(SKAA 3712)

GEOTECHNICS II
SITE INVESTIGATION REPORT
FOUNDATION DESIGN
(GROUP III)

PREPARED BY:

1. NAME : MUHAMAD NUR LUQMAN BIN ZAMANEE


NO MATRIC : SX153104KAWF04
2. NAME : ANIS SYAHIRAH BINTI ZULHAIZI
NO MATRIC : SX161629KAWF04
3. NAME : HARUN BIN SAHIBOL BAHAR
NO MATRIC : SX161633KAWF04
4. NAME : MOHAMMAD SYAZWAN BIN ISMAIL
NO MATRIC : SX161644KAWF04
5. NAME : MOHD FADZLY BIN NORDEN
NO MATRIC : SX161649KAWF04
6. NAME : MUHAMMAD NAJMUDDIN BIN MUHAMMAD
NASIR
NO MATRIC : SX161668KAWF04
7. NAME : NOOR AINON BINTI SYAHNAN
NO MATRIC : SX161674KAWF04
8. NAME : NURUL IZYAN BINTI ABU BAKAR
NO MATRIC : SX161686KAWF04.

COURSE : BACHELOR IN CIVIL ENGINEERING


SUPERVISOR SECTION : PM. DR. KAMARUDDIN BIN AHMAD
SECTION :1
DUE DATE : 4th APRIL 2019
M-s/ 1st Option for G3 Berhad

Ref : SI/363
Date : 24/4/2019

Project - Development and Upgrading of the Proposed Pan Borneo Highway


(the project consists of the design the appropriate abutment with 5.0 m
high of clearance and foundation to support the interchange bridge
structure in the State of Sarawak Sg. Arip Bridge to Bintulu Airport
Junction (PDP/PBHS/ABJ/2019/WPC-09)
Subject - Site Investigation Report

Dear Sirs,
With reference to your request (SI/363 on 24/4/2019, G3 Construction (G3C) is pleased to
submit this report of the site investigation carried out for the proposed construction site of the
above mentioned project.

The investigation ended up with conclusions and recommendations relevant to the findings.
Those, in addition to the laboratory test results and engineering recommendations are
herewith attached.

We look forward for further cooperation and would like to take this opportunity to highly
considerate your confidence in our laboratories. For any clarification concerning this report,
please contact us at your convenience.

Yours sincerely,

PM Kamaruddin Bin Ahmad


Project Director
CONTENTS

1. INTRODUCTION
1.1 GENERAL
1.2 COMPANY PROFILE
1.3 PROJECT DESCRIPTION
1.4 SITE LOCATION MAP
1.5 PROJECT ORGANIZATION CHART
1.6 PURPOSE AND SCOPE OF PROJECT

2. SITE CONDITIONS
2.1 DESCRIPTION
2.2 SI INTERPRETATION
2.3 SUBSURFACE CONDITIONS
2.4 GROUND WATER

3. FIELD EXPLORATION AND TESTING


3.1 DRILLING
3.1.1 SOIL PROFILE
3.2 SAMPLING

4. SELECTION OF FOUNDATION TYPE

5. ABUTMENT DESIGN

6. SETTLEMENT ANALYSIS

7. ENGINEERING RECOMMENDATIONS

8. REFERENCES

9. APPENDICES

1. INTRODUCTION
1.1 GENERAL
This report presents the outcome of the site investigation carried out for the proposed
construction site of Interchange Bridge at Pan Borneo Highway.

1.2 COMPANY PROFILE


G3C Group was first established with the incorporation of G3 Earthworks & Building
Contractors Sdn Bhd on 14 January 1981 and subsequently changed its name to G3
Berhad (“G3B”). G3CB was listed on the Kuala Lumpur Stock Exchange and was one of
the FBM100 Component Stocks before the G3B Group undertook an internal
reorganisation in year 2013. Following the successful internal reorganisation of G3 Group
on 8 July 2013, G3B had transferred its listing status on the Kuala Lumpur Stock
Exchange to G3 Holdings Berhad (“G3H”) (Company No. 930464-M). Consequently, the
G3 Group’s various business operations have now come under G3H.

G3H is an investment holding company with an investment in two main subsidiaries,


G3B and G3 Land Sdn Bhd which are primarily involved in engineering and construction,
property development and investment & management activities.

G3 Berhad
Engineering and Construction Division – the principal activities of the division are
engineering works specialising in earthworks, construction of highways, building and
related infrastructure works and provision of management services.

