Mec Cost Estimation Methodology Report PDF
Mec Cost Estimation Methodology Report PDF
Mec Cost Estimation Methodology Report PDF
methodology
The Marine Energy Challenge approach to estimating
the cost of energy produced by marine energy systems
Neither the Carbon Trust nor Entec UK Ltd. nor their respective
directors, employees or affiliated companies give any
representation or warranty, express or implied, as to the accuracy,
completeness or fairness of the contents of the report, nor accept
any responsibility or liability for any loss, whether direct, indirect
or consequential, arising from reliance on it.
Any use of this report by any third party for whatever purpose is
solely the responsibility of that party who should use such due
diligence to verify the report's contents and consult its own
advisers as may be appropriate.
The Carbon Trust does not give investment advice and nothing in
this report constitutes, or should be taken as, a recommendation to
enter into, or the giving of any advice in relation to, any
investment.
This report may be copied and distributed only with the consent of
the Carbon Trust.
Contents
1. Introduction 1
1.1 Why is this report needed? 1
1.2 Marine Energy Challenge approach to cost of energy 1
2. Cost of energy 3
2.1 The cost of energy equation 3
2.2 The present value approach 3
3. Performance 6
3.1 Device characteristics 6
3.2 Resource 6
3.3 Losses 6
3.4 Availability 7
3.5 Annual energy production 8
4. Cost 10
4.1 Key factors affecting cost of energy 10
4.2 Capital costs 10
4.2.1 Structure costs 11
4.2.2 Mechanical and electrical costs 11
4.2.3 Mooring costs 13
4.2.4 Installation 13
4.2.5 Grid connection 14
4.2.6 Project management 14
4.3 Deployment location 14
4.4 Operating costs 15
4.4.1 Planned maintenance 15
4.4.2 Unplanned maintenance 15
5. Uncertainty in estimates 18
1. Introduction
• Shows some ways that costs can be estimated in the absence of accumulated
experience
• Provides a framework for collecting information on devices at different stages of
development
the fundamental operation of the design but might not describe the optimal configuration.
Nevertheless the design should be one that could actually be built (i.e. using certain materials
and known construction techniques), could be deployed (i.e. using certain vessels and moorings
or foundations) and will work (i.e. produce electricity reliably and survive the marine
environment).
During the Marine Energy Challenge, the first stage of evaluation was to define a baseline
design. The costs and performance were then determined and the baseline cost of energy
estimated. In some cases, this indicated that the costs were too high to justify the performance,
and subsequently ways were sought to either decrease the costs, improve the performance, or
both. An iterative design process followed during which different design possibilities were
explored and their potential benefits were quantified. This resulted in improved designs with
lower costs of energy and/or greater confidence that certain cost and performance levels could
be reached.
The cost of energy is a moving metric. As designs evolve the costs will change. Ultimately
developers need to reduce the cost of energy to as low a level as possible. In the meantime this
may mean trying slightly more expensive options that have greater long-term cost-reduction
potential. Whatever the approach, the cost of energy should always be kept under review and
any previous estimates and assumptions revised.
2. Cost of energy
Risk An investor who puts money into a project expects a return on the investment. If the investment is
risky then they expect a higher return. For a given level of risk the investor might set a minimum return
that they are willing to accept. This could be called their ‘hurdle’ rate.
Opportunity Investors often have several choices of where to place their money. For example an investor may
choose to leave their money in the bank. This would provide them with a modest return. If they place
their money elsewhere then they lose the ‘opportunity’ to make the return from the bank. An investor
would then compare other investments against the ‘opportunity’ that they would lose. In most cases
they would expect a greater return.
1
Further reading: Corporate Finance, Brealy, Myers, Allen, McGraw-Hill International Edition,
ISBN 0-07-111551-X
Discount rates can represent either the project return or risk. Different industries carry different
levels of risk and are often assigned different discount rates. We consider that the discount rate
for the first commercial marine energy schemes would be around 15% whilst 8% might be
applied to it when the technology matured and became established in the market.
This means that when we calculate the cost of energy using this present value approach we
incorporate the project return into the cost of energy. Thus a scheme that produces energy at a
cost of 5p/kWh at 8% discount rate might produce electricity at a cost of 6p/kWh at 15%2. This
is the same scheme working in the same way, but with two different interpretations of project
risk or investment return.
