Visvesvaraya Technological University: Belgaum, Karnataka-590 014
Visvesvaraya Technological University: Belgaum, Karnataka-590 014
CERTIFICATE
Certified that the project work entitled “BLAST FRAGMENTATION
ANALYSIS USING SPLIT-DESKTOP SOFTWARE AND
OPTIMIZING THE COST OF DRILLING AND BLASTING” carried
out by Rajamani J (USN-1GV14MI031), Saravanan I(USN-1GV15MI049),
Saravanan J (USN-1GV15MI050) and Sujith Sagar T (USN-1GV16MI410)
bonafide students of Dr. T. Thimmaiah Institute of Technology, in partial
fulfillment for the award of Bachelor of Engineering in Mining Engineering
department of the Visvesvaraya Technological University, Belgaum during
the year 2018-2019. It is certified that all corrections/suggestions indicated
for Internal Assessment have been incorporated in the Report deposited in
the departmental library. The project report has been approved as it satisfies
the academic requirements in respect of Project work prescribed for the said
Degree.
We would like to express our deep gratitude to Dr. T. Thimmaiah Institute of Technology
for the support in successful completion of this project.
We are very much thankful to Dr. Syed Ariff, Principal, Dr. TTIT and Dr. Ramesh,
Head of the Department, Department of Mining Engineering, Dr. TTIT for providing
support for all project related activities.
We express our profound and cordial gratitude to our external project guide Mr. C. P. Hari
Prasad, Assistant Manager, Dalmia Cements Limited for providing us an opportunity
to pursue our project in the esteemed institute and for the guidance and encouragement.
We sincerely thank by heart and soul to our internal guide Dr. Syed Ariff, Principal,
Dr.TTIT and Associate Professor Mr. J. John Gladious, Department of Mining
Engineering, Dr.TTIT whose timely support and suggestions went a long way in the
completion of project.
We thank our project coordinator, Mr. Paul Prasanna Kumar, Associate Professor,
Department of Mining Engineering, Dr.TTIT, for his useful guidance and valuable
suggestions that helped us in successful completion of this project.
Finally we thank all the teaching and non-teaching staff of Dr.TTIT, Employees of Dalmia
Cements Limited for their support and the encouragement in our endeavor and of course,
nothing could have come true without the support and cheerful encouragement of our
parents and friends.
ABSTRACT
Drilling and blasting being the cheapest amongst the various methods of
fragmentation and also suitable to the strongest of the rocks should be designed properly to
produce optimum fragment size that can be efficiently handled by equipment used. The
smaller the fragments the higher would be the equipment efficiency and lesser would be
the wear and tear of the equipment. But smaller the fragments produced by blasting, the
higher would be the cost of drilling and blasting though the equipment utilization cost is
reduced. Hence it is a must to fix an optimum fragment size for a set of equipment type and
size, such that the equipment operates at a greater efficiency and hence result in reduced
overall cost of drilling and blasting.
CONTENTS
CHAPTER I
INTRODUCTION 1-4
1.1 INTRODUCTION
1.2 BLASTING PARAMETERS
1.3 BLASTING PERFORMANCE
1.4 DEGREE OF FRAGMENTATION
1.5 BENEFITS OF OPTIMUM FRAGMENTATION
1.6 SPLIT-DESKTOP SOFTWARE
1.7 REASON FOR SELECTING THE PROJECT
CHAPTER II
2.2 OBJECTIVE
CHAPTER III
METHODOLOGY 8-13
CHAPTER IV 14-27
REFERENCE 28
BLAST FRAGMENTATION ANALYSIS USING SPLIT-DESKTOP SOFTWARE AND
OPTIMIZING THE COST OF DRILLING AND BLASTING
CHAPTER I
INTRODUCTION
1.1 INTRODUCTION
The primary purpose of drilling and blasting is to break rock & mineral and prepare
the same for excavation and subsequent transport. The end purpose of rock blasting is to
produce input materials for a crusher. So, fragments produced by blasting should be small
enough to pass into the crusher opening. Performance of the other machinery largely
depends on blast fragmentation produced. So optimum fragment size is required for keeping
the overall cost of mining low. Drilling and Blasting is one of the major unit operations in
mining. In spite of best efforts to introduce mechanization in mining industry, blasting will
continue to dominate production because of its suitability to a wide variety of rock types and
strength and also being the cheapest of the different rock breaking techniques.
CHAPTER II
LITERATURE REVIEW
1) F. I. Siddiqui, S. M. Ali Shah & M. Y. Behan (2009) [1] The result obtained from
the analysis of muck-pile images using Split-Desktop software shows that the mean
fragment size is 149.76mm and P20, P80 and Top-size are 11.66mm, 426.31mm and
1057.44mm respectively. The product size of primary crusher is below 30mm. They
observed that 25% of the fragments from the blast of size below 30mm. This
percentage can be enhanced by optimizing the overall blasting operation to be
optimize the overall blasting operation. Proper explosives in an appropriate quantity
can also results in good fragmentation and reduce the overall cost of production.
