Analysis, Design and Applications: The PCC Piling Method

Download as pdf or txt
Download as pdf or txt
You are on page 1of 144

The PCC piling method

Analysis, design and applications

Master Thesis Geotechnical Engineering


Faculty of Civil Engineering Delft University of Technology

Wouter Karreman
1004956
August 2006

1
The PCC piling method

The PCC piling method


Analysis, design and applications

Master Thesis as a final work on the study of Civil Engineering


at the Delft University of Technology

Wouter Karreman

Graduation committee
Prof. dr. ir. A.F. van Tol (Delft University of Technology, Geotechnical Engineering)
ing. H.J. Everts (Delft University of Technology Geotechnical Engineering)
Dr. ir. C. van der Veen (Delft University of Technology, Structural and Building Engineering)

Front page photo: PCC pile installation [Michiel van der Ruyt]

2
The PCC piling method

Preface

This is report titled “the PCC piling method” was written as a finalization of my Master
study in Delft at the Geotechnical Engineering section of the Faculty of Civil engineering of
the Delft University of Technology.
The research on the PCC piling method was done in the framework of the
cooperation between the geotechnical institutes of GeoDelft, Delft and GeoHohai, Nanjing,
China. I was allowed to go to Nanjing to study the PCC piles and bring back information on
the possibilities of this system.
I would like to thank the members of my graduation committee, prof. dr. ir. Van Tol,
ing. Everts and dr. ir. Van der Veen for their guidance and support during the months of my
study in Delft.
At GeoDelft I would like to thank mr. Martin van Staveren for creating the possibility
for me to visit GeoHohai and making all sorts of arrangements make my stay there as
enjoyable as it was. Thanks also go out to all my colleagues at the departments of foundation
engineering and construction and soil constructions for their support during my study. I
would especially like to thank Ad Verweij for his useful comments and discussions which were
sometimes even about the PCC pile.
Last but certainly not least I would like to thank all the members of GeoHohai for
their warm welcome and great support in my study. Special thanks go out to prof. Liu
Hanlong, Dr. Zhou Yundong, Dr. Zhang Ting and Dr. Tan Hiuming. All the students of prof.
Liu with whom I shared an office are thanked for their support and tireless efforts to show
me as much of Nanjing and China as possible in the short time of my stay.

Delft, August 31, 2006

Wouter Karreman

3
The PCC piling method

Summary

At the GeoHohai research institute at Hohai University in Nanjing, China a new


ground improving piling system is developed. The function of this system is to minimize the
settlements and differential settlements after the construction of an embankment on soft soil.
The PCC pile is an open, cast-in-place, hollow, concrete tube pile constructed using a
casing consisting of two steel pipes with different diameter placed inside of each other. The
space between the two pipes is closed off at the bottom and the pile is vibrated into the soil.
At the design depth concrete is cast in the hollow area created between the two pipe piles
and the casing is retracted. This process opens the closure between the two casings allowing
the concrete tube to remain in the soil while the casing is being retracted. The final pile has a
diameter of 1.0 to 1.5 m, a wall thickness of 100 to 150 mm, a length of up to 25 m and a
centre-to-centre distance of approximately 3 to 3.5 m. On the complete pile field a geotextile
mattress consisting of 3 layers of geotextile with gravel in between is laid to redistribute the
load of the fill to the piles. It is found that the installation speed is quite slow but that by
streamlining the concreting a lot of time can be gained.
Several tests can be done to verify the quality of the single pile and the entire soil
improvement. These include low strain test, load tests on single piles and on the composite
foundation, partly excavations and long term monitoring. The results of these tests point to
the PCC pile having a high and consistent quality. Some possible problems noted to occur in
the Netherlands during construction of cast-in-place piles, like demixing of the concrete at
higher depths of the pile and necking are not yet sufficiently addressed.
A comparison is made between the PCC piling method and two new ground
improving piling systems developed in the Netherlands, the HSP and the AuGeo piling
methods. Both the HSP and AuGeo systems apply small cast in place solid concrete pile with
diameters ranging from 150 to 180 mm and lengths up to 17 m. They can be installed much
faster than the PCC pile and with reinforcement but have lower bearing capacity and smaller
spacing. A rough comparison shows that a field of PCC piles would it be applied in the
Netherlands can be made faster than an AuGeo pile field with slightly more concrete. In thick
layers of soft soil the PCC pile’s advantage of high shaft bearing over HSP and AuGeo
because more prevalent.
The currently used design methods in China for the bearing capacity and settlement
of the PCC pile and the pile improved area are very simple and are not according to the
Dutch norms. A detailed calculation method for the single pile bearing capacity and
settlement has been obtained from the Dutch norms and the advice for plugging calculations.
The method includes:
• Shaft bearing capacity,
• Negative skin friction,

4
The PCC piling method

• Plugging according to the spring method and


• Tip bearing capacity.
The calculation method was verified on the Yan-Tong case where load tests were
executed on a single PCC pile. The results of the calculation, based on the soil investigation in
the area, closely approximated the measured bearing capacity and settlement.
The high quality and high single pile bearing capacity open the door for the
application of the PCC pile in other cases then soil improvement. Two cases are considered:
• PCC pile in building foundation in the Rotterdam area including tension forces due to pull-
out and head moments and comparison to the Vibro-pile and
• PCC pile in bridge abutment where the pile is subjected to horizontal forces and the
resulting bending moments in the pile.
When applied in a building foundation it was found that the bearing capacity of the pile when
placed 2 m into a stiff sand layer is a little higher than that of the Vibro pile per unit of
concrete. The unique shape of the pile also reduces the tension forces due to the bending
moment when the pile is loaded eccentrically. This same reduction compared to solid piles is
found in the application of the PCC pile in a bridge abutment. Some tension forces are
however occurring in the pile and reinforcement is found to be required.
Three reinforcement methods are discussed:
• Traditional reinforcement which is cheap but due to the required reinforcement netting
difficult to apply,
• High strength reinforcement which requires less bars and netting but is susceptible to
corrosion and expensive and
• Reinforcing with steel fibres which has no problems with netting and cover but add only a
limited tension strength.
Installation of the reinforcement into the thin walled casing is a difficult problem with the
attachment of the bars to the casing as a possible solution.
Import conclusions of the report are:
• Application of the PCC pile in the Netherlands as a ground improving method is viable in
many cases and a robust design and installation method is available and
• The PCC pile is applicable in foundations and bridge abutments, if necessary
reinforcement is possible.

5
The PCC piling method

1 Introduction ............................................................................................................9
2 Research question ................................................................................................. 11
2.1 Problem Definition ......................................................................................... 11
2.2 Aspects ........................................................................................................11
2.2.1 Execution..................................................................................................11
2.2.2 Pile quality ................................................................................................11
2.2.3 Comparison pile based ground improvement................................................ 11
2.2.4 Cost .........................................................................................................11
2.2.5 Bearing capacity........................................................................................ 11
2.2.6 Improvements for foundation application..................................................... 12
2.2.7 Comparison pile foundation ........................................................................ 12
3 The PCC pile..........................................................................................................13
3.1 Introduction.................................................................................................. 13
3.2 Installation method ....................................................................................... 13
3.2.1 Introduction.............................................................................................. 13
3.2.2 Installation Method.................................................................................... 13
3.2.3 Equipment and personnel........................................................................... 16
3.2.4 Attention points......................................................................................... 19
3.3 Quality assurance ..........................................................................................24
3.3.1 Introduction.............................................................................................. 24
3.3.2 Low strain test .......................................................................................... 24
3.3.3 Excavation ................................................................................................ 26
3.3.4 Load test .................................................................................................. 28
3.3.5 Long term settlement monitoring ................................................................ 31
4 Comparison other methods ..................................................................................... 36
4.1 Introduction.................................................................................................. 36
4.2 HSP..............................................................................................................36
4.2.1 Introduction.............................................................................................. 36
4.2.2 Pile properties ...........................................................................................37
4.2.3 Installation process.................................................................................... 37
4.3 AuGeo ..........................................................................................................38
4.3.1 Introduction.............................................................................................. 38
4.3.2 Pile properties ...........................................................................................38
4.3.3 Installation process.................................................................................... 39
4.3.4 Quality control...........................................................................................40
4.4 Comparison .................................................................................................. 41
4.4.1 Introduction.............................................................................................. 41

6
The PCC piling method

4.4.2 General ....................................................................................................41


4.4.3 Construction ............................................................................................. 41
4.4.4 Economic comparison ................................................................................ 41
4.4.5 Conclusion ................................................................................................42
4.5 Conclusion ....................................................................................................43
5 Calculation method ................................................................................................44
5.1 Introduction.................................................................................................. 44
5.2 Bearing capacity............................................................................................ 44
5.2.1 Introduction.............................................................................................. 44
5.2.2 Chinese practice ........................................................................................ 44
5.2.3 Dutch practice........................................................................................... 46
5.2.4 Negative shaft friction................................................................................ 51
5.2.5 Plugging ................................................................................................... 54
5.2.6 Soil bearing capacity.................................................................................. 66
5.3 Settlement.................................................................................................... 68
5.3.1 Chinese practice ........................................................................................ 68
5.3.2 Dutch practice........................................................................................... 72
5.3.3 Piled raft and pile group responses ............................................................. 74
5.4 Yan-Tong example case ................................................................................. 82
5.4.1 Introduction.............................................................................................. 82
5.4.2 Site description .........................................................................................82
5.4.3 Chosen calculation methods ....................................................................... 84
5.4.4 Bearing capacity single pile ........................................................................ 85
5.4.5 Soil bearing capacity.................................................................................. 92
5.4.6 Bearing capacity composite foundation........................................................ 92
5.4.7 Settlement single pile................................................................................. 93
5.4.8 Settlement of the composite foundation ...................................................... 95
5.5 Conclusion ....................................................................................................96
6 Further applications ............................................................................................... 98
6.1 Introduction.................................................................................................. 98
6.2 Requirements................................................................................................ 98
6.2.1 Introduction.............................................................................................. 98
6.2.2 Vertical loading .........................................................................................98
6.2.3 Horizontal load ........................................................................................ 101
6.2.4 Settlement .............................................................................................. 101
6.3 Case studies ............................................................................................... 102
6.3.1 Introduction............................................................................................ 102
6.3.2 Case 1: Foundation on tip bearing ............................................................ 102

7
The PCC piling method

6.3.3 Case 2: Piled bridge abutment .................................................................. 112


6.3.4 Conclusion .............................................................................................. 114
6.4 Reinforcement ............................................................................................ 115
6.4.1 Introduction............................................................................................ 115
6.4.2 Traditional reinforcement ......................................................................... 115
6.4.3 Dywidag bars .......................................................................................... 116
6.4.4 Fibre reinforcement ................................................................................. 117
6.5 Design changes........................................................................................... 121
6.5.1 Introduction............................................................................................ 121
6.5.2 Reinforcement......................................................................................... 122
6.5.3 Pile properties ......................................................................................... 124
6.5.4 Equipment .............................................................................................. 124
6.6 Conclusion .................................................................................................. 125
7 Conclusions and recommendations ........................................................................ 127
7.1 Conclusions................................................................................................. 127
7.2 Recommendations ....................................................................................... 128

8
The PCC piling method

1 Introduction
During and after construction of embankments on soft subsoil large settlements often
occur due to the consolidation and creep of the soft material. Because of the load on the soil
caused by the embankment, excess pore pressures occur. The outflow of water leads to a
volume loss of the soft soil.
The consolidation time and settlement are mainly dependent on the thickness and
permeability of the soft soil layers but can be years and meters. This can cause problems
during construction of, for example, a highway embankment for which after a certain period
of time only small settlements are allowed. Differential settlements, where some parts of the
construction settle more than others, can also occur in inhomogeneous subsoil.
To reduce the settlement several soil improving methods are available. One of the
methods is placing the embankment on piles. Several methods for this kind of ground
improving piles are available all over the world.
In recent years the Chinese Geotechnical Institute of HoHai University in Nanjing
(GeoHohai) has developed a new ground improving pile system, the PCC piling system. The
PCC pile is essentially a hollow, cast in place, concrete pile. This pile has an advantage over
solid concrete piles in that it can obtain a higher shaft resistance with the same amount of
concrete. The main advantage over pre-casting is that no reinforcement is needed to prevent
damage during transportation.
During construction a hollow double steel casing is vibrated into the subsoil. The
space between the two casings is sealed at the pile tip while vibrating the pile into the soil.
The seal, see figure 1-1, consists of several spring plates attached to the outer casing, which
will be pushed against the inner casing due to the vertical downward movement.

Figure 1-1: Seal that connects the two tubes [33];

9
The PCC piling method

After vibrating the double casing to its appropriate depth the space between the
casings is filled with a grout mix. The grout mix is poured through an opening at the top part
of the double casing, see figure 1-2.

Figure 1-2: Casing with pour mouth at the top [33];

The total amount of grout mix depends on the length of the pile and the width of the
hollow space between the two casings. After filling the space between the casings, the pile is
vibrated out of the soil while approxrimately 30% additional grout mix is added to
compensate for expansion and volume loss due to the vibration. The top 0.5 m of soil above
the pile is excavated and replaced by concrete to provide a solid concrete head at the top of
the pile.
This type of soil improvement has been used effectively for several projects in thick
soft soil layers in China. It might therefore be interesting to apply this method in the soft soils
of the Netherlands, as a ground improving method or as a foundation pile. To determine if
the PCC method is viable in the Netherlands an analysis of the method and a comparison with
existing soil improving piles and foundation piles will have to be made. The purpose of this
Master Thesis is to provide this analysis and comparison.

10
The PCC piling method

2 Research question

2.1 Problem Definition


To reduce settlement and provide stability to embankments, GeoHoHai has
developed the PCC pile. To determine if this type of pile is viable in the Netherlands as a
ground improving method and/or as a foundation pile, the technical and economical feasibility
needs to be determined. This includes an analysis of the execution method, the calculation
method and a comparison with existing ground improving methods and foundation piles.

2.2 Aspects

2.2.1 Execution
The execution method of the PCC pile will be analysed. During execution of cast-in-
place piles certain problems can be expected. Demixing of the grout can, for example, occur
which can result in the forming of gravel arches that prevent the grout from filling the entire
volume of the hollow space.

2.2.2 Pile quality


The quality of the pile determines its ability to function. A pile that is not continous
over its length or has other failures can have a lower bearing capacity than designed. The
quality of the pile can be determined by a number of tests.

2.2.3 Comparison pile based ground improvement


At the moment several types of piles are used in the Netherlands for ground
improvement purposes. Two of the newest methods, HSP and Augeo piles, will be reviewed
and compared to the PCC piling method.

2.2.4 Cost
The cost of the pile is dependent on the material, the equipment, the personnel
required and the installation time. Differences between the Netherlands and China in cost
ratios between these categories can be expected.

2.2.5 Bearing capacity


The lateral and vertical bearing capacity of the PCC piles, and the method in which
these are calculated, is very important to determine the effectiveness and applicability of the
PCC pile in the Netherlands.

11
The PCC piling method

2.2.6 Improvements for foundation application


For application of the PCC method in foundations of buildings some adjustments will
have to be made. Reinforcement of the head or of the entire pile can, for example, be
considered.

2.2.7 Comparison pile foundation


At the moment several types of piles are used in the Netherlands for foundation
construction. A comparable foundation piling system, the Vibro pile, will be considered and
compared to the PCC pile.

12
The PCC piling method

3 The PCC pile

3.1 Introduction
A general introduction on the PCC pile is given in chapter 0. In this chapter the
installation method and quality assurance of the PCC pile will be described in detail.
In paragraph 3.2 the installation method is discussed based on observations in the
field and available literature. Required equipment and personnel are described and attention
points during installation including possible solutions are discussed.
In paragraph 3.3 the quality assurance during and after construction is described
from the results of different tests executed at the Yan-Tong project.

3.2 Installation method

3.2.1 Introduction
This chapter gives a description of the installation method based on the observation
of the installation of two PCC piles and available literature on PCC pile installation. This
chapter also contains an analysis of the attention points during PCC pile installation is
obtained based on past experiences from literature.
The observed PCC pile installation was part of the construction of an embankment for
a secondary road just outside Nanjing, the Jin Yang Road in ZhenJiang. The piles where
installed to a depth of 15.4 m below ground level and have a 1000 mm outer diameter, a 120
mm wall thickness and a centre-to-centre distance of 3 m. The subsoil consists of
approximately 2 m thick stiff clay on a thick base of softer clay.
The PCC piles are applied in this case to limit the settlement due to compression of
the soft soil by redistributing the load of the embankment to the stiffer lower clay layers via
the shaft and tip bearing of the piles. The load of the embankment is brought to the piles by
application of a geotextile mattress which is laid on top of the piles [18]. This application of
the PCC pile is the most common in China at the moment of writing.

3.2.2 Installation Method


The installation method consists of roughly four steps, which are extensively
explained in the following paragraphs:
• Vibrating the steel casing into the soil,
• Pouring the concrete,
• Vibrating the steel casing out of the soil and
• Installation of the pile head.

13
The PCC piling method

Vibrating the casing into the soil


A double walled steel casing is vibrated into the soil using a double headed vibratory
hammer. The casing is closed with flaps at the pile tip, see figure 3-1.

Figure 3-1: The flaps at the tip of the pile are closed using a temporary steel wire;

The flaps are closed during installation with a steel wire to prevent penetration of water and
soil into the open area between the two steel tubes. The casing is then pushed into the soil,
firstly using only the dead weight of the hammer and the installation platform to minimize
vibration, later also with help from the vibratory hammer. The process is continuous with a
speed of 3-4 m/min (dependent on soil resistance) until the design depth is reached. An
alternative for the use of the flaps is using a concrete expendable driving shoe to close off
the area between the two piles [18].
The driving, vibration and squeezing effects of the penetration, and to a certain
extent the extraction, of the casing compacts the soil. The degree of this compaction depends
on the wall thickness, the vibratory hammer and the soil properties.
In this project there is an existing landfill of 2 m on the top of the soft soil layers. If
the building manager suspects that this landfill is heavily compacted, for example if the pile is
installed on a route used by the concrete truck, the pile is installed slightly differently. First
the pile is pushed through the fill and then pulled out and cleaned before pushing it in again.
This is to prevent the stiff fill material from blocking the opening of the flaps in a later stage.

Pouring the concrete


When the design depth is reached, concrete is added through shunt at the top of the
pile, see figure 3-2.

14
The PCC piling method

Figure 3-2: Pouring of the concrete;

The annulus area between the two steel pipes is filled with concrete until above
ground level. By hitting the outer pile with a hammer and by experience the level of the
concrete can be estimated. The pressure of the concrete column breaks the wire and opens
the flaps at the tip of the pile. If for any reason the flaps do not open, the pile is retracted,
cleaned and installed again. The concrete is produced in a small concrete plant on site, see
figure 3-3. Alternatively the concrete can be delivered by truck from a regular concrete plant,
but this is less economical.

Figure 3-3: Concrete plant on site;

Vibrating the steel casing out of the soil


When a sufficient level of concrete is reached the casing is vibrated out of the soil at
a speed of 3-4 m/min. At certain times the extraction is stopped to add more concrete to
compensate for the loss of volume due to outflow and compaction of the concrete and the
filling of the volume of the walls of the tubes. The added quantity of concrete is 10-40% for
most projects but depends on the soil properties; in this case 30% was found to be sufficient.
After a few piles the value is known by the crew and no further monitoring of the concrete
level is required. A sufficiently large volume is added in order to ascertain that when the

15
The PCC piling method

casing leaves the ground there is still concrete left in the annulus area, thus guaranteeing a
continuous pile.

Figure 3-4: Sufficient concrete is added during extraction of the casing;

Installation of the pile head


After the concrete has had sufficient time to harden, the top 0.5 m of the inside of
the pile is excavated by the construction crew using shovels. Concrete with the same
properties as the pile is cast into this top 0.5 m to assure a good connection between the
geotextile mattresses placed over the piles, see figure 3-5.

Figure 3-5: Excavated and concreted pile head [20];

3.2.3 Equipment and personnel


The required equipment for the installation of the PCC pile is the following:
• Jacket,
• Vibratory Hammer,
• Casing and
• Concrete Plant.
Personnel are required to man all the installation equipment.

16
The PCC piling method

Jacket
The components of the installation jacket are shown in figure 3-7.

Figure 3-6: Jacket overview; Figure 3-7: Components of installation jacket [18];

The jacket is able to move itself on two rails connected to the base, see figure 3-8. During
installation, the tube at the side of the pile can be moved while the jacket rests on the pile.

Figure 3-8: The jacket can move itself, to the right the control station can be seen;

The movement of the jacket is controlled from the base; the vibratory hammer is also
controlled from here. The winch used for lifting the concrete container to the shunt is
remotely controlled the concreting crew.

Vibratory Hammer
For the installation of the casing a double vibratory hammer is mounted in such a
way that the two hammers reduce the horizontal movement and amplify the vertical

17
The PCC piling method

movement of the casing. In this case he double vibratory hammer can develop a pressure of
48 t on the casing and the dead weight of the jacket and hammer of 30 t, see figure 3-9. If
the force delivered by the dead weight of the jacket is insufficient for installation the vibratory
hammer is used. The high capacity of the hammer and the deadweight are to ensure a high
penetration speed of 3-4 m/min. The type of hammer used in the installation depends on the
properties of the subsoil.

Figure 3-9: Vibratory Hammer;

Casing
The casing consists of two steel pipe piles with different diameters. The spacing
between the two pipes is 100 mm in this case. So the typical wall thickness is also at least
100 mm. The piles are connected at the tip with flaps, see figure 3-1. The flaps are closed
during installation with a steel wire to prevent penetration of water and soil into the area
between the piles. Each 4-5 m steel blocks are welded between the steel pipe piles to assure
a continuous wall thickness. A shunt is connected to the top of the casing to allow for entry
of concrete in the annulus area, see figure 3-7.

Concrete plant
The concrete plant for this project is located on site. The concrete quality is typically
C15-C20. This strength is considered enough, higher quality is more expensive to make and is
less fluid thus decreasing the workability. Additives are typically only used to guarantee
workability at low temperatures.

Personnel
The vibratory hammer and movement of the jacket are controlled by 1-2 men
personnel. The casting of the concrete is done by 2-3 men personnel. The concrete plant is
operated by 3 people and 1 person transports the concrete to the pile location. The total
personnel required for this project is 8 people, excluding building managers.

18
The PCC piling method

Time Planning
The installation time of the PCC pile in the Jin Yang Road project is approximately 50-
60 minutes per pile. This time is divided as follows:
• 2-3 minutes for moving the jacket to the pile location,
• 10 minutes for casing preparation and installation (highly dependent on geology) and
• 40-50 minutes for concreting and retracting.
As can be seen the concreting takes the most time; this is because the distance between the
concrete plant and installation site is quite large and approximately twenty batches (of 0.27
m3) of concrete are required to fill the pile.

3.2.4 Attention points


A few points of attention for the installation of the PCC piles are obtained from
literature. Most of the attention points are based on experiences with the Vibro pile which is
very similar in method of construction [43] and some general notes on pile installation [1].

Vibrating the steel casing into the soil


Attention points during the penetration of the steel casing into the soil are:
• Negative effects of vibration on adjacent piles
The vibration of the casing can have a negative effect on adjacent piles. The level of
the concrete can rise due to the installation of a pile close by due to the horizontal
displacement of the soil. If the level of the fresh concrete observed to be lowering during
installation of an adjacent pile an increase of the pile diameter is taking place due to
compaction of the soil.
• Negative effects of vibration on adjacent buildings
The installation can cause settlement of foundations of nearby buildings due to the
dynamic load on the foundation or the densification of the soil. This can lead to unwanted
settlements and/or damage to the buildings.
• Encountering rocks and debris
The soil can contain loose rocks and debris not detected by the soil investigation. If
encountered the installation of the pile can be blocked or seriously hampered. Damage to
the installation equipment can also occur.
• Water and soil entering the pile at the tip
Water and soil entering the tip of the pile during installation can have a negative
effect on the concrete quality at the pile tip. Mixing the concrete with soil and/or water
will reduce its quality and thus the bearing capacity of the entire pile.

