Gas Pressure and Conditioning Skids PDF
Gas Pressure and Conditioning Skids PDF
Gas Pressure and Conditioning Skids PDF
A Thesis
Submitted to the Department of Petroleum & Mineral Resources Engineering
In partial fulfillment of the requirements for the degree of
MASTER OF PETROLEUM ENGINEERING.
by
ii
CANDIDATE’S DECLARATION
It is hereby declared that this project or any part of it has not been submitted elsewhere for
the award of any degree or diploma.
iii
RECOMMENDATION OF THE BOARD OF EXAMINERS
iv
DEDICATED
TO
MY
BELOVED
PARENTS
Invocation of who might be the sources for the blessings of Allah in completion of this study
v
ACKNOWLEDGEMENT
I would like to express my respect and gratefulness to Dr. Md. Ehsan, Professor Department
of Mechanical Engineering, for his valuable suggestions and advices during this project.
I would like to express my respect and gratefulness to Dr. Mohammad Tamim, Professor,
Department of Petroleum and Mineral Resources Engineering, for his valuable advices and
inspiration during this project.
I also express my gratitude to the faculty and staff of Petroleum and Mineral Resources
Engineering Department for their cooperation of this project work.
I would like to thanks Titas Gas T & D Co. Ltd. personnel Engr. Md. Golam Sarwar, Engr.
Rana Akbar Hyderi, Md. Rezaul Karim, Engr. Md. Alauddin, Engr. Md. Sumsuddin Al Azad,
Engr. Md. Nasimul Islam, Engr. Golam Faraque, Engr. Satyajit Ghosh, Engr Md.
Nazimuzzaman and Engr. Md. Siddiqur Rahman for their kind cooperation in providing
necessary data, documents and facilities regarding preparation of this report.
vi
ABSTRACT
In gas transmission and distribution system, the gas pressure and flow rate are controlled by
using CGS, TBS, DRS and RMS. It is important to supply uninterrupted gas at a desired
pressure and flow rate to the customer premises. The Regulating and Metering Station (RMS)
is generally used for controlling the gas pressure and measuring the gas volume for fiscal
purpose. It is apparent that proper design of RMS is very important for a customer for
supplying desired amount of gas at a required pressure as well as measuring the supplied gas
accurately which is very much crucial for gas supplier in fiscal context. A large number of
RMS’s are used for gas supply to different customers in the Titas franchise area.
The major objective of this project is to design an ideal gas Regulating and Metering Station
for uninterrupted gas supply to a 50 MW power plant. In this project work, fluid
characteristics, process data, gas safety rules, International codes and standards (ASTM,
ASME ANSI, API) have been followed for the proposed RMS design. Design considerations,
selection criteria and installation of RMS equipments are incorporated. Safety and
Environmental issues have been considered in designing the gas facilities for the power plant.
The negative effects on environment are negligible. The gas load of the power plant is
calculated around 12 MMSCFD at minimum outlet pressure of 50 psig. Design has been
checked allowing variation of some related variables such as inlet pressure, specific density,
specific heat, compressibility factor and heating value. Variation of these parameters needs
no change in the design. Instrumentation and piping diagrams of the proposed RMS are also
shown in the report. Some recommendations have been made for improvement of the RMS
design. Finally, cost estimation is performed for the project.
The cost estimation of the project have been calculated on the basis of preconstruction
expenditure, construction cost and material cost. The total cost of the project is estimated as
Tk. 494.463 Lakh.
vii
TABLE OF CONTENT
TITLE PAGE ------------------------------------------------------------------------- i
DECLARATION------------------------------------------------------------------------- iii
ACKNOWLEDGEMENT-------------------------------------------------------------- vi
ABSTRACT------------------------------------------------------------------------------ vii
CHAPTER 1: INTRODUCTION 1
2.1.1 Conditioning------------------------------------------------ 3
viii
2.2.7 Condensate Collection and Storage system ------------ 9
2.2.8 Gas Regulator----------------------------------------------- 9
2.2.9 Valve --------------------------------------------------------- 13
2.2.10 Gas Heating System ------------------------------------- 14
2.2.11 Gas Metering System ------------------------------------- 15
2.2.12 Auxiliary devices ----------------------------------------- 21
2.2.13 SCADA System ------------------------------------------ 26
3.5 Header-------------------------------------------------------------- 36
ix
3.9 Meter selection --------------------------------------------------- 48
3.9.1 Parameters for meter selection -------------------------- 48
3.9.2 Meter type selection procedure ------------------------- 49
3.9.3 Meter sizing ----------------------------------------------- 50
3.9.4 Meter run design ------------------------------------------ 51
3.9.5 Turbine meter installation -------------------------------- 52
3.9.5.1 Recommended for installation of meter ------ 52
3.10 Operational short coupling installation ---------------------- 54
3.11 Straightening vanes -------------------------------------------- 55
3.12 Strainers --------------------------------------------------------- 55
3.13 Over range protection ------------------------------------------ 56
3.14 By- pass --------------------------------------------------------- 57
3.14.1 Additional installation requirements ---------------- 57
3.15 Accessory installation ------------------------------------------ 57
3.16 Flow conditions ------------------------------------------------- 58
3.16.1 Velocity profile and swirl------------------------------ 58
3.16.2 Reynolds number -------------------------------------- 60
3.17 Orifice meter selection ----------------------------------------- 60
3.17.1 Installation requirements of orifice meter ---------- 61
3.17.2 Minimum upstream and downstream length-------- 61
x
5.4 Detail design calculation----------------------------------------- 68
5.4.1 Inlet pipe line section ------------------------------------ 68
5.4.2 RMS Inlet ------------------------------------------------- 68
5.4.3 Filtering system ------------------------------------------ 69
5.4.3.1 Filter separator connection size --------------- 69
5.4.3.2 Filter separator size calculation ----------------- 70
5.4.3.3 Liquid separator size calculation --------------- 73
5.4.4 Gas heating system --------------------------------------- 75
5.4.4.1 Heat requirement calculation ------------------- 75
5.4.4.2 Heat RMS ----------------------------------------- 76
5.4.5 Pressure regulating unit --------------------------------- 78
5.4.5.1 First stage pressure regulating unit ----------- 79
5.4.5.2 Second stage pressure regulating unit -------- 81
5.4.6 Metering unit ---------------------------------------------- 86
5.4.6.1 Turbine meter sizing ---------------------------- 87
5.4.7 Straightening vane ---------------------------------------- 87
xi
CHAPTER 7 : POSSIBLE VARIATION IN DESIGN 104
xii
APPENDIX 121
APPENDIX A: TERMINOLOGY ------------------------------------------------ 121
xiii
LIST OF TABLES
xiv
LIST OF FIGURES
xv
LIST OF ABBRIVIATIONS
AGA American Gas Association
API American Petroleum Institute
ANSI American National Standards Institute
ASTM American Society for Testing and Materials
ASME American Society of Mechanical Engineers
AFV Axial Flow Valve
BS British Standards
BTU British Thermal Unit
CSA Canadian Standard Association
CPP Captive Power Plant
DN Nominal Diameter
DCS Distributed Control Systems
DOE Department of Environment
ESD Emergency Shut Down
EVC Electronic Volume Corrector
ERW Electrical Resistance Welding
EIA Environmental Impact Assessment
FC Flow Computer
FPD Flame Photometric Detector
FID Flame ionization Detector
GC Gas Chromatograph
GSA Gas Sells Agreement
HART High Way Addressable Remote Transmitter
IGE Institution of Gas Engineers
ISA International Society of Automation
IEC International Electro technical Committee
ISO International Standards Organization
IPP Independent Power Producers
IJ Insulating Joint
JGTDSL Jalalabad Gas Transmission and Distribution System Ltd.
xvi
KOD Knock Out Drum
MSCFH Thousand Standard Cubic Feet per hour
MMSCF Million Standard Cubic Feet
MMSCM Million Standard Cubic Meter
MW Mega Watt
NDT Non-destructive Testing
NRV Non Return Valve
OIML Organization International De Metrology Legal
PSIA Pound Per Square Inch (Absolute)
PSIG Pound Per Square Inch (Gage)
P&I Piping and Instrumentation
PN Nominal Pressure
PLC Programmable Logic Controllers
PID Photo-Ionization Detector
RTU Remote Terminal Units
ROW Right of Way
SAR Submerged Arc Welding
SCADA Supervisory Control and Data Acquisition
SSV Slam Shut off Valve
SPP Small Power Plant
TGTDCL Titas Gas Transmission and Distribution Company Limited
TCD Thermal Conductivity Detector
CP Cathodic Protection
xvii
CHAPTER 1
INTRODUCTION
A network of transmission pipeline system transports natural gas from producing fields to
consumers. Gas transmission pipeline normally operates at high pressure of 1000/960/850/350
psig (GTCL, 2007). The customers usually do not use gas at such high pressures. It is
necessary to control the pressure and flow rate for supplying gas to a customer at desired
pressure and flow rate. In gas transmission and distribution network, the gas pressure and
flow rate are controlled at pressure reduction stations located at suitable places. There are
known as City Gate Station (CGS), Town Bordering Station (TBS), District Regulating
Station (DRS), Regulating and Metering Station (RMS). After reducing pressure through
these stations, gas is supplied to different bulk customers like Power and Fertilizer Producer
of Government Sector, Independent power producers (IPP), Small Power Plant (SPP), Captive
Power Plants (CPP) and Non bulk customers such as industrial, commercial and domestic
customers.
Regulating and Metering Station means a station comprising of Regulator, Meter and other
equipments necessary for the delivery of specification gas to a customer. Pressure Regulator
means all devices required to maintain a specified pressure at the outlet of the RMS under
variable gas flow conditions. Meter means all devices to be installed, operated and maintained
by the company for measuring, recording and computing the gas flow volumes delivered to
the customer.
This study aims to undertake and estimate of design an ideal Regulating and Metering Station
for gas supply to a 50 MW power plant in accordance with International codes and standards
(ASTM, ASME ANSI, API). The design will be carried out according to the fluid
characteristic and process data. Technical details of different equipments of the RMS will be
studied. The findings can then be incorporated in designing an improved RMS. Cost
estimation will be conducted for the proposed RMS design and construction for gas supply to
the said power plant.
1
A schematic diagram of pipeline network is shown in the following Figure-1.1
1.1 Objectives
The main objectives of this study are as follows
· Design of an ideal gas Regulating and Metering Station to supply conditioned gas
at a desired pressure as per requirement of the power plant.
· Cost estimation of the proposed RMS.
1.2 Methodology
2
CHAPTER 2
LITERATURE REVIEW
Regulating and Metering Station (RMS) means a station comprising of Regulator, Meter and
other equipments necessary for the delivery of specification gas to the customer. Pressure
Regulator means all devices required to maintain a specified pressure at the outlet of the RMS
under variable gas flow conditions. Meter means all devices to be installed, operated and
maintained by the company for measuring, recording and computing for fiscal purpose the gas
flow volumes delivered to the customer.
In this chapter, typical gas regulating and metering system, different types of RMS
equipments and their working principle, advantages and disadvantages will be discussed.
2.1.1 Conditioning
Natural gas quality has a strong effect on operation of the regulating and metering station and
measurement system. The gas should be pipeline quality gas. Gas conditioning is the
technique to remove surge of liquid, condensate, water and entrained solids from gas stream
by using separator and rising up the temperature of gas at a desired level to prevent hydrate
formation by using heater to prevent the damage of regulator and meter
2.1.2 Regulating
Regulating is the technique to control the flow of gas and maintain the system pressure and
flow with certain acceptable limit of a regulating station.
2.1.3 Metering
Gas metering is the technique to measure the gas volumes for transmission system, CGS,
TBS, DRS and RMS. The metering bank consists of meter runs according to AGA report for
the computation of the gas volume. Different types of meters are used for gas metering.
3
Fig 2.1: Typical Gas Metering and Regulating System
(Source : ZICOM Equipment Pvt. Ltd.)
4
(xiii) Temperature Gauge
(xiv) Chart recorder
(xv) Differential pressure transmitter
(xvi) Temperature transmitter
(xvii) Density and specific gravity transducer
(xviii) Gas Chromatograph
(xix) Flow Computer
(xx) Electronic Volume Corrector (EVC)
(xxi) Supervisory Control and Data Acquisition (SCADA) System
(xxii) Condensate tank
(xxiii) Weld-neck Flanges, Blind Flanges, Metallic and Asbestos Gaskets, Tees,
Elbows, End caps, Reducers, Saddle/weld-o-lets, Needle valves, Screwed gate
and ball valves, Socket welded fittings (Flange, Tee, Elbow, Reducer etc.),
Screwed Fittings, SS tubes, Compression Coupling and Stud Blots (As per
requirements), etc.