Alternatively, if this same scheme secured a power purchase contract and was paid 5p/kWh for
all the power it produced over its life then it would make a return of 8%, but if the contract paid
6p/kWh it might make a return of 15%.
2
These figures are purely to illustrate the point about sensitivity to rate of return. Details of the costs of
marine energy systems can be found in the Carbon Trust report ‘Future Marine Energy’.
The Marine Energy Challenge used a range of discount rates between 8-15%. These covered the
likely range of financing options for technically proven products first entering the market
through to well-proven products in wide deployment.
3. Performance
3.2 Resource
The available resource is then measured or estimated. At a tidal stream site the most important
measurements will be of tidal current velocity. For wave sites both wave height and period are
important. For both technologies the amount of time for which each sea condition occurs must
be estimated. An estimate of the annual energy output can be calculated by multiplying the
power output of a device in each sea condition to the annual occurrence of that condition.
The energy production will vary depending on the site and, in general, devices placed in more
energetic climates will produce more energy. However, if the devices are poorly matched to the
climate then the energy output could be lower. Alternatively, the benefits of additional income
from increased output may be offset by the cost of increasing the device strength to tolerate
more severe wave loads or increased maintenance requirements. Either case would result in a
higher cost of energy.
3.3 Losses
Once the theoretical energy output has been calculated some account is taken of the various
energy losses. The power curves and power surfaces include some account of inefficiency.
These include, for example, the conditions when the device is deliberately turned off when the
incident energy is too low. Other losses must also be accounted for; these include losses in the
electrical cable to shore, and lost energy due to an imperfect match between incident energy
direction and device orientation. Many of these losses can be accounted for by applying a
simple reduction factor to the energy generated by the device. For example if the cable losses
are assumed to be 2% then for every 100kWh supplied to the cable 98kWh are delivered to the
electricity grid on the shore, the remaining 2kWh is generally lost as heat to the sea. Many of
the losses of this kind apply equally to all levels of power produced and are often assumed
constant in the high-level cost of energy predictions used in the Marine Energy Challenge.
3.4 Availability
The availability of a device is a measure of the amount of time that it is running without fault.
This time does not include periods when the device is working but is not generating due to a
lack of waves or tides. Availability is a measure of the reliability of the device.
During the Marine Energy Challenge, several methods for calculating availability of marine
energy devices were considered. These used various combinations of the following—
the conditions were right. A more realistic availability level would be say 95%, when about 5%
of the time the system would be under repair or suffering a fault that stopped it generating.
A more sophisticated, and less conservative, measure of availability would consider the time
variation of energy production. This would mean that if all servicing could be undertaken at
times when the device would not be generating anyway, such as when there are no waves, the
availability could reach very high levels.
Figure 3.1 Simplified process for calculating the energy production of a marine energy project
5
8
3
5
7
5 2
Significant wave height [m]
3 3 5
6
5 5 2 5
3 8 2 5 3 3 5
5
3 5 5 3 10 2 3 2
3
8 10 5 5 5 10 5 5 5
4
7 8 3 5 2 5 5 3
6 15 8 18 7 10 3 3 2 5 5 2
3
10 13 35 22 28 15 17 2 5 5 5 3 5 3
10 13 22 20 25 30 12 12 8 8 7 2 5
2
2 18 15 30 20 13 10 12 15 8 5 2 3
3 3 7 10 15 15 22 22 15 8 7 2 5 3 2
1
3 2 5 3 8 10 12 10 10 3
3 2 2 3
0
4 5 6 7 8 9 10 11 12 13 14 15
Energy period [s]
Availability Efficiency
4 5
Some energy is lost in
Some energy generation is
transmission
lost when the device is
unavailable to generate
6
Electricity delivered to the grid
4. Cost
What affects the costs of marine renewables, and at what costs can electricity be generated
from waves and tidal streams today?
These questions were the starting point for our assessment of cost-competitiveness. This section
summarises the findings based on data gathered during the Marine Energy Challenge.
The cost of energy is an important parameter, but it is not a static one. As technologies develop
their cost of energy will alter. Some technological advances may reduce the overall cost of
energy, some may increase it. The aim is to produce an overall reduction over time. There can
be many routes to achieving this. Whichever is taken the cost of energy should be reviewed and
managed routinely. This means that technology developers and energy farm operators need to
revise their estimates often, as part of continual product development.