19
The PCC piling method

To avoid the occurrence of problems a number of steps that can be taken is given below; first
the recommendations from [43] are given. After that the current practice as observed and
described in PCC literature is given.
• Negative effects of vibration on adjacent piles
Monitoring of the concrete level in the piles adjacent to the pile currently being
installed. If the concrete level in the pile increases a change in installation order has to be
considered. If the level in the pile lowers the distance between the piles should be
increased to three times the tip diameter. The visual inspection of the pile to 0.5 m below
ground level or the execution of low strain tests is advised [43].
In this project no steps are taken to monitor the adjacent piles, although the distance
between the piles is less than three times the tip diameter. Although vibration of the soil
can clearly be felt at the location of the adjacent piles the concrete level can not be
visually monitored because of the extra concrete cast on the pile head, see figure 3-4, so
no decrease or increase of concrete level could be observed.
• Negative effects of vibration on adjacent buildings
Monitoring of vibration and settlement in adjacent buildings. If the vibration and load
become larger than allowed, stop the installation. The damage can be minimized by
increasing the distance between the building and the PCC piles.
In this project no buildings are located adjacent to the construction. In general, if
buildings are located close to the pile installation, a vibration reduction trench is
sometimes used.
• Encountering rocks and debris
Sufficient soil investigation can minimize the chance of encountering rocks and
debris. If rocks are encountered that prevent further installation, the casing will have to
be retracted and installed somewhere else.
In this project rock and debris are not often encountered. In general, if soil
investigation determines rock to be located at planned installation locations the design is
changed. If rock is encountered during installation the decision to either construct a new
pile or leave the pile somewhat shorter than designed, falls to the designer.
• Water and soil entering the pile at the tip
To prevent water and soil from entering the pile tip, the tip has to be sufficiently
closed. After installation the presence of water in the shaft can be verified by use of
measuring tube on a line. The decision if the water level in the shaft is unacceptable lies
with the contractor, in general not more than 50 mm water and no soil can be accepted.
The PCC piles are closed of with steel wire over the flaps. No tests are done to
determine if water or soil has entered the pipe pile. In literature [18] it is mentioned that
concrete can be cast in the shaft just above the ground water table. Installation is then
continued. This was not observed in practice.

20
The PCC piling method

Pouring of the concrete


• Demixing of concrete
Demixing of the concrete has taken place when the gravel in the concrete is
separated from the cement. This can result in the formation of gravel ‘nests’ in the pile which
have a very low bearing strength. The demixing is dependent on the collisions of the concrete
with the steel. This effect will only have influence on the first few batches of concrete, this
will be explained below.
• Concrete penetration
The quality of the pile is heavily determined by the ability of the concrete to reach
every part of the pile. This depends on the quality of the concrete and the arching effect. The
arching effect is described in [43] as the creation of a concrete ‘arch’ over the diameter of the
wall, mostly on reinforcement rings. This arch prevents the penetration of more concrete in
the tube thus reducing the strength. An example of arching occurring in insitu concrete piles
(Vibro piles) is given in figure 3-10.

Figure 3-10: Arching over reinforcement ring in Vibro pile [43];

To avoid the occurrence of problems a number of steps that can be taken is given
below, first the recommendations from [43] are given. After that the current practice as
observed and described in PCC literature is given.
• Demixing of concrete
The demixing of the concrete is mainly caused by the interaction with (clean) steel.
The use of ‘clean’ steel equipment, for example at the start of the day will result in
cement forming a coating on the steel and thus demixing the concrete. The first batch of
concrete should therefore contain more cement or consist of only cement. Furthermore
the presence of obstacles during casting, for example reinforcement netting should be
minimized. If used large windows and thick reinforcement rods are preferred to small

21
The PCC piling method

diameter rods and small windows. The presence of broken gravel instead of rounded
gravel also increases the chances of demixing.
To avoid demixing of the concrete due to ‘clean’ steel pipe piles the contact areas are
treated with oil before the tubes are connected. This treatment is done at the start of the
project and is assumed to guarantee no demixing. The piles are cleaned at the end of
each day but the coating will stay on. No reinforcement is currently used in the PCC pile
but the contact area is relatively large compared to non-pipe piles. Except low strain
tests, minimal measurement is done to determine the concrete quality at the bottom of
the pile so no data on the demixing is available.
• Concrete penetration
As with demixing the concrete penetration is best when as little obstructions as
possible are present. The presence of horizontal reinforcement rings enlarges the chance
of arching and should be minimized. The pipe pile casing should have a constant
diameter of the entire length. The fluidity of the concrete has to be high enough to fill the
pile from the tip to ground level; the concrete can also be cast under pressure.
No reinforcement is present in the PCC pile casings and the fluidity of the concrete of
quality C15-C20 is considered high enough. Excavation of the top 5-10 m and low strain
tests are done to guarantee the continuity of the pile, see paragraph 3.3 but the pile tip
is not checked.

Vibrating the steel casing out of the soil


Attention points during the extraction of the steel casing are:
• Different permeability of soil layers
In permeable sand layers the concrete can drain very fast, while in less permeable
layers, the concrete will drain/harden much slower. After installation the diameter in the
lower part of the pile expands a little, this triggers some flow of wet concrete. The
concrete in the permeable layer will be less able to flow due to the fast drying. This can
lead to a loss of concrete in the transition area between permeable and non-permeable
layers, which results in the formation of a bottleneck. This effect is called necking, see
figure 3-11.

22
The PCC piling method

Figure 3-11: “Necking” in Vibro pile due to permeability differences in soil layers;

• Support pressure provided by soil


In very weak soils, like peat, the lateral support pressure provided by the soil may
not be sufficient to prevent outflow of the concrete..
• Compaction of the concrete
To assure sufficient bearing capacity the pile the concrete has to be compacted.
• Adding of the additional concrete
If the additional concrete is added while the tip of the casing is in a weak soil layer,
the diameter of the pile just under the casing will become oversized due to the pressure
of the concrete.

To avoid the occurrence of problems a number of steps that can be taken is given
below, first the recommendations from [43] are given. After that the current practice as
observed and described in PCC literature is given.
• Different permeability of soil layers
If different soil layers with large differences in permeability are encountered it is
advised to change the installation order of the piles to avoid increase of pile diameter due
to soil compaction following from adjacent pile installation. This to avoid the occurance of
“necking”.
The distance between the piles is considered sufficient to avoid this problem with the
PCC piles.
• Support pressure provided by soil
If not enough support pressure can be delivered by the soil it is better to use another
piling technique.
The soils where PCC piles are applied provide enough support pressure.
• Compaction of the concrete
The retraction speed has no influence on the quality if not higher then 3-4 m/min. It
is considered important [43] to jack the pile forty times in place after casting the concrete

23
The PCC piling method

(for vibro-piles) to let the trapped air escape. Compaction will not take place because
water is insufficiently able to escape from the casing.
When retracting the pile is vibrated in place for a short time and then retracted at a
speed of 3-4 m/min.
• Adding of the additional concrete
The additional concrete should be added while the head of the casing is in a relatively
stiff soil layer. After adding additional concrete some extra jacking has to be done (10
blows for Vibro piles). The concrete level should never fall below ground level.
During execution of the PCC piles it is monitored if the level of concrete is above
ground level. Extra vibration is done after adding concrete but no special care is taken to
add the concrete in stiff soil layers.

3.3 Quality assurance

3.3.1 Introduction
Next to the possibilities to assure the quality of the PCC pile during construction,
several methods are also available to verify the consistency, bearing capacity and predicted
settlement. This chapter gives an overview of the commonly used methods in China. These
are:
• Low strain tests,
• Excavation of the pile head,
• Load tests on single pile and pile treated area and
• Long term monitoring.
Results are shown from measurements of the Yan-Tong highway project [17].

3.3.2 Low strain test


The low strain test (or short wave test) is used to verify the length and integrity of
pile by sending a short wave through the pile and measuring the reflection. A picture of the
equipment can be seen in figure 3-12.

24
The PCC piling method

Figure 3-12: Pile integrity testing system, low strain [23];

Because of the special nature of the PCC pile it is unclear how the integrity can be
correctly verified with the low strain test. A recent study by GeoHohai on prefab hollow
concrete piles states that the full pile can be checked by testing two points on the pile, a
quarter of the perimeter apart, see figure 3-13.

Figure 3-13: locations for low strain test;

Low strain tests were executed on the piles of the Yan-Tong highway embankment.
Sixty piles were checked, some typical results are shown in figure 3-14.

25
The PCC piling method

Figure 3-14: Low strain test result for Yan-Tong highway [17];

Although some of the peaks in the test result are not so clear which can be attributed to the
shape of the PCC pile it is possible to determine the pile length and no obvious discontinuities
are observed.

3.3.3 Excavation
The pile heads of some piles are excavated to 5 or 10 m below ground level. This is
an excellent way to visually inspect the quality of the pile. Examples of excavated piles are
shown in figure 3-15.

Figure 3-15: Excavated pile heads [17];

26
The PCC piling method

From the excavation it can be seen that the inner surface of the PCC pile is smooth,
pile rupture, segregation of concrete and contraction of the diameter are not observed.
However at several piles a slight deflection of the pile head was observed and the wall
thickness was found to not be uniform. This phenomenon is likely to be caused by the extra
concrete that extrudes from the casing when the pile is finished. It is therefore advised to
remove the extra concrete after driving and lift the casing higher [17].
Measurements were also done to determine the wall thickness, see table 3-1.

Table 3-1: Measured wall thickness of PCC pile [17];

Design Average Minimum


Design value
value of value of wall value of wall
length of wall
Section Num. diamete thickness in thickness in
[m] thickness
r measure measure
[cm]
[m] [cm] [cm]
K30+740~ A8-21 15.0 1.0 12 13.9 13.6
K30+778 A4-10 15.0 1.0 12 14.1 13.6
K30+778~ A2-19 15.0 1.24 12 14.1 13.8
K30+808 A1-8 15.0 1.24 12 14.2 13.9
K30+808~ A6-22 15.5 1.0 12 14.0 13.6
K30+838 A10-20 15.5 1.0 12 14.3 13.8
K30+838~ A3-21 15.5 1.0 12 14.0 13.5
K30+868 A2-19 15.5 1.0 12 13.9 13.6
K30+868~ A4-3 15.5 1.0 12 14.2 13.9
K30+898 A6-4 15.5 1.0 12 13.9 13.6
K31+509~ A5-5 15.5 1.0 10 11.8 12.1
K31+559 A6-4 15.5 1.0 10 12.1 11.8
K31+559~ A8-3 15.5 1.0 12 14.1 13.8
K31+600 A3-2 15.5 1.0 12 14.2 13.9

As can be expected the wall thickness is larger than the design value (the distance
between the casings). The extra diameter is approximately 1.5 - 2 cm. For the head
excavation it was found that the minimum wall thickness was always found near the pile
head. It is advised to keep the pulling speed of the casing at 0.8 to 1.2 m/min at the pile
head to keep the wall thickness guaranteed [17].
Samples were also taken for uni-axial compression tests. The results are shown in
table 3-2.

Table 3-2: Compression test results [17];

Sample Compressive
Age
Section Num. depth Strength
[days]
[m] [MPa]
K30+740~ A8-21 2.0 21 38
K30+778 A4-10 10 24 45
K30+778~ A2-19 2.0 19 63
K30+808 A1-8 10.0 20 61
K30+808~ A6-22 2.0 21 70
K30+838 A10-20 10.0 23 77

27
The PCC piling method

K30+838~ A3-21 2.0 20 89


K30+868 A2-19 10.0 23 88
K30+868~ A4-3 10.0 19 67
K30+898 A6-4 2.0 22 65
K31+509~ A5-5 2.0 27 106
K31+559 A6-4 10.0 22 107
K31+559~ A8-3 2.0 21 66
K31+600 A3-2 10.0 24 72

It can be seen from the compression tests results that the compressive strength of
the concrete is always higher than the design value of C12/15 concrete of 15 N/mm2. It can
also be concluded that in general the compressive strength of the concrete becomes larger
with larger depth.

3.3.4 Load test


Load tests were executed on a number of piles. The principle of load testing is to find
the maximum load that can be sustained by a part of the construction. A pile can fail in two
ways: constructional (load is higher than strength of the pile shaft) or geotechnical
(deformation of the soil is higher than the deformation defined as failure). The test load can
be applied dynamically or statically. To divide the load over the pile cross section a cap plate
is placed over the pile head. The loading can be executed in 2 ways: the load (ballast) is
placed directly on the pile or the load is placed on the pile using a jack. The jack is placed
between the pile head and the loading frame [17].
In this case a ballast load is used, see figure 3-16. Four trial piles were chosen for the
static loading test of a single pile. The relationship curves of load Q and displacement s on
the top of piles are shown in figure 3-17.

Figure 3-16: Load test on single pile [17];

28
The PCC piling method

Figure 3-17: Load - settlement diagram static loading [17];

The length of all tested piles is 15.5 m, the diameter of piles A14 and A15 are 1000 mm and
the diameter of piles A5 and A6 are 1240 mm.
Based on the load settlement diagram, the limit bearing capacity of a single pile with
a length of 15 meter and a diameter of 1240 mm is found to be 1650 kN, 9% higher than the
theoretical design values [17]. The failure is geotechnical. The diameter of the piles A6-20
and A5-18 is 1240 mm and the other piles 1000 mm; it can clearly be seen that a larger
diameter gives a higher bearing capacity.
Load tests were also executed on two composite foundations. The composite
foundation is defined as a single PCC pile and its influence area of surrounding soil. This test
is done to better simulate a highway embankment. The equipment setup can be seen in
figure 3-18.

Figure 3-18: Test set-up for composite foundation load test [17];

29
The PCC piling method

The test is executed on an area of 3.3 by 3.3 m consisting of a single PCC pile and its
influence area. The results of the test are shown in figure 3-19.

Figure 3-19: Results of load test on composite foundation [17];

Pile A7-12 has a diameter of 1240 mm and a wall thickness of 120 mm while pile A7-18 has a
diameter of 1000 mm and a wall thickness of 100 mm. The slope of A7-12 is smaller than A7-
18, while the settlement is higher, which indicates that the settlement of PCC pile composite
foundation increases with the decrease of displacement ratio that is defined as the ratio
between the pile and soil cross-sections.
To study the working mechanism of PCC pile composite foundation under loads, the
inner soil, pile body and soil between piles are equipped with soil pressure boxes. These
boxes can monitor the soil pressure during every stage of the test loading, the test results
are shown in Figure 3-20.

Figure 3-20: Static load test on composite foundation, stress measurements [17];

30
The PCC piling method

It can be seen in figure 3-20 that the stress in both pile head and soil between piles
increases as the load increases, in the beginning there is only a small difference. When the
load is increased the load transfers to the pile head and a steep increase in the pile stress can
be seen while the soil pressure stays approximately constant. It can also be seen that the
stress in the inside soil stays very low during the test. Literature [19] indicates that the inner
soil of the PCC pile has little contribution to the bearing capacity. As a result, in Chinese
practice the effect of inner soil is neglected when calculating the bearing capacity of the PCC
pile in complicated soft soil foundations.
An overview of the load test results is shown in table 3-3.

Table 3-3: Results load tests on single piles and composite foundation [17];

Ultimate
Ultimate Settlement at Maximum
Total Loaded capacity
capacity the ultimate elastic
Pile load unto composite
pile capacity deformation
[kN] failure? foundation
[kN] [mm] [mm]
Area [kPa]
A5-18 1650 × 1650 13.63 7.53
K30+778
A6-20 1800 √ 1650 42.74 21.64
~K30+808
A7-12 2995 × 137.5 13.61 7.40
K30+868 A7-18 2700 × 124.0 12.11 6.18
~K30+898 A8-16 1500 √ 1350 50.98 12.81
K31+509 A14-10 1000 × 1000 13.18 6.22
~K31+559 A15-8 900 × 900 11.70 5.33

The piles loaded unto failure have an ultimate capacity of respectively 1650 and 1350 kN.
This corresponds to the outer diameters and wall diameter of 1240 mm and 120 mm and
1000 mm and 100 mm respectively. As can be expected the bigger piles have a higher
bearing capacity due to larger shaft friction and larger tip bearing. Measurements of the
ultimate capacity of the composite foundations are also influenced by the pile type 137.5 kPa
for the 1240/120mm piles and 124.0 for the 1000/100mm piles. Since the composite
foundation was not loaded unto failure no definite ultimate capacity can however be given.

3.3.5 Long term settlement monitoring


After pile installation the highway embankment is constructed over a period of seven
months. During this construction monitoring of settlement, soil pressure, differential
settlement, horizontal displacement and pore pressure is done. The different types of
monitoring for each area are shown in table 3-4.

Table 3-4: Long term monitoring per section [17];

Section Num. Monitoring content


1 K30+756.5 Surface settlement, soil pressure
2 K30+794.5 Surface settlement, differential settlement, horizontal displacement,
soil pressure, pore pressure

31
The PCC piling method

3 K30+822 Surface settlement, differential settlement, horizontal displacement,


soil pressure, pore pressure
4 K30+853 Surface settlement, differential settlement, horizontal displacement,
soil pressure, pore pressure
5 K30+884.5 Surface settlement, differential settlement, horizontal displacement,
soil pressure, pore pressure
6 K31+535.4 Surface settlement, differential settlement, horizontal displacement,
soil pressure, pore pressure
7 K31+578.8 Surface settlement, soil pressure

The surface settlement for section 1 is shown in figure 3-21. It can be seen that the
settlement of the pile is the lowest and the settlement of the centre of the embankment the
highest. The final settlement is almost reached for the pile settlement at 252 mm and 351
mm for the centre of the road. These values are much higher than that of the composite load
test; the difference can be attributed to consolidation and creep effects.

Figure 3-21: Settlement of section 1, K30+765.5 [17];

The rate of settlement is shown in figure 3-22. It is clearly visible that the settlement
rate increases when the last, larger, part of the fill is applied. As can be seen in Figure 3-21,
at first the soil settles more than the pile while the pile rate of settlement (shown by the
triangles in the graph) picks up late which indicates that a settlement of the soil is required
before the load is distributed to the piles. After a while the settlement of the pile and soil has
the same rate indicating that there is neither positive nor negative skin friction. The equal
settlement rate of soil and pile indicates that there is only compression of the soil layers
below the pile tip.

32
The PCC piling method

Figure 3-22: Settlement rate of section 1, K30+765.5 [17];

The difference in settlement rate can also be observed from figure 3-23, where the
differential settlement between the pile and the soil is shown. It is clear that the differential
settlement does not increase after December 25.

Figure 3-23: Different settlement between soil and pile of K30+756.5 [17];

Figure 3-24 gives an overview of the measured settlement of the soil next to the pile
with the depth. It can be seen that the largest settlements take place in the top layers since
this is the cumulative settlement of all layers but also that the soil below the pile tip settles
approximately 250 mm.

33
The PCC piling method

Figure 3-24: Settlement in depth of K30+794.5 [17];

From this and the previous graphs it can be concluded that the soil layers next to the
pile settle approximately 100 mm more than the pile while the group of piles and soil settle
another 250 mm due to compression of the layers below the pile tip.
Figure 3-25 gives an overview of the measured soil pressures. It is clear that the soil
pressure on the pile head reaches a much higher value than the soil pressure. It can also be
seen that the pressure on the top of the soil inside the pile is almost zero.

Figure 3-25: Soil pressure of K30+794.5 [17];

In figure 3-26, the pore pressure measured is presented. It can be seen that the
influence of the small load steps on the pore pressure is almost unnoticeable. For the small
load steps the reaction of the soil can be considered undrained. The last, and largest, load

34
The PCC piling method

step gives a large increase in pore pressure on all levels which indicates undrained behaviour.
After about three months the pore pressure is almost fully dissipated.

Figure 3-26: Pore pressure for K30+794.5 [17];

35
The PCC piling method

4 Comparison other methods

4.1 Introduction
The PCC pile is used in Chinese practice as a ground improving pile, part of the
research question is to determine the viability of the application of the PCC piling method in
Dutch practice, see paragraph 2.2.3.
To this end the PCC piling method is compared to two relatively new ground
improving piling systems developed by Dutch companies and applied in the Netherlands.
In paragraph 4.2 the HSP system developed by Voorbij Foundation Technics is
described and in paragraph 4.3 the AuGeo system developed by Cofra.
In paragraph 4.4 a comparison between the PCC piling method and the two Dutch
systems is made.

4.2 HSP

4.2.1 Introduction
The Voton-HSP system is developed by Voorbij Foundation technics as a cast-in-situ
ground displacing pile system [40]. The pile is installed using a vibrated steel casing. During
construction the concrete pressure, speed, resistance and depth are measured continuously.
The pile can be reinforced with traditional steel reinforcement or steel fibre reinforcement
and the length is, depending on local conditions, maximal 17 m. The production speed is
about 200 piles of 15 m per day.
Different types of HSP piles are:
• Standard, various reinforcement and diameter, used as standard pressure pile
• HSP VV, higher concrete pressure, used when higher bearing capacity is required
• HSP Renovation pile, steel tube, used for jacking inside of buildings with limited space.
• HSP tension element, production process is halted for reinforcement, used in under water
concrete floors.

36
The PCC piling method

Figure 4-1: Typical HSP field [40];

4.2.2 Pile properties


The pile is made with concrete of C20/25 or C30/35 grading. The standard pile
diameter is 170 or 180 mm but can be made larger if required for a project. The pile length is
2-17 m and can be varied per pile and the bearing capacity value for the standard pile is 250
kN. The reinforcement consists of one steel bar of 16 mm diameter and a length of 1.5 m,
but also 4 bars of 10 mm diameter can be used in a frame up to a length of 6.0 m.
Alternatively steel fibre concrete can be used. The practical minimum for the centre-to-centre
distance of the piles is 1.0 m.

4.2.3 Installation process


An overview of the installation process is shown in figure 4-2. First a test pile is made
without concrete to verify the computer program. The steel tube is vibrated into the soil using
a high frequency vibratory hammer. If necessary the process is supported by fluidization at
the tip of the pile. In the steel casing a tube is located for transporting the concrete. The tube
is closed of by a valve that is controlled by a central computer. When the required depth is
reached the valve is opened and the injection of concrete starts. The concrete pumping is
continuous and after the required pressure is reached the casing is pulled. If the available
winch force is not enough to pull the casing, the vibratory hammer is automatically used.
During the pulling of the casing concrete is added continuously so the concrete pressure
remains constant. At ground level the valve is closed automatically. The whole process takes
about two minutes and the installation machine can move on to the next pile location.
Heavy loads between the new piles have to be avoided to minimize horizontal
pressures. If reinforcement or the pile head is required it can be added at this stage. All the
processes are monitored and controlled by computer. Bottlenecks are avoided and a good
connection between the surrounding soil and the pile is obtained.

37
The PCC piling method

Vibratory hammer

Concrete mixture

Reinforcement

Valve

Figure 4-2: Construction method HSP [40];

Figure 4-3: Concrete mixer and pile installation equipment for HSP [40];

4.3 AuGeo

4.3.1 Introduction
The AuGeo system consists of lightweight piles with an enlarged pile cap and foot
founded in a stable sand or gravel layer. To limit the settlements of the soil the load of the
embankment is transferred to the pile caps by a geogrid mattress.

4.3.2 Pile properties


The pile properties are shown in table 4-1.

38
The PCC piling method

Table 4-1: AuGeo pile specifications [6]

AuGeo specifications
Casing material PE
Diameter [mm] 150
Wall thickness [mm] 14
Pile length [m] 2-15
Bearing capacity pile [kN] 150
Height fill [m] 1-7
Tension strength geotextile [kN/m] 50-350
Strain geogrid [%] <4

4.3.3 Installation process


Firstly borings are done to determine the expected pile tip depth, the foundation
layer thickness, the presence of stiff intermediate layers and the presence of soft layers under
the foundation layer. This last point is important to determine the chance of punching
through the foundation layer. If necessary a working layer of 1 m sand is placed to support
the installation equipment. The HDPE tube is cut to the required length and the cap is
attached to the tube, see figure 4-4.

Figure 4-4: AuGeo Tubes [6];

The pile is inserted using a drain “stitcher” commonly used for installing vertical
drains. The HDPE tube is loaded into a steel casing (mandrel) with dimensions 200x200x10
mm [34] which is pushed into the soil until a certain resistance is reached, see figure 4-5.

39
The PCC piling method

Figure 4-5: Loading the casing on the stitcher [6];

This resistance will mostly be found in layers with CPT values of 6 MPa and SPT
values of 12-15 blows per 300 mm or higher. At this depth the mandrel is retracted and the
casing is cut of at the required level.
Alternatively the mandrel can be pressed into the soil without the HDPE tube. In this
case the bottom plate is placed below the mandrel and pressed into the soil. At the design
depth the HDPE tube is placed in the casing.
Six steel reinforcement bars are placed into the casing and the casing is filled with
self-compacting foam concrete with a compressive strength of 30 N/mm2 after 28 days. A
concrete cap of 300x300x16 mm is placed on top [34]. The final bearing capacity of the 150
mm diameter pile will have a maximum value of 350 kN. The shaft bearing capacity is not
considered to add to the total bearing capacity.
The installation speed is about 20 piles per hour when a stable working floor is
present with the advantages of no vibration, no noise and no problems with heavy prefab
piles.