Partial view of a gas regulating and metering station is shown in Fig 2.2
5
Function of the equipments are described as follows
2.2.4 Headers
A header is a way to combine multi sources or multi-outlets into a single source or outlet.
Headers need to be designed to distribute the gas symmetrically. They are typically larger
sized pipe, tees, and caps. Headers are used when more than one regulator or meter run are
required. In sizing headers it is a rule of thumb that the cross sectional area of the header be
1.5 times larger than the sum of the inlet or outlet cross sectional area (which ever is larger).
6
2.2.6 Liquid Separation System
The liquid separation system is composed by two identical filtering lines to provide separation
of liquid condensate mist from gas down stream pressure reduction . Each of them is designed
for the maximum station flow rate, so that during the normal operation of the plant one filter
will be in service and the second will be stand-by. Each filter will be put in/ on of service only
manually operating through the inlet/outlet filter gear operated ball valves.
Types of Separators
Separators can be categorized into three basic types. These are vertical separator, horizontal
separator, and spherical separator.
The well stream is feed to the vertical separator tangentially through an inlet diverter that
causes the primary separation by three simultaneous actions on the stream – gravity settling,
centrifugation, and impingement of the fluids against the separator shell in a thin film. Figure
2.3 is depicting a vertical separator.
7
2.2.6.2 Horizontal Separators
Horizontal separators may be of a single-tube or a double-tube design. In the single-tube
horizontal separator, the well stream upon entering through the inlet strikes an angle baffle
and then the separator shell. The liquid drains into the liquid accumulation section, via hori-
zontal baffles as shown in Figure 2.4. These baffles act as sites for further release of any
dissolved gas. Gas flows horizontally in a horizontal separator.
8
2.2.7 Condensate Collection and Storage System
Water and liquid hydrocarbons coming from the filtering system and liquid separators will be
collected and stored in the condensate tank. The condensate storage tank will be manually
emptied with local control. It will be equipped with a safety valve to prevent any internal over
pressure and level indicator with a high level alarm in control room.
If the load flow decreases, the regulator flow must decrease also. Otherwise, the regulator
would put too much gas into the system and the pressure (P2) would tend to increase. On the
other hand, if the load flow increases, then the regulator flow must increase also in order to
keep P2 from decreasing due to a shortage of gas in the pressure system. If the regulator were
capable of instantaneously matching its flow to the load flow, then we would never have
major transient variation in the pressure (P2) as the load changes rapidly.
Regulator Types
9
2.2.8.1 Pressure reducing regulators
A pressure reducing regulator maintains a desired reduced outlet pressure while providing the
required fluid flow to satisfy a downstream demand. The pressure which the regulator
maintains is the outlet pressure setting (set point) of the regulator. Pressure reducing
regulators can be direct-operated or pilot-operated.
2. Pilot-operated
2.2.8.1.2 Pilot-operated
Pilot-operated regulators are preferred for high rates or where precise pressure control is
required. A popular type of pilot- operated system uses two-path control. In two-path
control, the main valve diaphragm responds quickly to downstream pressure changes,
causing an immediate correction in the main valve plug position. At the same time, the
pilot- diaphragm diverts some of the reduced inlet pressure to the other side of the main
valve diaphragm to control the final positioning of the main valve plug. Two-path control
results in fast response and accurate control.
10
Fig 2.5: Pilot-operated regulator
(Source: Fisher Controls, 2005)
· Regulator Pilots
· Set point
· Spring Action
Regulator Pilots
The major function of the pilot is to increase regulator sensitivity. If it can sense a change in
P2 and translate it into a larger change in P L, the regulator will be more responsive (sensitive)
to changes in demand.
Set point
Set point and many performance variables are determined by the pilot. It senses P2 directly
and will continue to make changes in PL on the main regulator until the system is in
equilibrium. The main regulator is the "muscle" of the system, and may be used to control
large flows and pressures.
11
Spring Action
Notice that the pilot uses a spring-open action as found in direct-operated regulators. The
main regulator, shown in Figure 1, uses a spring-close action. The spring, rather than loading
pressure, is used to achieve shutoff. Increasing PL from the pilot onto the main diaphragm
opens the main regulator.
Relief valve and backpressure regulators are the same devices. The name is determined by the
application.
12
A backpressure regulator maintains a desired upstream pressure by varying the flow in
response to change in upstream pressure.
2.2.9 Valve
A valve is a device that regulates the flow of a fluid (gases, liquids, fluidized solids, or
slurries) by opening, closing, or partially obstructing various passageways. Valves are
technically pipe fittings, but are usually discussed as a separate category. In an open valve,
fluid flows in a direction from higher pressure to lower pressure.
Valves are used in oil and gas, power generation, mining, water reticulation, sewerage and
chemical manufacturing.
Valves may be operated manually, either by a hand wheel, lever or pedal. Valves may also be
automatic, driven by changes in pressure, temperature, or flow. These changes may act upon a
diaphragm or a piston which in turn activates the valve, examples of this type of valve found
commonly are safety valves fitted to hot water systems or boilers.
Gate valves are generally used in systems where low flow resistance for a fully open valve is
desired and there is no need to throttle the flow. Globe valves are used in systems where
good throttling characteristics and low seat leakage are desired and a relatively high
head loss in an open valve is acceptable. Ball valves allow quick, quarter turn on-off
operation and have poor throttling characteristics. Plug valves are often used to direct flow
13
between several different ports through use of a single valve. Diaphragm valves and pinch
valves are used in systems where it is desirable for the entire operating mechanism to be
completely isolated from the fluid. Butterfly valves provide significant advantages over other
valve designs in weight, space, and cost for large valve applications. Check valves
automatically open to allow flow in one direction and seat to prevent flow in the reverse
direction. A stop check valve is a combination of a lift check valve and a globe valve and
incorporates the characteristics of both. Safety/relief valves are used to provide automatic
over pressurization protection for a system.
There are several types of heaters which may be used in regulating and metering station.
Water bath heater, Heat exchangers and electric heater may be used depending on the station
capacity and design.
14
Heat exchangers are used to increase the temperature (above the dew point) of natural gas.
Their performance is based on the heat exchanger between water (or steam) and the gas to be
treated. Heat exchangers are designed to be suitable for an easy inspection and cleaning of all
the parts.
In RMS the metering bank consists of one metes runs design accordance to AGA report no.3
for the computation, of the gas volume flow delivered. Different types of meters are used for
gas metering which describes as follows :
· Positive displacement - Diaphragm meter ,Rotary meter & Turbine meter
· Differential pressure measurement – Orifice, Venturi and nozzle meter
· Ultrasonic flow meter - Doppler flow meter
· Fluid oscillatory – Vortex meter, Swirl meter
· Electro magnetic flow meter – Magnetic flow meter
· Direct mass – Coriolis mass flow meter.
· Thermal - Thermal profile flow meter.
15
Positive displacement meter measures gas volume passing through it by repeatedly filling
and discharging one or more chambers in sequence. Each chamber’s volume is known &
the operating cycles are counted to get the volume passed. Meters incorporating the
positive displacement principle of measurement are of the diaphragm and rotary type
Meter.
a) Diaphragm Meter
In diaphragm meters there are two chambers alternately fill and empty, with slide values
at the top of the meters controlling the flow to the chambers. The gas volume is obtained
through a mechanical linkage mechanism, which connects the diaphragm motion to the
mechanical readout system, where the number of displacements is counted.
b) Rotary Meter
This type of meter contains two oppositely rotating impellers, which are the measuring
mechanism. The volume of gas is directly related to the number of revolutions of one of
the impeller shafts. The rotary meter’s capacity rating is much greater than the diaphragm
meter. Rotary meters are available in ranges of 800 to 102,000 CFH. It can be used in high
pressure applications with up to an ANSI 600 rating available. These meters are compact
and reliable, however since the operation depends on maintaining proper clearance
between the impellers and the case, they can be susceptible to stress and if a malfunction
occurs, then the gas flow could be stopped. The rotary meter is limited at high pressure.
Therefore this meter although an excellent performance is not regarded as appropriate for
large capacity, high pressure metering of natural gas.
C) Turbine Meters
16
The turbine meter is classified as a rotary inferential meter. These flow meters are used
successfully in both liquid and gas measurement. Turbine meters are velocity sensing
meters with the volume of fluid being derived from the rotations of the turbine rotor. The
speed of this rotor is proportional to flow rate. Turbine meters has been established as a
means of measuring fluid for nearly 80 years. Since the 1950s, they have been considered
favorably for the measurement of large volume gas flows. The designs have proved
receivable, accurate and repeatable. As well as being used as the primary measurement
standard, axial flow gas turbine meters are increasingly being used as calibration and
reference meters.
The turbine meter (Figure-2.6) has wide range ability (to 200:1 depending on meter
size and line pressure), greater accuracy potential and more versatility in adding
mechanical and electronic auxiliary devices. Like an orifice meter, a turbine meter
does not impede flow if there is damage or failure. This is important when maintaining
gas service to a downstream consumer is critical.
17
2) The pulsed output frequency of the pick-up is proportional to angular velocity of
the rotor.
The axial flow gas turbine meter comprised of three main components:
a) The body through which the gas passes.
b) A rotor with bearings and supporting structure.
c) A device to transfer the internal revolutions of the rotor to an external counter.
Gas flowing through the meter impinges on turbine blades located centrally along the axis of
the unit. Turbine blades are free to rotate, and do so in a manner directly proportional to the
velocity of the gas passing the blades.
The area of the rotor face as defined by the mean radius of the rotor can be determined.
Permanent magnets installed in the hub of the rotor, turn with the rotor to produce a magnetic
field, which passes through a coil. As each of the magnets pass the coil a separate and distinct
voltage pulse is created. The frequency of these pulses is proportional to the velocity of the
rotor is also proportional to the flow rate. Each pulse is also proportional to a small unit of
volume. The pulses, the effective flow rate and total flow are transmitted by frequency and by
counting the pulses. The output frequency has been conditioned into a square wave through a
preamplifier. This conditioning allows it to be transferred to a remote flow computer. Each
pulse represents only a small incremental volume of flow. Since the turbine meter measures
volume at line conditions, the gas laws can be applied to change the register volume to base
conditions.
2) Inferential Meters
Orifice and turbine meters operate on the inferential measurement principle. Here the flow
rate is found by inferring from other measured variables.
a) Orifice Meters
Orifice Metering is the most common form of gas metering used throughout the world for the
accounting of large volumes of natural gas. It is also used for the measurement of liquids.
18
Based on the differential pressure method, the rate of flow is computed on the basis of long
established physical principles. The common equation used for determining the total flow
volume being based on the current AGA or ISO Standard.
The orifice plate meter is classified as a differential pressure (dp) meter. There are a number
of types of flow meters, with different shapes and sizes, which fit into this category of
inferring flow rate from the pressure drop across a restriction. An Orifice plate flow meter
system consists of three discrete components the meter tube, the orifice assembly, and the
differential pressure gauge. The meter tube and orifice assembly are considered to be the
primary element and the differential pressure gauge, pressure and temperature gauge or
recorder are being referred to as secondary element.
Orifice meters must be designed, fabricated and installed according to AGA Report no 3
(ANSI/API 2530). When designing an orifice meter run, differential pressure should range
between 10” and 90” of water column for a 100” chart and 20” and 180” of water column for
a 200” chart. This avoids large measurement errors at low differential pressures and
overhanging the chart. Although AGA Report no 3 does not specify upper or lower
differential pressure limits, industry standard is 10” to 200” of water column. If the
differential pressure falls below 10” of water column, it does not stabilize and measurement
errors result.
19
The orifice plate meter is classified as a differential pressure (dp) meter. There are a number
of types of flow meters, with different shapes and sizes, which fit into this category of
inferring flow rate from the pressure drop across a restriction. An orifice plate flow meter
system consists of two basic elements, namely the primary flow element, which is the orifice
plate, and secondary elements which include the differential pressure transmitter, or
differential pressure indicating device such as a manometer, and the associated pipe work and
valves. The orifice plate meter relies on the principle of when a fluid is flowing a closed
medium (a pipe) and encounters a restriction, a pressure drop is developed. This pressure drop
is related to the flow rate of the fluid. By measuring the differential pressure across the orifice
plate (upstream and downstream of the plate) and the condition at which the orifice is being
used, then this pressure differential can be translated into a volume flow rate according to a
formula. Accurate measurement is definitely possible with this type of flow meter, if
malfunctions occur the flow of gas will not be stopped. Orifice meters are not limited by high
pressure or high flow so they can therefore be considered for high flow, high pressure gas
metering. Naturally the correct selection of orifice plate type is important.