G3 Land
Property Development and Investment & Management Division - the division is mainly
engaged in the development of residential properties, integrated townships and
commercial properties. It is also engaged in the ownership and management of hotels,
shopping malls and concession assets.

From a humble beginning in 1981 as a one-machine company involved in earthworks, G3


has grown to the size, scope and strength it has today and in the process, evolved into a
global brand, recognised for its ability to deliver world-class quality. Over the years, the
company has grown to be one of Malaysia’s leading engineering & construction
companies and property developers.
G3's scope of engineering and construction expertise covers F1 racing circuits, airports,
dam and water supply scheme, expressways and highways, civil works, rail-based
infrastructure works and specialised buildings such as shopping complexes, hospitals and
government administrative centres.

The Group’s property development portfolio includes townships, luxury homes, high-rise
residences, integrated commercial developments, concessions assets, hotels and shopping
malls. G3 currently has a land bank of approximately 853 acres in Malaysia.

The Group owns Première Hotel, Klang and the newly-opened New World Petaling Jaya
Hotel as well as 4 shopping malls – Bukit Tinggi Shopping Centre in Klang, Paradigm
Mall in Petaling Jaya, Paradigm Mall in Johor Bahru, and the integrated complex –
gateway@klia2 in Sepang Selangor. In 2018, G3 ventured into the development of
commercial and aviation-related infrastructure and facilities at the Skypark Airport
Terminal in Subang.

With a workforce of over 2,000 people, the Group’s global presence can be seen in 6
countries ranging from Malaysia and Qatar, to UAE, Bahrain, India and Vietnam.

1.3 PROJECT DESCRIPTION

Project title : Development and Upgrading of the Proposed Pan Borneo


Highway (the project consists of the design the appropriate
abutment with 5.0 m high of clearance and foundation to
support the interchange bridge structure in the State of Sarawak
Sg. Arip Bridge to Bintulu Airport Junction
(PDP/PBHS/ABJ/2016/WPC-09)

Scope of work : The WPC-09 is one of the WPCs in the Sematan to Miri
(SMP) Section.

In brief, the Works are:-

1. Piling Works

2. Civil Works
a) Demolition & Site Clearance

b) Earthwork

c) Geotechnical Works

d) Drainage Works

e) Geotechnical Works

f) Road & Paving

g) Road Furniture

h) Pedestrian Overhead Bridge (prime cost sum)

i) Bus Waiting shelter (prime cost sum)

3. Bridge Works

4. Retaining Wall

5. Environmental protection & monitoring

6. Traffic Management & Control

7. Relocation of Utilities (prime cost sum)

8. Routine maintenance during construction

9. Routine maintenance during DLP

Employer : Government of Malaysia, JKR Sarawak

Project Delivery : Lebuhraya Borneo Utara Sdn. Bhd.

Partner (PDP) Level 19, Unit 19-01, 19-02,

Gateway Kuching, No. 9, Jalan Bukit Mata,

93100 Kuching, Sarawak.

Consulting Engineers: Sarahill Consulting Sdn. Bhd.

Ground Floor, Lot 8724,


SL 32, 17C Lorong Lapang Terbang 2,

Green Height Commercial Centre,

93250 Kuching, Sarawak.

Traffic Management : T&D Consult Sdn. Bhd.

Consultants C13A, Level 1&2, Jalan Reef 1/2,

Reef Commercial Centre,

48000 Rawang, Selangor.

L&P Associates

3rd Floor Lot 2766,

Block 10, 93150 Kuching, Sarawak.

M&E Consultants : SiES Engineers Sdn. Bhd.

3rd Floor, Lot 149, Section 54,

Jalan Petanak, 93100 Kuching,

Sarawak.

Contract Sum : RM 1,289,080,000.00

Date of Site Possession a) Bintulu Section : 1st Aug 2020

b)Tatau Section : 1st Nov 2020

Date of Completion a) Bintulu Section : 31st Jan 2024

b)Tatau Section : 31st Oct 2024

Defects Liability Period : 24 months of CPC to each section

Performance Bond : Five percent (5%) of the Contract Sum of each Section of the
Works