4.3.4 Quality control


A test field was executed in ‘s Gravendeel, The Netherlands [34]. Before installation
the verticality of the rig was assured. During installation the following data was logged:
position of the pile, soil resistance, maximum installation depth and resistance, amount of
piles installed and date and time. Low-strain tests (sonic wave tests) were executed to verify
the diameter of the installed piles. This is especially important at close pile spacing, when
newly installed piles can influence the quality of the piles already in place. Settlements of the
embankment were all well within the maximum allowance. Dynamic loading tests were also

40
The PCC piling method

executed which showed that the constructed embankment was suitable for trains with a
maximum speed of 350 km/h.

4.4 Comparison

4.4.1 Introduction
A comparison is made between the PCC piling method for soil improvement and the
HSP and AuGeo piling methods. The comparison is qualitative not quantitative and an
indication and a cost comparison will not be given but the comparison is based on the
construction method and bearing capacity.

4.4.2 General
In table 4-2 an overview of the properties of the different piles is given. It can be
seen that the PCC pile can be applied to a larger depth and has a larger diameter.

Table 4-2: Overview general properties HSP, AuGeo and PCC piles;

HSP AuGeo PCC


General Solid circular pile Solid circular pile Pipe pile
Maximum pile length 17 m 15 m 25 m
Embankment force Geotextile mattress Geotextile mattress Geotextile
redistribution (pile cap optional) and pile cap mattress
Diameter 170-180 mm 150 mm 1000-1500 mm
Wall thickness n.a. 14 mm 100-150 mm
Casing material n.a. HDPE n.a.
Type of fill material Concrete C20/25 or Foam concrete Concrete C12/15
C30/35 C27/30
Reinforcement Steel bars Steel bars or fibres none

4.4.3 Construction
In table 4-3 an overview of installation time and equipment per piling method is
given. The installation time of the PCC pile is much longer than the HSP and AuGeo piles and
requires more personnel to be constructed.

Table 4-3: Overview construction properties HSP, AuGeo and PCC piles;

HSP AuGeo PCC


Equipment Vibratory hammer Drain stitcher Double Vibratory
on rig hammer on rig
Force capacity Ca 55 tons 25 tons 78 tons
Pressing and retracting casing 2-3 minutes 2-3 minutes 10 minutes
Total time including filling 2-3 minutes* 2-3 minutes 45-60 minutes
Personnel required 3-4 persons** 6-7 persons** 8 persons
*installation device can move on before filling
**estimation

4.4.4 Economic comparison


A rough comparison between the PCC piling system and the AuGeo piling system
based on available data is made. For an embankment of approximately 5 m (equal to the

41
The PCC piling method

Yan-Tong case [17]) a typical PCC application is compared to a typical AuGeo application. Pile
data is taken from [17] and [34] and shown in table 4-4.

Table 4-4: Pile specifications for 5 m fill;

PCC AuGeo
Centre-to-centre distance 3.3 m 0.8 m
Number of pile per day 20 200
Pile cross section 0.41 m2 0.018 m2

Based on the measurements done at the Jin Yang Road project, see paragraph 3.2.3, the
PCC pile production per day would be assumed lower at approximately 10 piles per day.
However as already described there most time is spend by transporting the concrete from the
plant to the pile, it is roughly estimated that using concrete trucks and/or pumps about a
double pile production per day can be reached in the Netherlands.
If we assume a 26 m wide pile area with a length of 260 meter and the required pile
length would be 15 m for both types of pile, this would result in the requirements given in
table 4-5.

Table 4-5: Example case PCC and AuGeo, 5 m fill;

PCC AuGeo
Number of piles required 640 10890
Total construction time 32 days 54 days
Load on single pile 950 kN 55 kN
Volume of concrete 3940 m3 2940 m3

It can be seen that the construction time of the PCC piled embankment is about 60% that of
the AuGeo piled embankment, this because a much smaller number of piles is required. The
load on a single PCC pile, based on the assumption that the total load of the embankment is
placed on the piles, is much larger than that on a single AuGeo pile. However the PCC pile
has been proven to be able to sustain even larger loads, see paragraph 3.3.4. The volume of
concrete required is larger for the PCC pile.
It should be noted that in this rough comparison the required equipment and
personnel is not taken into account. Another very important not is that the centre-to-centre
distance of the PCC piles is based on the experiences in China where the soil properties are
different from the Netherlands. It is therefore required to determine if a distance of 3.3 m is
allowable in Dutch soil too. As can be seen the number of piles and thus the installation time
depends heavily on the centre-to-centre distance.

4.4.5 Conclusion
An overview of the advantages and disadvantages of the PCC pile compared to the
HSP and AuGeo piles is given in this paragraph based on the comparison given in the
previous paragraphs.
42
The PCC piling method

Advantages
• High shaft bearing capacity due to large circumference,
• High tip bearing capacity especially when plugged,
• Large application depth,
• Larger pile spacing reduces installation effects,
• Smaller construction time for entire project,
• Economical ratio between concrete and bearing capacity and
• Large pile head ensures good connection with geotextile.

Disadvantages
• Heavy machinery required during construction,
• Much personnel required during construction,
• More concrete required,
• Larger pile spacing requires more load redistribution so a thicker mattress,
• No reinforcement possible and
• Large circumference leads to larger negative skin friction (when applicable).

Analysis
From the economical analysis the PCC pile seems to be comparable to the AuGeo
piling system. The larger application depth of the PCC pile makes it an even more viable
solution in subsoil with deep stiff layers where its larger wall friction becomes a great
advantage. When a stiff layer at a depth of less than 15 meters below surface exists the PCC
is possibly more expansive to build than the AuGeo and HSP systems. Reinforcement is also
not yet possible for the PCC pile.
The high shaft bearing capacity and efficient use of concrete makes the PCC pile
applicable for the foundations of buildings on soft soil. This would however require some
reinforcement of the pile or pile head to sustain horizontal forces without damage.

4.5 Conclusion
The PCC pile is mainly applied in very thick (more than 20 m) packets of soft layers.
Its high shaft bearing capacity can effectively reduce settlements in this kind of subsoil. In
less thick soft layer packets when the pile tip can be placed in a stiff layer it is possibly a
competing method for the HSP and AuGeo.
With adjustments it might be possible to apply the PCC pile in building foundations.
Aspects that will have to be considered are:
• Bending moments,
• Bearing capacity,
• Connection to the foundation,
• Equipment adjustment.

43
The PCC piling method

5 Calculation method

5.1 Introduction
The possibilities for application of the PCC pile in the Netherlands are highly
dependent on the existence of a robust system for bearing capacity and settlement
calculations.
In paragraph 5.2 calculation methods for the bearing capacity of the PCC pile are
evaluated.
In paragraph 5.3 calculation methods for the settlement of the single PCC pile and
the composite foundation are evaluated.
In paragraph 5.4 a choice is made based on the evaluations and a number of
methods are applied to an existing case in the China.

5.2 Bearing capacity

5.2.1 Introduction
In this paragraph the calculation methods for the bearing capacity of the PCC pile
and the surrounding soil is given. First the Chinese practice is described followed by several
methods obtained from the Dutch practice adapted to the PCC pile. Two special aspects of
the PCC pile, negative shaft friction and plugging are described separately.

5.2.2 Chinese practice


The calculation method for the bearing capacity used by GeoHohai is fairly basic since
the maximum bearing capacity is mostly determined with pile load tests. Because of the
ground improving nature of the pile the bearing capacity is considered less important than
the ability of the pile to reduce settlement and increase the bearing capacity of the soil.
Nevertheless two methods are available for the calculation of the bearing capacity of the pile
improved soil:
• The most commonly used method is the separate calculation of bearing capacity of the
pile and the soil and addition of those bearing capacities.
• The second method is to consider the pile and soil to be one body and calculate the
bearing capacity of this body. This method is seldom used and no description is available.

Method: Separate calculation pile and soil


The bearing capacity is determined by separately calculating the bearing capacity of
the soil and the pile and adding the results under certain conditions. The allowable load on
the composite foundation consisting of soil and PCC pile is defined as:

44
The PCC piling method

pcf (5.1)
pcc =
K

where:
pcc bearing capacity of the composite foundation
pcf ultimate bearing capacity of the composite foundation
K factor of safety

The ultimate bearing capacity of the composite foundation is defined by:

p cf = K 1 λ1m ⋅ p pf + K 2 λ 2 (1 − m ) p sf (5.2)

where:
ppf ultimate bearing capacity of the PCC pile, from calculation or load test on a
single pile
psf ultimate bearing capacity of the soil, based on CPT and/or vane tests
K1 correction coefficient for the PCC pile in a composite foundation (generally
larger than 1)
K2 correction coefficient for the soil in a composite foundation (may be larger or
smaller than 1)
λ1 load factor PCC pile (smaller or equal to 1)
λ2 load factor soil (smaller or equal to 1)
m exchange ratio composite foundation
Ap
=
Atotal
Ap cross section of the pile in the horizontal plane
Atotal total influence area of the pile in the horizontal plane, for square pile layout
the square of the centre-to-centre distance

The factor K1 is used for the conversion of the bearing capacity of a single pile to the bearing
capacity of a pile group, including the strengthening effect on the soil caused by the pile
installation. The factor K2 describes the effect of the pile installation on the bearing capacity
of the soil. The factors K1 and K2 are based on the properties of the soil and experience. The
factors λ1 and λ2 are reduction factors for the determined bearing capacity depending on
whether or not the pile or soil is loaded to ultimate capacity. If the pile is loaded to bearing
capacity (λ1 = 1) and the soil is not (λ2 < 1) the formula for the bearing capacity becomes:

p cf = m ⋅ p sf + λ 2 β (1 − m ) p sf (5.3)

45
The PCC piling method

where:
β coefficient of soil strength
ppf ultimate bearing capacity of the PCC pile, from load test on a single pile,
including K1
psf ultimate bearing capacity of the soil, based on CPT and/or vane tests,
including K2

The ultimate limit state bearing capacity of the PCC pile is determined using the
following formula:

p sf =
u ∑ f sik l i (5.4)
Ap

where:
u pile perimeter
li layer thickness
fsik layer friction, obtained from CPT

Limitations of this method are:


• Many of the design factors are based on experience,
• It is unclear how the bearing capacity of the soil is calculated and
• The ultimate bearing capacity of the pile is based on only the shaft friction; plugging, tip-
bearing and negative skin friction are not taken into account.

5.2.3 Dutch practice

Tip bearing capacity


The bearing capacity of the tip of the PCC pile can be calculated by two well known
methods:
• As a pile, according to Koppejan or
• As a deep foundation wall, according to Prandtl.

Method 1: Koppejan
The 4D-8D method as described in [12] is used for pile tip bearing capacity of solid
piles. The name refers to the logarithmic-spiral failure zone around the pile tip, which extends
to a distance of 0.7 D0 to 4 D0 beneath the pile tip and 8 D0 above the pile tip, where D0 is
the outer diameter of the pile. The ultimate bearing capacity of the pile tip is determined by:

F r; max; tip = Atip p r; max; tip (5.5)

46
The PCC piling method

where:
Fr;max;tip ultimate tip resistance force
Atip surface of the pile tip
pr;max;tip ultimate tip resistance
⎛ q c ;I ;avg + q c ;II ;avg ⎞
= α p ⋅ β ⋅ s ⋅ 0.5⎜⎜ + q c ;III ;avg ⎟ ≤ q lim

⎝ 2 ⎠
αp pile class factor, 1.0 for cast-in-place piles soil displacing
β pile tip shape factor, 1.0 for PCC pile.
s pile tip shape factor, 0.6 for PCC pile.
qc;I;avg mean value of cone resistance in trajectory I that runs from the pile tip to a
level that is at least 0.7 times and at most 4 times the equivalent pile
diameter deeper. It must be selected in such a way that qb is minimal.
qc;II;avg mean value of the cone resistance in trajectory II that runs from the bottom
of trajectory I to the pile point level, where the value used for the cone
resistance may never be higher than the previous value in the trajectory.
qc;III;avg value of the cone resistance in trajectory III that runs from the pile point to a
level that is 8 times the equivalent pile diameter higher, where the value
used for the cone resistance may never be higher than the previous value in
the trajectory.

Limitations of this method are:


• The method is designed for solid piles so the influence of plugging is not taken into
account and
• The method is empirical.

Method 2: Prandtl
The bearing capacity of a strip foundation has been analyzed by Prandtl and others.
The schematization is given in figure 5-1 and the commonly used formula is [38]:

Figure 5-1: Prandtl method, left shallow foundation, right deep foundation [38];

47
The PCC piling method

p r ;max = c ' N c + γ ' dN q + 0.5γ ' BN y (5.6)

where:
pr;max maximum tip bearing resistance
c’ effective cohesion
B width of the foundation
d depth of the foundation level
γ’ effective volumetric weight of the soil
Nc bearing capacity factor for the influence of the cohesion
Nq bearing capacity factor for the influence of the soil cover
Nγ bearing capacity factor for the influence of the effective volumetric weight of
the soil under the foundation surface

The factors N can be calculated by [13]:

N c = (N q − 1) cot ϕ ' e ;d
Nq = e (tan(45° + 0.5ϕ 'e d ))
π tan ϕ 'e ,d
;
2
(5.7)
Nγ = 2(N q − 1) tan ϕ ' e d ;

where:
φ’e,d design value of the effective angle of internal friction

The friction angle, cohesion and unit weight are determined as an average parameter for an
influence depth of 1.5 B.
Equation (5.6) can also be used for different cross-sections like piles with the
following shape factors [13]:

sqNq −1
sc =
Nq −1
⎛B ⎞ (5.8)
s q = 1 + sin ϕ ⎜ ⎟
⎝L ⎠
⎛B ⎞
s r = 1 − 0.3⎜ ⎟
⎝L ⎠

where:
L length of the foundation

If the soil inside the PCC pile forms a stiff soil plug and the friction along this plug
exceeds the tip resistance of the inner soil then the PCC pile can be seen as solid pile. The

48
The PCC piling method

bearing capacity can then be calculated with equation (5.6) and (5.8). However, according to
the GeoHohai literature [19] full plugging does not occur and in that case it is uncertain how
much bearing capacity can be attributed to the soil in the pile. It is therefore considered safe
to assume the PCC pile tube as a circular wall with no inner bearing capacity. The length of
the equivalent wall is the average perimeter of the wall and the width of the equivalent wall
is equal to the wall thickness. While for a solid circular plate the ratio B/L would be 1, for a
PCC pile of 1000 mm outer diameter and 100 mm wall thickness the ratio B/L would become:

B 100
= = 0.035
L 1000 − 100
2 ⋅π ⋅
2

The small B/L ratio leads to shape factors sq and sγ to be close to 1 so the PCC pile
schematized like this is closely corresponding to an infinite wall.

Limitations of the method are:


• The method is designed for shallow foundations and
• The method is designed for infinitely long strip foundations and although shape factors
are available for piles the PCC pile’s shape is difficult to model.

Shaft bearing capacity


The friction along the shaft of the PCC pile is commonly calculated with two different
methods:
• Based on the cone resistance
• Based on the shear strength

Method 1: Cone resistance (according to NEN 6743)


The equation for the ultimate shaft friction is given as [12]:

p r ;max;shaft ;z = α s q c ;z ;a (5.9)

where:
pr;max;shaft ultimate unit shaft friction
αs pile class factor for compression, see table 5-1
qc;z;a cone resistance at depth z, with a maximum value of 12 MPa, for layers < 1
m thickness and 15 MPa for layers > 1 m thickness

49
The PCC piling method

Table 5-1: Values for αs [12];

soil type relative depth αs


clay/silt qc ≤ 1 MPa 5 < z/d < 20 0.025
clay/silt qc ≤ 1 MPa z/d ≥ 20 0.055
clay/silt qc > 1 MPa - 0.035

Limitations of this model are:


• The method is empirical.

Method 2: Shear strength


This method is also called the slip method and is based on the analysis of the stress
situation and the pile properties on the boundary between the pile shaft and the soil. The
friction force follows from [38]:

p r ;max;shaft ;z = σ ' h ;z tan δ = K s ;z σ 'v ;z tan δ (5.10)

where:
Ks horizontal ground pressure coefficient after pile installation
σ'v average value of the effective vertical stress for the considered layer
δ friction angle between soil and shaft

Typical values for Ks and δ are shown in table 5-2.

Table 5-2: values for the wall friction angle and the horizontal earth pressure coefficient [38];

Pile type Friction angle Earth pressure coefficient for sand


Low density High density
Rd < 0.6 Rd > 0.6
Soil displacing
- Prefab concrete 3/4 φ 1.0 2.0
- Cast-in-place φ 1.0 2.0
- Jacked wooden 2/3 φ 1.5 4.0
- Jacked closed steel tube 20º 1.0 2.0

Little soil displacement


- Steel profiles 20º 0.5 1.0
- Open steel tubes 20º 0.5 1.0

Ground removing 3/4 φ Horizontal earth pressure based


On 80% of grout/water pressure

Limitations of this method are:


• The average value of the effective stress is difficult to determine in situ and
• The soil-wall friction angle and earth pressure coefficient are empirical.

50
The PCC piling method

5.2.4 Negative shaft friction


If piles are installed through soft soil layers and the pile tips are placed in soil layers
with a high bearing capacity, the piles will behave almost settlement free. The soft soil layers
will then, if they settle, load the piles with a downward friction force. This friction force on the
pile shaft is called the negative shaft friction. The friction force is already maximized by
displacements of 20 mm or less. In that case it is not expected that negative skin friction will
occur over the full height of the soft layers. It is assumed that for ground level settlements of
more than 100 mm, there will be negative skin friction in all soft layers. In a soil profile with
fully settled soft layers it can be safely assumed that the upper boundary of the negative skin
friction is equal to the added load on the soil due to a fill or construction. The negative skin
friction can be calculated with two methods [38]:
• The slip method
• The method Zeevaert - De Beer

Method 1: Slip method


The slip method [38] is the simplest method for negative skin friction calculation and
gives an upper boundary for the negative skin friction. The schematization of the slip method
is shown in figure 5-2.

Figure 5-2: Schematisation of the slip method [38];

The method is based on the stress situation and friction properties of the boundary surface
between the pile shaft and the soil. The downward friction force can be determined by:

F s ;nk = O s hK 0 σ 'v tan δ (5.11)

where:
Fs;nk force due to negative skin friction
Os perimeter of the pile shaft
h thickness of the considered layer
K0 neutral earth pressure coefficient

51
The PCC piling method

σ’v mean value of the vertical effective stress in the considered layer
δ friction angle between pile and soil

When the friction angle between pile and soil is taken equal to that of the soil and
the earth pressure coefficient K0 = 1-sinφ, it follows for clay and peat layers that K0 tan δ
varies from 0.2 to 0.3. In practice a value of 0.25 is used. For displacement piles a value of
0.50 is more realistic [38].
Limitations of this method are:
• Only an upper boundary of the shaft friction is determined and
• The earth pressure coefficient and friction angle between soil and pile are determined
using empirical formulae.

Method 2: Zeevaert - De Beer


This method is based on the vertical equilibrium of a small layer of soil around a pile
and is used for pile groups instead of the slip method. The difference with the slip method is
that in this case the vertical effective stress is reduced by the already conveyed negative skin
friction. This is done by taking into account the mean vertical stress on the top and bottom
side of small area (A) with a height of Δz and to distribute the shear stress along the pile over
the area A, see figure 5-3.

Figure 5-3: Method Zeevaert-De Beer [38];

52
The PCC piling method

The equation for the friction force is given by [12]:

i =n
F s ;rep ;nf = A ∑ (σ '
i =1
0 ;h ;i ;rep −σ ' m ;h ;i ;rep ) (5.12)

with:
σ ' 0;h ;i ;rep = σ ' m ;hli −1;rep +h1γ ' i ;rep

σ ' m ;h ;i −1;rep = p 0;rep for the first layer

γ ' i 'rep
σ ' m ;h ;i ;rep =
mi
(1 − e − m i hi
)+ σ ' m ;h ;i −1;rep (e −m i hi
)
where:
Fs;nf;rep representative value of the friction force due to negative skin friction
A influence area of the pile
σm;l;i;rep representative value of the effective vertical stress in the soil for layer i
σ0;l;i;d representative value of the effective stress due to the top load for layer i
p0;d representative value of the top load
mi factor for layer i
u ⋅ K 0;i ;rep tan δ i ;rep
=
A
u pile perimeter

For a single pile (A becomes infinite) the method Zeevaert gives the same value for
the negative skin friction as the slip method because m = 0. This value is an overestimation
because, also in case of a single pile, shaft friction occurs, which results in a decrease of the
effective stress. De Beer proposed to limit the size of area A dependent on the layer thickness
h. For a top load A is limited to 1/4πh2 and for only characteristic weight of the soil to
1/16πh2. If more than one soft layer is present the negative skin friction is calculated with h1
for the top layer and then the weight of the top layer is reduced by the negative skin friction
that works as a load on the second layer. The second layer is calculated with h2. The
disadvantage of this method is that the negative skin friction is also determined by the order
of the layers. This can not be proven theoretically and may lead to reduction of the negative
skin friction. Especially for large pile distances it is advised to take the relation between layer
thickness and pile distance in the order of 2.
Limitations of this method are:
• The shaft friction for a single pile cannot be correctly calculated and
• The earth pressure coefficient and friction angle between soil and pile are determined
using empirical formulae.

53
The PCC piling method

5.2.5 Plugging

General
Plugging is the phenomenon where an open-ended pipe pile develops a rigid soil
“plug” at the bottom which prevents soil from entering the pile and essentially makes the
pipe pile behave as a closed-ended pile. The phenomenon can occur at two moments:
• During driving, at some point during driving the friction builds up sufficiently between the
soil plug and inner pile wall so that the pile becomes plugged, preventing additional soil
from entering [27]. When a plug is formed the installation effort increases.
• During loading, the pile is considered to fail plugged when the shear capacity along the
length of the soil plug exceeds the end-bearing capacity at the base of the plug [31] [12].
According to [31] plugging is less likely to occur during driving because the inertia of the soil
plug encourages slip relative to the pile preventing plugging.
A pile can be driven in either fully coring mode, with no plug formation at all (the soil
enters the pile at the same rate it advances) fully plugging, where no soil enters the pile, or
partially plugging, with some plug formation, see figure 5-4. After plug formation a fully
plugged pile behaves in the same way as a closed-ended pile [26]. The plug formation
depends on several variables, mainly the shape of the pile tip, the pile geometry, the
installation method and the soil type [27].
Several methods are available to describe the plugging effect in pipe piles. The spring
model and the inner friction model as described in [2] and the one-dimensional analysis of
soil plugs according to [31] will be discussed here.

Figure 5-4: Plugging [31];

Method 1: Spring model


In the spring model [2] for steel pipe piles the soil inside and outside of the pile is
modelled as a spring. The end-bearing response is modelled as a combination of three spring

54
The PCC piling method

systems: a spring underneath the pile wall with a spring constant Kw, a spring underneath the
soil plug with spring constant Ki and a spring inside the pile representing the compression of
the soil plug due to end bearing loading with a spring constant Kpl, see figure 5-5.

