunder and for the due performance of
all the terms and conditions of the Contract.
b. The Owner’s consent to any subletting of work hereunder shall not be granted in any event until the
Contractor has furnished the Owner with satisfactory evidence that the sub-contractor is carrying ample
insurance to the same extent and in the same manner as is herein provided to be the contractor.
c. If the Contract is assigned or any part thereof is sublet, the Contractor shall exonerate, indemnify and save
harmless the Owner from and against any and all loss or expense caused thereby.
d. In case of any such transfer without the previous written consent of the Owner, the Owner may refuse to
carry out the Contract either with the transferor or transferee; but all rights of action breach of this Contract
by the Contractor shall be reserved to and remain within said Owner.
33.03 DAMAGES: Should either party to this Contract suffer damages because of any wrongful
act or neglect of the other party or of anyone employed by him, claim shall be made in writing to
the party liable within a reasonable time to the first observance of such damage and not later than
the final payment, except as expressly stipulated otherwise in the case of faulty or materials, and
shall be adjusted by agreement or arbitration.
33.04 DISPUTES:
a. The Architect shall, within a reasonable time, make a decision on all claims of the Owner or Contractor and
on all matters relating to the execution and progress of the work or the Interpretation of the Contract
Documents.
b. Except as otherwise specifically provided in the Contract, all disputes concerning questions of fact arising
under the Contract shall be decided by the Architect, whose decision shall be final and conclusive upon the
parties thereto as to questions of fact.
c. The Architect’s decisions shall be final, if within the terms of the Contract
d. If however, the Architect fails to render a decision within fifteen days after the parties have presented their
evidence, either party may then demand arbitration. If the Architect renders a decision after arbitration
proceedings have been initiated, such decision may be entered as evidence but shall not disturb or interrupt
such proceedings except where such decision acceptable to the parties concerned.
33.05 ARBITRATION: All disputes, claims or questions subject to arbitration under this contract
shall be settled in accordance with the provisions of this article.
a. Notice of the demand for arbitration of a dispute shall be filled in writing with me other party to the
contract, and a copy filed with the Architect. The demand for arbitration shall be made within a reasonable
time after the dispute arisen; In no case however, shall the demand be made later than the time of the final
payment except as otherwise expressly stipulated in the contract.
b. When formal arbitration is requested, a Board of arbitration shall be formed in the following manner. The
Owner and the Contractor shall each appoint one member of his board and these members shall appoint a
third member who shall act as chairman. No one with a financial interest in the subject under arbitration will
be permitted to serve on this board. This Board may engage experts to act in an advisory capacity. Minutes
shall be kept off all meetings and signed by all members of the board. Decisions of the board shall require
only a simple majority and all interested parties shall be informed thereof. Expenses of the Board shall be
paid in accordance with the agreement set forth before the proceedings of the board.
c. It is mutually agreed that the decision of the arbitrators shall be a condition precedent to any right of legal
action that either party may have against the other. The Contractor shall not cause a delay of the work
during any arbitration proceedings, except by agreement within the Owner.
SECTION X
AUTHORITY OF ARCHITECT, ENGINEERS AND PROJECT REPRESENTATIVES
a. The Engineers shall be solely responsible for their respective designs, computations and other professional
services they rendered in connection with the preparation of Drawings and Specifications. They shall assist
the Architects in the general supervision and direction of the particular portion of the work where their
professional services are concerned.
b. The Engineers shall inspect the work for conformance with the approved Drawings and Specifications and
shall report to the Architect any discrepancy between such work and said Drawings and Specifications. They
shall make recommendations when necessary and as required consistent with the ethics of the profession.
c. The Engineers shall perform any professional service necessary for the accomplishment of the work subject
to the terms and conditions of the Inter-professional agreement between the Architect and the Engineers or
any existing contract affecting or relative to the project.
36.02 DUTIES: The duties of the Project Representatives, Resident Architects, Resident Engineers
and Construction Inspectors are stipulated in the Special Provision of the Contract.
36.03 DISPUTES: In case of any dispute arising between the Project Representative, Resident
Architect, Resident Engineer, or Construction Inspector, and the Contractor, they shall have
authority to reject materials or suspend the work until the question at issue can be referred to and
decide by the Architect.
Nothing in the provisions of this article will relieve the Contractor from the responsibility of
performing the work in accordance with the Drawings, Specifications and other Contract
Documents.
SECTION XI
SCHEDULE OF TIME LIMITS
The Contractor performs his work subject to certain Time limits. This is indexed section, as based on
the entire General Conditions, is provided for in order to facilitate the execution of his work.
1.CONTRACT TIME
1.1 Contract time Reckoning To commence on the 21.02
7th day from receipt of
notice to Proceed
1.2 Request for Time Extension To be filed within 15 21.04
days from occurrence of
delay (item a. par.1)
1.3 Beginning, Suspending or Resuming of Work Written notice to be 21.04
given to Architect at
least 10 days prior to
beginning, suspending
(except in case of
accident), or resuming
the work. (item f).
1.4 Other Related Matters
a. Request for supply of owner-furnished Materials Written request to be 21.04
made 10 days before
they are actually needed
(item a. Par.2).
b. Request for Drawings No claim for delay shall 21.04
be allowed on account
of failure to furnish
drawings until two
weeks after demand for
such drawings (item d.)
2. CONTRACT SUM
2.1 Contract Sum Breakdown To be submitted within 22.01
15 days from the receipt
of Notice to Proceed
2.2 Claim for Extra cost Notice to be given to 20.08
Architect within 15
days
If Contractor fails to
remove condemned
work within a
reasonable time from
notice, Owner may
remove and store the
same at Contractor’s
expense.
1) Declare bankruptcy,
become insolvent or
assign his assets for the
benefit of his creditors
2) Disregard or violate
provisions of the
Contract Documents or
Architect’s Instructions.
3) Fail to provide
superintendent,
workmen or sub-
contractors or proper
materials.
4) fail to make prompt
payment to sub-
contractors, workmen
or material dealers.
8. DISPUTIES If the Architect fails to 33.04
render a decision within
15 days after parties
have presented their
evidence, either party
may demand arbitration
(item d).
9.BONDS AND INSURANCES
9.1 Contractor’s Liability Insurance Insurance policy shall 31.01
not cancelled by
insurance company
without 10 days written
notice to Owner of
Intention to cancel.
9.2 Contractor’s Performance and payment Bond Such bonds shall 31.03
remain in effect until
replaced by the
Contractor’s Guarantee
Bond
9.3 Contractor’s Guarantee Bond To be furnished the 31.04
Owner after expiration
of Performance and
Payment Bonds and
shall be effective for a
period of one year
commencing from the
date of acceptance as a
guarantee that all
materials and
workmanship installed
are of good quality.
Posted 20th March 2014 by Unknown