2) Mohammad Farouq Hossaini, etal (2013) [2], Blast fragmentation of Ghoghart Iron
mine has been analysed and fragmentation distribution has been defined through
muck pile images using Split-Desktop software. The value of P50 obtained were in
the range of 88.89 to 390.8. Relationship between P50 and specific charge has been
defined for which a co-efficient of determination was 0.95. This co-relation shows
that in Ghogart Iron mine the amount of P50 is increased with increasing specific
charge.
3) Zubair Ahmed Nizamani, Shahzad Ali Rajput, Sanaullah Bhoot, Nasir Ali
Magsi (2013) [3], The results obtained from the analysis of muck pile images using
Split-Desktop shows that approximately 7.45% of the fragments are below 25.45
mm. As the results indicates that 7.45% fragments are below 25.45mm, which is the
product size of primary crusher, this percentage can be enhanced by optimizing the
overall blasting operations. The Burden and spacing are the two most important
factors in the blasting because these factors can be adjusted to obtain the required
fragmentation. Proper explosives in an appropriate quantity can also results in good
fragmentation and reduces the overall cost of production.
4) F. Sereshki, S.M. Hoseini, M. Ataei (2016) [4] In this paper, they compared the
efficiency of Split-Desktop and Goldsize software in predicting the Rock
fragmentation and concluded that the Split-Desktop software there is a need of
manual correction of errors which will be a time-consuming process. Similarly, in
the Goldsize software the rock boundaries can only be segmented manually which
will take a lot of time.
5) I. C. Engine (2016) [5], In this study, rock factor representing the rock mass
properties of a quarry was determined indirectly by the resultant fragmentation of
the blasting operations carried out by using the specified blast design parameters.
Rock factor was calculated by Kuz-Ram model by means of designed parameters
and fragments size investigated by Split-Desktop image analysis software. The first
optimization study used the Langefors and Kihlstrom (1976) approached which
predicted the required fragment size and other targets but predicted relatively high
total drilling and blasting costs. In the second optimization process optimum blast
design parameters were determined by using suggested formulae used in the Bench
blasting operations and observed with cost reduction of around 50% in total drilling
and blasting costs.
6) Tavakol Elahi & Hosseini (2017) [6] In this paper, the authors investigated blast-induced
fragmentation in three blocks using the digital image processing feature of Split Desktop. In
each block they used different blast patterns. In first pattern, they observed the vibration
troubles. The second pattern resulted in the formation of numerous blast-induced
boulders, which caused problems to the loading and transport of rock fragments. The
third pattern neither causes the vibration troubles nor brings the existence of
numerous boulders. So, they conclude that the third pattern as the best choice.
7) Julio Cesar de Souza, Carlos Santos da Silva, Suelen Silva Rocha (2017) [7] They
compared results obtained from the simulation of Kuz-Ram model and the blasting
practiced in Herval Quarry using the Split-Desktop Software and concluded that the
Kuz-Ram model is more efficient in predicting the fragmentation but there some
limitations such as over estimation of amount of fines, doesn’t predict the particle
size of rock for different mesh.
8) Eugie Kabwe (2018) [8] In this context, it is observed that the VOD recorded in blast
hole 5 is lower as compared to other blast holes. This is a result of reduced
confinement caused by movement of the burden on the block. The fragmentation
size distribution analysis shows that more than 82,620m3 representing 90% of the
blasted muck-pile are within 700mm passing rate and 46m3 of muck-pile
representing 0.05% are above 1100mm. The fragmentation size distribution analysis
using Split-Desktop shows that the 20% (x20), 50% (x50) and 80% (x80) passing
fractions are in close range with the predicted values from the empirical
fragmentation models, which presents the data consistency.
9)J. B. Ninepence, etal (2018) [9], They analysed the blast output of Boss Mining
Company Limited (BMCL), an open pit mine in Tarkwa in the Western Region of
Ghana, using Split-Desktop software for fragmentation analysis. The results showed
that the mean fragmentation of the mine using current drill and blasting parameters
were below the expected mean fragment size of 415mm. Blast optimization was
therefore carried out using the Kuz-Ram Model proposing two options by varying
the spacing and burden. They concluded from the study that the current drill and
blast parameters of the mine result in finer fragmentation than the desired. Blast
optimization has been successfully carried out using Kuz-Ram model.