Figure 5-5: spring analogy open ended pipe pile [22];

A load on the pile wall only will result in wall displacement and plug displacement:

Qw
u ww = (5.13)
Kw

u plw =α 1⋅u ww (5.14)

In the same way a load on the plug only will result in plug displacement and wall
displacement:

Q pl
u plpl = (5.15)
Ki

u wpl = α 2 ⋅ u plpl (5.16)

where:

55
The PCC piling method

uww pile wall displacement due to load on pile wall


uplpl displacement soil below the plug due to load on the plug
Qpl load on the plug
Qw load on the pile wall
Kw spring constant soil below pile wall
Ki spring constant soil below plug
uplw displacement soil below the plug due to load on pile wall
uwpl pile wall displacement due to load on plug
α1 spring interaction factor soil below pile wall to soil below plug
α2 spring interaction factor soil below plug to soil below pile wall

The interaction factors α1 and α2 represents the influence of the wall displacement on the
plug displacement and visa versa. Combining the equations gives (if no failure occurs):

Qw Q pl
u w = u ww + u wpl = + α2 (5.17)
Kw Ki

Q pl Qw
u pl = u plpl + u plw = + α1 (5.18)
Ki Kw

The compression of the soil plug inside the pile is given as the relative displacement of the
pile wall to the displacement of the soil below the plug:

Q pl
u w − u pl = (5.19)
K pl

where:
Kpl spring constant soil in plug

and the total end bearing load:

Q = Q w + Q pl (5.20)

where:
Q total end bearing load

The spring constants can be obtained from literature [32] [28]:

56
The PCC piling method

E soiltip R i
Ki =2 (5.21)
1 −ν 2

E soiltip R o
Kw = 2 (5.22)
(1 − ν )ω (n )
2

K pl = 2πR i β a D M (5.23)

with:

1 −ν
DM = E pl
(1 + ν )(1 − 2ν )

where:
Esoiltip stiffness of the soil at the pile tip
ω(n) factor dependent on inner and outer radius of the pile, see table 5-3
Ri inner diameter pile
Ro outer diameter pile
βa active friction ratio
= K a tan δ p

Ka ratio between the radial effective stress and vertical effective stress
δp passive angle of friction between pile wall and soil plug
DM stiffness factor [32]
Epl stiffness soil in plug
ν Poisson’s ratio soil

Table 5-3: ω(n) values [28];

Ri
n= 0 0.2 0.4 0.6 0.8 0.9 0.95
Ro
ω(n) 0.50 0.50 0.51 0.52 0.57 0.60 0.65

Combining these equations for the equations of a closed ended pile in:

n ⎛⎜1 − 2 1 − n 2ω (n ) ⎞⎟
α2 = ⎝ ⎠ (5.24)
1− 1−n 2

57
The PCC piling method

n −1 + 1 − n 2
α1 = (5.25)
2n 1 − ν 2 ω (n )

⎛ ⎞
⎜ ⎟
⎜ 1 − α1 ⎟
Q =⎜ + 1 ⎟Q w (5.26)
K K
⎜ (1 − α 2 ) w + w ⎟
⎜ K K ⎟
⎝ i pl ⎠

Qw Q − Qw
uw = + α2 (5.27)
Kw Ki

Assuming that the soil plug is sufficiently long that failure can only occur due to failure of the
wall, while the soil inside and below the soil plug still behaves elastically, this results in an
ultimate wall resistance (Qw;u) and total end bearing load (Q1):

⎛ ⎞
⎜ ⎟
⎜ 1 − α1 ⎟
Q1 = ⎜ + 1 ⎟Q w ;u (5.28)
⎜ (1 − α 2 ) K w + K w ⎟
⎜ Ki K pl ⎟
⎝ ⎠

Q w ;u Q − Q w ;u
u w ;1 = + α2 (5.29)
Kw Ki

Additional load is only carried by the plug:

ΔQ = ΔQ pl (5.30)

⎛ 1 1 ⎞⎟
Δu = ⎜ + ΔQ (5.31)
⎜ K pl K i ⎟⎠

This will continue until failure of the plug occurs.


It is also suggested to add another spring to the model because not all the soil in the
pile will form a plug. Furthermore it is noted that this model only models the pile tip reaction,
for good measure there should also be a spring modelling of the effect of the skin friction.
The spring constant for the shaft resistance (Kshaft) is modelled based on the deformations
required to obtain fully mobilized shaft friction. According to [12] for soil displacing piles the
tip displacement required for full mobilization of the shaft friction is about 10 mm. If the

58
The PCC piling method

mobilized shaft friction is considered to be linear (which it is not, but this is an approximation)
then the spring constant becomes:

Q max
K shaft = for u ≤ 0.01 m
0.01
Q
K shaft = max for u > 0.01 m
uw

where:
Kshaft spring constant for shaft
Qmax maximum bearing capacity of the pile shaft (calculated with [12])

In words: The bearing capacity of the shaft is linearly increasing between 0 and 10 mm wall
displacement and constant after 10 mm wall displacement. In this model there is no
interaction between the friction spring and the springs at the tip. It is assumed the load taken
by the soil dissipates in horizontal direction and does not influence the soil layers below the
pile tip. This is a simplification. The spring model now becomes:

Kshaft

Figure 5-6: Suggested adjustments to spring theory [2] (edidted);

The length of the plug spring is advised to have a length of 2 to 4 times the inner
diameter of the pile. The value of Kinner should be based on the average cone resistance

59
The PCC piling method

inside the pile. It should also be noted that a plug spring should only be applied by sufficient
L/D ratio when a soil plug is expected.
Limitations of this model are:
• Model has been created for sand plugs,
• Soil stiffness is hard to determine in situ,
• The increase of the soil stiffness with higher loads is not taken into account,
• For settlement calculations the group effect is not taken into account and
• The earth pressure coefficient and friction angle between pile and soil are determined
using empirical formulae.

Method 2: Inner friction model


The equilibrium of forces requires that the added bearing capacity due to plugging is
the lesser of the physical maximum of the total inner shaft resistance and the end bearing
capacity of the soil below the plug [31] [12][24].
In [2] an analytical derivation of the silo formula concerning plugging is given, see
figure 5-7.

σ 'z

τ τ

∂σ z
σz + dz
∂z

2⋅ R

Figure 5-7: forces on a disc shaped layer of soil inside a pile [2]:

The equilibrium of downward and upward forces leads to the following equation:

⎛ ∂σ z ⎞
πR 2σ z + 2πRτdz + πR 2 γ ' dz = πR 2 ⎜⎜ σ z + dz ⎟⎟ (5.32)
⎝ ∂z ⎠

If the friction is fully mobilized:

τ = c '+Kσ z tan δ (5.33)

60
The PCC piling method

Combining these equations and solving the differential equation and then rewriting for the
vertical stress gives:

2K z tan δ
γ ' R + 2c ' 1
σz = − + (γ ' R + 2c '+2Kσ 0 tan δ )e R (5.34)
2K tan δ 2K tan δ

where:
γ’ effective volume weight inner soil
R radius of the pile
K lateral earth pressure coefficient
δ friction angle pile-soil
σ0 surface load
c’ effective cohesion

As can be seen the influence of the lateral earth pressure coefficient K is very large in
equation (5.34), to use this formula in practice a method has to exist to determine K tan δ
exactly.
The inner soil can be divided in an “active” plug and a “passive” plug, see figure 5-8.

Lp

La

Figure 5-8: Division of soil in the pile in active and passive soil plug;

An approach is given to calculate the minimal active plug length (La), for which the calculated
end bearing equals the wall-end bearing plus plug-end bearing. The unit plug-end bearing is
calculated as follows:

⎛ γ' ⎞ θ a La γ'
q ebplug = ⎜⎜ p a + ⎟e − (5.35)
θa ⎟ θa
⎝ ⎠

61
The PCC piling method

with:

4βa (5.36)
θa =
D

and a formula for the active friction ratio, (βa) at active failure:

−0.75
⎛La ⎞ (5.37)
β a = 1.05D −0.25 ⎜⎜ ⎟⎟ Dr 0.30
⎝D ⎠

where:
γ' effective unit weight (≈ 10 kN/m3 in sand)
pa vertical effective stress acting on the top of the soil plug
= Lp γ '

La active plug length


Lp passive plug length
D plug diameter
Dr relative density, calculated with the Jamiolkowsky formula [2], with K0 taken
0.4

If upward direct shear stresses were to occur between the “passive” soil plug and the pile
wall (silo type arching behaviour), the value of pa would be considerably less than Lp γ':

pp =
γ'
θp
(
−θ L
1−e p p ) (5.38)

with:
4β p
θp = (5.39)
D

and the “passive” friction ratio, (βp) is given by:

τ r ,z
β p = K p tan δ p = (5.40)
σ 'v

where:
pp vertical effective pressure at the bottom of the “passive plug” with length Lp

62
The PCC piling method

γ' effective unit weight in the passive plug (assumed to be the same as in the
active plug)
Kp ratio between the radial effective stress and vertical effective stress in the
passive plug (assumed to be constant along the entire length Lp)
δp angle of friction between pile wall and passive soil plug (assumed to be
constant along the entire length Lp)

In [2] it is recommended to assume a vertical effective stress acting on the top of the
soil plug (pa) equal to the vertical effective pressure at the bottom of the “passive” plug. For
infinite values of Lp/D this becomes:

pp =
γ 'D
4β p
(
1 − e −∞ = ) γ 'D
4K p tan δ p

γ 'D
4 ⋅ 0.25
≈ γ 'D (5.41)

This leads to an overestimation of the active plug length if the vertical stress acting on top of
the soil plug is larger than this (low) value. For small piles (L/D<5) it is recommended to take
pa equal to zero. The plug end bearing is related to the inner pile area and the wall-end
bearing to the rim area. The equation, which has to supply the active plug length and
therefore the minimal penetration depth, becomes:

( )
q eb = 1 − n 2 q ebwall + n 2 q ebplug (5.42)

with

Di
n =
D0

The active plug length will have to be found iteratively. The report presents some
calculations which find La/Do to be between 4 and 8 although the cut-off point for the friction
formula La/Do = 2 is still valid because almost no friction is developed between 2 and 4.
Limitations of this model are:
• Model has been created for sand plugs,
• Determination of the active and passive plug length is difficult and
• Determination of active and passive earth pressure coefficient is difficult.

Method 3: One-dimensional soil plug analysis


In [31] it is stated that most open-ended piles will fill up with soil during driving and
then fail as closed-ended piles during static loading. The end bearing capacity of the pile is
taken to be the lesser of:

63
The PCC piling method

Q bo = πdhτ i ⎫
⎪ (5.43)
πd 2

Q bc = qb ⎪
4 ⎭

with:
Qbo bearing capacity in open-ended failure mode
Qbc bearing capacity in closed-ended failure mode
i pile inner diameter
h soil plug length (height of soil in pile)
qb end bearing stress
τi inner shaft friction per layer
= βσ 'v

The value for β depends on the ratio of horizontal to vertical effective stress in the plug. A
minimum value of β is obtained assuming that the soil near the plug is at active failure, from
the Mohr’s circle in figure 5-9 it can be seen that:

τi sin ϕ sin(Δ − δ )
β = =
σ 'v 1 + sin ϕ cos (Δ − δ )
sin δ
sin Δ =
sin ϕ

where
φ internal friction angle of the soil in the plug
δ friction angle between the soil and the pipe pile

64
The PCC piling method

Figure 5-9: Mohr’s circle of soil plug at active failure [31];

If the plug is considered to be loaded undrained there will be no compression of the


soil plug and the response will be rigid-plastic with the following capacity:

4 βh 4 βγ ' h 2 (5.44)
q bu = p + 0.5
d d

If the plug is considered to be drained the limiting end-bearing capacity in excess of


the initial effective stress is:

⎛ 4 βh
⎞⎧ p γ ' hd ⎫
q bd = ⎜ e d
− 1 ⎟⎨ + ⎬ − γ 'h (5.45)
⎜ ⎟⎩ γ ' h 4 βh ⎭
⎝ ⎠

If the end-bearing stress is raised incrementally in the drained case, the internal skin friction
will be mobilized over an active length of the plug l, as shown in figure 5-10. The vertical
stress increment over the active plug length is then given directly by:

⎛ 4 βz ⎞⎧ dγ ' ⎫
Δσ 'v = ⎜ e d − 1 ⎟⎨γ ' (h − 1) + ⎬ −γ'z (5.46)
⎜ ⎟⎩ 4β ⎭
⎝ ⎠

65
The PCC piling method

Figure 5-10: Active and passive plug length [31];

With an elastic soil plug with a one-dimensional modulus E0 the active plug compression, or
tip displacement, may be approximated by:

d Δq
Δw ≈ (5.47)
4β E 0

The main limitations of this model are:


• The value of β is dependent on the stress, via the change of the friction angles due to
grain crushing,
• The influence of installation on the in situ stress state is not taken into account and
• The analysis has concentrated on carbonate soils, which are known to undergo volume
reduction during shearing, which in turn will affect the response of the plug.

5.2.6 Soil bearing capacity


The bearing capacity of the soil can be calculated with two methods:
• The Brinch-Hansen method for shallow foundations and
• The settlement based bearing capacity.

66
The PCC piling method

Method 1: Brinch-Hansen
The undrained bearing capacity of the soil can be calculated with the Brinch-Hansen
method [13]. This method is applicable for stiff shallow foundations and describes the
formation of a failure surface, see figure 5-11.

Figure 5-11: Failure surface for shallow foundation [13];

According to [13] the bearing capacity of the soil on ground level (undrained state) is defined
by:

σ ' max;d = (π + 2)f imdr ;d ⋅ s c ⋅ i c + σ 'v ;z ;0;d q (5.48)

with:

⎛ ⎛ F s ;h ⎞
0.5

ic = 0.5⎜⎜1 + ⎜⎜1 − ⎟



⎝ As ⋅ c u ⎠
⎝ ⎠
B ef
s c = 1 + 0.2
Lef
i =n
σ 'v ;z ;0;d = γ f ;g ∑ (d
i =1
i ⋅ γ char ) − u

where:
σ'max;d design value of the maximum foundation pressure on the effective
foundation surface
fundr;d design value of the undrained shear strength according to [11]
σ'v;z;o;d design value of the original vertical soil stress at a depth z
di thickness of layer i
γchar characteristic volumetric weight of the soil
u water pressure according to [11]
γf;g load factor according to [14]

67
The PCC piling method

n number of horizontal soil layers


Lef length of the effective foundation area
Bef width of the effective foundation area
Fs;h;d design value of the load component on the foundation area
ic reduction factor for the slope of the load
sc shape factor for the influence of the cohesion

Limitations of this model are:


• Stiff foundations are assumed while for the PCC pile flexible geotextile is used and,
• The influence of the piles and the pile installation is not taken into account in the bearing
capacity.

Method 2: Settlement based bearing capacity


It is important to remember that the reason for installing the PCC piles is a reduction
of settlement of the soil. The two aforementioned methods describe two failure mechanisms
that can occur caused by the load of the fill. However, it is possible, even probable, for
unacceptable large settlements to occur before failure via one of the above methods. The
bearing capacity of the soil can also be based on the acceptable settlement. The method for
calculating the settlement belonging to a load on the soil will be given in paragraph 5.3.
Limitations of this method are:
• A maximum bearing capacity will still have to be calculated and
• Acceptable settlement has to be defined correctly and verified.

5.3 Settlement

5.3.1 Chinese practice


The total settlement of the composite foundation is composed of two parts: the
settlement of the pile-improved area and the settlement of the underlying stratum.

Settlement of the pile improved area


For the settlement of the composite foundation two methods are available:
• The composite modulus of elasticity method
• The stress correction method.

68
The PCC piling method

Figure 5-12: Settlement of the composite foundation consists of two parts [17

Method 1: Composite modulus of elasticity


The settlement of the pile-improved area is based on the modus of elasticity of the
composite foundation. The stiffness of the soil will be improved due to installation of the pile.
In this method the increase in stiffness is based on the exchange ratio of the composite
foundation, m, as given in equation (5.2) . The settlement of the pile improved area becomes
[19]:

n
Δp i
s1 = ∑E
i =1 csi
Hi (5.49)

where:
s1 settlement of pile improved area
n number of soil layers in pile improved area
Hi thickness of the i-th soil layer
Δpi additional stress due to fill
Ecsi modulus of elasticity of the composite foundation
= mE ps + (1 − m )E ssi

Eps modulus of elasticity of the pile


Essi modulus of elasticity of the i-th soil layer
m exchange ratio of the composite foundation

Limitations of this method are:


• The soil and pile are assumed to behave as one block while in paragraph 3.3.5 it can be
seen that the soil settles more than the pile,
• The modulus of elasticity of the soil is difficult to determine and

69
The PCC piling method

• The effect of the geotextile is not taken into account for calculation of the composite
modulus of elasticity; the exchange ratio is only based on the surface ratio.

Method 2: Stress correction method


The stress correction method is based on the stress ratio between pile and soil. Only
the settlement of the soil is calculated but the load on the soil is reduced by the load taken by
the pile. The load on the soil becomes [19]:

p
ps = = μs p (5.50)
1 + m (n − 1)

with:

σp
n= (5.51)
σs

where:
ps load on the soil
n stress ratio
σp stress from the fill on the pile head
σp stress from the fill on the pile head
μs reduction factor
m exchange ratio composite foundation

The settlement of the pile treated area now becomes:

n
Δp si
s1 = ∑E
i =1 csi
H i = μ s s 1s (5.52)

where:
s1s settlement of the soil without improvement

A limitation of this method is:


• The stress ratio, n is hard to determine when using a geotextile mattress on top of the
piles without load testing on the composite foundation.

Settlement of the underlying stratum


For the underlying stratum the layer summation system is used [19]:

70
The PCC piling method

n max
Δp b
s2 = ∑
i =n +1 E si
Hi (5.53)

where:
s2 settlement of the underlying soil stratum

The load on the underlying stratum can be defined with two methods [17]:
• The pressure diffusion method
• The equivalent entity method

Method 1: Pressure diffusion

Figure 5-13: Pressure diffusion method [17];

The load of the embankment is assumed to spread over de pile improved area, see
figure 5-13. The equation for the 2D situation becomes:

Bp
pb = (5.54)
(B + 2h tan( β ))

where:
pb load on the lower strata
B width of the fill
p load due to the fill
β spreading angle

This is a safe approximation because the load also spreads in the underlying stratum,
thus reducing the settlement.

71
The PCC piling method

Limitations of this model are:


• The soil and pile are assumed to settle as a composite block and
• The spreading angle can only be determined based on experience.

Method 2: Equivalent entity


The improved area is considered to settle as one equivalent solid soil body. The
friction between the loaded and the not loaded soil is taken into account, as can be seen in
figure 5-14.

B
Top load

Pile improved area h


pb

Underlying stratum

Figure 5-14: Equivalent entity method [17];

The load on the underlying stratums now becomes:

p b = p + ΔG − 2hf (5.55)

where:
ΔG weight of the pile
h length of the pile
f friction with the soil that is not loaded

The value of the friction with the soil that is not loaded, f, is determined from the CPT tests.
Limitations of this model are:
• The soil and pile are assumed to settle as a composite block and
• The friction with the soil that is not loaded has to be determined with special CPT tests.

5.3.2 Dutch practice


According to [12] the calculation value of the settlement of a foundation is calculated
as follows:

72
The PCC piling method

w d = w 1;d + w 2;d (5.56)

where:
wd design value of the settlement of the foundation
w1;d design value of the settlement of the head of the pile
w2;d settlement due to the compression of the soil layers under the pile tip (group
effect)

The settlement of the head of the pile consists of two parts:

w 1;d = w tip ;d + w 2;d (5.57)

where:
wtip;d design value of the settlement of the pile head due to the load on the pile
wel;d design value of the settlement of the pile head due to elasticity of the pile

To calculate the settlement of the pile tip for pile groups the values of the maximal shaft and
tip forces have to reduced by a factor dependant on the number of piles and the number of
CPT’s given in table 1 of [12]. The value of the settlement of the pile head due to the load on
the pile is then constructed from the graphs given in Appendix A, based on the resulted load
on one pile. The settlement due to pile elasticity is given by:

L ⋅ F avg ;d
w el ;d = (5.58)
Ashaft ;d ⋅ E p ;mat ;d

where:
Fgem;d design value for the average force in the pile, determined according to [11]
I ⋅ F s ;tot ;d + 0.5(L − I )(F s ;tot ;d + F r ;tip ;d )
=
L
Fs;tot;d design value of the total load on the pile head
Fr;tip;d design value of force in the pile tip
L distance between pile tip and pile head
I distance between the highest point in the pile for which shaft friction is
presumed and the head of the pile
Ashafd;d design value of the surface of the pile shaft
Ep;mat;d design value of the modulus of elasticity of the pile shaft material

73
The PCC piling method

For a distance of more than 10 times the smallest diameter of the pile, w2;d is
assumed to be zero, else:

m * ⋅σ 'v ;4D ⋅0.9 A4D


w 2;d = (5.59)
E g ;avg ;d

where:
σ’v;4D effective vertical stress on the surface b1 times b2 on a depth of 4D under the
pile points
D smallest cross section of the pile tip
b1,b2 dimensions of the loaded surface at a depth of 4D under the pile points
A4D loaded surface at a depth of 4D under the pile points
Eg;avg;d design value of the average modulus of elasticity at the 4D level,
E = 5qc;z;avg
m* factor dependent on the shape of the loaded surface, see table 5 of [12]

Limitations of this method are:


• Only the settlement of a single pile is modelled and
• Many empirical factors are used that are not (yet) determined for the PCC pile

5.3.3 Piled raft and pile group responses


In literature different methods are proposed for the settlement calculation of piled
raft and pile group foundations:
• Settlement ratio method
• Equivalent raft method
• Equivalent pier method
• Piled raft

Method 1: Settlement ratio method


In this method the stiffness of a pile group can be expressed as a fraction of the sum
of the individual pile stiffness [30]:

K = ηnk (5.60)

where:
K pile group stiffness
η group efficiency
≈ n −e
k pile head stiffness of a single pile

74
The PCC piling method

n number of piles

While the exponent e will lie between 0.3 and 0.5 for primarily friction piles it actually
depends on the pile slenderness ratio, L/d, the pile stiffness ratio, λ=Ep/Gl, the pile spacing
ratio, s/d, the homogeneity of the soil, ρ and the Poisson’s ratio, υ. Design charts for the
group efficiency are shown in Appendix B
An elastic solution for the axial response of a single pile is presented in [30], based
on the separate treatment of the pile shaft, using the linear load transfer function and the
pile base, using the Boussinesq solution for a rigid punch acting on an elastic half space:

4η 2π tanh μl l

Pt (1 − ν )ξ ζ μl r0
= (5.61)
G l r 0w l 1 4η
1+
πλ (1 − ν )

with:

⎛ rm ⎞
ζ = ln⎜⎜ ⎟

⎝ r0 ⎠
r m = l ⋅ (0.25 + ξ (2.5 ρ (1 − ν ) − 0.25 ))

2 ⎛ l ⎞
μl = ⎜ ⎟
ζλ ⎜⎝ r 0 ⎟

where:
Gl shear modulus at z = l
Pt load at the top of the pile
wt displacement at the top of the pile
η under-reamed piles (rb/r0)
ξ end-bearing piles (Gl/Gb)
ρ heterogeneity of soil modulus (Gavg/Gl)
λ pile-soil stiffness ratio (Ep/Gl)
rm maximum radius of influence
μl pile compressibility
NB: the subscript b refers tot conditions at or below the pile base.

To simulate a group of piles the load transfer parameter should be replaced by:

75
The PCC piling method

n
⎛si ⎞
ζ * = nζ − ∑ ln⎜⎜⎝ r
i =2


0 ⎠
(5.62)

The base stiffness is adjusted:

⎡ 2
n
rb ⎤
π ∑s
ξ * = ξ ⎢1 + ⎥ (5.63)
⎣⎢ 1= 2 i ⎦⎥

where:

si spacing of the ith pile from pile 1

Finally the settlement of a group pile can be calculated by:

P group
w group = = δ sinlge R s
K

with:

K = ηkn

If a soft soil layer is present below the pile tip this will cause extra settlement due to
the load of the pile group. The rate of stress spreading below the pile area is taken the rate
of 1:4 [30], see figure 5-15:

r m = [0.25 + (2.5 ρ (1 − υ ) − 0.25)ξ ]L

76
The PCC piling method

Figure 5-15: Use of equivalent raft for calculating the effect of a soft layer underlying the pile group
[30];

The theoretical values for the settlement ratio for floating pile groups are shown in
Appendix C. The settlement ratio for floating pile groups is reduced by the presence of a stiff
layer, the Poisson’s ratio and the distribution of the soil modulus. Graphs for reduction factors
are given in Appendix C
Limitations of this method are:
• Only pile groups and no single piles are discussed,
• The method is based on stiff rafts not geotextile and
• The pile improved area is assumed to settle as a composite body.

Method 2: Equivalent raft method


The foundation is considered as a whole. Traditionally an ‘equivalent’ raft is
considered, located two-thirds of the way down the part of the piles which penetrate the
main founding stratum, or at the level of the pile bases for end-bearing piles, see figure 5-16.

77
The PCC piling method

Figure 5-16: Equivalent raft approach for pile groups [30];

The average settlement at the ground level is then calculated by:

w avg = w raft + Δw (5.64)

where:
wavg average settlement at ground level
wraft raft settlement
Δw elastic compression of the piles above the level of the equivalent raft
(treated as free-standing columns)

The main advantage of this method is that it enables the variations in soil stiffness below the
level of the raft to be taken into account. The raft settlement is evaluated by integrating the
vertical strains, allowing for variations in soil modulus and correcting for the raft embedment
below the ground surface:

78
The PCC piling method

n
⎛ Iε ⎞
w raft = F D q ∑ ⎜⎜⎝ E
i =1
⎟ hi

s ⎠i
(5.65)

where:
q average pressure applied to the raft
Iε influence factor from which the vertical strain may be calculated, see
figure 5-17
hi thickness of the ith soil layer
Esi Young’s Modulus of the ith soil layer
FD correction factor


Figure 5-17: Influence factor for the vertical stain [30] ;

Limitations of this method are:


• Only pile groups and no single piles are discussed,
• The method is based on stiff rafts not geotextile and
• The pile improved area is assumed to settle as a composite body.