The rangeability of a single orifice meter is about 3:1, by adding further orifice meter runs in
parallel, this rangeability increases by the square. That is, a dual run meter station would have
a theoretical rangeabilitiy of approximately 9:1. Rangeability is the term used with meters to
express the flow range over which a meter operates whilst continuing to meet a given
accuracy tolerance. The rangeability can also be expressed as ‘turndown’, which is a ratio of
the maximum flow divided by the minimum flow, again over a given accuracy tolerance.
Ultrasonic Meters
Ultrasonic meters, as custody transfer devices, are relatively new to the gas industry. A.G.A.
Report no-9 refers to the industry accepted standard for installation of an ultrasonic meter.
Report no- 9 is vague compared to Report no-3. It leaves a lot of the design and installation
up to the manufacture of the ultrasonic. This is due to the fact that there is not a good
understanding of installation effects of Ultrasonic's yet. Choosing the appropriate meter, out
of all the meters available, a designer must choose a meter to fit the need of the station. First
look at the flow rates and pressures and decide what type of meter would best fit for the
application. Positive displacement meters are usually used for low flow applications. Orifice
20
and ultrasonic meters are usually considered for large flow applications. After choosing a
meter the regulators may be sized.
Because they are microprocessor based, they are more versatile (perform more tasks)
and flexible (in date retrieval, manipulation and transmission) than mechanical
devices. They are also less subject to accuracy loss due to vibration, wear and other
mechanical failures. Features include:
· pressure and temperature correction
· calculated super compressibility factor using fixed gas quality values
· various volume outputs: uncorrected, corrected, totals
· imperial or metric unit choice
· built-in alarms indicating battery condition, pressure and temperature over under
ranges, etc.
· telemetry capability (with data transmission devices added)
EVCs are mounted above the meter's output drive shaft. They conserve battery power by
remaining dormant between flow calculations, which are only performed on every
complete revolution of this shaft. They are used on diaphragm, rotary and most turbine
meters.
2) Flow Computers :
A flow computer has more program options than an EVC. Features include those listed
for EVC's with the following:
· Calculated super compressibility factor using full gas composition data (if available)
21
· Wide variety of alarm settings
· Most are not approved for use in hazardous areas
· Continuously calculated flow using AGA Report no3 or 7 equations
· Reprogrammable for other applications
· Performs some logic functions
· Calculated flows for several meter runs simultaneously
· Differential pressure (in mA) or pulse input accepted
· Pulse output for an odorant injection system.
An orifice meter requires a flow computer with a differential pressure input. The unit
usually used in this case is approved for use in a Class 1, Division 1, Group D hazardous
area. All other flow computers can not be used in hazardous areas, so must be installed in
a site control building.
3) Chart Recorder
Chart recorder is standard for accurate, reliable measurement and recording of pressure,
differential pressure and temperature in a wide variety of applications.
Although very significant advances have been made in the direct processing of flow
measurement data by means of microprocessor based equipment, a need still exists for the
chart recorder because it is reliable. The use of the direct reading chart has the advantage
that the measurement being recorded can be read at a glance. Some organizations retire
charts as a permanent record for accounting purposes. The recording and calculation
process is the final consideration for obtaining accurate flow measurement. In the
evaluation of equipment, one significant factor tends to be overlooked in the selection
process – that of the skill and training of operators. The proper operation of complex data
processing equipment in many cases gets down to the skill.
Chart recorders are simple and fairly robust and therefore do not require highly skilled
operators or expensive diagnostic equipment, however malfunctions can occur if they are
not serviced properly or incorrect charts are used. Cost wise, the chart recorder can be an
22
attractive option. When a back correction is required or a prior event needs investigation,
a chart recording can be invaluable.
By using the concept of Bellows, Bourdon tube and thermos well mechanical recorder are
produced by the manufacturer of different ranges and sizes, which are used to measure the
differential pressure, static pressure of gas with circular chart. The accuracy of their
device is
Chart recorders are mainly two types one type is VPT recorder and another is flow
recorders for orifice meters.
4) Flow Recorders
The flow recorders are a differential flow recorder for orifice meters. They are used as the
primary record of flow through an orifice meter. The chart records static pressure,
pressure differential and flowing temperature. Chart drives are available to turn the charts
faster or slower, but in most installations 24 hour or 7 day charts are used.
Flow recorders are no longer used for backup in new installations because EVC's have
proven reliable and contain their own internal backup. Technical services, measurement
and electronics' standard is Graphic Controls disposable pens for all recorders.
5) Pressure Gauge
There are a number of devices and instruments available for the measurement of
pressure. The simplest pressure-measuring device is the pressure gauge, and the most
23
common of all the pressure gauges utilizes the ‘Bourdon tube’.[The principle of
operation of Bourdon tube, which is a thin metallic tube closed at one end, is that when
pressure is applied to the tube internally the tube will tend to straighten out from its
normal cylindrical form. The sealed top of the tube moves linearly with the applied
internal pressure, therefore this movement can be translated to a scale. When the
pressure is removed the tube will return to its normal state. Care must be taken not to
over range a Bourdon tube type pressure gauge otherwise damage through distortion of
the tube may occur]. An accuracy of about ± 1% should be available for at least the
upper range value of a good Bourdon tube type pressure gauge. These are some master
pressure gauge with an accuracy of ± 0.25%.Pressure gauges also adopt bellows as the
means of translating the pressure into a visual scale.
6) Temperature measurement
Two scales tend to be more commonly used these being the Celsius and the Fahrenheit
scales. For the international system of units (SI), the Kelvin (K) is the unit used and for
F. P. S. system it is Rankine (R). Among the process variables temperature is very
difficult to control. Temperature must be measured without any interference. This can
be achieved by a number of ways ad includes expansion and contraction of liquids and
metals. Changes in electrical resistance, change in intensity of emitted radiation and
changes in volume or pressure of gas the most common temperature measurement
devices are:
24
Selection of the best sensor for a given application can be a function of temperature range,
sensitivity, response time, initial cost, maintenance, accuracy, reliability and power
requirements. Overall control requirements are also important. This can lead to the
selection of a mechanically or pneumatically transmitted system, giving freedom from
external power sources and simple maintenance requirements. On the other hand higher
accuracy and sensitivity and multi sensing ability may make the electronic system more
attractive. Temperature measurement and its conversion have a strong effect on
measurement. Incorrectly measured temperature value can alter the actual flow quantity.
Now we can discuss some of the potential error of temperature measurement.
7) Density measurement
Measurement of density is necessary not only for mass flow measurement system but also
for a computerized volumetric flow measurement system.
The traditional methods for density measurement are to measure the mass of a fixed
volume of fluid or the volume of a fixed mass. This usually involves taking a sample of
the fluid from the process vessel or a pipeline to a laboratory for weighing. Although this
method can produce accurate results, it is impractical for most process and pipeline
applications. Due to the requirement for an in-site measurement device, the densitometer
was developed. Densitometer sometimes shows higher value than the actual due to
condensation of gas in the device. This may alter the value of actual gas used. So it has a
strong effect on system loss.
25
From a SCADA terminal authorized users can
· Open and closed valves
· Monitor the flow, pressure and chemical composition of the gas
· View current conditions in the system
· View and print detailed information about the operation of the system and the data
received by the system
26
CHAPTER 3
Sustained safety, accuracy and control are the primary considerations in the design of
regulating and metering station. Many factors must be considered and assembled into
specifications and drawings to ensure safety and to provide accuracy, accessibility and work
space for operations. These factors can be combined into a piping structure with adequate
foundation and a partial or complete shelter arranged to fit the site. The station should be
designed with predicted load changes considered and to require a minimum of piping
alteration with unpredicted load change. Most regulating and metering stations are likely to be
in service for a long time.
After considering the safety, purpose and cost of a high pressure measuring and regulation
station one can follow a few steps in selection of basic components to design a reliable,
accurate, safe and cost efficient station. There are a variety of sources available for
information details on all the components of a high pressure measuring and regulation station,
including A.G.A. Report no-3, A.G.A. Report no-7, Bangladesh natural gas safety
rules,1991(Amendment 2003), National Regulations, company policy and manufacturer's
literature. Also consulting with the field operations personnel for ideas during the design will
help give practical perspective to the design of a station.
In this chapter, the basic design considerations and procedures in designing a regulation and
measuring station will be discussed. The equipment selection criteria are also elaborated here.
27
· In order to ensure supply continuously, alternate system must be taken for emergency
and scheduled maintenance of important equipment (By pass system)
· Provision of filter separator to protect valuable and sensitive regulators and meters
from dirt and condensate
· Provision of slam shut valve to protect down stream station from unexpected high
pressure
· Provision of emergency shut down (ESD) valve to isolate main station from
transmission network in case of any emergency situation
· Provision of heater to prevent the possibility of gas freezing due to the pressure drop
during the reducing step and low atmospheric temperature
· Use of silencer to reduce the noise level due to gas de-pressurization
· Meter selection
· Control device selection
· The requirements for maintenance
· Establish sophistical Flow computer/Supervisory Control and Data Acquisition
(SCADA) System
Safety, cost, site location, constructability, operation and maintenance, environmental impact,
government regulations. All of these will impact the design parameters.
28
3.2.1 Recommended Minimum Requirements
The overall design of Regulating and Metering Station (RMS) should comply as a minimum
requirement as per Institution of Gas Engineer’s recommendation IGE TD-9.
· Two or more high-pressure inlet filters with suitable valving and connections to permit
design throughput to be maintained with one unit out of action. Means to avoid the
entertainment of liquids in the gas entering a regulator assembly and, if necessary
suitable provision made for their removal. It is particularly important that the gas supply
to regulator control instruments should be fee of liquids and dust and suitable filters or
filter/separators should be installed as appropriate.
· Two or more streams of pressure regulators each stream to contain at least two
regulators, so impulse that if any one fails, the remainder will maintain safe conditions.
Where the installation is not a major supply or is reinforcement off take, consideration
may be given to the provision of a single stream of regulators only. Upstream slam–shut
valves should be fitted on all streams of regulators. This requirement for the provision of
slam-shut valves may be waived at the discretion of a responsible engineer in the case of
very small installations where the potential gas release via a relief valve can be allowed.
29
· It is necessary to consider whether or not preheating of the gas is required to avoid
unacceptable low temperature in the down stream pipe work and auxiliary systems
following pressure reduction. If heater is installed then they should be controlled in such
a way as to avoid high gas temperatures, which can damage any seals, diaphragms or
valve seats in equipment such as regulators, meters, relief valves etc.
3.3.1 Volume
The gas volume passing through a station is a very important factor to design a regulating and
metering station.
The design should be based on peak load requirements and not the daily average. regulating
and metering station. The peak load conditions must be considered in sizing meters and
regulators. Peak loads will be different from average volumes determined by the average daily
load.
30
3.3.2.2 Outlet pressure
The outlet pressure of a regulating station will be set by operational requirements. Metering
station without regulating equipment will have an outlet pressure rating equal to the inlet
pressure. The regulating station specifications should indicate the quality of outlet pressure
control required and the minimum and maximum outlet pressure acceptable to the system.
The amount of pressure reduction is a major indication of whether a single stage pressure
regulator will be satisfactory or if multiple stage reduction is required.
31
3.3.6 Site condition
The characteristics of the station site or proposed area should be considered to determine the
type of external station design. A regulating station creating noise levels of greater than 85 db
will not be tolerated in a populated area, while the same station in a rural area may be
satisfactory. If population growth is in the direction of the site, then this should be considered
early in the design because it will have an influence on what protective measures must be
taken to make the station satisfactory over a long period of time. Prior to design, in addition to
becoming familiar with local in ordinances and regulating concerning site improvements,
consideration should be given to flooding ease of access to the site during adverse weather
and outlet lines crossing roadways and presenting frost-heaving problems. These and many
other details should be considered when gathering facts to prepare the station design.
