SUNTRUST ASMARA - TOWER 2

DWAR MONITORING SUMMARY

MANPOWER ASEC
LEADMAN UME 22-Apr-19 23-Apr-19 24-Apr-19 25-Apr-19 26-Apr-19 27-Apr-19 APR 22-27 29-Apr-19 30-Apr-19 APR 22-30 APRIL UOM
QTY. STANDARD

ARCHITECTURAL GROUP ACTING FOREMAN - NONATO STEWART

STIFFENER R. MONTER l.m. - 12 lm / day

CHB LAYING T. BARTOLOME 15 sqm 9.18 10.14 18.18 18.06 13.74 15.36 14.11 - - - - 60 sqm / day

CHB LAYING/ RUBBED CONCRETE E. ABUNYAWAN sqm - - - - - - - - - - - 60 sqm / day

PLASTERING - SHOTCRETE A. PANGLAO sqm - - - - - - - - - - 80 sqm / day

PLASTERING - SHOTCRETE J. RICO sqm - - - - - - - - - - 80 sqm / day

RUBBED CONCRETE - INTERIOR R. FELICIANO sqm - - - - - - - - - - 120 sqm / day

RUBBED CONCRETE - INTERIOR E. ARGUELLES sqm - - - - - - - - - - 120 sqm / day

RUBBED CONCRETE - EXTERIOR E. TORRES sqm - - - - - - - - - - 120 sqm / day

LINEAR PLASTERING S. ALQUIN set - - - - - - - - - - 12 set / day


WOOD DOOR INSTALLATION (DOOR
M. CATALAN set - - - - - - - - - - 18 set / day
PANEL)
WOOD DOOR INSTALLATION (DOOR
M. CATALAN set - - - - - - - - - - 20 set / day
JAMB)
CONCRETE TOPPING J. MARIÑAS sqm - - - - - - - - - - 100 sqm / day

TILE WORKS M. EREDIANO sqm 36.45 33.93 - - - - 11.73 - - - 60 sqm / day

TILE WORKS M. CALAPATI sqm - - - - - - - - - - 60 sqm / day

TILE WORKS M. LARRON sqm - - - - - - - - - - 60 sqm / day