Method 3: Equivalent pier method


An alternative for the equivalent raft method is to consider the region of soil in which
the piles are embedded as an equivalent continuum. For a pile group the equivalent pier
diameter may be taken as:

4 (5.66)
d eq = Ag = 1.13 Ag
π

where:

79
The PCC piling method

deq equivalent pier diameter


Ag pile group area

The Young’s modulus of the pier is:

⎛ Ap ⎞
E eq = E s + (E p − E s )⎜ ⎟ (5.67)
⎜ Ag ⎟
⎝ ⎠

where:

Eeq Equivalent Young’s modulus


Ep Young’s modulus of the piles
Es Average Young’s modulus of the soil penetrated by the piles

The advantages of the equivalent raft and pier approaches may be assessed by considering
the overall aspect ratio of the pile group, as shown in figure 5-18.

Figure 5-18: Replacement of pile group by equivalent pier [30];

The overall aspect ratio also depends on the degree of interaction between the piles (l/s) and
becomes:

80
The PCC piling method

ns (5.68)
R =
l

where
R aspect ratio
n number of piles
s spacing piles
l embedded length

For values of R greater than 4, it is shown that the pattern of differential settlement is very
similar to that of a raft foundation. An equivalent raft would then be a logical solution. For
smaller values the outset of an equivalent pier is more logical.
Limitations of this method are:
• Only pile groups and no single piles are discussed,
• The method is based on stiff rafts not geotextile and
• The pile improved area is assumed to settle as a composite body.

Method 4: Piled raft


The settlement of the soil and PCC pile can be compared to the settlement of a piled
raft foundation where the raft foundation where the stiffness of the raft is equivalent to that
of the soil. With subscripts p for the pile group and r for the raft the settlement may be
expressed as [30]:

⎡ 1 α rp ⎤
⎢ ⎥
⎧w p ⎫ ⎢ k p kr ⎥ ⎧P p ⎫
⎨ ⎬ ⎢α = ⎨ ⎬ (5.69)
⎩w r ⎭ rp 1 ⎥ ⎩Pr ⎭
⎢ ⎥
⎢⎣ k p k r ⎥⎦

where:

w settlement
αpr interaction factor
αrp interaction factor
P load
k stiffness

For large pile groups αrp becomes a constant value of 0.8 and the piled raft stiffness:

81
The PCC piling method

⎛k ⎞
1 − 0.6⎜ r ⎟
⎜kp ⎟
⎝ ⎠ (5.70)
k pr = kp
⎛ kr ⎞
1 − 0.64 ⎜ ⎟
⎜kp ⎟
⎝ ⎠

Similar the ratio of loads carried by the pile cap (or raft) and the pile group is:

Pr 0.2 kr
=
Pp ⎛k ⎞ kp (5.71)
1 − 0.8⎜ r ⎟
⎜kp ⎟
⎝ ⎠

Limitations of this method are:


• Only pile groups and no single piles are discussed,
• The method is based on stiff rafts not geotextile and
• The pile improved area is assumed to settle as a composite body.

5.4 Yan-Tong example case

5.4.1 Introduction
As an illustration of the calculation method the case of the Yan-Tong highway
embankment is considered. PCC piles were applied here to limit the settlement. Before,
during and after construction measurements were done to determine the settlement and the
bearing capacity of the piles and the pile treated area.

5.4.2 Site description


The Yan-Tong highway embankment is placed on the soft soil layers of the shore
plains of the Yellow Sea. The soil is made up of silty soil to a depth of about 30 meters. table
5-4 shows the soil properties. The distribution of the different types PCC piles over the area is
shown in table 5-5.

82
The PCC piling method

Table 5-4: Soil properties at Yan-Tong site [17];

Table 5-5: Pile properties [17];

Application Design Wall Centre-to- Final


Diameter Number
Pile area length length thickness centre length
[mm] of piles
[m] [m] [mm] [m] [m]
K30+740∼ K30+778 38 16 1000 120 3.3 142 15.0

K30+778∼ K30+808 30 18 1240 120 3.3 113 15.0

K30+808∼ K30+838 30 18 1000 120 2.8 158 15.5

K30+838∼ K30+868 30 18 1000 120 3.0 139 15.5

K30+868∼ K30+898 30 18 1000 120 3.3 116 15.5

K31+509∼ K31+559 50 18 1000 100 3.3 193 15.5

K31+559∼ K31+600 41 16 1000 120 3.3 155 15.5

Measurements have been done to determine the physical and mechanical properties
of the soil. The results are shown in Appendix D.
The cross section K30+793 is chosen for the example calculations, it should be noted
however that not all soil properties are determined on this exact location, some differences
with the measured results are therefore to be expected. Based on the CPT test and borings
the soil profile is shown in . According to table 5-6, the pile at K30+793 has a length of 15.0
m, a wall thickness of 120 mm, a diameter of 1240 mm and a centre-to-centre distance of
3.3 m.

83
The PCC piling method

Table 5-6: Layer properties for K30+793 [17];

Layer number 1 2 3 4 5
Soil type Clay Silty Clay Clay Silt Sandy Silt
Top [m] 0.00 1.70 13.10 18.70 28.00
Bottom [m] 1.70 13.10 18.70 28.00 28.50
Thickness [m] 1.70 11.40 5.60 9.30 -
Water Table [m] -2.90 -2.90 -2.90 -2.90 -
q_c [MPa] 1.82 0.67 1.65 7.58 10.94
f_s [kPa] 46.31 11.68 51.49 81.41 95.06
R_f [%] 2.54 1.75 3.22 1.09 0.87
E_s [MPa] 6.70 3.34 6.22 18.42 22.02
c_u [kPa] - 30.48 - -
sigma_0 [kPa] 130 80 140 160 180
tau [kPa] 35 17 44 43 45

Water content [%] 25 37 29 29 -


Natural density [g/cm3] 1.85 1.45 1.44 1.76 -
Dry density [g/cm3] 1.48 1.34 1.44 1.47 -
Saturated density [g/cm3] 81.00 98.00 98.00 93.67 -
Void ratio [-] 0.82 1.02 0.885 0.84 -
Specific density [-] 2.70 2.70 2.72 2.69 -
Liquid limit [-] 28 31 46 30 -
Plastic limit [-] 20 23 26 24 -
Plasticity index [-] 8 9 20 6 -
Liquidity index [-] 0.59 1.73 0.13 0.90 -
Coefficient of compressibility [-] 0.33 0.61 0.27 0.18 -
Modulus of compressibility [MPa] 5.34 4.23 6.77 11.57 -
Preconsolidation pressure [kPa] 240 158 270 292 -
Compression index [-] 0.17 0.27 0.257 0.07 -
Relaxation index [-] 0.01 0.23 0.257 0.04 -
Coefficient of consolidation (100kPa) [10E-03 cm2/s] 3.72 4.43 4.65 5.10 -
Coefficient of consolidation (200kPa) [10E-03 cm2/s] 4.03 4.01 2.97 0.62 -
Permeability coefficient vertical [10E-06 cm/s] 5.73 2.41 2.75 29.68 -
Permeability coefficient horizontal [cm/s] 1.43 0.60 0.69 3.50 -
Cohesion [kPa] 41 43 46 9 -
Angle of internal friction [degrees] 19.5 16.3 15.7 41.7 -
Effective cohesion [kPa] 31 27 29 4 -
Effective angle of internal friction [degrees] 26.9 29.5 25.3 31.7 -

5.4.3 Chosen calculation methods


In the previous chapters a number of calculation methods for bearing capacity and
settlement are given. As decided in paragraph 4.5 the main focus will lie on the bearing
capacity and settlement of a single pile. Some verification of the Chinese and Dutch practice
methods will also be executed. Based on the limitations of the models described in the
previous chapters the following methods will be used:
• Bearing capacity single pile:
o PCC pile bearing capacity from the Chinese practice
o Tip bearing capacity with Koppejan
o Negative shaft friction with the method Zeevaert - De Beer
o Shaft bearing capacity according to NEN6740
o Plugging with the spring model
• Soil bearing capacity
o Brinch-Hansen
• Bearing capacity composite foundation

84
The PCC piling method

o Chinese practice
• Settlement single pile
o NEN6740 method
o Spring model
• Settlement composite foundation
o Chinese practice
o Equivalent raft / Equivalent pier method

5.4.4 Bearing capacity single pile


Bearing capacity calculations of single piles for the Yan-Tong case are made with the
above mentioned calculation methods, based on the descriptions in the previous chapters and
the pile and soil data of paragraph 5.4.2.

Chinese practice
A calculation of the bearing capacity is made with the most commonly used GeoHohai
method.
The bearing capacity of a single PCC pile is defined by equation (5.4) :

F sf = u ∑f l = 3.9(46.13 ⋅ 1.70 + 11.68 ⋅ 11.40 + 51.49 ⋅ 1.90) = 1200 kN


sik i

Pile tip bearing capacity with Koppejan


The pile tip bearing capacity is calculated with equation (5.5), the cone resistances
are determined from the CPT, see Appendix E:

⎛ q c ;I ;avg + q c ;II ;avg ⎞


Fr; max; tip = Atip ⋅ α p ⋅ β ⋅ s ⋅ 0.5⎜⎜ + q c ;III ;avg ⎟⎟
⎝ 2 ⎠

⎛ 1.8 + 1.7 ⎞
= 0.42 ⋅ 1 ⋅ 1 ⋅ 0.6 ⋅ 0.5⎜ + 1.6 ⎟ = 450 kN
⎝ 2 ⎠

Negative shaft friction


The negative shaft friction is based on the Method Zeevaert – De Beer. The
maximum negative shaft friction follows from equation (5.12). The value of the load on the
soil used in the Zeevaert-De Beer method depends on the fill height, the fill material, the pile
layout and the geotextile mattress. Since the load redistribution by the geotextile mattress is
beyond the scope of this report the load on the soil is taken from the long term monitoring
executed on the composite foundation, see paragraph 3.3.5. For the Yan-Tong case the
stress at the top of the soil is found to be approximately 50 kPa. The soil around the pile is
schematized as layer 2 for the entire pile length because of the calculation errors occurring

85
The PCC piling method

when using thin soil layers in the Zeevaert – De Beer model [12]. Layer 2 is chosen because
this is the thickest layer. The shaft friction then becomes:

i =n
F s ;nf ;d = A ∑ (σ '
i =1
0 ;h ;i ;d −σ 'm ;h ;i ;d ) = 9.68 ⋅ (118 − 40 ) =755 kN

with:

σ 'm ;h ;i −1;d = p 0;d = 50 kPa

σ '0;h ;i ;d = σ 'm ;h ;i −1;d +h1γ 'i ;d = 50 + 15 ⋅ 4.53 = 118 kPa

γ 'i ;d
σ 'm ;h ;i ;d =
m1
( ) ( )
1 − e − mi hi + σ 'm ;h ;i −1;d e − mi hi =
4.53
0.12
( ) ( )
1 − e − 0.12 ⋅15 + 50 e − 0.12 ⋅15 = 40 kPa

There are only soft soil layers present in this profile and the calculated negative shaft
friction is larger than the total load on the soil of 480 kN, calculated based on the measured
soil stress. This can be explained by the measurements in paragraph 3.3.5 where the
settlement of the soil is approximately 100 mm more than that of the pile, while in [38] a
minimum differential settlement of 200 mm is required for full mobilisation of the shaft
friction in all the soft layers. To try to make a realistic approach of the negative shaft friction
it is assumed that there is negative shaft friction until the level where the entire load on the
soil is brought to the pile. So h for Fs;ns = 480 kN. A value of h of 9.4 m is then found
iteratively.
Only from this level on, the shaft bearing capacity can be calculated, since when
negative skin friction occurs no positive skin friction can be mobilized for the bearing
capacity. The positive shaft friction, or pile shaft bearing capacity is only active over the
length of the pile between 9.4 and 15 m below pile head level. The pile can be divided into
two parts, one where negative shaft friction occurs and one where positive shaft friction
occurs, see figure 5-19.

86
The PCC piling method

Negative skin friction,


soil settles more than pile

Positive skin friction, pile Inner shaft


settles more than soil bearing
capacity or
plug bearing

Tip bearing capacity

Figure 5-19: All interaction forces with the soil for a schematised single PCC pile;

Pile shaft bearing capacity according to NEN6743


The pile shaft bearing capacity is calculated according to the Koppejan method [12].
Two values are calculated: with and without the negative skin friction, corresponding to
respectively the pile load test and the long term monitoring. The shaft bearing resistance
follows from equation (5.9):

With negative skin friction:

Fr ;max;shaft ;z = uα s ∑q c ;s ;i H i = 3.90 ⋅ 0.025(0.67 ⋅ 3.7 + 1.85 ⋅ 1.9) = 550 kN

Without negative skin friction (shaft bearing over full pile length):

Fr ;max;shaft ;z = uα s ∑q c ;s ;i H i = 3.90 ⋅ 0.025(1.82 ⋅ 1.7 + 0.67 ⋅ 11.4 + 1.65 ⋅ 1.9 ) = 1350 kN

Plugging with the spring model


The bearing capacity of the plug and the resulting settlement are determined with
the spring model, see paragraph 5.2.5. Since the spring model is not often applied in practice
and there is little experience with the model the effect of variation of parameters on the plug
bearing capacity is determined. This is done based on the parameters of the Yan-Tong
project.
There are large differences between the load test on the single pile and the
measurements during embankment construction:
• Load test: quick loading until failure with small settlements and large load on the pile,
undrained.

87
The PCC piling method

• Embankment: slow loading with stresses in the pile far below bearing capacity but with
large settlements due to consolidation and group-effect, drained.
Since the main focus of this analysis is to determine the bearing capacity of a single pile only
the load test on a single pile is discussed here. An overview of the relevant parameters is
shown in table 5-7.

Table 5-7: Relevant soil parameters plugging;

Parameter Load test


Calculation Undrained
Soil stiffness at tip 8.14 MPa
Soil stiffness active plug 6.20 MPa
Soil stiffness passive plug 3.84 MPa
Load on the pile 1650 kN
Pile head displacement 15 mm
Poisson’s ratio soil 0.45
Friction angle soil-pile infinite

The spring model consists of five different springs with the following spring constants
(based on table 5-7):

E soil _ tip R i 8.14 ⋅ 10 3 ⋅ 0.5


Ki =2 =2 = 10.2 MN/m
1 −υ2 1 − 0.45 2
E soil _ pile R i 3.84 ⋅ 10 3 ⋅ 0.5
K inner = 2 =2 = 4.82 MN/m
1 −υ2 1 − 0.45 2
E soil _ tip R 0 8.14 ⋅ 10 3 ⋅ 0.62
Kw = = = 11.1 MN/m
(1 − υ 2 )ω (n ) (1 − 0.33 2 ) ⋅ 0.57

K pl = 2πR i β a D M = 2π ⋅ 0.5 ⋅ 0.17 ⋅ 9.19 ⋅ 10 3 = 19.1 MN/m

where:
1 −υ 1 − 0.45
D M= E pl = ⋅ 6.20 ⋅ 10 3 = 9.19E+03 kN/m2
(1 + υ )(1 − 2υ ) (1 + 0.45)(1 − 2 ⋅ 0.45)

0.45
β a = K 0 tan δ = tan 17.5° = 0.26
1 − 0.45

The interaction factors between the springs are given by:

n −1 + 1 − n2 0.81 − 1 + 1 − 0.812
α1 = = = 0.48
2n 1 − υ 2 ω (n ) 2 ⋅ 0.81 1 − 0.452 ⋅ 0.57

n ⎛⎜1 − 2 1 − n 2ω (n ) ⎞⎟ 2
α2 = ⎝ ⎠ = 0.81(1 − 2 1 − 0.81 ⋅ 0.57 = 0.64.
1 − 1 − n2 1 − 1 − 0.812

88
The PCC piling method

The contribution of the wall bearing to the total end bearing load follows from these formulas
and the relationship between the wall and plug settlement:

⎛ ⎞ ⎛ ⎞
⎜ ⎟ ⎜ ⎟
⎜ 1 − α1 ⎟ 1 − 0.48
Q =⎜ + 1 ⎟Qw = ⎜ + 1 ⎟Qw = 1.16 ⋅ Qw
K Kw ⎜ 11.1 11.1 ⎟
⎜ (1 − α 2 ) w + ⎟ ⎜ (1 − 0.64) + ⎟
⎜ K K ⎟ ⎝ 10 .2 3.9 ⎠
⎝ i pl .total ⎠

where:

1 1 1
= + → K pl .total = 3.9 MN/m
K pl .total K inner K pl

So the total end bearing load is 1.16 times the wall end bearing load, which means the plug
only has about 16% of the bearing capacity of the wall in the load test according to the
spring theory.
The wall displacement, which equals the pile head displacement, can be calculated
with:

Qw Q − Qw
uw = + α2
Kw Ki

The shaft bearing is fully mobilized if the displacement is more than 10 mm, it is assumed
this will be the case and this will be verified later. The ultimate wall bearing load can now be
calculated from the total pile bearing (3.3.5) and the calculated maximum shaft resistance,
calculated above. This gives: Qu = 1650-1350 = 300 kN, which results in a settlement at
failure of:

Q w ;u Q − Q w ;u 300 / 1.16 300 − 300 / 1.16


u w ;u = + α2 = + 0.64 = 34 mm
Kw uK i 11.1 10.2

This is about a factor 2 larger than the measured settlement of 15 mm. Note that only the
compression of the layers 4D below the pile tip is considered. The assumption of the full shaft
mobilization is correct.
The parameters in the spring model that are determined from soil tests and are of
influence on the plug bearing capacity and overall settlement are the following:
• Soil stiffness
• Poisson’s ratio: ν
89
The PCC piling method

The soil stiffness in table 5-4 is taken from the measurements of the Yan-Tong project
geotechnical survey and is based on borings, the resulting stiffness is assumed to be
determined undrained. This undrained stiffness is as a rule of thumb reduced to a quarter of
the original value in the drained case. The Poisson’s ratio is not known but assumed to be
around 0.45 for the undrained case and around 0.33 for the drained case. In figure 5-20 the
soil stiffness of the soil below the pile, the soil in the passive plug and the soil in the active
plug is varied from 10% to 1000% of the values given in table 5-7.

0.200
Stiffness soil below tip
0.180 Stiffness soil in passive plug

0.160 Stiffness soil in active plug

Measured settlement
0.140

0.120
uw [m]

0.100

0.080

0.060

0.040

0.020

0.000
0.10 1.00 10.00

E/E measured

Figure 5-20: Sensitivity of spring model to soil stiffness variations, undrained case;

From the figure it can be seen that the influence of the soil stiffness in the plug, both active
and passive, is very small. For the variation of 10-1000% of the soil stiffness the final
settlement only lies between 25 and 27 mm. The soil stiffness below the plug is much more
influential, for the given variation the calculated settlement lies between 3 and 235 mm.
The relationship between the active plug and passive plug soil stiffness and the
spring constants is linear, see equations (5.21), (5.22) and (5.23), so the spring properties of
the soil plug in the considered range have almost no effect on the end settlement of the pile.
This can be explained by (5.26) and (5.27) where it is seen that an increase in the overall
plug stiffness will lead to a higher part of the load taken by the soil under the pile plug,
expressed in the relationship between Q and Qw. Since the spring constants of the soil below

90
The PCC piling method

the pile wall (Kw) and the plug (Ki) are comparable and the factor α2 is not very small (~0.7 in
this case), the calculated settlement only varies slightly.
Although the calculated settlement with different stiffness of the soil in the pile hardly
changes, the ultimate bearing capacity does. A strong spring in the plug will lead to a
distribution of forces on the soil below the plug and the soil below the pile wall. A weak plug
however will result in a large force on the soil below the pile wall and a smaller force on the
soil below the plug. In the last case failure of the soil will be reached earlier than in the first
case.
In figure 5-21 the Poisson’s ratio of the soil is varied between the 0.20 and 0.50.

0.035

0.030

0.025
uw [m]

0.020

0.015

Poisson's ratio
0.010

Measured settlement
0.005

0.000
0.20 0.25 0.30 0.35 0.40 0.45 0.50

Poisson's Ratio [-]

Figure 5-21: Sensitivity of spring model to Poisson’s ratio variations, undrained case;

It can be seen that the variation of the Poisson’s ratio between 0.20-0.50 leads to a variation
in the calculated settlement of 24-32 mm. The influence of the Poisson’s ratio is significant
but, as can be seen from figure 5-21, not large enough to explain the difference between the
measured value for the settlement and the calculated value.
In conclusion it can be said that for the settlement of the loaded pile both the soil
stiffness below the pile and the Poisson’s ratio are of large influence of the settlement. These
parameters are hard to determine correctly in situ thus limiting the viability of the spring
method. For a correct settlement result the soil stiffness below the pile should be about two
times larger than measured in the Yan-Tong case.

Total bearing capacity single pile


The total bearing capacity of a single PCC pile in the Yan-Tong highway embankment
according to the different methods is given in table 5-8.

91
The PCC piling method

Table 5-8: Overview calculated bearing capacity single pile according to Dutch practice;

Method Bearing
capacity
Chinese practice (only friction) 1200 kN
Dutch practice 1750 kN
• Tip capacity (Koppejan) 340 kN
• Shaft capacity (Koppejan) 1350 kN
• Plug capacity (16% of tip capacity) 55 kN
Measured capacity single pile 1650 kN

5.4.5 Soil bearing capacity

Brinch-Hansen
As discussed in paragraph 5.2.6 the bearing capacity from the soil can best be
determined by the acceptable settlement, with the Brinch-Hansen failure mechanism for the
undrained case as an upper limit. The maximum bearing capacity according to the Brinch-
Hansen criterion is given in equation (5.48). The factors sc and ic both become unity since the
length of the foundation is very large compared to the width. For the limit of the bearing
capacity at a depth z = 0, follows:

σ ' max; d = (π + 2)f undr ;d ⋅ s c ⋅ i c + σ 'v ;z ;o ;d = (π + 2) ⋅ 30.48 ⋅ 1 ⋅ 1 + 0 = 157 kPa

Note that the undrained shear strength is taken for layer 2 since most of the slip circle will be
in this layer. The ratio te/Bef, where te is the influence depth of the slip circle, is around unity
for a internal friction angle of 25-30 degrees. The undrained shear strength of layer 1 and 3
is higher so layer 2 is governing.

5.4.6 Bearing capacity composite foundation

Chinese practice
The bearing capacity of the soil is taken from the CPT test result and is 100 kPa
according to [17]. The correction and loading factors are based on experience and are also
given in [17], where λ2 is chosen 0.9 and β as 1.0. With a value of m of Ahead/Atotal = 0.11,
the bearing capacity of the composite foundation is given by equation:

pcf = m ⋅ p pf + λ2 β (1 − m ) p sf = 0.11 ⋅ 1000 + 0.9 ⋅ 1(1 − 0.11) ⋅ 100 = 190 kPa

92
The PCC piling method

Note that the bearing capacity of the single pile is taken from the GeoHohai calculation
method in paragraph 5.2.2. If the pile bearing capacity according to the Dutch practice is
taken combined with the soil bearing capacity according to the Brinch-Hansen method it
follows that:

pcf = m ⋅ p pf + λ2 β (1 − m ) p sf = 0.11 ⋅ 1450 + 0.9 ⋅ 1(1 − 0.11) ⋅ 157 = 290 kPa

It has to be evaluated if a load of this magnitude will not lead to unacceptable high
settlements.

5.4.7 Settlement single pile

NEN 6743
A single pile without group effect is considered. The maximum load of 1650 kN is
taken from the measurements of the load test on the single pile, see paragraph 3.3.5.
Because the group effect is not taken into account w2;d in equation(5.56) is zero and the total
settlement becomes equal to the calculation value of the settlement of the top of the pile as
in equation (5.57). This settlement consists of two parts, the compression of the pile and the
settlement of the pile tip due to the load on the pile.
The settlement of the pile tip is calculated in figure 5-22, where the maximum shaft
resistance and the maximum tip resistance are shown. The equivalent pile diameter is defined
as the smallest cross section of the pile surface, taken in this case as the wall thickness. The
tip bearing capacity and shaft bearing capacity are taken from table 5-8 where the plug
bearing capacity is added to the tip bearing capacity.