Where,
V = Limiting velocity of gas, feet per second
Q = Maximum flow rate, cfh
P = Minimum operating pressure, psia
D = Internal diameter, inches
32
Where,
Qmmscfd = Flow rate, MMSCFD
P1 = Up stream pressure, PSIA
P2 = Down stream pressure, PSIA
d = Inside diameter of pipe, Inches
L = Length of pipeline, Miles
Using Barlow’s Formula one can determine the size and strength of pipe needed for the
station.
33
Where,
F - above ground pipe = 0.5 or 0.4
E - seamless or electric resistance welded pipe =1
T - temperatures between 20 °F and 250 °F = 1
34
Table 3.2 :Value for joint factor (E)
Weld type ASME B31.8
Seamless 1
ERW 1
SAR 1
Butt Welded 0.6
Spiral seam welded 0.8
(ERW= Electrical Resistance Welding, SAR = Submerged Arc Welding)
The effect of the Location factor is to increase pipe wall thickness for a given size and grade
of pipe as the construction area becomes more populated and the failure of a pipeline would
be more serious.
35
Table 3.4:Temperature de rating factor (T)
Temperature ( 0F) Value as per ASME B31.8
Up to 250 1.00
251-300 0.97
301-400 0.93
401-450 0.91
451 and above 0.87
3.5 Headers
A header is a way to combine multi sources or multi-outlets into a single source or outlet.
Headers need to be designed to distribute the gas symmetrically. They are typically larger
sized pipe, tees, and caps. Headers are used when more than one regulator or meter run are
required. In sizing headers it is a rule of thumb that the cross sectional area of the header be
1.5 times larger than the sum of the inlet or outlet cross sectional area (which ever is larger).
36
3.6 Filtering system
The vessel of filters separator will be designed and manufactured in accordance with ASME
section-8, Division1 and welding the vessel with AP1-1104 Code. The followings are
important matter in order to design filter separator:
1. Permissible particle size (5 micron is allowable)
2. Filtering efficiency
3. Pressure should not be reduce with filtering operation.
To perform efficiently, a well designed separator should meet the following criteria –
· Control and dissipate the energy of the well stream as it enters the separator, and
provide low enough gas and liquid velocities for proper gravity segregation and vapor-
liquid equilibrium. For this purpose, a tangential inlet to impart centrifugal motion to
the entering fluids is generally used.
· Remove the bulk of the liquid from the gas in the primary separation section. It is
desirable to quickly achieve good separation at this stage.
· Have a large settling section, of sufficient volume to refine the primary separation by
removing any entrained liquid from the gas, and handle any slugs of liquid (usually
37
known as “liquid surges”).
· Minimize turbulence in the gas section of the separator to ensure proper settling.
· Have a mist extractor (or eliminator) near the gas outlet to capture and coalesce the
smaller liquid particles that could not be removed by gravity settling.
· Have proper control devices for controlling the back-pressure and the liquid level in
the separator.
· Provide reliable equipment for ensuring safe and efficient operations. This includes
pressure gauges, thermometer, liquid level indicator, safety valve etc.
38
The gas capacity at the operation conditions rg, in ft3/sec is given below:
rg = Avg = (пD2/4) Kl [(rl - rg)/rg] 0.5 -----------------------------------------------(3.6)
Where,
A = cross sectional area of the separator, ft2
D = internal diameter of the vessel, ft
Here the gas velocity, vg is based upon the total separator area and it is therefore more
appropriate to refer to it as the superficial gas velocity. The gas capacity at standard condition
(14.73 psia and 60 0F), generally reported in units of MMSCFD is thus given by:
qgas = 2.40D2 Kl [p/Z(T+460)][(rl - rg)/rg] 0.5 --------------------------------------(3.7)
Where,
qgas = Gas capacity at the operation conditions, MMSCFD
p = Operating pressure, PSIA
T = Operating temperature, 0F
Z = Gas compressibility factor at the operation conditions.
Above two Equation can be used to calculate the separator diameter required to handle a
given gas rate or to calculate the gas rate that a separator of a given size can to handle.
39
The liquid setting volume, VL can be used to calculate as follows:
VL = 0.1399D2h for vertical separators
VL = 0.1399D2 (L/2) for horizontal single tube separators
VL = 0.1399D2 L for horizontal double tube separators
VL = 0.0466D3 (D/2) 0.5 for spherical separators
Where, h = height of liquid column above the bottom of the liquid outlet in the vertical
separators, ft
L = separator length (height), ft
For good separators, a sufficient retention time, t must provide. From field experience, the
following liquid retention times have been suggested (Kumar,1987).
Oil-gas separation : 1 min.
High pressure oil water gas separation : 2 to 5 min.
Low pressure oil water gas separation : 5 to 10 min. at > 100 0F
10 to 15 min. at > 90 0F
15 to 20 min. at > 80 0F
20 to 25 min. at > 70 0F
25 to 30 min. at > 60 0F
40
3.7 Regulators
The regulator is a component of the system and therefore its selection and installation should
be based on the system requirements. After these have been selected the designer must then
determine how many pressure cuts are needed to meet the design requirements. Due to large
pressure drops across the station there may be a need for multiple pressure cuts to eliminate
freezing and maintenance problems. The making of multiple pressure cuts will reduce or
eliminate noise caused by large pressure drops across a control valve. Another way to
eliminate noise is to increase the wall thickness of the piping. Next, a regulator or control
valve should only be sized for 75% of its capacity at the maximum volume and minimum
inlet pressure of the station. Properly sizing the regulator is essential to the design of the
station in order to reduce maintenance cost and operational problems.
It is recommended that regulators be installed with 5 pipe diameters upstream and 8 pipe
diameters downstream. This will allow time for the control valve or regulator to sense and
react to a change in the process.
• Maximum volumes
• Site location
• Operation and Maintenance
• Environmental impact
• Safety
The first step in selecting a regulator is to know what type of control is desired
• Volume
• Pressure
The second step is to determine what type of regulator is needed
• Spring operated
• Pilot operated
• Controller operated
In the RMS both axial flow valve (AFV) and on line maintenance type regulators are used .
41
3.7.1 Regulators installed
It is recommended that regulators be installed with 5 pipe diameters upstream and 8 pipe
diameters downstream (AGA Report 7). This will allow time for the regulator to sense and
react to a change in the process.
42
3.7.2 Inlet and outlet connections
The piping to and from regulator should be supported adequately to minimize pipe strains.
The piping should be designed to have adequate capacity for the expected maximum flow and
the pressure conditions. Velocities in regulator valve passages can reach sonic velocity
conditions. High velocities create noise so piping should be sized to keep gas velocities at a
reasonable level. There are specific pipeline velocity limits used by many companies to
maintain a relatively quiet pipeline system and to keep pressure losses low. Such limiting
velocities range between 50 feet per second to a maximum of approximately 400 feet per
second. There are situations where higher velocities may be required for short distances;
however, the designer should calculate the pipe velocities to be encountered and determine
the steps that may be necessary to maintain satisfactory noise levels.
Two Equations are used for sizing regulator all over the world :
1.Universal gas sizing Equation and
2. ISA gas sizing equation.
ISA gas sizing equation is more precisely used for pressure control valve. But Universal
gas sizing Equation is popular in natural gas industries. This Equation is described as follows:
43
Where,
Q= Flow rate (SCFH)
Cg = Gas sizing co-efficient
P1 = Inlet Pressure (Psia)
P2 = Outlet Pressure (Psia)
C1 = Cg/Cv = Valve recovery co-efficient
G = Specific gravity
T = Temperature, 0 Rankine (460+F0)
In order to choose the best type of regulator for a particular application it is need to know the
outlet pressure (delivery pressure) and Cg value. The following Table 3.6 is used for
conversion of Cg value to regulator size. Then refer to the regulator selection chart
(Fig. 3.1) to determine the type of regulator that is best for the application.
44
600
500
400
200 Pilot Operated regulator shaded area
Pressure (psig)
100
Self Operated
Farm Tap Self Operated
roll out diaphragm type
45
1 14.3 28.2 42.3 132 249 484
The following steps are required to size and select a pilot operated regulator
· Calculate the Cg required form the service conditions. Adding 20-25 % with Cg
value to ensure good performance.
46
· Dividing the Cg value by 0.70 or multiplying by 1.43 to determine the size of
monitor and active regulator. Because when two regulators are used in series their
capacity is approximately 70% of a single regulator of the same size.
· Select a body class rating for the inlet pressure requirements.
· Select a body size based on published Cg values or sizing tables.
· Select a pilot pressure range for the outlet pressure desired.
47
Dt1= Joule-Thomson effect = (Pi – Po) 0.5 in K
Dt2 = temperature different between minimum gas inlet temperature and
temperature required after gas pressure reduction in K
rn = Specific density of natural gas, kg/m3
Cp = Specific heat of natural gas, kJ/kg
Pi = Inlet pressure of natural gas, bar
Po= Outlet pressure of natural gas, bar
On the basis of the heat required to rise up the temperature of gas a suitable capacity heater is
designed. The vessel size of heater will be design in accordance with ASME section 8,
Devission-1.
48
· The extremes of pressure and temperature at measurement conditions.
· The consequences of the gas flow being stopped by meter malfunction.
· Duration of operation of the meter. (continually or intermittently).
· The economic consequence of uncertainties in the measurement.
· Available for the installation of such meters.
· Legal metrology requirement – Approval of legal metrology (OIML – Organization
international metrology de legal).
· Cost effectiveness.
49
Meter sizing has a strong effect on system loss. If meter sizing is not appropriate such under
or over size then it cannot measure properly. In this context turn down ratio is very important.
It is the ratio of the maximum to minimum volume of gas that can be measured properly and
safely with desired accuracy. Meter should be sized so that it can cater minimum flow rate
and also maximum flow rate properly with out any damage. Meter is generally sized and
selected on the basis of hourly load. Presently meter is selected on the basis of G-rating.
G rating is a standard established by Organization International De Metrology Legal (OIML).
Flow rate in cubic meter at line condition can be get if we multiply the G-rating with 1.6.
The following type of Gas meter is used for Natural Gas Metering system
50
As per approved load, Diaphragm, Displacement type meter are used for metered domestic
and commercial type customers. Rotary and turbine meter is used for industrial customer.
Presently rotary meter is produced with G-rating from G-10 to higher rating. Due to compact
size rotary meter is easy to installed in the customer yard. All most all the domestic customer
has no meter. They use gas on the basis of flat rate billing system imposed by the government.
Purchase point meters are orifice meter. Bulk users meters are turbine meter. Some of the
individual power producers (IPP) customers used orifice meter for gas billing.
The meter run design requirements and limitations must be reviewed in conjunction with the
flow meter characteristics. Taking this into account, together with meter manufacturers
recommendations and those given in the appropriate standards generates a list of items may
include but not be necessarily be limited to;
51
3.9.5 Turbine meter installation
The most common installation configuration is in line. A minimum of ten (10) pipe diameters
of straight pipe must be placed between any flow disturbing device (other than flow-
throttling) and the inlet flange of the turbine meter. An additional eight (8) pipe diameters
must be added between the meter inlet flange and any throttling device (regulator, control
valve etc) installed upstream of the meter. Inlet piping must be of the same nominal diameter
as the meter body.
Minor variations in piping ID caused by different wall thickness will not affect meter
accuracy. In-line straightening vanes located four or five pipe diameters upstream of the meter
are recommended.
To ensure a proper velocity profile at the meter inlet, the two 900 turns into the inlet end of the
meter run must be in the same plane. Elbows or tees can be used for the 900 turns. Reducing
fitting may be used as long as the reduction at the inlet end does not exceed one nominal pipe
size. Fitting sizes downstream from the meter are not critical, as long as the ID of the
connection to the meter outlet flange is equal to the meter ID.
A ¼ NPT pressure connection for instrumentation is located on each meter body. Temperature
connection for sensors or recorders should be located within two pipe diameters down-stream
of the meter.
52
throttling device should be placed an additional eight nominal pipe diameters upstream of the
meter.
According to AGA Report No.07 the necessary installations for accurate flow measurement
through turbine meter are mainly piping configurations(Minimum length), Straightening
vanes, strainers or filters, over-range protection, By-pass, Accessory installations that would
be discussed below:
53
Figure 3.4 Recommended Installation of an in-line gas turbine meter (Minimum Length)
(Source: AGA Report No.7)
Figure 3.5 Short coupled installation of an in-line gas turbine meter (Minimum Length)
(Source : AGA Report 7)
54
3.11. Straightening vanes
The purpose of a straightening vane is to eliminate swirls and cross currents set up by the pipe
fitting valves or regulators preceding the meter inlet piping. While the specifications which
follow up particularly to the type of vanes shown in figure 3.6, vanes of other designs can be
used if they meet the specifications.