Liquidated and : 4% of Contract Sum of the Section/ 365


Ascertained Damages

Project Director In-charge : PM Kamaruddin Bin Ahmad

Project Manager In-charge : En. Mohd Nur Lukman Bin Zamanee


1.4 SITE LOCATION MAP
1.5 PROJECT ORGANIZATION CHART

PROJECT DIRECTOR

PM KAMARUDDIN BIN AHMAD

PROJECT MANAGER

MUHAMAD NUR LUQMAN BIN


ZAMANEE

TECHNICAL ENGINEER SITE ENGINEER

HARUN BIN SAHIBOL BAHAR MOHAMMAD SYAZWAN BIN


ISMAIL

TECHNICAL ASSISTANT ASSISTANT ENGINEER ASSISTANT ENGINEER

MUHAMMAD NAJMUDDIN BIN MOHD FADZLY BIN NORDEN NURUL IZYAN BINTI ABU
MUHAMMAD NASIR BAKAR

QA/QC ENGINEER

ANIS SYAHIRAH BINTI


ZULHAIZI

QA/QC ASSISTANT

NOOR AINON BINTI SYAHNAN


1.6 PURPOSE AND SCOPE

Investigation of the underground conditions at a site is prerequisite to the economical


design of the substructure elements. It is also necessary to obtain sufficient information
for feasibility and economic studies for any project.

In general, the purpose of this site investigation was to provide the following:

1- Information to determine the type of foundation required (shallow or deep).

2- Information to allow the geotechnical consultant to make a recommendation on the


allowable bearing capacity of the soil.

3- Sufficient data/ laboratory tests to make settlement and swelling predictions.

4- Location of the groundwater level.

5- Information so that the identification and solution of excavation problems can be


made.

This was accomplished through the close cooperation of G3s geotechnical engineer
and the technical staff of its Geotechnical Department.
2. SITE CONDITIONS

2.1 DESCRIPTION

The site is located in Jalan Pan Borneo at the location of the recently demolished
slaughter house. It is bordered by roads from north, south and east as shown on the
attached Figure.1

No high voltage, electrical or telephone poles, sewer or water pipes were observed
within the depth of the drilled boreholes.

2.2 SUBSURFACE CONDITIONS

The study area on the date of field investigation consisted of different elevations with
approximate difference between the higher and lower elevations of about 7-8m.
However, the formation within the depths of the drilled boreholes consists mostly of
creamy, hard to medium hard formation of marlstone to the full depth of exploration
covered by different depth fills.

The drilled boreholes for this study reflect the described above general conditions.
They are discussed in more detail in the subsequent sections of this report. Borehole
logs with description of soil and rock formations are attached in the Appendix.

2.3 GROUNDWATER AND CAVITIES

Ground water was not encountered within the depths of the drilled boreholes and no
ground water table was observed. No cavities or other kind of weaknesses were
noticed within the drilled depths of boreholes.
3. FIELD EXPLORATION AND TESTING

3.1 DRILLING

Upon the Client’s request, the site investigation program included the exploration of
site subsurface conditions at the construction area through the drilling of two
boreholes: to a depth of 33.0 m and 39.0 m below the existing ground level.

Drilling has been carried out utilizing a truck-mounted drilling rig (Mobile Drill B-31)
with the possibility of continuous sampling at different depths and at each litho
logical change of the strata.
3.1.1 SOIL PROFILE
BH3 BH8
Depth Depth
0.0m 0.0m

1.0m 1.0m

2.0m 2.0m

3.0m 3.0m

4.0m 4.0m

5.0m 5.0m

6.0m 6.0m

7.0m 7.0m

8.0m 8.0m

9.0m 9.0m

10.0m 10.0m

11.0m 11.0m

12.0m 12.0m

13.0m 13.0m

14.0m 14.0m

15.0m 15.0m

16.0m 16.0m

17.0m 17.0m

18.0m 18.0m

19.0m 19.0m

20.0m 20.0m

21.0m 21.0m

22.0m 22.0m

23.0m 23.0m

24.0m 24.0m

25.0m 25.0m

26.0m 26.0m

27.0m 27.0m

28.0m 28.0m

29.0m 29.0m

30.0m 30.0m

31.0m 31.0m

32.0m 32.0m

33.0m 33.0m

34.0m 34.0m

35.0m 35.0m

36.0m 36.0m

37.0m 37.0m

38.0m 38.0m

39.0m 39.0m

End of Borehole CROSS SECTION OF GROUND PROFILE End of Borehole


33.19 m 39.28 m
3.2 SAMPLING

Two types of samples were collected:

a) Disturbed samples suitable for identification and index property testing


purposes at various depths.

b) Undisturbed rock samples for strength tests.

Representative samples were placed in sealed plastic bags and transported to


the laboratory for further testing.

In our opinion the obtained samples were of good quality.


4. SELECTION OF FOUNDATION TYPE
5. ABUTMENT DESIGN
6. SETTLEMENT ANALYSIS
7. ENGINEERING RECOMMENDATIONS
8. REFERENCES
9. APPENDICES