Fr;shaft;d [kN] Fr;tip;d [kN]


1400 1200 1000 800 600 400 200 0 200 400

5
1650 kN

10

15 wtip;d

Figure 5-22: Calculation pile head settlement [12];

As the total bearing capacity of the pile determined by the Dutch practice for displacement
piles is higher than the measured settlement, the full pile head displacement is not yet

93
The PCC piling method

reached in figure 5-22. The calculated pile head settlement for 1650 kN is approximately 9
mm while the maximum settlement is 12 mm and will be reached at a load of 1750 kN.
The elastic compression of the pile head is calculated with equation (5.58) where:

L ⋅ Favg ;d 15 ⋅ 1000
w el ;d = = = 1.1 mm
Atip ⋅ E p ;mat ;d 0.41 ⋅ 20 ⋅ 10 4

with
0 ⋅ 1650 + 0.5(15 − 0 )(1650 + 350 )
Favg ;d = = 1000 kN
15

Since there is positive shaft friction over the entire length of the pile, I is zero.
In figure 5-23 the calculated settlement with the NEN method and the settlement
measured during the Yan-Tong project are plotted. It can be seen that the NEN method
underestimates the settlements. This could be caused by simplification or insufficient exact
soil data.

Load [kN]
0 250 500 750 1000 1250 1500 1750
0

4
Displacement [mm]

8
NEN 6743 Calculation

10
Yan-Tong measurements

12

14

Figure 5-23: Comparison calculated settlements and measurements for Yan-Tong project;

94
The PCC piling method

Spring model
The settlement calculated with the spring model is shown in paragraph 5.4.4 and is
about 34 mm. A sensitivity analysis of the input parameters is also given there.

5.4.8 Settlement of the composite foundation

Composite modulus of elasticity of Chinese practice


The settlement of the pile improved area of the Yan-Tong project is calculated with
the modulus of elasticity of the composite foundation, equation (5.49):

n
Δp i 105 105 105
si = ∑E
i =1 csi
Hi =
587
1.7 +
586
11.4 +
588
1.9 = = 3 mm

where:

E cs 1 = mE ps + (1 − m )E ss 1 = 0.04 ⋅ 1.4 ⋅ 10 4 + (1 − 0.04) ⋅ 5.34 =


587 MPa

E cs 2 = mE ps + (1 − m )E ss 2 = 0.04 ⋅ 1.4 ⋅ 10 4 + (1 − 0.04) ⋅ 4.23 =


586 MPa

E cs 3 = mE ps + (1 − m )E ss 3 = 0.04 ⋅ 1.4 ⋅ 10 + (1 − 0.04) ⋅ 6.77 =


4
588 MPa

The load on the lower strata is commonly calculated with the pressure diffusion
method of equation (5.54), with a spreading angle of 1:2 gives:

Bp 62 ⋅ 105
pb = = = 71 kPa
(B + 2h tan( β ) ) (62 + 2 ⋅ 15 tan(45))

The settlement of the underlying stratum is calculated with equation (5.53) where
the location of the stiff layer is assumed at 50 meter below surface (based on table 5-4):

n max
Δp bi 71 71 71
s2 = ∑E
i = n +1 si
Hi =
6.8
3.7 +
18.4
1.1 +
22.0
22 = 145 mm (drained situation)

This is assuming that layer 5 continues to a depth of 50 m below surface and that the
stiffness remains constant, which is not the case. In reality the stiffness will increase with
depth.
The total calculated settlement now become 148 mm with very rough and
conservative estimate for the lower strata. The measured settlement of the piles was
approximately 250 mm and that of the soil between the piles was approximately 350 mm. It
can be seen that using the composite modulus of elasticity underestimates the settlement of

95
The PCC piling method

the composite foundation. This method also does not take into account consolidation and
creep effects.

Equivalent raft/pier method


The first step is to determine which of the two schematizations can be best applied.
In paragraph 5.3.3 it is stated that an equivalent raft can best be applied when the value of R
is greater than 4 in equation (5.68) and an equivalent pier if the value is smaller than 4.
Assuming a square foundation layout (20x20 piles, where 20 is the number of piles in the
cross section of the Yan-Tong embankment) this gives:

ns 400 ⋅ 3.3
R = = = 9.4 > 4
l 15

which gives the equivalent raft method as best approximation.


The equivalent raft is located at 2/3 of the pile length in the bearing stratum for
primarily friction piles. For calculation purposes it is proposed that the “soft soil” layers in
figure 5-16 are defined as the layers where negative skin friction occurs because these layers
do not add to the bearing capacity of the piles. The bearing stratum therefore starts from z =
9.4 (see paragraph 5.4.4) below ground level. The elastic compression of the pile is small and
can be neglected. Equation (5.65) then gives the settlement of the equivalent raft, calculated
for all the layers below the equivalent raft (modulus of elasticity for the undrained case):

n
⎛ Iε ⎞
w raft = F D q ∑ ⎜⎜⎝ E
i =1
⎟ hi

s ⎠i

⎛ ⎛ 0.50 ⎞ ⎛ 0.70 ⎞ ⎛ 0.75 ⎞ ⎛ 0.50 ⎞ ⎞


= 1 ⋅ 105⎜⎜ ⎜ ⎟3.7 + ⎜ ⎟5.6 + ⎜ ⎟9.30 + ⎜ ⎟22.0 ⎟⎟ = 198 mm
⎝ ⎝ 4.23 ⎠ ⎝ 6.77 ⎠ ⎝ 18.42 ⎠ ⎝ 22.02 ⎠ ⎠

Note that the factor FD is kept at 1.0 and that a stiff raft is assumed on top of the piles. Again
layer 5 is assumed to continue until a depth of 50 meters below surface and again no
consolidation and creep is taken into account.

5.5 Conclusion
The results can be compared with the data obtained from the long term monitoring
and load tests. The comparison is shown in table 5-9.

Table 5-9: Comparsion calculation methods with measurements for single pile;

Method Bearing capacity Offset Final settlement Offset

96
The PCC piling method

Load test 1650 kN - 15 mm -


Chinese practice 1200 kN -27% n.a. -
Dutch practice* 1750 kN +6% 11 mm** -27%
Spring model n.a - 34 mm +127%
*including plugging
**for a load of 1650 kN, for 1750 kN a settlement of 13 mm is calculated

Table 5-10: Comparsion calculation methods with measurements for embankment;

Method Bearing capacity Final settlement Offset


Embankment 150 kPa* 250-350 mm -
Chinese practice 190 kPa 148 mm -50%
Equivalent raft - 198 mm -34%
*not loaded until failure

The NEN method gives a rather good approach for both the bearing capacity of the
single pile and the settlement. The somewhat simplistic GeoHohai method for bearing
capacity calculations gives a margin of error of less than 30%. The spring model
overestimates the settlement noting that the influence of the, difficult to determine, soil
stiffness is very large on this result.
Although conservative assumptions are made for the soil properties of the layers
below -28 m both the methods underestimate the settlement. For the Chinese practice this
overestimation can be explained due to the use the composite stiffness modulus. The
negative offset of the equivalent raft can partly be explained by the assumption of a stiff raft.
Both methods also only include direct compression and when using the drained modulus of
elasticity not the consolidation and creep which takes place in the period of time of the Yan-
Tong embankment construction.
For the settlement of a single PCC pile the NEN method is advised with inclusion of
negative shaft friction and plugging.

97
The PCC piling method

6 Further applications

6.1 Introduction
In chapter 4 the application of the PCC pile as a soil improving pile is evaluated
compared to the HSP and AuGeo piles. Part of the conclusion was the notion that the quality
of the PCC pile was such that it would be feasible to apply the system apart from soil
improvements. This part of the report will discuss the possibilities.
In paragraph 6.3, two applications, building foundations and bridge abutments, are
discussed. The bearing capacity for both compression and tension loading is calculated.
Following these calculations different reinforcement solutions for resisting a bending
moment are described in paragraph 6.4.
In paragraph 6.5 the application of these solutions to the PCC pile and the required
changes to the design are described.
Based on the previous chapters a conclusion drawn in chapter 5 to determine the
viability of the PCC pile in the discussed cases.

6.2 Requirements

6.2.1 Introduction
To determine if and how the PCC piling method can best be applied outside the
traditional soil improvement field an overview of two possible applications is given. The
applications are:
• Foundation of a large building and
• Foundation of bridge abutments.
Both applications have their own problems and demands on the piling system used. The
focus will be on application in soft soil since the PCC pile is considered to be especially suited
for that case.

6.2.2 Vertical loading


One of the most important functions of the foundation pile is the ability to carry the
load applied on it. An extensive description of the vertical bearing capacity of the single PCC
pile is given in paragraph 5.2 of this report. Below some special comments for the application
in a foundation are made.

Pressure loading
The main purpose of the foundation of a large building is to limit the settlement and
differential settlement of the building when constructed on soft soils. This can be done by
transferring the load of the building to a stiffer layer which will settle less than the soft layers.

98
The PCC piling method

The commonly used method for this load transfer is a pile foundation connected to the
building, the pile tip placed in a bearing sand layer.
Sufficient piles must be applied so that the load on a single pile is not higher than the
bearing capacity of this pile. The soil mechanical bearing capacity consists of pile end
bearing, plug bearing, shaft bearing (including negative shaft friction), see paragraph 5.2.

Tension loading
Apart from pressure loading a foundation pile can also be subject to tension loading
when the pile is used as a tension pile or when high wind loads cause a number of piles in
the foundation to be subjected to tension, see figure 6-1.

Wind load

Tension or reduced
compression

Compression

Figure 6-1: Tension and pressure forces in piles due to wind loading;

Since un-reinforced concrete can only sustain small tension forces [42],
reinforcement over the length of the pile might be required to sustain the tension forces in
the pile. The amount of reinforcement required is dependent on the tensile load on the pile.
The upper value of the tension force in a pile as a result of the tensile load is the force
required to pull the pile out of the soil, the pull-out capacity.
The pull out capacity of a single pile is given in [4] as:


F r ;tenstion ;d = u p ;avg ⋅ p r ;z ;d dz
0
(6.1)

where:
Fr;tension;d design value of the bearing capacity of a pile loaded on tension
up;avg mean circumference of the pile

99
The PCC piling method

L pile length over which shaft friction is calculated


pr;z;d design value of the shaft friction at depth z
q c ;z
= αt ⋅ ξ
γm
z depth
αt factor from table 6-2 depending on the installation process
qc;z cone resistance at depth z
ξ safety factor dependent on number of piles (0.8 in this case)
γm material safety factor (1.4 in this case)

Table 6-1: Maximum values for αt for sand and sand with gravel;

Pile class/type αt
ground displacing methods
• Driven prefabricated concrete piles and steel tube piles with closed tip 0.007
• Cast-in-place where the concrete column is pressed against the soil and tube 0.0012
back by driving
• Idem, tube back by vibration 0.010
• Driven MV piles 0.012
• Continuous flight auger piles:
o Grout injection or mixing 0.009
profiles with little soil displacements
• Steel profiles, driven (including open steel tubes and sheet pile walls) 0.004
piles with soil removal
• Bored piles 0.0045

Table 6-2: Values for αt for clay and silt [4];

Soil type Relative depth αt*


Clay/silt qc ≤ 1 MPa 0 < z/Deq < 20 0.02
Clay/silt qc ≤ 1 MPa z/Deq > 20 0.025
Clay/silt qc > 1 MPa - 0.025
*Values are based on literature

The occurrence of a soil plug influences the tension capacity of the PCC pile. In [12]
it is stated that the plug compression bearing capacity is equal to the tip bearing capacity of
the plug or the inner shaft bearing capacity, whichever is the lowest. In the same way it can
be derived that the pull out resistance of the plug in the PCC pile is the lowest of the inner
shaft capacity calculated with equation (6.1) and the dead weight of the soil inside the pile.
Either the wall friction is large enough to let the whole plug cling to the pile or the soil weight
is large enough to break the wall friction. In the first case the soil plug is pulled out with the
pile and in the second case the pile is pulled out of the soil leaving the plug behind.

100
The PCC piling method

6.2.3 Horizontal load


When applied as a soil improvement the PCC pile will only have to bear very small
horizontal loads. When applied in foundations however, the pile head is connected rigidly to
the construction and significant horizontal loads can occur. In designing these connections it
is common practice to assume a certain eccentricity of the load on the pile. This eccentricity
results in a moment on the head of the pile resulting in a tension load on the concrete. A
concrete pile has only a very limited capacity for tension loading, so reinforcement of the
head can be required.
The eccentricity of the load is dependent on the installation of the pile and the
position of the connection between pile and building. In design the eccentricity is commonly
assumed to be 50 mm. Because of its large radius a larger eccentricity is assumed for the
PCC compared to commonly used foundation piles. The eccentricity is taken at an arbitrary
and conservative value 100 mm for the PCC pile. The occurring moment is defined as force
multiplied by arm. In this case the load on a single pile multiplied by the 100 mm:

M head ;d = F head ;d ⋅ u ecc (6.2)

where:
Mhead;d design value of the maximum moment in pile head
Fhead;d design value of the maximum load on pile head
uecc eccentricity of load (100 mm)

Bending moments in the pile can also be caused by horizontal displacements of the
soil. Using analytical programs like MSheet, the resulting tension force in the pile can be
calculated.

6.2.4 Settlement
The main reason for applying piles in a foundation is to limit the settlement and the
differential settlement thus preventing damage to the building. The settlement calculation of
a single PCC pile and a pile group is extensively described in paragraph 5.3. The allowable
settlement for buildings is generally much smaller than that of embankments. This should be
considered in the design.
An important item is the connection between the foundation and the building.
Difference can be made between piled rafts, where there are piles connected to stiff plates,
and pile groups, where a summation of each single pile is made [30]. Both methods are
described in chapter 5

101
The PCC piling method

6.3 Case studies

6.3.1 Introduction
The case studies serve as a means for identifying possible applications of the PCC
pile. The application as ground improvement is already discussed in previous parts. In the
western part of The Netherlands where the big cities and thus big building projects are
located the soil profile mainly consists of a number of soft soil layers underlain by a stiff sand
layer at depth of 15-20 meter below ground level. Case 1 considers a foundation in this kind
of soil.
To test the limits of the PCC pile a case is considered where the pile is used in a
foundation for a bridge abutment, where piles are generally subjected to high bending
moments. Case 2 considers the application of the PCC pile here.
The PCC pile might also be usable as a building foundation pile on friction only. Since
the field of application for this kind of pile in The Netherlands is rather small due to the
presence of stiff layers at medium depths, this case is left out.

6.3.2 Case 1: Foundation on tip bearing

Description
The construction of a fictional high rise building in the Rotterdam area is considered
where foundation piles have to be applied. A representative CPT test is shown in Appendix F.
The calculation of the piles will be made based on this. The purpose of this case is to
compare the bearing capacity of the PCC pile and the Vibro pile.
The considered piles are the PCC pile as described in the Yan-Tong case in chapter 5.
The Vibro pile is basically a cast-in-place circular concrete pile, comparable to the PCC pile
but solid instead of hollow, the design is based on the description in [43] without an
increased footplate as is normally applied. The pile properties are given in table 6-3.

Table 6-3: Pile properties after installation;

Pile Value
PCC pile
• Outer diameter 1240 mm
• Inner diameter 1000 mm
• Cross-section surface 0.42 m2
• Equivalent diameter 120 mm
• Centre-to-centre distance 3.3 m
• Concrete C12/15
Vibro pile
• Outer diameter 400 mm
• Cross-section surface 0.13 m2
• Equivalent diameter 400 mm
• Centre-to-centre distance 1.8 m
• Concrete C30/35

102
The PCC piling method

The soil properties are given in table 6-4.

Table 6-4: Soil properties;

Layer 1 Layer 2 Layer 3 Layer 4


Soil type [-] Sand Peat Clay Sand
Top level (NAP) [m] -0.5 -5.0 -11.0 -17.0
Bottom level [m] -5.0 -11.0 -17.0 -35.0
Layer thickness [m] 4.5 6.0 6.0 18.0
Saturated unit weight [kN/m3] 21.0 12.0 20.0 20.0
Dry unit weight [kN/m3] 19.0 12.0 20.0 19.0
Angle of internal friction [degrees] 32.5 15.0 25.0 32.5

The ground water table is assumed at ground level (-0.5 m NAP). In this case the piles will be
installed with the pile tip 2 m in the stiff sand layer at 17 m below NAP. The efficiency of the
piles will be determined by the volume of concrete used per meter length compared to the
bearing capacity.

Bearing capacity
The bearing capacity of the PCC and Vibro piles is calculated with the 4D-8D method
[12] as described in paragraph 5.2.

Tip bearing
The bearing capacity of a single PCC pile has been calculated based on the CPT
values, see Appendix G:

⎛ q c ;I ;avg + q c ;II ;avg ⎞


F r ;max;tip = Atip α p ⋅ β ⋅ s ⋅ 0.5⎜⎜ + q c ;III ;avg ⎟⎟
⎝ 2 ⎠

⎛ 16.5 + 14.5 ⎞
= 0.42 ⋅ 1 ⋅ 1 ⋅ 0.6 ⋅ 0.5⎜ + 13.0 ⎟ = 3.6 MN
⎝ 2 ⎠

The same calculation for the Vibro pile, see Appendix H, results in:

⎛ q c ;I ;avg + q c ;II ;avg ⎞


F r ;max;tip = Atip α p ⋅ β ⋅ s ⋅ 0.5⎜⎜ + q c ;III ;avg ⎟⎟
⎝ 2 ⎠

⎛ 12 + 10.2 ⎞
= 0.13 ⋅ 1 ⋅ 1 ⋅ 1 ⋅ 0.5⎜ + 5 ⎟ = 1.0 MN
⎝ 2 ⎠

The equivalent diameter of the PCC pile is smaller than that of the Vibro pile which
results in smaller values of 4D and 8D because the failure planes are also smaller. Therefore
higher values for the qc can be taken. This is a positive aspect of the PCC pile however the tip

103
The PCC piling method

shape also results in a reduction via the shape factor s because of the non-square/round
shape of the pile tip.

Positive shaft friction


Since the ground level in the Rotterdam area is settling at a rate of approximately 1 cm/year,
negative shaft friction is assumed over the height of the soft soil layers and positive shaft
friction over the foundation layer. The design value of the positive shaft friction is calculated
by:

F r; max; shaft; z = u ⋅ L pos ⋅ α s ⋅ q c ;z = 3.9 ⋅ 2 ⋅ 0.012 ⋅ 10000 = 935 kN

For the Vibro pile this value is calculated in the same way:

F r; max; shaft; z = u ⋅ L pos ⋅ α s ⋅ q c ;z = 0.38 ⋅ 2 ⋅ 0.012 ⋅ 10000 = 90 kN

The circumference of the Vibro pile is much smaller, resulting in a lower shaft bearing
capacity.

Negative shaft friction


The negative shaft friction is calculated with the Zeevaert-De Beer method according
to [12] for pile groups with multiple soil layers, see paragraph 5.2.4

i =n
F s ;rep ;nf = A ∑ (σ '
i =1
0 ;h ;i ;rep −σ ' m ;h ;i ;rep )

The values of K0;i;reptanδi;rep for calculation of m as described in paragraph 5.2.4 are assumed
to be 0.5 for sand and 0.25 for clay and peat [38]. Now follows:

σ ' m ;h ;i −1;rep = p 0;rep 0 kPa (no top load on the soil)

σ ' 0;h ;i ;rep = σ ' m ;hli −1;rep +h1γ ' i ;rep

γ '1'rep
σ 'm ;h ;1;rep =
m1
( ) (
1 − e − m1h1 + σ 'm ;h ;0;rep e − m1h1 = )
11
0.18
( ) ( )
1 − e − 0.18 ⋅ 4.5 + 0 ⋅ e − 0.18 ⋅ 4.5 = 34 kPa

γ '2;rep
σ 'm ;h ;2;rep =
mi
( ) (
1 − e − m2h2 + σ 'm ;h ;1;rep e − m2h2 =
2
0.09
) ( ) ( )
1 − e − 0.09 ⋅6 + 34 ⋅ e − 0.09 ⋅6 = 29 kPa

γ '3;rep
σ 'm ;h ;3;rep =
m3
( ) (
1 − e − m3h3 + σ 'm ;h ;2;rep e − m3h3 =
10
0.09
) ( ) ( )
1 − e − 0.09 ⋅6 + 34 ⋅ e − 0.09 ⋅6 = 63 kPa

and:

104
The PCC piling method

σ ' 0;h ;1;rep = σ ' m ;hl 0;rep +h1γ '1;rep = 0 + 4.5 ⋅ 11 = 50 kPa

σ ' 0;h ;2;rep = σ ' m ;hl 1;rep +h 2 γ ' 2;rep = 34 + 6 ⋅ 2 = 46 kPa

σ ' 0;h ;3;rep = σ ' m ;hl 2;rep +h 3γ ' 3;rep = 29 + 6 ⋅ 10 = 89 kPa

This results in:

i =n
F s ;rep ;nf = A ∑ (σ '
i =1
0 ;h ;i ;rep −σ ' m ;h ;i ;rep ) = 10.9((50 − 34 ) + (46 − 29 ) + (89 − 63)) = 630 kN

The same method is used for the calculation of the negative skin friction for the Vibro
pile. The area of effect of the Vibro pile is dependent on the pile spacing. For, a centre-to-
centre distance of 1.8 m the negative skin friction becomes:

i =n
F s ;rep ;nf = A ∑ (σ '
i =1
0 ;h ;i ;rep −σ 'm ;h ;i ;rep ) = 3.24 ((50 − 44 ) + (56 − 48 ) + (108 − 95 )) = 85 kN

As expected, the negative shaft friction is also much smaller due to the smaller size of the
Vibro pile’s shaft.

Plugging
Since the piles are placed 2 m in the stiff bearing layer some plugging might occur in
the PCC pile. In [31] the active plug length in a steel pipe pile in sand is considered to be 2-4
times the inner diameter of the pile. It is therefore not guaranteed that installing the PCC pile
2 m into the sand will result into full plugging. In [2] the inner friction model (as described
paragraph 5.2.5) is used to calculate the plug bearing of a pile in sand:

⎛ γ ' ⎞ θ a La γ '
q ebplug = ⎜⎜ p a + ⎟e −
⎝ θ a ⎟⎠ θa

with:
4βa
θa =
D
τi sin ϕ sin(Δ − δ )
β = = active friction ratio for the pile at failure
σ 'v 1 + sin ϕ cos (Δ − δ )
sin δ
sin Δ =
sin ϕ

105
The PCC piling method

pp =
γ'
θp
(
−θ L
1−e p p ) passive plug bearing

with:
4β p
θp =
D
sin ϕ sin(Δ − δ )
βp = passive friction ratio for the pile at failure
1 − sin ϕ cos (Δ − δ )

The subscript a and p stand for “active” and “passive” plug. This results in:

sin 32
sin Δ = =1
sin 32
sin ϕ sin(Δ − δ ) sin 32 sin(90 − 32)
βp = = = 0.43
1 − sin ϕ cos (Δ − δ ) 1 − sin 32 cos (90 − 32 )

sin ϕ sin(Δ − δ ) sin 32 sin(90 − 32)


βa = = = 0.35
1 + sin ϕ cos (Δ − δ ) 1 + sin 32 cos (90 − 32 )

4βa 4 ⋅ 0.35 4β p 4 ⋅ 0.43


θa = = = 1.41 and θ p = = = 1.73
D 1 D 1

pp =
γ'
θp
(
−θ L
1−e p p =
7.4
1.73
) ( )
1 − e −1.73⋅15 = 4.25 kPa

⎛ γ ' ⎞ θ a La γ ' ⎛ 10 ⎞ 1.41⋅1.2 10


q ebplug = ⎜⎜ p a + ⎟e
⎟ − = ⎜ 4.25 + ⎟e − = 182 kPa
⎝ θa ⎠ θa ⎝ 1.41 ⎠ 1.41

The results in a value for the plug bearing capacity of:

F plug ;max = q ebplug ⋅ u inner 140 kN

Overview
Table 6-5 gives an overview of the results of the pile bearing capacity calculation. All
results are maximum values..