In construction of vanes the maximum transverse dimension, “a” of any passage through the
vane should not exceed one- fourth the inside diameter, “D” of the pipe. Also the cross
sectional area, “A” of any passage within the assembled vanes should not exceed one-
sixteenth of the cross sectional area of the containing pipe. The length, “L” of the vanes
should be at least 10 times the maximum inside dimension, “a”.
The vanes may be built of standard weight pipe or thin- walled tubing either welded together
securely attached into the meter inlet piping or mounted into two end-rings small enough to
slip in the pipe. Square, hexagonal or other shaped tubing may be used in making the vanes. It
is not necessary that the vane passages be of the same size, but their arrangement should be
symmetrical.
55
A greater degree of meter protection can be accomplished through the use of dry-type or
separator type filter installed upstream of the meter inlet piping. It is recommended that the
differential pressure across a filter be monitored to maintain it in good condition so as to
prevent flow distortion and possible customer outage.
As a rule of thumb, the blow-down valve should not be larger than one-sixth of the meter size.
In those installations where adequate pressure is available, either a critical flow orifice or
sonic venture nozzle may be installed in the piping downstream of the meter and should be
sized to limit the meter to approximately 120% of its maximum rated capacity. A critical flow
orifice so designed will result in a 50% permanent pressure loss and a sonic venture nozzle
will in a 10-20% permanent pressure loss.
56
3.14 By- pass
It is good practice to provide a by-pass so the meter can be maintained and calibrated without
a service interruption. This should include proper valving relative to the type of calibrating
equipment to be used.
57
be installed to insure that the temperature is not influenced by heat transfer from the piping
and well attachment.
58
fluid particles and a stationary surface. Under ideal conditions all of the particles flowing in a
pipe will travel at the same velocity and the position of particles relative to each other does
not change with time.
Under “real conditions” there is friction present between adjacent fluid particles as well as
between fluid particles and a stationary surface. The particles immediately adjacent to a
stationary surface will have nearly zero velocity.
The Reynolds number also characterize the velocity profile and stability of the fluid flow
pattern. For laminar flow (Re < 2000) the profile is parabolic and it is not influenced by the
pipe wall roughness. At these conditions, a particle at the centre of the flow would be
traveling at about twice the velocity of the average of the fluid particles. In the total turbulent
region, the flow profile is nearly flat, with particles traveling at same velocity. The exception
being particles close to the pipe wall interface which travel at a lower velocity.
The more common factors are the upstream and downstream pipe length, the location of
bends, valves, reciprocating plant, changes in pipe diameter and general conditions of the
internal pipe walls within the immediate and general proximity of the orifice plate. these
conditions can result in non-ideal flow conditions such as swirl, flow transients and profile
distortion or jetting. Swirl and profile distortion are the two more common dominant
disturbances. they may occur separately or together, especially where poor pipe work design
is present. These non-ideal flow conditions can produce errors which magnitude is higher than
the basic uncertainty in the orifice meter co-efficient. Swirl is caused by adjacent bends in
different planes in the pipe work, whereas irregularities in the pipe, such as partially closed
valves or partially blocked flow conditioners, other fittings like headers, tees and reducers are
the cause of the profile distortion. It may also occur alone within a pipe line system or
together with velocity profile distortion.
The use of straight lengths of pipe can reduce or eliminate swirl. With the viscosity of the
fluid influencing the length of straight pipe required. This means a liquid would require a
much shorter pipe length than would say natural gas.
Of course flow conditioners can also be used for reducing swirl within a pipe. The decay of
swirl is also influenced by the pipe wall roughness. For a very smooth internal pipe wall, swirl
may persist for well over 100 pipe diameters downstream of the source.
59
3.16.2 Reynolds number
Reynolds number Re is a dimensionless variable which represent the nature of flow in a pipe.
Re = (vd)/k --------------------------------------------------------------------------- (3.15)
Where Re = Reynold’s number
v = flow velocity m/s
d = inside diameter of pipe, m
k = kinematics viscosity at p and t m2/s
Reynolds number has been found to be an acceptable correlating parameter that combines the
effect of viscosity , density and pipe line velocity. A flow coefficient that is obtained for water
at a specified Reynold’s number will be the same for oil and gas at the same Reynolds
number. A high Reynold’s number means that viscous forces are small whereas a low value
means that viscous forces dominate.
The Reynold’s number should be kept above 1000000 if flow accuracy is to be maintained.
When the value of Reynold’s number is below 2000, the flow is termed as laminar. Turbulent
flow is said to exist when the value is above 40000. For Reynold’s numbers which fall
between these two values, the flow may be laminar or turbulent – this being termed the
transition area.
For the measurement of natural gas, the Reynold’s number will be normally well above the
transition zone. It is always advisable to check the Reynold’s number sensitivity when
considering a particular flow meter type for a given application.
60
3.17.1 Installation requirements of orifice meter
For determining the orifice plate co-efficient accurately at first to be maintained favorable
flow conditions that is achieved installing the primary device and other necessaries as per
standard requirements, would be described briefly in the following:
The primary device shall be installed in the pipeline at a position such that the flow conditions
immediately upstream approach those of a fully developed profile and are free from swirl.
The primary device shall be fitted between two sections of straight cylindrical pipe of
constant cross-sectional area, in which there is no obstruction or branch connection other than
those specified by ISO. The pipe is considered as straight when it appears so by visual
inspection.
The pipe bore shall be circular over the entire minimum length of straight pipe required. The
internal diameter D of the measuring pipe shall comply with the values given for each type of
primary device.
The inside surface of the measuring pipe shall be clean and free from encrustations, pitting
and deposits and shall conform with the roughness criterion for at least a length of 10D
upstream and 4D downstream of the primary device.
The pipe may be provided with drain holes and/or vent holes for the removal of solid deposits
and fluids other than the measured fluid. However, there shall be no flow through the drain
holes and vent holes using the measurement of flow.
The drain holes and vent holes shall not be located near to the primary device, unless it is
unavoidable to do so. In such cases the diameter of these holes shall be smaller than 0.08D
and their location shall be such that the distance, measured on a straight line from one of these
holes to a pressure tapping of the primary device placed on the same side of this primary
device, is always greater than 0.5D
3.17.2 Minimum upstream and downstream straight lengths required for installation
If any flow conditioner shall be installed in the upstream straight length between the primary
device and the disturbance or fitting closet to the primary device and unless it can be verified
that the flow conditions at the inlet of the primary device conform with fully developed
profile and free from swirl. In such a cases the straight length between this fitting and the
conditioner itself shall be equal to at least 20D, and the straight length between the
61
conditioner and primary device shall be equal to at least 22D. These length are measured from
the upstream face and the downstream face respectively of the conditioner. Conditioners are
only fully effective if their installation is such that the smallest possible gaps are left around
the resistive elements of the device, therefore permitting no by-pass flows which would
prevent their proper functioning.
62
CHAPTER 4
A schematic line diagram of 4" DN ×500 psig pipe line network from Dhanua TBS to
power plant RMS is shown in Fig 4.1.
63
Power Generating Station that generate electricity by using natural gas is called gas
based Power Plants. These type of Power Plants are Gas Turbine, Steam Turbine and gas
generator.
Considering Rolls-Royce generator for proposed power plant, the required data is given
as follows (Appendix D).
64
Lower calorific value of natural gas = 915 Btu/SCF (Appendix C)
The selected type of gas generators requires minimum 50 psig pressure for their
operation. Therefore, the total gas will be required around 11 MMSCFD at pressure of
above 50 psig for the power plant.
For designing, the gas flowing capacity of the RMS should be consider as the sum of
power plant consumption, heater RMS consumption and decreasing the efficiency of the
power plant.
From the above discussion, it is recommended 10% additional load for RMS design.
From the data, it is seen that the maximum flowing capacity of the RMS is 12 MMSCFD
and the minimum flowing capacity of the RMS is 1.8 MMSCFD. Therefore, the turn
down ratio of the RMS is 12:1.8, which should be consider for proper size selection of
the RMS equipments.
65
CHAPTER 5
In this chapter, the detail design procedure of the proposed RMS will be discussed. The
related calculation for size selection of the various components of RMS are also
elaborated here as per internationally recognized recommendation of Institution of Gas
Engineers (IGE-TD-9), AGA Part-9, American Petroleum Institute (API) and Natural
Gas Safety Rules of Bangladesh, 1991 (Amendment 2003). After designing the RMS a
Piping and Instrumentation (P & I) diagram will be drawn.
66
identical runs each of 100% capacity and each regulating runs will consist of inlet
isolating valve (01 no), slam shut off valve (01 no), regulator (2 no), outlet isolating valve
(01 no) and safety relief valve (01 no) installed at the outlet header of the each regulating
unit. The details of pressure reduction is stated in article 5.4.5 of this chapter. Metering
unit consists of two metering runs (streams) with turbine meters for gas flow
measurement and each of 100% capacity. The meters are installed after regulating unit
and immediately before the delivery point of the RMS. The metering unit also includes
mechanical 2 pen chart recorder to record static pressure and flowing temperature for gas
flow rate calculation. The metering runs comprise with isolation valves. One insulating
joint is installed at inlet and another is out of the RMS to protect the eddy current. In the
station outlet, a Non return valve (NRV) is used to prevent the back pressure. There is a
condensate storage tank in the RMS premises to collect the condensate through discharge
lines from filter separator and liquid separator. The RMS is also well equipped with a
Flow computer (FC) and Gas chromatograph (GC) for automated billing from field data.
67
5.3.2 Fluids Characteristics
The RMS which is required to be designed for supplying conditioned gas suitable for
delivery to the power plant. It is not possible to indicate very precisely the composition of
the inlet gas to the RMS. A sample gas composition analysis report that shows the extent
of variability of different components is given in the Appendix C.
Q = 12 MMSCFD
Off take point pressure (minimum), P1 = 425 psig = 439.73 psia
RMS inlet pressure (minimum), P2 = 400 psig = 414.73 psia
Length, L = 0.5 Km = 0.5x0.621 = 0.310 miles
By using Equation no-(3.2)
12 MMSCFD = 0.00128084 [(439.73)2 – (414.73)2]/0.310)0.51*d 2.53
or, Diameter, d = 3.93 inches
Therefore, the line pipe diameter size is 4 inch DNx Schedule-40
68
= [0.75*(12000000/24)/(60*414.73)]1/2
or, D = 3.882 inch
= [0.75**(12000000/24)/(60*414.73)]1/2
= 3.88 inch
Inlet and outlet size will be same because the pressure is same pressure reduction occurs
after filtration.
69
Therefore, the pipeline size of inlet and outlet connection is 4 inch DN
Size : Inlet connection 4 inch RF, ANSI CL 300
Outlet connection 4 inch RF, ANSI CL 300
A) Vertical separator
From Table 3.5 for vertical separator with a mist extractor, Kl = 0.167
Putting the value of Kl in Equation no-5.1, the diameter of the vertical separator is
D = [1.6040/0.167] 0.5 = 3.099 ft
According to design consideration for vertical separator, minimum length (height) should
be 6 ft (Kumar,1987), So L/D = 6/3.099 = 1.936
But this value does not satisfy the design consideration. Length verses diameter ratio
should be between 3 to 8 (Kumar,1987).
B) Horizontal separator
From Table 3.5 for horizontal separator with a mist extractor, Kl = 0.382
Putting the value of Kl in Equation no-5.1, the diameter of the horizontal separator is
D = [1.6040/0.382] 0.5 = 2.049 ft = 24.60 inch
But design consideration for horizontal separator should be of minimum diameter 26 inch
(Kumar,1987).So the diameter of horizontal separator should be 26 inch (2.166 ft).
70
According to design consideration for horizontal separator, Length verses diameter ratio
should be between 3 to 8 (Kumar,1987).
Therefore, a 26 inch(dia)x 6.5 ft (length) horizontal separator is required for the proposed
RMS.
C) Spherical separator
From Table 3.5 for spherical separator with a mist extractor, Kl = 0.35
Putting the value of Kl in Equation no-5.1, the diameter of the spherical separator is
D = [1.6040/0.35] 0.5 = 2.14 ft = 25.68 inch
Therefore, a spherical separator of diameter 26 inch is required for the proposed RMS.