2.1 OBJECTIVES
1) Fragmentation analysis of existing blast using Split-Desktop software
CHAPTER III
METHODOLOGY
3.1 METHODOLOGY FLOW CHART
The result of automatic delineation is a binary image (2 grey levels, black and white)
that contains white particles and a black background. The black areas in these images contain
fine material too small to delineate in addition to the unfiled air space between particles.
This black area is very important in estimating the amount of fines.
3) EDITING OF THE DELINEATED BINARY IMAGE
In most muck pile images and in many images from other sources such as haul trucks
or leach piles, there are instances when the automatic delineation algorithms in Split-
Desktop will not delineate the fragments properly. This may be due to situations where the
lighting is poor, there is abundance of fines in the image, and the image quality is low or
other reasons. In these cases, the binary file containing the delineated fragments needs to be
edited using hand editing tools in the program.
There are three common cases where minor editing is needed. First of all, if there are
large patches of fines in the image, Split-Desktop sometimes mistakes these patches as a
single large fragment. Secondly, if there is excessive “noise” on a fragment (due to bedding,
rock texture, etc.), the Split-Desktop program may split this fragment into a number of
smaller fragments. Thirdly, some of the delineated particles are neither rock fragments nor
fines.
Split-Desktop has built in editing capabilities to handle the situations described
above. The program first makes a stack of images, where one file in the stack is the
delineated image and the other file in the stack is the original grayscale image. The user can
quickly toggle between the original and delineated images to determine which parts of the
image need editing. Three kinds of editing are most common: paint bucket filling of fines,
erasing unwanted delineations, and identifying non-rock features. In most cases the images
can be edited by a skilled user in less than 5 minutes.
4) SIZE ANALYSIS
Once the individual fragments in the images have been delineated, the next step is to
use characteristics of the fragments to calculate their size distribution. These characteristics
include the area and dimensions of each fragment and the area of the non-particle regions.
The second step is to determine a realistic distribution for the fine material. Two options for
the distribution within the fines are available in Split-Desktop, a Schumann distribution and
a Rosin-Rammler distribution. Each of these distributions has two unknown parameters and
these parameters are determined from two known points in the size distribution, one point
at the fine size and the other at 1.5 times the fine size. The part of the size distribution curve
represented by the fine assumption is shown in grey.
3.1.2CALCULATION METHOD
CHAPTER IV
4.1 FIELD VISIT
M/s Dalmia Cement (Bharat) Limited (DCBL), one of the leading cement
manufacturing companies in India operating its cement plants at Tamilnadu, Andhra
Pradesh, Karnataka, Orissa, Assam and Meghalaya. In Tamilnadu, two plants are located at
Trichy and Ariyalur districts. The production capacity of each plant is 2.4 million and 2.0
million tons per annum respectively. The raw material requirements of these plants are
accomplished from its captive mines operating at various locations in Trichy and Ariyalur
districts. The Amalgamated Periyanagalur, Aminabad & Khairulabad Limestone Mines is
located at Ariyalur district and it is planned to mine around 1.9 million tons of limestone per
annum to supply cement plants located in Dalmiapuram and Ariyalur.
The limestone deposit in this area is of sedimentary origin and is placed in the middle
Ariyalur stage of the Upper Cretaceous formations of the Indian Stratigraphy, which was
formed, in Marine Transgressional environment. The rocks in these region form part of the
marine sedimentary formation of cretaceous age and referred to Kallankurichi formation of
Ariyalur stage. The Kallankurichi formation is overlaid by Nallamedu formation and under
lained by Sillakkudi formation. A massive ruddiest bivalve carbonate shell bank underlain
by conglomerate bed at the base, is approximately aligned in North- South direction with a
maximum thickness of 40 m. The limestone are hard and compact having large Gryphea,
Terebratulids, Alectryonia and a host of other brachiopod species were identified.
by drilling and blasting. Drill Holes of 115mm diameter are which has got a self-provision for
water sprinkling while drilling which reduces dust emission. Blasting is carried out using Slurry
Explosives & ANFO initiation by Milli Second Electric Delay Detonators (MSDD) and
NONEL Shock tubes. The blasted limestone is loaded with the help of Hydraulic excavators
and Wheel loaders and transported by 31 tons Tipping Taurus to the crusher hopper located
at Dalmiapuram and Ariyalur plant.
Drilling costs
Parameters Costs (Rs/hr)
Blasting costs
Parameters Values
No. of holes 59
Booster% 8%
ANFO% 92%
DED (Nos) 4
Blasting Costs
Items Quantity Costs (Rs)
Booster (Rs.70/kg) 88kgs 6,160
AN Prills (Rs.45/kg) 1000kgs 45,000
DED (Rs.15) 4 Nos 60
Shock Tube 200ms/8m (Rs.85) 59 Nos 5,015
Labour cost (Rs.400/each) 6 Nos 2,400
Total costs 58,635
Table 5: Blasting costs
Fig 3. Size distribution curve and percentage of various fragment sizes of trail blast-1 by split
desktop software
The mean fragment size (K50) produced from blast 1 is 67.09cm. Optimum feed size for
crusher is 60cm, here the fragment size above 60cm is considered to be boulders. The
percentage of boulder formed is 57% of total volume produced.