This section describes the approach taken in the Marine Energy Challenge to estimate these
costs. Figure 4.3a shows an example of a cost breakdown for a wave energy device.
Simple Complex
100-tonne 100-tonne
structure structure
The Marine Energy Challenge used engineering experience and a build-up of unit costs, as well
as quotes for the construction of the whole unit from experienced fabricators. Both approaches
are needed. The first is simpler and allows the trade-offs between cost and performance to be
made more readily and the second is suited better to refined designs.
The experience of the fabrication industry is essential to developing low-cost solutions. Often
the most expensive manufacturing operations can either be simplified or eliminated completely
without significant changes to the overall concept. The advice of experienced fabricators was
particularly useful in the refinement of the Marine Energy Challenge devices’ structural designs.
gearbox that increases shaft speed, and the electrical generator that converts the motion to
electrical power.
The mechanical and electrical costs are strongly device specific. These components are sized
mainly according to the peak power output of the device. Thus a gearbox is sized such that the
product of its rated torque and its rated rotation speed is roughly equal to the power of the
device. Likewise the product of rated generator current and the rated generator voltage is
roughly the rated power of the device.
Determining the optimum power level of the device is an iterative process. It is generally not
economic to install a power conversion system that can convert the highest levels of energy in
the sea. This is because these high levels do not often occur and thus the device would be
underutilised most of the time. Instead a compromise is made and the device is rated at less than
the highest power likely to be seen. Occasionally some of the energy is shed and not extracted
by the device.
The ratio of the mean power output to the peak power is known as the capacity factor3. A
capacity factor of 30% means that the generator will produce the energy equivalent to 30% of
that produced if it could run at full load. The device cannot run at full load all the time because
there is insufficient power in the sea.
Energy output[kWh]
Capacity factor[%] =
Energy available[kWh]
Annual energy output[kWh]
=
Rated power of device[kW ]× time in the year[h]
Equation 2
3
In conventional power systems the concept of the capacity factor is also applied. In this case it is
termed the load factor. The difference is that in renewable energy systems it is the fuel supply (e.g. the
waves or tides) that varies, whereas for conventional system the fuel supply is constant but the load
varies. The load varies as people turn lights and machines on and off.
cases, manufacturers of similar systems were contacted for advice. This advice included advice
on novel electrical systems, hydraulics, control systems and new materials.
4.2.4 Installation
The method of installation will depend on the nature of the device. The choice of vessels, for
example, will also change. Some devices can be towed to site using a tug and their anchors
placed using an anchor-handling vessel. Others might be carried on a heavy-lift vessel or a
barge. Piles and other structures might be positioned using stable platforms such as jack-up
barges that can float out to the site and then ‘jack’ themselves up out of the sea to form a
temporary platform.
The costs associated with deployment are usually estimated with vessel charter rates. These are
usually daily rates. The day rates for vessels change in response to the demand for the vessels.
During the Marine Energy Challenge (2004-2005) costs for anchor handlers increased several-
fold due to increased demand for their services in the oil and gas fields of the North Sea.
The Marine Energy Challenge used long-term average rather than spot rates for vessel costs.
This means that some prototypes may well incur dramatically lower costs, or indeed unfortunate
higher costs depending on their timing and their ability to negotiate good prices.
Marine energy systems though are slightly different to other offshore operations. Many marine
energy systems are designed to be deployed in large numbers. This means that some will need
longer vessel-hire periods and will ultimately be able to either negotiate lower day rates or
indeed justify procuring their own dedicated vessel. Many of these options were considered in
the Marine Energy Challenge.
Deployment costs are also strongly related to the location. The sea conditions, tidal ranges, etc.
will dictate the choice and thus the cost of the vessel. The distance to port will also affect the
transportation time and the duration of vessel charters.
Table 4.1 The influence of the deployment location on the cost of energy
Foundations and moorings Water depth, ground conditions, tidal streams, tidal ranges, energy density
Grid connection Distance to shore, ground conditions along any cable route
Installation Water depth, tidal streams, tidal ranges, distance to suitable port
The deployment location has a strong influence on the energy production and the costs of a
scheme. Thus suitable target locations for each device were decided early on in the Marine
Energy Challenge.