From the above calculated values all the dimensions of separator are tabulated as follows
Vertical filter separator should be more suitable because this type of separator provides
better liquid surge control without carryover into the gas outlet and occupies less floor
space. A Vertical filter separator of size 9 inch (dia)x 6 ft (length) have been selected for
the proposed RMS. A schematic diagram of filter separator unit of the RMS is shown in
Fig 5.1.
71
Fig 5.1. Schematic diagram of filter separator unit of the RMS
72
5.4.3.3 Liquid separator size calculation
A 48 inch(dia)x10 ft(length) vertical liquid separator is capable for handling of gas and
liquid 12 MMSCFD and 1.2 bbl/day respectively.
Vertical liquid separator should be more suitable because this type of separator provides
better liquid surge control without carryover into the gas outlet and occupies less floor
space.
Therefore, a vertical liquid separator of size 48 inch(dia)x10 ft(length) have been selected
for the proposed RMS. A schematic diagram of liquid separator unit is shown in Fig 5.2.
73
Fig 5.2. A schematic diagram of liquid separator unit
74
5.4.4 Gas heating system
Preheating of the gas is necessary for smooth operation of the gas station and correct flow
measurement. Pre heaters are installed to heat the gas after the gas has passed the filter
and before pressure reduction. The requirement of heater is explained in details in chapter
2 and 3.
Process Data
Natural gas of 0.6 specific gravity (air =1)
qn = Gas Flow rate (max) = 12 MMSCFD = 12524 nm3/h
Pi = Inlet pressure of natural gas = 500 Psig = 514.73 Psia = 35.7451 bar(abs)
Po= Outlet pressure of natural gas = 60 Psig = 74.73 Psia = 5.190 bar(abs)
Minimum inlet temperature of gas = 20 °C (50° F)
Minimum outlet temperature of gas = 18 °C (64 °F), (As per engine requirement)
rn = Specific density of natural gas = 0.71 kg/m3
Cp = Specific heat of natural gas = 0.60 kcal/kg
Velocity of gas , V= ft/sec
(Before filtration, 60 ft/sec and after filtration, 120 ft/sec)
Therefore, the temperature of gas will be raise up as per engine requirement (Appendix D),
Dt gas = (Minimum gas temperature required at outlet + temperature drop due to Joule
Thomson effect- Minimum temperature of gas at RMS inlet)
Or, Dt gas = (18 +15.30-20) 0C = 13.3 0C
Heat required for preheating the natural gas can also be calculated by using the Joule-
Thomson effect Equation (McAllister,1996).
75
Heat quantity, W = qn.Dt gas.rn.Cp
W = qn.Dt gas.rn.Cp
= 12524x13.3x0.71x0.60 kcal = 70958 kcal = 297087 kJ = 82.52 kw
The efficiency of heater is 85 % (Assumed)
Heat to be required = 82.52 kw/0.85 = 97.082 kw
Though 97.082 kw capacity of heater is not available in the market, Therefore a 100 kw
capacity heater is recommended to raise up the temperature of gas.
Though the power plant RMS will be design for 10% additional load, so there is a
provision for gas consumption of the heater RMS. A schematic diagram of heating unit of
the RMS is shown in Fig 5.3.
76
Fig 5.3.A schematic diagram of heating unit of the RMS
77
5.4.5 Pressure regulating unit
The regulating run is designed as per internationally recognized recommendation of
International Gas Engineers, IGE-TD-9, AGA Part-9.
No single type of regulator can maintain an exactly constant outlet pressure under all
flowing conditions. Due to large pressure drops across a single regulator excessive noise,
vibration and hydrate formation may occur.
For good performance, the regulator’s valve opening should be maintained within a
range to 25% to 75% of its maximum flowing capacity and minimum inlet pressure of the
station. In this context turn down ratio of regulator is very important. The turn down ratio
of a single regulator is about 5:1(Appendix G). On the other hand turn down ratio of the
power plant is 6:1 according to gas consumption of the engine (Chapter-4).
The number of pressure reduction stage of the RMS runs depends on turn down ratio of
regulator, noise level and temperature drop across a regulator.
If the regulating unit is faulty in design then there may arise various technical problems
in operation of the RMS. To avoid the possibility of excessive noise, vibration and
damage of the regulator and piping, multiple stage pressure reduction provision is
needed.
From the above discussion, it is recommended a two stage pressure reduction provision
for the proposed RMS to ensure a continuous gas supply and smooth operation.
The proposed RMS is a two stage pressure regulating station, so the inter stage pressure
can be determined by using the equation no-(3.2).
78
Putting the value in equation no-(3.2).
The inter stage pressure, Pi = [Ö(514.73*74.73)] = 196 psia
Therefore, the inter stage pressure is assumed 200 psig. In first stage pressure reduction
unit the pressure cuts from 500 psig to 200 psig and in second stage pressure cuts from
200 psig to 60 psig. There are two identical regulating runs (streams) each having 100%
capacity of the maximum flow and each run consists of inlet isolating valve (01no), slam
shut off valve (01no), regulator (2no), outlet isolating valve (01no) and safety relief valve
(01no) installed at the outlet header of the each regulating unit. One regulating run is
operational and another is stand by mode.
Therefore, the inlet pipeline, valve size and Slam shut off valve (SSV) size of first stage
pressure regulating unit are 3 inch DNx Sch-40, 3 inch RF ANSI CL-300 and 3 inch RF
ANSI CL-300 respectively.
Outlet pipe and valve size of first stage pressure regulating unit
D = (0.75*Q/V*P)1/2
= [0.75*(12000000/24)/(120*214.73)]1/2
= 3.815 inch
Therefore, the outlet pipeline and valve size of first stage pressure regulating unit are
4 inch DNx Sch-40, 4 inch RF ANSI CL-300 respectively.
By using Equation no-(3.3)
Outlet header size of the first stage pressure regulating unit :
79
Where,
пD2/4 - Cross sectional area of header, square inches
пd12/4 – Cross sectional area of the 1st stream, square inches
пd22/4 - Cross sectional area of the 2nd, square inches
or, D = [(d12 +d22)* 1.5] ½ = [(42 +42)* 1.5] ½ = [(32)* 1.5] ½ = 6.928 inches
As the both regulating runs are 100% capacity of each and both the runs will not be
operated simultaneously, so there is no problem to use the outlet header size is 6 inch.
Therefore, the outlet header size of the first stage pressure regulating unit 6 inch DNx
Sch-40.
Regulator sizing
At minimum inlet pressure
P1 - P2/ P1 = (414.73-214.73)/414.73 = 0.48
Since, P1 - P2/ P1 £ 0.55 so the flow is sub critical
80
Therefore, the regulator type and size : Fisher- 2 inch RF, ANSI CL 300
Relief valve Size : 1 inch RF, ANSI CL 300
Slam shut valve Size :3 inch RF, ANSI CL 300
As, the outlet pipeline size of first stage pressure regulating unit is 4 inch DN, so the
length of sensing line of this regulating stream is recommended as follows
81
Therefore, the regulator type and size : Fisher- 3 inch RF, ANSI CL 300
Slam shut valve size : 4 inch RF, ANSI CL 300
Relief valve size : 1 inch RF, ANSI CL 300
Inlet and outlet pipe and valve size of second stage pressure regulating unit
Inlet pipe size of second stage pressure regulating unit
By using Equation no-(3.1)
D = (0.75*Q/V*P)1/2
= [0.75*(12000000/24)/(120*214.73)]1/2
= 3.815 inch
Therefore, the inlet pipeline & valve size of second stage pressure regulating unit are
4 inch DNx Sch-40, 4 inch RF ANSI CL-300 respectively.
Outlet pipe and valve size of second stage pressure regulating unit
D = Ö(0.75Q/VP)
= Ö[(0.75*12000000/24)/(120*(74.73)]
= 6.47 inch
Though 7 inch pipe and valve size is not available, therefore the regulator outlet valve
size 8 inch DN, ANSI CL 300
Outlet header size of the second stage pressure regulating unit is calculated By using
Equation no-(3.3)
D = [(d12 +d22)* 1.5] ½ = [(82 +82)* 1.5] ½ = [(64+64)* 1.5] ½ = 13.856 inch
As the both regulating runs are 100% capable and both the runs will not be operated
simultaneously, so there is no problem to use the outlet header size is 12 inch.
Therefore, the outlet header size of the second stage pressure regulating unit is 12 inch
DNx Sch-40.
82
Sensing or control line :
As, the outlet pipeline size of second stage pressure regulating unit is 8 inch DN, so the
length of sensing line of this regulating stream is recommended as follows.
= 10*8 inch
= 80 inch
= 6.66 feet
Noise attenuation
The selected regulators are designed to produce maximum noise level of 80 dBA at 1
meter distance (Fisher Controls, 2003). The regulating system of the RMS is a two stage
regulating unit, so comparatively low level noise will be produced due to several pressure
cut. The noise level will be approximately 70 dBA (Fisher Controls, 2003). The
environmental quality standards for Bangladesh have set noise guide for industrial sites in
Bangladesh, 85 dBA is usually nattered as the critical level for human ear damage
(DOE,1991). According to this standard, noise level should not exceed 75 dBA in
daytime and 70 dBA at night (Appendix L).
Therefore, no additional silencer is required to reduce noise for the proposed RMS.
Schematic diagram of first stage and second stage regulating unit of the RMS are shown
in Fig 5.4 and Fig 5.5 respectively.
83
Fig 5.4 Schematic diagram of first stage regulating unit of the RMS
84
Fig 5.5: Schematic diagram second stage regulating unit of the RMS
85
5.4.6 Metering unit
The metering run is designed as per internationally recognized recommendation of
Institution of Gas Engineers, IGE-TD-9, AGA Part-9 and AGA Report No.7
Rangeability or turn down ratio is very important for meter selection. Turn down ratio
has a strong effect on system loss. Because meter with improper ranged can not measure
accurately. In this context turn down ratio is very important. The turn down ratio of a
single orifice meter is about 3:1(AGA-3). On the other hand turn down ratio of turbine
meter is very high. At lower or medium pressure it is 20:1 and it increases as pressure
increases (AGA-7). Another considering factor is the turn down ratio of the power plant
is 6:1 according to gas consumption of the engine (Chapter-4). Where the gas
consumption is stable or where there is no load variation, it can be used orifice meter and
for load variation it can be used turbine meter.
Considering the above factors of both metering system, it is recommended for installation
of turbine meter in the RMS for accurate instantaneous gas flow measurement and
smooth operation of the station.
The configuration of the meter runs depends on the flow rate which have to be handled
and their turn down ratio.
For custody transfer application, the metering unit of the RMS consists of two metering
runs (streams) for uninterrupted gas flow measurement and each having 100% capacity of
the maximum flow. One metering run is operational and another is stand by mode. If
there is a provision of metering by pass run, the customer or RMS operators may miss
use of the metering by pass without any reason. Therefore, there is no provision of
metering by pass run to prevent theft or pilferage of gas.
From the above discussion it is recommend that, no by pass would be required for
metering unit and turbine meter is selected over orifice meter for the proposed RMS.
86
5.4.6.1 Turbine Meter sizing
Turbine meter size calculation
87
Therefore, it is recommended to install the straightening vane at 5 ft upstream of turbine
meter inlet and the length should be 2 ft.
Now a days, most of the turbine meters are built in straightening vane, which is attached
into the meter inlet piping, so this type of turbine meter should be used to avoid swirls
and turbulence.
88
From these primary inputs the minimum calculations performed by the flow computers
are usually:
· Volume rate
· Volume total
· Corrected Volume
· Uncorrected Volume
· Average density
· Total mass
· Average temperature
· Average static pressure
· Heating value and gas composition
89
· Carrier gas compotation : Should be low consumption of carrier gas.
· Detector technique : TCD, FPD, FID etc.
· Power supply and consumption : 220 VAC/24 VDC, low power consumption
· Area location : Hazardous or safe area.
· Column : Micro packed column or capillary column
· Detector accuracy : Should be capable to detection components up to PPM range
· Date and chromatograph storage capacity : Should be able to store in 3 days
analysis data @ each hour.
· Accuracy and repeatability: 0.05 Btu/1000Btu
· Stand along device to operate in field
· Analysis time per cycle : Typically 3-7 minutes
· Analysis and Heating value calculation are as per ISO 6976, GPA 2172
90
Fig 5.6. A schematic diagram of metering unit of the RMS
91
5.4.10 Measurement accuracy of RMS equipment
The measurement accuracy of the custody transfer metering system is related to the
accuracy of the following equipments.
a) Turbine Meter
b) Pressure Transmitter
c) Temperature Transmitter
d) On line gas Chromatograph
e) Flow Computer
The accuracy of the measuring device can be determined by following formula as per
ISO 5168 (2005).