Trail Blast 2
Time Study of Driller for Blast 2
Activity Time duration
(mins)
Total time spent 960
Setup & adjustments 60
Maintenance 60
Idle time 150
Shift changing time 120
Non-scheduled time 160
Production time 456
Table 7: Time study of drilling machine
Actual available time = 960-(60+60+150+120+160) = 410mins
Availability = (410/960) *100 = 42.70%
Utilization = (410/456) *100 = 89.91%
OEE = (0.4270*0.8991*100) = 38.39%
Net Production Rate = (0.38*30.66*3*3.5*2) = 244.67 t/hr
Drilling costs
Parameters Costs (Rs/hr)
Blasting costs
Parameters Values
No. of holes 41
Booster% 8%
ANFO% 92%
DED (Nos) 4
Blasting costs
Items Quantity Costs (Rs)
Booster (Rs.70/kg) 62 kgs 4,340
AN Prills (Rs.45/kg) 750 kgs 33,750
DED (Rs.15) 4 Nos 60
Shock Tube 200ms/8m (Rs.85) 41 Nos 3,485
Labour cost (Rs.400/each) 6 Nos 2,400
Total costs 44,035
Table 10: Blasting costs
Fig 5. Size distribution curve and percentage of various fragment sizes of trail blast-2 by split
desktop software
The mean fragment size (K50) produced for trial blast 2 is 56.54cm. The percentage of
boulder formed is 47% of total volume produced.
SUGGESTED BLAST
Time Study of Driller for Blast 2
Activity Time duration
(mins)
Total time spent 960
Setup & adjustments 60
Maintenance 60
Idle time 150
Shift changing time 120
Non-scheduled time 110
Production time 490
Table 12: Time study of drilling machine
Actual available time = 960 – (60+60+150+120+110) = 460mins
Availability = (460/960) *100 = 47.92%
Utilization = (460/490) *100 = 93.88%
OEE = (0.4792 * 0.9388 * 100) = 44.99%
Net Production Rate = (0.44 * 31.33 * 3 * 3 * 2) = 248.13t/hr
Drilling costs
Parameters Costs
(Rs/hr)
Hourly owning cost 637.20
Blasting costs
Parameters Values
No. of holes 57
Booster% 8%
ANFO% 92%
DED (Nos) 4
Blasting costs
Items Quantity Costs (Rs)
Booster (Rs.70/kg) 57 kgs 3,900
AN Prills (Rs.45/kg) 598 kgs 26,910
DED (Rs.15) 4 Nos 60
Shock Tube 200ms/8m (Rs.85) 57 Nos 4,845
Labour cost (Rs.400/each) 6 Nos 2,400
Total costs 38,205
Table 15: Blasting costs
Fig 7. Size distribution curve and percentage of various fragment sizes of Suggested Blast by Split-
Desktop Software
The mean fragment size (K50) is produced from Suggested Blast is 48.44 cm. The percentage
of boulder formed is 38% of the total volume produced.
Costs comparison
Items Blast 1 (Rs/t) Blast 2 (Rs/t) Suggested blast
(Rs/t)
Drilling costs 4.85 5.98 5.89
Blasting costs 9.92 9.00 8.26
Total costs 14.77 14.98 14.15
By comparing the three blasts, it is clear that the costs of Drilling and Blasting is optimized in the
suggested blast.
REFERENCE
1) F.I. Siddiqui, S.M.Ali Shah & M.Y.Behan “Measurement of size distribution of
blasted rock using digital image processing” 2009.
2) Mohammad Farouq Hossaini, Rostam Ghafoori, Alireza Yarahmadi, Mehdi
Pourghasemi “Effect of dynamic elastic properties of rock on fragmentation in
Choghart Ironore Mine” 2013.
3) Zubair Ahmed Nizamani, Shahzad Ali Rajput, Sanaullah Bhoot, Nasir Ali Magsi
“Measurement of size distribution of blasted rock using digital image processing”
2013.
6) Tavakol Elahi and Hosseini “Analysis of blasted rocks fragmentation using digital
image processing (case study: limestone quarry of Abyek Cement Company)” 2017.
7) Julio Cesar de Souza, Carlos Santos da Silva, Suelen Silva Rocha “Analysis of
Blasting rocks prediction and rock fragmentation results using Split-Desktop
software” 2017.