Table 6-5: Maximum values of bearing capacity calculation case 1;

PCC pile Vibro pile


Tip bearing capacity +3800 kN +1200 kN
Shaft bearing capacity +935 kN +90 kN
Negative skin friction (representative) -630 kN -85 kN
Plug bearing capacity +140 kN -
Total bearing capacity single pile 4245 kN 1205 kN
Concrete volume per m length 0.422m3 0.126m3
Bearing capacity per unit concrete volume 610 kN/m3 580 kN/m3

106
The PCC piling method

The design value of the bearing capacity is calculated by [12]:

F r; max
F r; fund; max; d = ξ ⋅
γm

where
ξ safety factor dependent on number of piles (0.8 in this case)
γm material safety factor (1.25 in this case)

This gives for the design value of the bearing capacity in case 1:

F r; max 4245
F r; fund; max; d = ξ ⋅ = 0.8 ⋅ = 2710 kN for the PCC pile and
γm 1.25

F r; max 1205
F r; fund; max; d = ξ ⋅ = 0.8 ⋅ = 770 kN for the Vibro pile.
γm 1.25

As was to be expected based on the size of the piles, the bearing capacity of the single PCC
pile is larger than that of the single Vibro pile. The bearing capacity per unit of concrete
volume of the PCC pile is about 5% higher than that of the Vibro pile. If only concrete volume
is considered in price calculation, the PCC pile is 5% cheaper in this case.
For the PCC pile the representative value of the compression stress in a single
concrete pile also includes twice the negative skin friction:

F r ;max + 2 ⋅ F r; rep; nf 4245 + 2 ⋅ 630


f c ;max = = = 13.1 N/mm2
A pile 0.42

and for the Vibro pile:

F r ;max + 2 ⋅ F r; rep; nf 1205 + 2 ⋅ 85


f c ;max = = = 10.6 N/mm2
A pile 0.13

The design value of the uni-axial compression strength of C12/15 and C30/35
concrete is given by:

f ' b = 0.6f ' ck

where:

107
The PCC piling method

f’ck characteristic cube compression strength, 15 N/mm2 for C12/15 and 35 N/mm2 for
C30/35.

This gives for the PCC pile:

f 'b = 0.6f 'ck = 0.6 ⋅ 15 = 9.0 N/mm2

and for the Vibro pile:

f ' b = 0.6f ' ck = 0.6 ⋅ 35 = 21.0 N/mm2

The design value of the bearing capacity for the PCC pile based on the compression strength
of the concrete becomes:

F r; fund; max; d = f ' b ⋅Apile = 9.0 ⋅ 0.42 = 3780 kN

This is larger than the design value based on the bearing capacity so the concrete is
sufficiently strong.
For the Vibro pile the design value of the maximum bearing capacity based on the
concrete strength, is calculated in the same way at 1890 kN. This is significantly larger than
the calculated design bearing capacity of 1205 kN.

Tension capacity

Tension due to pull-out


The absolute maximum of the tension force in the PCC pile is equal to the force
required to pull the pile out of the soil.
Since the tension capacity of the pile will differ per project only the order of
magnitude is calculated here. Case 1, as described in paragraph 6.3.2, is used as example
case for the pull-out capacity calculation. The pull out capacity is calculated with equation
(6.1) and the smallest of the dead weight of the soil and the inner shaft bearing capacity
(also calculated with equation (6.1)). The dead weight of the soil is taken as the effective soil
weight since the usability limit state is considered. The calculation value of the pull-out force
for case 1 is given by:


F r; tension; out; max = u p ;avg ;out ⋅ p r ;z ;max dz
0

= 3.90 ⋅ (0.020 ⋅ (4.0 ⋅ 4.5 + 0.5 ⋅ 6 + 0.5 ⋅ 6 ) + 0.010 ⋅ (10 ⋅ 2 )) = 2650 kN

108
The PCC piling method

plus:


F r; tension; in; max = u p ;avg ;in ⋅ p r ;z ;max dz
0

= 3.14 ⋅ (0.020 ⋅ (4.0 ⋅ 4.5 + 0.5 ⋅ 6 + 0.5 ⋅ 6 ) + 0.010 ⋅ (10 ⋅ 2 )) = 2140 kN

or:
L

F r ;tension ;weight = Ainner ⋅ γ soil ;z dz = 0.79 ⋅ (11 ⋅ 4.5 + 2 ⋅ 6 + 10 ⋅ 2) = 65 kN


∫0

Since Fr;tension;weight < Fr;tension;in the total pull out capacity is 2715 kN.
The maximum tension force in the PCC pile is therefore also taken 2910 kN to
determine the reinforcement required in the pile. Divided over the cross-section of 0.42 m2
this results in a tension of 6.9 N/mm2 in the concrete.

Tension due to bending moment


The single pile bearing capacity in Case 1 is approximately 4245 kN according to the
calculations in paragraph 6.3.2. Assuming and eccentricity of the load of 100 mm (paragraph
6.2.3) and loading of the pile until bearing capacity the maximum moment at the pile head is
given by equation (6.2):

M head ;max = F head ; max ⋅ u ecc = 4245 ⋅ 100 = 425 kNm

Tension resistance: General


The representative value of the long term uni-axial tension strength of concrete
without reinforcement is related to the characteristic cube pressure strength [42]:

f b ;d = 0.50 (1 + 0.05f 'ck ) (6.3)

where:
fb;d design value of the long term uni-axial tension strength
f’ck characteristic cube pressure strength

The characteristic cube compression strength of the C12/15 concrete used in Case 1 is: 15
N/mm2. This results in a tension strength of:

f b ;rep = 0.50(1 + 0.05 ⋅ 15) = 0.9 N/mm2

109
The PCC piling method

Tension resistance: Pull-out


The tension strength in the concrete when pull-out capacity is reached is 6.9 N/mm2 so the
concrete will fail under pull-out tension.
Using C12/15 concrete the representative value of the maximum tension force
allowable on the unreinforced PCC pile is be given by:

Ftension ;max; rep = f b ;rep ⋅ Apile = 0.9 ⋅ 0.42 = 380 kN

Depending on the pile application the tension forces might not exceed this value; in that case
no reinforcement would be necessary. For higher concrete qualities the tension strength of
the PCC pile increases. This might be a viable alternative for reinforcement but attention will
have to be paid to the workability.

Tension resistance: Bending moment


The resistance against tension force without reinforcement in concrete is rather
small. For concrete without any reinforcement the cracking moment when bending occurs is
given in [42] as:

M r = f br ⋅W (6.4)

where:
Mr cracking moment
fbr bending tension strength
W section modulus

The long term bending tension strength is related to the long term uni-axial tension strength
according to [42] with the relation:

f br
= (1.6 − h ) > 1 (6.5)
f b ;d

The bending strength is larger than the uni-axial tension strength since when rupture occurs
the concrete still keeps some of its strength, only after a certain rupture width (more than
0.15 mm) is reached the stress will drop to zero. Therefore the stress distribution over the
cross-section is not linear and a certain reserve is available. This is proven to be dependent
on the element width [42]. For hollow piles the relationship between fbr and fb;rep is taken
1:1.

110
The PCC piling method

The section modulus of a concrete tube is defined as:

W tube
(
1 R − Ri
= π o
4 4
) (6.6)
4 Ro

where:
Wtube section modulus of a tube
Ro outside radius of the tube
Ri inside radius of the tube

Using the values for the bending moment applied to the pile head and the inertia, the
representative value of the occurring bending tension stress can be calculated:

⎛ ⎛ 1.24 ⎞4 ⎛ 1.00 ⎞4 ⎞
⎜⎜ ⎟ −⎜ ⎟ ⎟
Wtube =
(
1 Ro − R i
π
4 4
) 1 ⎜
= π ⎝
⎝ 2 ⎠ ⎝ 2 ⎠ ⎟⎠
= 108E+06 mm3
4 Ro 4 1.24
2

gives:

M head; max 425 ⋅ 106


f b ;req = = = 3.9 N/mm2
Wtube 108 ⋅ 106

The compression stress in the concrete at design load is:

F r ;d + 2 ⋅ F r; rep; nf 2710 + 2 ⋅ 630


f c ;d = = = 9.4 N/mm2
A pile 0.42

It can be seen that there will be no tension stress in the pile since the stress due to the
bending moment does not exceed the normal compression stress due to the maximum top
load. However the moment does not only cause a tension stress but also a compression
stress at the opposite side of the pile cross section. This is not entirely correct since the
calculated compression stress only takes place at the edge of the pile and some redistribution
of the stress over the pile width is possible. The compression strength of the concrete can
therefore be a bit lower than the calculated compression stress including bending moment
although never lower than the compression stress due to the top load.. Considering C12/15
concrete and 100 mm eccentricity of the load and considering linear elastic behaviour the
design value of the pile bearing capacity may not exceed:

111
The PCC piling method

f 'b 9
F r; fund,d = = = 2720 kN
u ecc 1 100 1
+ +
W tube A pile 108 ⋅ 10 6 4.2 ⋅ 10 5

6.3.3 Case 2: Piled bridge abutment

Description
To investigate the limits of the applications of the PCC pile a piled bridge abutment is
considered. When a single pile is applied it is subjected to a small vertical load but a large
horizontal force, see figure 6-2.

Figure 6-2: Loads on piled bridge abutment originating from the approach embankment [36];

Since in this case the possibility of applying the PCC pile as abutment foundation is
considered some assumptions are made to allow for a quick scan of the occurring bending
moments and loads on the pile.
A single row of PCC piles is assumed under the abutment. This makes it possible to
schematize the row of PCC piles as a sheet pile wall. This simplification allows for the use of
the GeoDelft program MSheet to model the PCC pile behaviour as an abutment foundation.

Simulation MSheet

Input
The row of PCC piles under the abutment is modelled as a sheet pile wall. The
centre-to-centre distance of the piles is taken as twice the outside diameter thus creating a
spacing between the piles equal to the pile diameter. It is assumed that this spacing is small
enough that no soil can pass between the piles (arching effect) allowing the modelling of the
pile row as a wall. The bending stiffness of the sheet pile wall in the model is per meter wall

112
The PCC piling method

length equal to half the bending stiffness of the PCC pile. Considering the same pile as in
Case 1 the moment of inertia of the pile can be calculated:

1240
I = W ⋅ r out = 108 ⋅ 10 6 ⋅ = 6.70E+10 mm4
2

The bending stiffness is also dependent on the pile stiffness, for C12/15 concrete this is
respectively [42]:

E C 12 / 15 = 22250 + 250 ⋅ f ' ck = 22250 + 250 ⋅ 15 = 2.6E+04 N/mm2

In this calculation the time effects like creep are not taken into account, a reduction of the
pile stiffness for these effects is normally included. The resulting bending stiffness for a
C12/15 PCC pile is:

EI = 2.6 ⋅ 10 4 ⋅ 6.70 ⋅ 10 10 = 1.74+06 kNm2

The bending stiffness for the equivalent wall then becomes 8.70E+05 kNm2.
The soil profile is taken comparable to figure 6-2, where a sand embankment is
placed on clayey subsoil. Under the 15 m thick clay layer a stiff sand layer is located. The PCC
pile is embedded 2 m into this sand layer. The abutment is simulated as the continuous
equivalent PCC sheet pile wall to a level of 4 m above ground level. The bridge cover is
modelled as a support allowing rotation of the equivalent wall but blocking any horizontal
movement. An overview of the input is given in figure 6-3.

-35 -30 -25 -20 -15 -10 -5 0 5 10 15 20 25 m


30

0 Bridge cover

Sand fill

-5

-10
PCC equivalent wall
Clay Clay

-15

-20

Stiff sand Stiff sand

-25
m

Figure 6-3: Input soil profile MSheet;

113
The PCC piling method

The soil properties are given in table 6-6 based on typical values from [11] and [3].

Table 6-6: Soil properties MSheet simulation;

Properties Sand fill Clay Stiff sand


Unsaturated unit weight [kN/m3] 18.0 17.0 19.0
Saturated unit weight [kN/m3] 20.0 17.0 21.0
Cohesion [kN/m2] 0.0 10.0 0.0
Friction angle [degrees] 32.5 17.5 35.0
Modulus of subgrade reaction 50% [kN/m3] 20000 4000 40000
Modulus of subgrade reaction 80% [kN/m3] 10000 2000 20000
Modulus of subgrade reaction 100% [kN/m3] 5000 800 10000

Two construction stages are considered. In the initial stage the equivalent wall is
placed and in the final stage the embankment, including inner slope, is placed. For each side
and for each stage MSheet derives the lateral earth pressure coefficients using Culmann’s
method. This method is based on straight slip surfaces and includes the influence of soil
weight, non-horizontal ground surfaces and non-uniform surcharge.

Results
The resulting graphs for the bending moments, shear forces a displacement can be
found in Appendix I. The maximum bending occurring moment is located about 1 m below
the embankment - clay layer boundary and is approximately 165 kNm. This moment is given
per m length of the equivalent sheet pile wall. Since the pile spacing is taken as two times
the pile outer diameter of 1240 mm, each pile is equivalent to 2.48 m wall. The bending
moment on a single pile is then 2.48 times 165 equals 410 kNm. The tension force in the
concrete resulting from this bending moment is:

M max; d 410 ⋅ 10 6
f b ;d = = = 3.8 N/mm2
W tube 108 ⋅ 10 6

In the governing situation there is no load placed on the pile and so no compression force is
present in the concrete so there is no reduction of the tension force. The tension capacity of
the C12/15 concrete is calculated as 0.90 N/mm2 so the concrete cannot sustain this tension
force without additional reinforcement.

6.3.4 Conclusion
The high bending stiffness and section modulus of the PCC pile reduce the tension
forces in the pile. No reinforcement is therefore necessary when the PCC pile is applied in a
foundation with an eccentric load.

114
The PCC piling method

However when applied as the foundation of an bridge abutment or as a tension pile


the pile will sustain much larger tension forces and reinforcement will be necessary.

6.4 Reinforcement

6.4.1 Introduction
For application of the PCC in foundations the main change in the requirements is the
addition of a resistance against tension forces in the concrete. Since concrete has a low
tension resistance steel reinforcement is normally applied to bear the tension forces in
concrete constructions.
The nature of the PCC pile, with its thin walls makes application of reinforcement
more of a challenge than in solid piles. In this chapter three possible reinforcement methods
are described and in the next chapter the methods will be evaluated. The methods are:
• Traditional steel reinforcement,
• High tensile alloy steel (Dywidag) and
• Fiber reinforcement (steel and carbon).

6.4.2 Traditional reinforcement


For installation of Vibro piles which are cast in place, round concrete piles for which
the installation method is comparable to the PCC pile, reinforcement netting is used which
includes a number of steel bars connected and kept in place with steel rings and/or spirals
[43], see figure 6-4

0.15 m

Ring ∅ 10 mm Spiral ∅ 6 mm

6 xl ∅ 16 mm

Figure 6-4: Typical reinforcement in Vibro pile [43];

115
The PCC piling method

In [42] some notes for the application of reinforcement steel are given. It is advisable to use:
• As large as possible steel diameters and
• As little different steel diameters as possible.
The minimal distance between the bars should be:
• 4/3 of the largest grain diameter of the aggregate,
• the largest bar diameter or
• 30 mm for beams and columns, 25 mm for floors and 50 mm for walls.
This to avoid the formation of gravel “nests” between the bars.
A certain concrete cover is required to prevent the steel of being damaged by the
groundwater. The concrete cover is determined by the environment, in a salt or otherwise
hostile environment more cover is required. In [15] an overview of the environmental classes
and corresponding covers is given, partly shown in table 6-7.

Table 6-7: Concrete cover for a selection of safety classes [15];

Environment Class Cover*


Column, no risk of corrosion X0 -
Column in contact with water, seldom dry XC2 35 mm
Column in contact with water with chlorides other than
XD2 40 mm
from sea, seldom dry
Column in contact with water with chlorides from sea,
XS2 40 mm
seldom dry
*another 5 mm is added when the concrete surface is: treated after construction, not checked or has a characteristic
cube pressure strength of less then 25 N/mm2 (superposed if more than one condition occurs)

In [42] and overview is given of the commonly used reinforcement steel properties,
see table 6-8.

Table 6-8: Properties of reinforcement steel [42]

Concrete steel type fsrep fs εsu


N/mm2 N/mm2 %
FeB 220 HWL 220 190 5.00
FeB 400 HWL, HK 400 350 4.00
FeB 500 HWL, HK 500 435 3.25
FeB 500 HKN 500 435 2.75
FeB 500 HKN, HWN 500 435 2.75

The modulus of elasticity of the steel is Es = 2.0E105 N/mm2 and the steel is available in
diameters of 6,8,10,12,16,20,25,32 and 40 mm [42].

6.4.3 Dywidag bars


Dywidag is a high tensile alloy steel bar which features a coarse thread over its full
length [9]. The system is developed by Dywidag-systems international and has a wide range
of applications including reinforcement. The application is essentially the same as normal
reinforcement but features much higher tensile strength bars, see table 6-9.
116
The PCC piling method

Table 6-9: Technical date for Dywidag steel threadbar

Nominal Steel Ultimate Yield


diameter grade strength strength
[mm] [N/mm2] [kN] [kN]
15 900/1100 195 159
20 900/1100 345 283
26.5 900/1050 579 523
32 900/1050 844 764
36 900/1050 1069 967
40 900/1050 1320 1194
47 900/1050 1822 1648

The modulus of elasticity of the used alloy is 2.05E105 N/mm2 and like normal steel bars the
Dywidag bars need to be protected against corrosion.
A large disadvantage of high quality steel bars is that they are very susceptible to
corrosion in aggressive climates, like groundwater. Therefore only small ruptures in the
concrete are allowed which occur much faster than the yield strength of the bar is reached.
This makes this type of solution hard to apply in foundation piles.

6.4.4 Fibre reinforcement

General
An alternative for the use of steel bars is the use of steel fibres instead. Steel fibres
are used when installing the reinforcement netting is difficult or time expensive [8].
The first purpose of steel fibre reinforcement is the strengthening of the cement
matrix (micro scale). Fibres lying in different directions in the concrete will prevent micro
cracks from forming. The effect depends on the size and the concentration of the fibres. Non-
metal fibres function better in this way because they are less susceptible to temperature
changes. The second purpose is reinforcement (macro scale). The reinforcement is based on
the effect that the fibres will slip through the concrete and not break [37].

Composition
Steel fibres can be seen as an extra supplement to the concrete. It has certain
influences on the design of the mixture [22]:
• The fibre length should be chosen such that the L/3 or L/2 is not smaller than the
aggregate diameter to avoid the forming of clumps of fibres.
• The sand diameter influences the ability to pump the mixture. A small diameter (max 2
mm) makes it easier to pump the mixture and thus increases the tension burst strength.
A diameter of 4 mm or larger prevents the sinking of the fibres during compaction.
• 10% more cement is advised because the fibres disturb the packing of the grains so
more cement is required to fill the hollow spaces.

117
The PCC piling method

• The maximum percentage of fibres is determined by the workability of the concrete. The
maximum lies around 50-100 kg/m3.
• More water increases the workability of the concrete but decreases the strength and
durability.
The ACI commission (1993) gives recommendations for concrete mixtures with steel
fibres, see table 6-10.

Table 6-10: ACI recommendation for steel fiber concrete mixture [22]

Particle size
Mixture characteristics dmax= 10 mm dmax= 20 mm dmax= 38 mm
Water/cement factor 0.35-0.45 0.35-0.50 0.35-0.55
Cement (kg/m3) 360-600 300-540 280-420
Fine material/total (%) 45-60 45-55 40-55
Air content (%) 4-8 4-6 4-5
Vf straight fibers (%) 0.8-2.0 0.6-1.6 0.4-1.4
Vf deformed fibres (%) 0.4-1.0 0.3-0.8 0.2-0.7

Strength
The strength characteristics of fibres reinforced concrete are [22]:
• The fibres influence the shear strength of the concrete by working as a dowel (“bridging”
effect) and forcing the shear to develop over a number of small cracks.
• The compression strength of the fibre concrete will be the same as that of normal
concrete although the fibres will reduces the damage at failure. The “bridging” of the
fibres lets the concrete maintain some strength after failure occurs.
• The tension strength of the concrete increases, according to CUR recommendation 36, to
1.05 times the tension strength of normal concrete. The tension strength after cracking
of the concrete is much higher than that without fibres.
• The bending tension strength of fibre concrete will be approximately 35 % higher than
concrete without reinforcement. The value of the bending toughness (the surface under
the load-deformation graph after reaching the bending tension strength) is up to 40 times
that of normal concrete, due to the “bridging” effect.
• The modulus of elasticity of the fibre concrete will not change compared to normal
concrete.
• Concrete creep is not changed by adding fibres to the concrete.
Due to the fact that the fibers are distributed evenly in the concrete some damage to
the fibres at the edges of the fibre concrete element can be expected. Because the fibres are
small and unconnected, the rusting of the fibres will not lead to large damages [22].
CUR 35 provides a method for calculation of bending strength at breaking and
bending strength after breaking based on a three point bending test. The ultimate bending
strength, Fu, is determined from the F-δ graph as the highest value of F in an area left of a
line parallel (0.05 mm to the right) to the graph before failure, see figure 6-5.

118
The PCC piling method

Steel fiber concrete Steel fiber concrete

Figure 6-5: Breaking load Fu-[22];

The equivalent breaking bending strength is determined from the test-setup and the ultimate
bending strength:

Fu
f ctb ;equ = 1.5 (6.7)
bh 2

The characteristic crack bending tension strength is determined according to [22]:

f ctb ;char = f ctb ;equ ;avg − k ⋅ S p (6.8)

where:

fctb,equ,avg average result from the tests


k 1.64 for 5% chance of exceeding
Sp standard deviation of the test results

The calculation value of the tension strength is determined by dividing fctb,char by a material
factor. The breaking toughness (Df) is determined by the surface under the F-δ graph, see
figure 6-2, between the zero and deflections δ2 and δ3:

D f ,2
f ftb,equ , 2 = 1.5 (6.9)
1.5 ⋅ bh 2

D f ,3
f fctb,equ ,3 = 1.5 (6.10)
3.0 ⋅ bh 2

119
The PCC piling method

where:

Df,2 surface under the load-deflection graph “0” to δ2 = 1.5 mm


Df,3 surface under the load-deflection graph “0” to δ3 = 3.0 mm

Steel fiber concrete Steel fiber concrete

Figure 6-6: Definition of the breaking energy and the toughness [22];

The characteristic equivalent bending strength after breaking forming follows from:

f fctb,equ ,char , 2 / 3 = f fctb ,equ , avg , 2 / 3 − k ⋅ S p (6.11)

The design value of the tension strength is determined by dividing ffctb,char by a material
factor.
The modulus of elasticity of the fibre concrete is [37]:

E c = η1η 2 E f V f + E mVm (6.12)

where:
Ec modulus of elasticity of composite material
η1 efficiency factor dependent on fibre orientation
η2 efficiency factor dependent on fibre length
Ef fibre modulus of elasticity
Vf volume fraction of the fibres
Em concrete modulus of elasticity
Vm volume fraction of the concrete

120
The PCC piling method

Attention points and experience

Fibre ball
During addition of the steel fibres the stiffness of the concrete mix increases and a
fibre ball can be formed. It is advisable to limit the number of fibres per unit of volume to
limit this effect. For the popular Dramix fibre the allowable fibres per unit volume, dependent
on the L/D ratio of the fibre and the concrete particle size, are given in Table 6-11.

Table 6-11: Maximum allowable fibres per unit of volume for the Dramix fibre [37];

Concrete L/D = 60 L/D = 60 L/D = 75 L/D = 75 L/D = 100 L/D = 100


dmax normal pumping normal pumping normal pumping
4 mm 160 kg/m3 120 kg/m3 125 kg/m3 95 kg/m3 95 kg/m3 70 kg/m3
8 mm 125 kg/m3 95 kg/m3 100 kg/m3 75 kg/m3 75 kg/m3 55 kg/m3
16 mm 85 kg/m3 65 kg/m3 70 kg/m3 55 kg/m3 55 kg/m3 40 kg/m3
32 mm 50 kg/m3 40 kg/m3 40 kg/m3 30 kg/m3 30 kg/m3 25 kg/m3

Fibre concrete in Vibro piles


For the application of Vibro piles in the soft soil layers in the west of the Netherlands,
Mebin has designed a polypropylene fibre mortar (Fibrecrete) to increase the coherence of
the concrete and prevent large diameters from forming. It is investigated of the function of
the reinforcement netting in Vibro-piles can be taken over by a type of Fibrecrete. Tests were
done with synthetic fibre concrete and steel fibre concrete. The following conclusions were
drawn [8]:
• The piles where of excellent quality, no de-mixing of the concrete has taken place for
piles of 300 mm diameter and 16 m length, although a central steel bar was used (to pull
out the piles).
• The tested cubes of synthetic fibre and steel fibre concrete had the same pressure
strength properties as normally used concrete.
• The soil pressure at the pile tip is essentially identical for the fibre concretes compared to
the reference piles (made with the usual method).
• The experiments has proven that the steel fibre reinforced cross sections (30 kg RC-
80/60-BN) have equal or higher bending moment capacity and guarantee the prismatic
dimensions of the pile.
• The bending moment capacity of a steel fibre concrete pile (30 kg RC-80/60-BN) is
comparable to a traditional Vibro pile with 4 Ø 10 mm steel reinforcement bars with a
cover of 40 mm.

6.5 Design changes

6.5.1 Introduction
An overview of the required design changes to the PCC pile for application in building
foundations and bridge abutments is given in this chapter. The required changes are based

121
The PCC piling method

on the case studies in chapter 6.3 and take into account the reinforcement, the pile
properties and the required equipment.