Therefore, the overall measurement accuracy of the measuring device with turbine meter
of the proposed RMS is ±1.58%.
92
5.4.11 Condensate Storage Tank:
A condensate tank of about 500 gallons capacity will be required to store gas condensate
separated from sweet natural gas. The liquids will be stored under moderate pressure. The
tank should designed for maximum pressure of 10 bar. The condensate will be stored at a
pressure of 4.8 bar. The tank has been designed, fabricated and tested in accordance with
the ASME Boiler and pressure vessel code section V111 DIV 1. One inch diameter drain
line connection from filter separator and liquid separator equipped with dip pipe.
93
5.4.12 Wall thickness of pipe line
Calculation results for pipe wall thickness of line pipe of different sections have been
summarized in Tabular form.
Table 5.3 Pipe wall thickness
Location of Design Pipe Grade Outside Inside Wall
Pipe line Pressure Diameter Diameter thickness
(psig) (inch) (inch) (inch)
Station Inlet 750 API 5L-X46 4.00 3.86 0.068
Inlet of Filter 750 API 5L-X46 4.00 3.86 0.068
Separator
Outlet of Filter 750 API 5L-X46 4.00 3.86 0.068
Separator
Inlet of Heater 750 API 5L-X46 4.00 3.86 0.068
Outlet of Heater 750 API 5L-X46 4.00 3.86 0.068
Inlet Header of first 750 API 5L-X46 4.00 5.80 0.102
regulating run
Outlet Header first 500 API 5L-Gr. B 6.00 5.86 0.068
stage regulating run
Inlet Header of second 450 API 5L-Gr. B 6.00 5.88 0.061
stage regulating run
Outlet pipe of second 90 API 5L-Gr. B 8.00 7.96 0.021
stage regulating run
Outlet Header of 90 API 5L-Gr. B 12.00 11.94 0.032
second stage
regulating run
Inlet of Liquid 90 API 5L-Gr. B 12.00 11.94 0.032
separator
Outlet of Liquid 90 API 5L-Gr. B 12.00 11.94 0.032
separator
Meter run 90 API 5L-Gr. B 12.00 11.94 0.032
94
5.4.13 The major components size for the proposed RMS
Size of the major components for the proposed RMS have been summarized in the
flowing Table 5.4 on the basis of detailed calculations.
95
Table 5.4 RMS components size (Cont’d)
96
Figure 5.7: Piping and Instrumentation diagram
97
Figure 5.8: Top view of the Proposed RMS
98
CHAPTER 6
Safety and environmental impacts are the first considerations in the design of regulating
and metering station. Many factors must be considered in the design to ensure safety of
pipeline and RMS operation.. International codes and standards (ASTM, ASME, ANSI,
API), A.G.A. Report no-7 and Bangladesh natural gas safety rules,1991(Amendment
2003) have been followed for design of gas pipelines and RMS. In this chapter, safety
and environmental aspects in designing a regulating and metering station will be
discussed.
6.1 Environmental impacts of proposed gas facilities for the power plant
The impacts of a gas facilities project can be direct, such as the effect of toxic discharge
on air, noise and water quality or indirect, such as the effect on human health from
exposure to particulates or contaminants. It increases the possibility of explosion and
leakage due to accidents, malfunction of joints or corrosion and lack of skillness and
carefulness of related persons. These negative effects on the environment will be
negligible due to implementation of the project.
Taking proper precautions, these negative effects can be mitigated. The positive impacts
of the project will out weigh the negative one.
The negative impacts of the power plant are much more compared to that of RMS and
pipeline. Running of power plant will produce more noise, vibration, wear and rear
compared to RMS, so more protection should be taken to reduce the negative impacts of
power plant. The negative impacts of RMS and pipeline are less likely.
99
per ASTM, ASME, ANSI, API, A.G.A. Report no-7 and Bangladesh natural gas safety
rules,1991 (Amendment 2003), so that sound level dose not exceed 85dBA .
To prevent accidental over pressure, the flowing protective devices are used in the
proposed RMS.
100
· Pressure relief valve is used to prevent a rise of inlet pressure in excess of a
specified value in the pressure system..
· Slam shut valve: Slam shut valve is installed in series with active regulator.
· Active Monitor regulator : A monitoring regulator is installed in series with active
regulator.
· Non return valve is used to prevent flow in the reverse direction.
Pipe size Pressure 150 Psig to 350 Psig Above 350 Psig
Up to 20” 2.00 Meter 2.50 Meter
Above 20” 3.00 Meter 3.50 Meter
101
6.3.8 Controlling Hazards
Some control measures to prevent hazards are as follows:
· Marking hazards with signs, flags, lights, alarms, barricades, fences, labels,
placards or other materials.
· Providing personal protective and other safety equipments to workers.
There is a provision of fire extinguisher in the RMS premises for controlling of small
fires due to leakage of gas.
102
A safe and leak free pipeline network is essential for uninterrupted gas supply to the
power plant. For this reason a Cathodic Protection (CP) station is recommended for the
0.5 km 4" DN ×500 psig pipe line network of the power plant RMS within one year of
the construction of the pipeline.
The lighting arrangement for the RMS area should be explosion proof and suitable for
hazardous area. Lighting fixtures are mounted on a pole above the suitable height for
proper illuminations.
Hydrostatic test
Hydrostatic test is performed after mechanical completion of the pipeline. For hydrostatic
test, water is poured into the pipeline section. Then the pipeline is pressurized by
injecting small amount of water through hand pump. As per API standard minimum
hydrostatic test pressure should be 1.5 times of design pressure.
103
CHAPTER 7
RMS Inlet pressure, gas flow rate, gas composition, heating value and compressibility
factor has a strong effect on selection of equipment size and material type. Ultimately,
design of the RMS will be affected for variation of all these factors.
In this chapter the above mentioned subjects are discussed in designing a regulating and
metering station.
From the Table P.1, P.2 and P.3 (Appendix P) it is seen that the pipe and equipment size
will be decreased with increase of the inlet pressure for the maximum flow rate.
In the proposed design, the minimum inlet pressure is taken in sizing all equipments for
the maximum flow rate. Therefore, no change is required in the design of the proposed
RMS.
104
Table 7.1: Natural gas composition analysis report
If lower heating value increases, fuel consumption of the power plant will be decreased.
The fuel consumption of the power plant will be 10.5 MMSCFD for 940 BTU/SCF. This
value will also affect the design of the RMS. Considering the fuel consumption of heater
and decrease of the power plant efficiency, the proposed RMS has been designed for the
flowing capacity of 12 MMSCFD.
105
7.2.2 Change of specific gravity due to composition change
In first stage regulating unit, pressure cuts from 500 psig to 200 psig and in second stage
pressure cuts from 200 psig to 60 psig. In this situation putting the different value of
specific gravity (S.G) in the equation no. 3.10 and 3.11, the size of the regulators are
summarized in the following Table 7.2.
From the above data it is seen that the calculated results for different values of specific
gravity are similar to the selected sizes of the proposed RMS.
7.2.3 Effect on filter separator sizing due to change of composition and properties
Putting the different values of gas compressibility factor in the equation 3.7, the sizes of
the separator are summarized in the following Table 7.3.
Table 7.3: Separator sizing calculation
qgas T (°Rankine) p (psia) Z Kl D(ft) L/D
(MMSCFD)
12 520 514.7 1.00 0.167 3.099 1.936
12 520 514.7 0.98 0.167 3.068 1.955
(Minimum length (height) for vertical separator should be 6 ft (Kumar,1987), So L/D = 6/D)
All of the length verses diameter ratio do not satisfy the design consideration. Length
verses diameter ratio should be between 3 to 8 (Kumar,1987).
106
For Length, L = 6 ft = 72 inch
Maximum L/D ratio = 8, So L/D = 8 or 72/D = 8 or Diameter, D = 9 inch.
Therefore, a vertical filter separator of size 9 inch (dia)x 6 ft (length) is required for the
proposed RMS.
The recommended size of the filter separator is similar to the above mentioned size.
Required data:
qn = Gas flow rate (max) = 12 MMSCFD = 12524 nm3/h
Pi = Inlet pressure of natural gas = 500 Psig = 514.73 Psia = 35.7451 bar (abs)
Po= Outlet pressure of natural gas = 60 Psig = 74.73 Psia = 5.190 bar (abs)
Maximum inlet temperature of gas = 20 °C (68° F)
Minimum outlet temperature of gas = 18 °C (64 °F)
1 2 3 4 5 6 7 = (5/6)
12524 0.57 0.60 56967 66.25 85 78
From the above table it is seen that the calculated result of required heater for maximum
and minimum value of specific density (rn ), specific heat (Cp) is similar to recommended
107
heater capacity for the proposed RMS. Therefore, the selected capacity of heater is
acceptable.
The gas composition, properties and environmental factors are also affecting in selection
of material type. Raw natural gas may contain high qualities of sulfur and carbon dioxide
(sour gas). Sour gas is extremely corrosive, therefore, special pipe material has to be
used. In this case, the supplied gas is sweet and line quality gas. Therefore, the material
of line pipe and equipments are used usually steel or cast iron. Steel pipes are both
covered with a special coating to avoid corrosion and they are protected by cathodic
protection.
Considering the safety and environmental aspects, the pressure rating and materials of the
proposed RMS have been selected steel as per maximum allowable operating pressure in
accordance with ANSI and API codes and standards.
108
CHAPTER 8
COST ESTIMATION OF PROJECT
Cost estimation is an essential part of a project. The costing of this project is consists of a
0.5 Km×4"DN×500 psig inlet pipe line of RMS, a 0.3 Km×12"DN×65 psig outlet pipe
line of RMS and one gas regulating and metering station having capacity of
12 MMSCFD.
109
Table 8.1: Cost Estimation of RMS Materials (Cont’d)
Overall material Local Foreign
Item Name Specifications Total Price
Quantity Unit Unit Unit Price (Taka)
Price (Taka)
(Taka)
110
Table 8.1: Cost Estimation of RMS Materials (Cont’d)
Overall material Local Foreign
Item Name Specifications Total Price
Quantity Unit Unit Unit Price (Taka)
Price (Taka)
(Taka)
111
Table 8.1: Cost Estimation of RMS Materials (Cont’d)
Overall material Local Foreign
Item Name Specifications Total Price
Quantity Unit Unit Unit Price (Taka)
Price (Taka)
(Taka)
Pressure Gauge Type : Bourdon Tube 4 No 1,850 7,400
Connection Size :
1/2'' NPT-M
Pressure range :
0-100 psig
Dial Size :150 mm
Temperature Connection Size : 3 No 2,500 7,500
Gauge with 3/4'' NTP(M)
Thermo well Range : 0-150 F
Dial Size : 100 mm
Thermo-well Type : TXC 1 No 900 900
Connection Size :
3/4'' NPT-M
U-Length : 10''
Insulating Class : ANSI 300, 1 No 15,600 15,600
Joint (IJ) Size : 4'' DN
Insulating Class : ANSI 150, 1 No 38,000 38,000
Joint (IJ) Size : 12'' DN
Reducer Sch-40 Size : 4''x3'' 17 No 500 8,500
Reducer Sch-40 Size : 4''x2'' 2 No 700 1,400
Reducer Sch-40 Size : 3''x2'' 2 No 500 1,000
Reducer Sch-40 Size : 6''x4'' 4 No 800 3,200
Reducer Sch-40 Size : 6''x3'' 2 No 750 1,500
Reducer Sch-40 Size : 8''x6'' 2 No 1,000 2,000
Reducer Sch-40 Size : 8''x3'' 2 No 1,200 2,400
Reducer Sch-40 Size : 12''x8'' 2 No 1,500 3,000
Equal Tee Sch-40 9 No 600 5,400
Size : 4''x4''x4''
Equal Tee Sch-40 2 No 1,500 3,000
Size : 6''x6''x6''
Equal Tee Sch-40 5 No 5,000 25,000
Size : 12''x12''x12''
Elbow Sch-40 Size : 4"x 90 14 No 500 7,000
Elbow Sch-40 Size : 6"x90 2 No 1,000 2,000
Elbow Sch-40 Size: 12"x90 2 No 7,000 14,000
112
Table 8.1: Cost Estimation of RMS Materials (Cont’d)
113
Table 8.1: Cost Estimation of RMS Materials (Cont’d)
114
8.2 Land acquisition and requisition
Acquisition is the permanent possession of land. Eight meter wide strip land is required
for the pipeline route. Pipeline is laid along the acquisition land. Requisition is the
temporary possession of land for the construction period only. Fifteen meter wide strip at
the other end of acquisition land and along the pipeline route is requisitioned. After
completion of pipeline construction requisition land is handed over to the original land
owner. Requisition land is used to provide working space for construction crew and
equipments.
