Prince2 2017 Product Map

The document provides a diagram mapping out when PRINCE2 management products are created, updated, and by whom over the course of a project. It shows the creation and updating of key documents related to themes like business case, risk, quality, and plans throughout the different PRINCE2 processes.

Uploaded by

Vijay Jain
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
320 views2 pages

Prince2 2017 Product Map

The document provides a diagram mapping out when PRINCE2 management products are created, updated, and by whom over the course of a project. It shows the creation and updating of key documents related to themes like business case, risk, quality, and plans throughout the different PRINCE2 processes.

Uploaded by

Vijay Jain
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 2

The PRINCE2® Management Products Map MgmtPlaza

Corp..
by Frank Turley
Project
mandate
Corporate or Programme Management www.MgmtPlaza.com
Version 1.1
Project Board
Direction

Directing a Project (DP)


Authorize Authorize Authorize a Stage Give ad hoc Auth. project
initiation the project or Exception Plan direction closure

Outline BC Business Case Created Created Created


PPD End Project Rpt
SB: End Stage Rpt CS: Highlight
Project Brief
4 * Strategy
CM, CM, Q, R
P Follow on Acts
I SB: Next Stage Plan CS: Advice/Ex Rep
Project Manager

Lessons Rpt
Management

Project Plan
PDs
D or Exception Plan
Draft Closure Not.
IS Plan
Plan
Updated Updated Updated
CS: Issue Register Benefits Review Plan
SB: Business Case CS: Quality Register
Benefits Review Plan
CS: Lessons Log Business Case
SB: Project Plan CS: Daily Log
CS: CIR Project Plan
CIR
Work Packages Quality Register
Updated
Team Manager

Created
Delivery

-- Once during project


-- Once per stage Checkpoint Reports
-- Many times during stage
-- Once per Work Package
-- Many per Work Package Team Plan

Based on OGC PRINCE2® material. Reproduced under license from OGC


Pre-Project Initiation Stages - Execution Close
PPD – Project Product Description PDs – Product Descriptions CIR – Configuration Item Records
IS Plan – Initiation Stage Plan CM – Configuration Mgmt Strategy CM – Communications Mgmt Strategy
MgmtPlaza

The PRINCE2 Management Products Map


By Frank Turley, MgmtPlaza

Introduction:
• This document is based on the PRINCE2 Process Model Diagram (Link)
• It is useful to compare both diagrams with each other

This PRINCE2 Management Product Map shows:


• When management products are created in a project (in which process)
• When management products are updated (Logs, Registers, BC, PP)
• Who creates these documents (most are created & updated by the PM)
• The Inputs & Outputs for each process

Theme Information
• This diagram shows when the main Theme related documents are created & updated
• Business Case: Outline BC, Business Case updated in the SB process
• Risk: Risk Mgmt Strategy, Risk Register
• Quality: Quality Mgmt Strategy, Quality Register (update from the MP process)
• Plans: IS Plan, Project Plan, Stage Plan and Project Plan is updated
• etc…