6.5.2 Reinforcement
For an estimation of the required reinforcement the pull-out capacity as calculated in
Case 1 and the bending moment calculated in Case 2 are taken. This gives tension in the
concrete of respectively 6.9 N/mm2 and 2.7 N/mm2.

Traditional reinforcement
The traditional reinforcement consists of a number of vertically placed steel bars kept
in place using steel rings or spirals. When traditional reinforcement steel bars of Ø16 mm FeB
500 steel are applied, corresponding to the Vibro pile reinforcement, the required number of
bars is given in table 6-12.

Table 6-12: Required traditional reinforcement;

Case Tension Required Number Bar


force steel area of bars spacing
Tension pull-out 6.9 N/mm2 6660 mm2 34 100 mm
Bending moment 2.7 N/mm2 2600 mm2 14 240 mm

The bar spacing more than sufficient to meet the demands of [15] although a large
number of bars need to be applied. The concrete cover if the bars are placed in the middle of
the pile wall is given by:

w wall − d bar 1240 − 1000 − 16


d cover = = = 112 mm
2 2

which is more than the required 40 mm [16].


Advantages of this solution are:
• Common solution with lots of experience and
• Low cost.
Disadvantages of this solution are:
• Large reinforcement netting required and
• Difficulty in placing the reinforcement after concreting in long and slim PCC pile walls
or
• Possible de-mixing of concrete due to reinforcement netting when netting is present
during concreting.

122
The PCC piling method

Dywidag bars
The Dywidag bars have larger tension strength than the traditional reinforcement
bars and the required number of bars is therefore smaller. Considering 15 mm Dywidag bars
the results are given in table 6-13.

Table 6-13: Required Dywidag reinforcement;

Case Tension Number Bar


force of bars spacing
Tension pull-out 6.9 N/mm2 19 190 mm
Bending moment 2.7 N/mm2 8 450 mm

As with the traditional reinforcement the pile spacing and concrete cover is more than
sufficient.
Advantages of this solution are:
• Smaller number of bars required
Disadvantages of this solution are:
• Higher single bar cost,
• Highly susceptible to corrosion,
• Large reinforcement netting and
• Difficulty in placing the reinforcement after concreting in long and slim PCC pile walls
or
• Possible de-mixing of concrete due to reinforcement netting when netting is present
during concreting.

Fibre reinforcement
The use of fibre concrete gives only a limited extra tension strength, about 5% of the
un-reinforced concrete tension strength, of the concrete [22] but allows for a larger
remaining tension strength after cracking of the concrete.
The fibre reinforced bending strength will increase by approximately 35% of the
concrete strength using fibre concrete. The exact value of the bending strength is determined
based on load tests according to the most commonly used methods [22]. The PCC pile
executed with C20/25 concrete would then have a tension capacity of:

f bf = 1.05 ⋅ f b ;rep = 1.05 ⋅ 0.5(1 + 0.05 ⋅ 25) = 1.18 N/mm2

and a bending strength of

f bf = 1.35 ⋅ f b ;rep = 1.35 ⋅ 0.5(1 + 0.05 ⋅ 25) = 1.51 N/mm2

123
The PCC piling method

These values are estimations, the real tension strength and bending moment should be
calculated based on load tests on the improved concrete.
Advantages of this method are:
• No reinforcement netting required which lessens the chance of de-mixing and arching,
• No changes to the casing for reinforcement placement and
• Less loss of tension strength after rupture of the concrete.
Disadvantages are:
• Less experience with this method,
• Not a very large increase in tension and bending capacity and
• Reinforcement of the concrete in all directions instead of only the required direction gives
economical loss since more steel is required.

6.5.3 Pile properties


Case 1 has shown that the compression strength of C12/15 concrete is insufficient to
sustain the pressure in the concrete at a load close to the maximum bearing capacity of the
pile. It is therefore advisable to make the pile out of C20/25 concrete which has sufficient
strength. However it should be noted that the lower fluidity of stronger concrete might cause
problems for the concrete to reach all areas of the casing, especially when also reinforcement
is applied, see Part 2.
Tests will have to be executed to verify the continuity of the pile cast with higher quality
concrete. Enlarging the wall thickness facilitates the flow of the concrete but increases the
concrete use.

6.5.4 Equipment
Changes in casing design are only required when reinforcement steel bars are applied. In
that case the reinforcement has to be connected to the casing or lowered into it after
vibration of the casing. This can cause problems with both the flaps that close off the casing
and with the spacers that keep the distance between the inner and outer casing wall
constant, see Part 2. If a small number of bars are applied, for example the Dywidag system,
it might be possible to combine the function of spacing the inner and outer casing and
holding the bars in place in one system, see figure 6-7.

124
The PCC piling method

Vertical cross section


Detail, top view

Inner wall

Reinforcement bar

Outer wall

Figure 6-7: Possible reinforcement frame;

In the figure the reinforcement bar is placed through the holes in all the spacers and is left
behind during retraction of the casing ensuring no displacement of the bars and sufficient
concrete cover.

6.6 Conclusion
Based on the discussed cases it is concluded that the PCC piling system is a system that
can compete with the Vibro piling system as a foundation piling system based solely on
bearing capacity per unit of concrete volume, although a stronger type of concrete that the
currently used C12/15 is needed to insure sufficient concrete compression strength. C20/25
concrete is sufficient in the example cases.
The high bending stiffness of a single pile as a result of its tube shape make the system
resistant against bending moments and in some cases reinforcement of the concrete is not
required.
When reinforcement would be required difficulties in execution of the pile occur due to
the thin walls and current design of the installation casing. Reinforcement netting to ensure
the distance between the bars and the wall and between the bars themselves is difficult to
place after concreting due to the small wall thickness and potentially long pile length. Placing
the netting before concreting can cause de-mixing of the concrete and concrete quality in
lower parts of the pile. High strength bars are difficult to apply in this environment but the
application of fibre concrete might be a solution that does not have this problem. This is a
field for further research.

125
The PCC piling method

Changes to the installation equipment are expected to be required, especially when steel
bar reinforcement is used. A possibility might be the combination of wall spacers and
reinforcement bar distance holders.

126
The PCC piling method

7 Conclusions and recommendations


In this final chapter the conclusions of the report and the recommendations for
further research are given.

7.1 Conclusions
For the conclusion we look back to the beginning of the report where the research
question and the different aspects that would be looked at are stated. The purpose of the
report was to determine if the PCC pile is viable in the Netherlands as a ground improving
method and/or as a foundation pile. The technical and economical feasibility needed to be
determined including and an analysis of the execution method, the calculation method and a
comparison with existing ground improving methods and foundation piles.
It is concluded that the PCC piling method is a robust and viable method for ground
improvement. The studied tests and observations in the field show that the method is
successful in reducing settlement of a highway embankment on soft soil in the Chinese
practice.
Analysis of the execution method shows a number of attention points in the different
construction phases that can possibly cause problems with the pile quality when not sufficient
attention is paid during pile construction. Possible demixing of the concrete mixture during
casting and vibration damage caused by nearby pile installation are two of these attention
points.
To determine the viability of the PCC in the Netherlands a comparison with two new
ground improving piles developed in the Netherlands, the HSP and the AuGeo pile, is made.
The PCC pile appears to be a competing solution based on the installation time, required
amount of concrete and bearing capacity. Both the HSP and AuGeo systems however allow
for installation of steel reinforcement while this is not yet possible for the PCC pile. The PCC
pile is especially suitable when thick soft soil layers are present where its higher shaft bearing
capacity becomes a significant advantage.
To extend the basic Chinese calculation method a calculation method for the PCC pile
is derived from the Dutch norms and recommendations for plugging calculations. This
calculation method is verified based on load tests on a single pile executed in China. The
results of the calculation method according to the Dutch norms give a good approximation for
the single pile bearing capacity.
Further applications of the PCC pile as a foundation pile and as a bridge abutment
are discussed. Comparison of the PCC pile with the and a commonly used Dutch cast-in-place
pile, the Vibro pile, which is commonly used in the Netherlands gives a slightly better ratio of
concrete to bearing capacity. The high bending stiffness and section modulus of the PCC pile

127
The PCC piling method

due to its unique shape make it also suitable for application in bridge abutments with
relatively little reinforcement necessary.
Due to the shape and installation method of the PCC pile traditional steel bar
reinforcement is difficult to apply. A number of solutions for reinforcement of the PCC pile are
discussed; both the Dywidag system and fibre concrete are solutions for strengthening the
thin wall of the PCC pile against tension forces. Some changes to the design of the PCC pile
and the installation equipment are necessary.

7.2 Recommendations
The next step in the introduction of the PCC pile in The Netherlands might be the
installation of a number of test piles by a Dutch contractor. This is necessary to familiarize
with the equipment and get some experience with possible problems during installation. This
can best be done in cooperation with a Chinese contractor that already has experience with
the method.
Possible problems during construction mainly lie with the concreting where the
integrity of the wall will have to be ascertained. The thin wall combined with the large contact
area, even larger when reinforcement is applied, creates a risk of inconsistencies in the pile.
The PCC pile is competing with the Dutch soil improvements pile because of its large
single pile bearing capacity and the large centre-to-centre distance which results in a fast
construction of the project. It has to be verified if a centre-to-centre distance as applied in
China is also allowed on soils in the Netherlands. The viability of the PCC is dependent on
this.
Additional testing will have to be done for determining the PCC pile applicable for
building foundations. The connection between building and pile needs to be detailed and
detailed calculations for and design of the reinforcement is needed.
Verification of the bearing capacity calculation method by additional load tests in the
Dutch soil is also advised. Tests to verify the plug bearing capacity are also advised since little
experience with the calculation of plugging in clay and sand is available.

128
The PCC piling method

References

1. Bles, T. Risks during execution of pilefoundations: descision model for


identification, estimation and weighing of risks (Risico’s bij uitvoering
paalfunderingen; Beslissingsmodel, door identificatie, inschatting en afweging
van risico’s), Master Thesis Delft University of Technology, 2003.
2. Centre for Civil Engineering Research and Codes, Bearing capacity of steel
pipe piles, CUR 2001-8, 2001
3. Centre for Civil Engineering Research and Codes, Building with soil: Soil
construction on and in weak and compressible subsoil, CUR 166, 1992.
4. Centre for Civil Engineering Research and Codes, Design rules for tension
piles, CUR 2001-4, 2001.
5. Centre for Underground Construction (COB), Manual for underground
construction part 2: gravel and sand columns (Handboek ondergronds
bouwen deel 2 – grind en zandkolommen), Balkeman, 2000.
6. Cofra, Cofra website, www.cofra.com
7. Cortlever, N.G., Design of double track railway Bidor-Rawang on AuGeo Piling
system according to BS8006 and PLAXIS numerical analysis.
8. Dekker, L.J.G., Hoekstra, A., Nohl, W. Fibre concrete in Vibro piles
(Vezelbeton in vibropalen), Cement, 2004
9. DSI, Dywidag Prestressing steel Threadbar system
10. Duijvenbode, J.D. Woldringh, R.F., Venmans, A.M.M, No-recess test site
Hoeksche Waard, Balkema, 1999.
11. Dutch Norm Institute, Basic Requirements and loads, NEN6740, 1991.
12. Dutch Norm Institute, Calculation methods for foundations on piles:
Compression piles, NEN 6743, 1991.
13. Dutch Norm Institute, Calculation methods for shallow foundation, NEN6744,
1991.
14. Dutch Norm Institute, TGB 1990: Technical principals for building codes
1990: Loads and deformations, NEN6702, 1990.
15. Dutch Norm Institute, TGB 1992: Technical principals for building codes
1992: Concrete, NEN 6700, 1992.
16. ENCI, The correct environmental class in four steps (De juiste milieuklasse in
vier stappen), 2005
17. GeoHohai report, Definitive report Yan-Tong project.
18. GeoHohai report, Large-diameter driven cast-in-place concrete thin-wall pipe
pile the state of practice. Part I Research and Development, Prof Liu et al.
19. GeoHohai report, Large-diameter driven cast-in-place concrete thin-wall pipe

129
The PCC piling method

pile the state of practice. Part II Application


20. GeoHohai, Photo database GeoHohai
21. Guo, W.D., Randolph, M.F., An efficient approach for settlement prediction of
pile groups
22. Konter, E., The use of steel fiber concrete in tunneling (Staalvezelbeton in de
tunnelbouw), Master Thesis Delft University of Technology, 1998
23. Likens, G., Piscalko, G., Rausche, F., Morgano, C.M., Detection and
prevention of anomalies for augercast piling, Conference paper: Application
of stress wave theory to piles, Balkema Rotterdam, 2000.
24. Matsumoto, T., Sekiguchi, H., Shibata, T., Fuse, Y., Performance of steel pipe
piles driven in Pleistocene clays.
25. Moulton, L.K., Ganga Rao, H.V.S., Halvorsen, G.T., Tolerable movement
criteria for highway bridges, Report FHWA/RD-85/107, Washington highway
administration.
26. Paik, K., Salgado, R., Lee, J., Kim, B., Behaviour of open-and closed-ended
piles driven into sands, Journal of Geotechnical and Geoenvironmental
engineer, ASCE, 2003.
27. Paikowsky, S.G., Whitman, R.V., The effects of plugging on pile performance
and design, Canadian Journal of Geotechnics, 1990.
28. Poulos, H.G, Davis, E.H., Elastic solutions for soil and rock mechanics, New
York, Wiley, 421 pages, 1974.
29. Raither, M. Küster, V., Lindmark, A., Geotextile-Encased columns: a
foundation system for earth structures, illustrated by a dyke project for a
works extension in Hamburg, 2002.
30. Randolph, M.F., Design Methods for Pile Groups and Piled Rafts, Conference
paper XIII ICSMFE New Delhi, 1994
31. Randolph, M.F., Leong, E.C., Houlsby, G.T., One-dimensional analysis of soil
plugs in pipe piles, Geotechnique 41, 1991.
32. Randolph, M.F., Worth C.P., Analysis of deformation of vertically loaded piles
in sand, Journal of Geotechnical Engineering Divison ASCE, Vol 104 No 12,
1978.
33. Ruyt, M. van der, PCC piles: Site observations, Chinese practice, theory and
research (comments by Dr. ZHOU, GeoHohai), GeoDelft report, 2004.
34. Settlement free embankments with AuGeo piling system, N.Cortlever, Cofra
b.v.
35. Springman, S.M., Lateral loading on piles due to embankment construction,
PhD thesis, University of Camebridge.
36. Stewart, D.P., Jewell, R.J., Randolph, M.F., Design of piled bridge abutments

130
The PCC piling method

on soft clay for loading from lateral soil movements, Geotechnique 44, 1994.
37. Timmerman, F., Hollow concrete jacked piles with pre-tension reinforcement
and steel fibre reinforcement (Holle betonnen heipalen met voorspanning en
staalvezelwapening), Master Thesis Delft University of Technology, 2001.
38. Tol, A.F. van, Foundation Techniques, Lecture notes 3030 Delft University of
Technology, 2001.
39. Voton, Handout Voton HSP, 2005
40. Voton, Voton HSP website, www.voton-hsp.nl
41. Vries, J.H. de, The feasibility of pile-raft foundations in The Netherlands (De
haalbaarheid van paal-plaatfunderingen in Nederland), Master Thesis Delft
University of Technology, 2001..
42. Walraven, J.C., Reinforced concrecte (Gewapend beton), lecture notes
CT3050 Delft University of Technology, 2000.
43. Weele, A.F. van, Lencioni, B.M.L.G., The lessons learned from the failure of a
pile foundation are expensive but valuable (Het mislukken van een
paalfundering is duur maar leerzaam), Geotechniek, 1999.

131
The PCC piling method

Appendices

132
The PCC piling method: Appendices

Fr ,tip ,d
Fr .max ,tip ,d

wtip ,d
Deq

Relationship between Fr;max;tip;d in percents of Fr;max;tip;d and wtip;d in percents of Deq (1=ground
displacing pile, 2=augercast pile and 3=drilled pile);

Fr , shaft ,d
Fr , max , shaft ,d

wtip ,d

Relation between Fr;shaft;d in percents and Fr;max;shaft;d and wtipt in millimetres

Appendix A: Settlement chart from NEN6743 133


The PCC piling method: Appendices

In the first graph the value of e1 is based on typical values for the pile geometry and soil
properties: Ep/Gl = 1000, s/d = 3, ρ = 0.75, υ = 0.3. For a known slenderness ratio the
value of e1 can be determined. This value can then be corrected with the second graph.

Appendix B: Design charts for the group efficiency 134


The PCC piling method: Appendices

Table C-1: Theoretical values for the settlement ratio Rs for friction pile groups with rigid cap in a deep
uniform soil mass;

Rs values for other numbers of piles may be interpolated from this table. For groups of more
than 16 piles it has been found that Rs varies approximately linearly with the square root of
the number of piles in the group:

(
Rs = (R25 − R16 ) n 0.5 − 5 + R25 )

where:
R25 value for Rs for 25-pile group
R16 value for Rs for 16-pile group
n number of piles in the group

The pile stiffness factor is defined as:

Ep
K= RA
Es

with:

AP
RA =
(πd 2 / 4 )

Appendix C: Theoretical values for the settlement ratio 135


The PCC piling method: Appendices

Reduction factors for settlement ratio

The influence of the presence of a rigid layer on the settlement of typical pile groups
is shown in figure C-1

Figure C-1: Reduction coefficient for effect of finite layer (Poulos and Davis (1980))

The influence of the Poisson’s ratio on the settlement ratio is shown in figure C-2, it
can be seen that the effect becomes more pronounced for larger number of piles.

Appendix C: Theoretical values for the settlement ratio 136


The PCC piling method: Appendices

Figure C-2: Correction factor for effect of Poisson’s ratio (Poulos and Davis (1980));

The influence of the distribution of the soil modulus for a typical situation is shown in
figure C-3. The difference between uniform and non uniform soil become larger when the
number of piles increases.

Figure C-3: Effect of distribution of soil modulus on settlement ratio (Poulos and Davis (1980))

Appendix C: Theoretical values for the settlement ratio 137


property Plasticity limit
Coefficient of
Natural Saturate Specific gravity
Water content Dry density γdry Void ratio e compressibility
density γsoil density γsoil/ γwater Liquid limit
[%] [g/cm3] [-] Plastic limit plasticity index liquidity index av
[g/cm3] γsat [g/cm3] [-] 76g
[%] [-] [-] [MPa-1]
[%]
B—before driven)

depth
pile B A B A B A B A B A B A B A B A B A B A B A
( m)

1. 2
6
1.1-1.3 30.0 1.92 1.91 1.52 1.47 92 96 0.779 0.845 2.70 2.71 28.8 31.7 20.5 19.3 8 12 0.72 0.86 0.23 0.39
.
The PCC piling method: Appendices

5
4.1-4.5 40.8 37.4 1.79 1.83 1.27 1.33 98 98 1.124 1.027 2.70 2.70 34.3 31.1 26.5 21.5 8 10 1.83 1.66 0.92 0.51

K31+534 5.3-5.5 39.7 39.1 1.81 1.81 1.30 1.30 99 98 1.084 1.075 2.70 2.70 33.1 31.4 25.1 23.3 8 8 1.83 1.95 0.68 0.51

8.3-8.7 34.0 37.4 1.87 1.87 1.40 1.36 98 100 0.935 0.991 2.70 2.71 35.2 33.4 27.6 20.1 8 13 0.84 1.3 0.22 0.30

11.3-11.7 41.4 40.8 1.82 1.79 1.29 1.27 100 98 1.098 1.132 2.70 2.71 31.5 33.3 23.3 20.4 8 13 2.21 1.58 0.73 1.06

15.8-16.0 31.4 31.8 1.84 1.95 1.40 1.48 90 100 0.95 0.832 2.73 2.71 51.4 36.3 29.4 21.6 22 15 0.09 0.69 0.51 0.27

18.5-18.7 29.4 1.90 1.47 95 0.825 2.68 27.7 23.2 5 1.38 0.07 0.09

21.2-21.4 29.1 1.92 1.49 97 0.809 2.69 30.0 25.5 5 0.80 0.11
24.7-24.9 31.2 1.90 1.45 98 0.858 2.69 31.5 25.1 6 1.02 0.19

Appendix D: Physical and mechanical soil properties Yan-Tong


0.8-1.0 24.6 1.85 1.48 81 0.818 2.70 28.0 19.7 8 0.59 0.33

3.2-3.4 29.8 1.92 1.48 97 0.825 2.70 29.4 21.5 8 1.05 0.25

5.2-5.4 39.3 1.28 1.28 96 1.105 2.69 32.1 26.1 6 2.20 0.94
K30+793 10.2-10.4 38.5 1.35 1.35 100 1.000 2.70 31.8 21.1 11 1.63 0.37
12.2-12.4 42.0 1.26 1.26 99 1.142 2.70 31.9 22.0 10 2.02 0.87

15.2-15.4 28.9 1.44 1.44 98 0.885 2.72 46.3 26.4 20 0.13 0.27

18.7-18.9 26.9 1.46 1.46 86 0.845 2.69 27.6 21.0 7 0.89 0.23

138
Physical mechanic property parameters of soil before and after pile driven (A—after driven,
Permeability coefficient CU test
property Coefficient of
Modulus of pre-consolidation Coefficient of
Compression index relaxation index consolidation
compressibility pressure consolidation 200kPa
[-] [-] 100kPa vertical *10-6 horizontal Cohesion Internal friction angle effective cohesio
[Mpa] [kPa] [*10-3cm2/s]
[*10-3cm2/s] [cm/s] [cm/s] [kPa] [°] [kPa]
depth
[m]
pile
B A B A B A B A B A B A B A B A B A B A

1.1-1.3 7.72 4.54 420 157 0.077 0.20 0.0127 0.018 9.43 2.49 0.13 2.49 7.23 1.48
4.1-4.5 2.3 3.78 110 159 0.307 0.26 0.0127 0.025 10.17 4.31 0.13 4.31 2.58 4.37

5.3-5.5 3.05 3.85 165 127 0.227 0.25 0.0173 0.017 9.39 4.8 0.13 4.8 2. 6.54 0.757

8.3-8.7 8.77 6.34 335 173 0.073 0.18 0.0109 0.019 4.21 2.78 0.13 2.78 1.37 1.10
1. K31+5
11.3-11.7 2.87 1.94 110 120 0.243 0.43 0.0188 0.035 4.55 4.61 0.13 4.61 9.08
34
15.8-16.0 3.85 6.60 280 247 0.168 0.24 0.0457 0.023 7.84 3.76 0.13 3.76 0.0257
The PCC piling method: Appendices

18.5-18.7 25.64 235 0.024 0.0058 3.46 0.14 46.5

21.2-21.4 15.87 275 0.038 0.0051 7.8 0.067 79.1

24.7-24.9 10.00 324 0.062 0.0093 5.63 0.13 8.74

0.8-1.0 5.34 240 0.174 0.01 3.72 4.03 5.73 40.9 53.8 19.5 18.0 30.5 20.5

3.2-3.4 7.05 290 0.164 0.019 4.61 5.07 1.46 86.4 37.4 15.9 27.1 28.2 35.5

5.2-5.4 2.06 80 0.292 0.292 4.61 3.45 1.68 3.5 78.2 25.9 34.2 22.3 66.8

K30+793 10.2-10.4 5.41 194 0.204 0.204 3.83 3.94 1.51 32.4 19.9 13.2 15.0 16.1 11.9

12.2-12.4 2.38 68 0.420 0.420 4.66 3.582 4.98 50.8 1.4 10.1 17.9 39.4 19.7

Appendix D: Physical and mechanical soil properties Yan-Tong


15.2-15.4 6.77 270 0.257 0.257 4.65 2.97 2.75 46.3 38.9 15.7 22.7 28.8 8.3

18.7-18.9 8.83 278 0.120 0.120 1.86 1.66 1.21 9.3 25 41.7 30.7 0.0 4.1

139
The PCC piling method: Appendices

q_cIII_a

8D level
pile level

4D level

q_cII_a q_cI_a

Appendix E: CPT Yan-Tong project 140


The PCC piling method: Appendices

Appendix F: CPT Rotterdam 141


The PCC piling method: Appendices

qc;III = 13.0 8D level

Pile level

qc;II = 14.5 4D level

qc;I = 16.5

Appendix G: CPT Rotterdam with 4D8D PCC pile 142


The PCC piling method: Appendices

8D level

qc;III = 5.0

Pile level

4D level

qc;II = 10.2 qc;I = 12.0

Appendix H: CPT Rotterdam with 4D8D Vibro pile 143


The PCC piling method: Appendices

Appendix I: Results MSheet calculation 144

You might also like