115
Table 8.2: Capital Cost
From the above estimation and calculation it is found that the total cost of the project is
Taka 494.463 Lakh.
116
CHAPTER 9
CONCLUSIONS AND RECOMMENDATIONS
9.1. Conclusions
Based on the objectives of this project to design an ideal gas Regulating and Metering
Station and cost estimation of the project, the following conclusions are made from this
study.
· Gas flow capacity, maximum inlet pressure and outlet pressure of the RMS are
12 MMSCFD, 500 psig and 60 psig respectively for uninterrupted gas supply to
the 50 MW power plant.
· In this project work, fluid characteristics, process data, gas safety rules,
International codes and standards (ASTM, ASME ANSI, API) have been
followed for proper design.
· All the equipments of Regulating and Metering station have been selected and
arranged as per internationally recommended standards (IGE TD 9, AGA 7 and
API ) maintaining the entire requirements for filtering, regulating, metering to
prevent various operational difficulties and measurement error.
· The pipe and fittings have been chosen in such a way that turbulence can be
avoided or made minimum.
· Meter type and size have been selected considering variation of flow rate and
pressure to measure the gas volume accurately because the revenue earning for
the company is related to measurement.
· The RMS has been proposed to be well furnished with modern flow computer for
gas measurement and online gas chromatograph for continuous gas analysis for
smooth, quantitative and accurate measurement of gas flow.
· Variation in different variables such as inlet pressure, specific density, specific
heat, compressibility factor and heating value within the allowable limit do not
require any change in the proposed design.
· The cost estimation of the project has been calculated on the basis of
preconstruction expenditure, construction cost, material cost etc. The total cost of
the project is estimated as Tk. 494.463 Lakh.
117
9.2 Recommendations
· A Regulating and Metering station should be designed to meet the present and
future demand under variable gas flow and pressure conditions and decreasing
efficiency of the power plant.
· The RMS should be kept under a SCADA system for remote controlling of the
system such as the valves, regulators and also for monitoring the status of flow
rate and pressure for the case of operation as per international practice of the gas
industry.
· After construction of the pipe line of RMS, cathodic protection (CP) system
should be installed in the pipeline network and RMS for safe and leak free
network in accordance with the requirements of British standard specification
code BS CP 1021 or American National Association of Corrosion Engineers code
RP 01-72.
· RMS equipments, piping and inlet outlet direction of gas flow should be painted
as per colour coding of pipes and equipments.
· Before commissioning of the pipeline and RMS, both the pipeline and RMS
should be tested by means of standard hydrostatic test for ensuring the safety and
integrity of the pipeline and RMS.
118
REFERENCES
[1] AGA Report Part Nine : ‘Design of Meter and Regulator Stations’ Operating section
American Gas Association 1515 Wilson Boulevard Arlington, Virginia 22209, U.S.A.
[2] AGA Report Number-7: Measuring of fuel gas by Turbine meters’ Operating section
American Gas Association 1515 Wilson Boulevard Arlington, Virginia 22209, U.S.A.
[3] AGA Report Number -3: Orifice Metering of Natural Gas and other related
hydrocarbon’ Operating section American Gas Association 1315 Wilson Boulevard
Arlington, Virginia 22209, U.S.A.
[4] ASME B 31.8 (1995): ‘Gas and Transmission and Distribution Piping System’.
[7] C. Richard Sivalls, P.E(1987), ‘Oil and gas separator design manual’, Sivalls, Inc.
Odessa, Texas, U.S.A.
[8] DOE Report (1991), ‘Environmental Quality Standards for Bangladesh’, Published by
Department of Environment, Dhaka.
[9] DOE (1997), EIA Guide Lines for Industries, Department of Environment, Ministry
of Environmental and Forest, Government of Peoples Republic of Bangladesh.
[10] Fisher Controls, (2005), ‘Natural Gas Regulators Application Guide’, Fisher
Controls International Inc,U.S.A.
[11] GTCL (2007): ‘Report on High Pressure Transmission Lines’, Operation Division.
[13] Instromet, (2001), ‘Turbine Gas Meter Handbook’ Instromet Inc, Houston, Texas.
119
[14] ISO 14001, (2004), ‘Standard for International Environmental Management System’,
Geneva, Switzerland.
[17] Mc.Allister, E.W. (1998), ‘Pipe Line Rules of Thumb Handbook’ Gulf Publishing
Company, Houston, Texas, U.S.A.
[18] Natural Gas Safety Rules of Bangladesh, 1991(Amendment 2003), Published by the
Ministry of Energy and Mineral Resources, Government of Bangladesh.
[19] OHSAS 18001, (2007), ‘Standards for Occupational Health and Safety Management
Systems’.
[20] Parker, M.E, (1954) “Pipeline Corrosion and Cathodic Protection”, First Edition,
Houston, Texas.
[21] Roy, K. R. (1989), ‘A survey of the processes entailed in the design of natural gas
regulating stations in United Kingdom’, Department of Mechanical and process
Engineering, University of Strathclyde, U.K.
[22] Richard J. Mooney (1999), ‘Regulator sizing and selection’ Mooney Controls Inc.
[26] Shanghai Fiorentini (2008),‘ Filter Separators Catalogue’ Shanghai Fiorentini Gas
Equipment Company Ltd, Shanghai, China.
[28] TGTDCL (2007-2008): ‘Annual Report’, Titas Gas Transmission and Distribution
Com. Ltd.
120
APPENDIX A : TERMINOLOGY
Backpressure Regulator - This is a device that controls and responds to changes in its
upstream/inlet pressure. Functions the same as a relief valve in that it opens on increasing
upstream pressure.
British Thermal Unit (Btu) - The quantity of heat required to raise one pound of water
from 59°F to 60°F.
C1 - A term used in a sizing equation. It is defined as the ratio of the gas sizing
coefficient and the liquid sizing coefficient and provides a numerical indicator of the
valve's recovery capabilities.
Capacity, Flow - The amount of a specified fluid that will flow through a valve, specific
length and configuration of tubing, a manifold, fitting, or other component at a specified
pressure drop in a fixed period of time. (scfh, gpm, m3/h(n), lpm, pph)
Cg (Flow Coefficient) - A term used in gas and steam valve sizing equations. The value
of Cg is proportional to flow rate and is used to predict flow based on physical size or
flow area.
Control Line - The external piping which connects the regulator actuator or pilot to the
point on the main line where control is required.
Critical Flow - The rate at which a fluid flows through an orifice when the stream
velocity at the orifice is equal to the velocity of sound in the fluid. Under such conditions,
the rate of flow may be increased by an increase in upstream pressure, but it will not be
affected by a decrease in downstream pressure. Critical flow occurs when P2 is
approximately 1/2 of P1.
Critical Velocity - The velocity at critical flow. Also called sonic velocity.
.
121
Downstream - Any site beyond a reference point (often a valve or regulator) in the
direction of fluid flow.
Hunting - A condition where a regulator's outlet pressure slowly fluctuates on either side
of a set point.
Lockup Pressure - Increase over set point when the regulator is at no-flow condition.
m3/h(n) - meters cubed per hour (normal); measurement of volume rate of a gas at
atmospheric pressure and 0°C.
m3/h(s) - meters cubed per hour (standard); measurement of volume rate of a gas at
atmospheric pressure and 60°F.
Monitor: A general term for an instrument used to sense the magnitude or status of one
or more variable.
Maximum Allowable Operating Pressure (MAOP) - The maximum pressure that the
system may be operated at as determined by its components, taking into account function
and a factor of safety based on yield of parts or fracture.
Pilot (Amplifier) - A relatively small controlling regulator which operates the main
regulator. They are used to increase accuracy.
Rangeability - The ratio of maximum rated capacity to the minimum controllable flow
within the specified accuracy band.
122
Repeatability: Repeatability is a meter’s ability to replicate the same reading each time,
given that the same flow conditions exist.
Retention time: The amount of time a liquid stays in a vessel is called retention time.
The retention time assures that equilibrium between the liquid and gas has been reached
at separator pressure. The retention time in a separator is determined by dividing the
liquid volume inside the vessel by the liquid flow rate.
Set point: An input variable that determines the value of the output variable.
Standard Pressure: The standard base pressure is generally recognized as 14.73 psia or
1.0136 Bara.
SCADA : Supervisory Control and Data Acquisition system is the overall system –the
combination of software and hardware.
Sonic Velocity - The speed of sound for a particular gas at a given inlet pressure and
temperature.
Transducer: A device that receives information in the form of one or more physical
quantities and converts the information and produces an output signal.
Transmitter: A device that responds to a process variable through a sensor and has an
output, which varies in relation to the process variable.
Vent - An opening in the regulator spring case to allow atmospheric pressure access to
the diaphragm, thus allowing free movement of the diaphragm during operation.
123
APPENDIX B : CODE AND STANDARDS
Gas Regulating and Metering Station designed and manufactured in accordance with the
latest edition of the following Codes and Standards :
a) Mechanical :
Equipment will generally be mechanically designed in accordance with the relevant
Institute of Gas Engineers (IGE) codes and the following principal codes of practice:
IGE Codes :
IGE/TD/9, IGE/GM/1.
ASME
Section V : Non-destructive Examination
Section VIII : Pressure Vessels, Div. 1
Section IX : Welding and Brazing Qualifications
ANSI
API
ASTM
124
b) Instrumentation :
Instrumentation will generally be in accordance with the applicable section of the
following principal codes of practice:
enclosures.
atmospheres.
c) Electrical
Civil design will be performed in accordance with British Standard and Bangladesh
Regulations.
125
APPENDIX C : GAS COMPOSITION ANALYSIS REPORT
Components % Mole % Wt
Nitrogen : 0.356 0.592
Carbon dioxide : 0.236 0.617
Methane : 96.241 91.577
Ethane : 2.202 3.928
Propane : 0.464 1.215
i-Butane : 0.173 0.596
n- Butane : 0.086 0.296
i-Pentane : 0.052 0.224
n-Pentane : 0.036 0.153
Hexane : 0.090 0.448
Heptane+ : 0.062 0.354
Total 100 100
126
APPENDIX D : GAS GENERATOR DATA SHEET
127
APPENDIX E : UNIT CONVERSION
1 Kg 14.22 Psig
1 Barrel 42 Gallons
1 Nm3 37.32566 Nf 3
1 sm3 35.3147 sf 3
128
APPENDIX F : G-RATING FOR TURBINE METER
129
APPENDIX G : TURN DOWN RATIO
130
APPENDIX H : PIPE SCHEDULE
Add three inches to the actual inside diameter; divide this by the wall thickness; the
schedule number can then be identified by the following Table H.1
30 40 to 50
40 29 to 39
60 25 to 29
80 20 to 23
100 16 to 18
120 13 to 15
140 11 to 13
160 9 to 11
131
APPENDIX I : PRESSURE RATING FOR VALVE, REGULATOR
AND FITTINGS
Class PN
Bar Psi
150 20 290
300 50 725
400 64 928
600 100 1450
900 150 2176
1500 250 3626
2500 420 6092
PN = Nominal Pressure
132
APPENDIX J : GAS CAPACITY OF SEPARATOR
The Separator size can be selected by using the following Figure J.1
133
APPENDIX K : SETTLING VOLUME OF VERTICAL SEPARATOR
The settling volume of vertical separator can be determined by the following Table K.1
134
APPENDIX L : STANDARD VALUES FOR NOISE
The Environmental Quality Standards for Bangladesh (DoE, 1991) have been set noise
guide noise for industrial sites in Bangladesh. According to standard, noise level should
not exceed 75 dBA in the daytime and 70 dBA at night.
A dBA 45 35
B dBA 50 40
C dBA 60 50
D dBA 70 60
E dBA 75 70
135
APPENDIX M: MATERIAL SYMBOLS
136
APPENDIX N: COLOUR CODING OF PIPES AND EQUIPMENTS
7 Regulators/Meters : Gray
8 Skid : Black
9 Pipes : Aluminium
137
APPENDIX O
138