• Cost of servicing the vessel in terms of the time and personnel required
• The costs of spares kept in case of failure (for small schemes only small spares are
carried (e.g. a puncture-repair kit), but for larger farms maybe entire devices can be
kept as spare (e.g. a spare racing car)
• Cost of servicing the system in terms of the time and personnel required
Capital cost
Structure cost Material cost Cost per tonne, tonnes of material
Extreme loads
Mechanical and Rating of the machine (installed capacity) Peak power output, mean power output
electrical costs
Moorings Water depth
Tidal range
Tidal flow
Storm conditions
Compliance
Installation Type and availability of vessels required Vessel day rates
Distance to port
Time taken for installation
Time waiting on weather
Grid connection Power transmission level Cost per kilometre
Distance to shore
Project management Project management Proportion of the total capital cost
Insurance
Permissions
Operating cost
Planned maintenance Cost of replacement parts
Component design duty and known service
intervals
Time to complete service
Distance to port
Time waiting on weather
Unplanned Cost of replacement parts
maintenance Cost of spares
Time to complete service
Time waiting on weather
Cost of personnel and materiel standby
Figure 4.3 Cost breakdowns for an example wave energy device a) capital b) O&M
a) b)
Notes: Based on data gathered during the Marine Energy Challenge. The charts refer to specific types of
wave energy converter and are not representative or typical of wave energy technologies as a whole.
There are considerable variations between different technologies, project locations and project sizes
(numbers of machines installed). Also, future design improvements, performance/cost optimisations and
learning effects could change the relative weighting of some cost centres. The O&M chart shows annual
average costs evaluated over the entire life of a wave farm.
5. Uncertainty in estimates
Only when much experience has accumulated, both of developing and running marine energy
technologies, can good estimates of the cost of energy be made. Even then, estimates for
particular projects will still be uncertain. It is good practice when making any estimates to
estimate also the uncertainty in them. For example we might conclude that a particular item
might cost about £1000, but in reality could cost anything from £900 to £1200. We would say
that the £1000 middle estimate was our ‘best’ guess.
Some times we assign probabilities to these figures. For example we might conclude that there
is a 90% chance that the item above would cost less than £1200, but only a 10% chance that it
might cost less than £900. Sometimes we can work out these estimates using statistical
techniques, but often we have to make our own estimates of the uncertainties instead.
Whichever method is available, assigning a range with a nominal ‘confidence’ level provides
much more useful information.
Narrow confidence bands show more certainty in an estimate than wide ones. For example if we
were to estimate the cost of readily available raw material (e.g. steel) we might find it was in the
range £995-£1010, whereas a similar value of a less common material (e.g. silicon) might cost
£800-£1200. Both will cost the project around £1000, but we are surer of the steel costs than the
silicon costs.
Uncertainty information helps us identify which areas we need to investigate further, e.g. where
costs need to be calculated in more detail perhaps. It also shows where uncertainties will always
exist and where these need to be managed differently. For example the estimate of the long-term
energy output of a wave energy farm will always be uncertain because it depends on the weather
and the weather is extremely difficult to predict for the whole life of the project. This means that
project investors need to find other ways to deal with this uncertainty. One way is to treat it as a
project risk, in much the same way as they treat the ‘market’ risk of other products.
Combining estimates and their uncertainties can be difficult. If the estimates are calculated with
rigorous statistical techniques, then the best estimates and their uncertainties can be combined
statistically too. However, more often the estimates are not based on statistical observations and
additionally there are complex interactions and trade-offs between the different options. For
example, it is quite unlikely that all the costs (if estimated properly) will all be at their lower
end, neither is it likely that they will all be at their higher end. Thus adding all the low costs
together does not give a reasonable low overall cost.
Additionally, if one parameter reduces the cost of energy it might influence another to increase
it again. For example, if the wave resource turns out to be at the high end of the estimate, more
energy might be produced and the cost of energy lowered, but this might also cause an increase
in wear rates and thus more maintenance is required, hence raising the cost of energy again.
For very complicated systems models of the cost of energy can be constructed that allow for all
of these interactions. Once again, techniques such as Monte Carlo analyses can be used to
calculate both the best combined estimate and the uncertainty in that estimate.
It is good practice to make estimates of the uncertainty in all individual estimates as well as in
combined estimates.
B/15992/C001/065