Structural Design Calculation: Main Receiving Sub-Station (MRSS)

This document appears to be a structural design calculation for a main receiving sub-station project. It includes ETABS modeling of the structure showing load cases, reinforcement requirements, and rebar percentages. Analysis was performed to design the structure and ensure code compliance based on ACI 318-05/IBC 2003 standards. Loads, joint forces, and element designs are reported.

Uploaded by

Min Khant
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
81 views15 pages

Structural Design Calculation: Main Receiving Sub-Station (MRSS)

This document appears to be a structural design calculation for a main receiving sub-station project. It includes ETABS modeling of the structure showing load cases, reinforcement requirements, and rebar percentages. Analysis was performed to design the structure and ensure code compliance based on ACI 318-05/IBC 2003 standards. Loads, joint forces, and element designs are reported.

Uploaded by

Min Khant
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 15

STRUCTURAL DESIGN CALCULATION

Project .:
MAIN RECEIVING SUB-STATION (MRSS)

Client .:

LOC. NO.: PROJECT NO.: DOCUMENT NO.: REV. NO.:

- - - -
STRUCTURAL DESIGN CALCULATION

Project .:
MAIN RECEIVING SUB-STATION (MRSS)

Client .:

A Issued for Approval S.H.A S.H.A - -

REV Description Prep'd Chk'd App'd Date

TITLE

STRUCTURAL DESIGN CALCULATION

LOC. NO.: PROJECT NO.: DOCUMENT NO.: REV. NO.:

- - - -
ETABS Thu Kha Cho

ETABS v9.7.1 - File: Model-3_For_Design_Report - March 30,2019 8:44


3-D View - N-mm Units
ETABS Thu Kha Cho

ETABS v9.7.1 - File: Model-3_For_Design_Report - March 30,2019 8:47


Plan View - TIE - Elevation 36.04462 Uniform Loads GRAVITY (FINISH) - lb-ft Units
ETABS Thu Kha Cho

ETABS v9.7.1 - File: Model-3_For_Design_Report - March 30,2019 8:47


Plan View - TIE - Elevation 36.04462 Uniform Loads GRAVITY (LIVE) - lb-ft Units
ETABS Thu Kha Cho

ETABS v9.7.1 - File: Model-3_For_Design_Report - March 30,2019 8:46


3-D View Frame Span Loads (WALL) - lb-ft Units
ETABS Thu Kha Cho

ETABS v9.7.1 - File: Model-3_For_Design_Report - March 30,2019 8:48


3-D View Wind Pressure Coeffs (WX) - lb-ft Units
ETABS Thu Kha Cho

ETABS v9.7.1 - File: Model-3_For_Design_Report - March 30,2019 8:48


3-D View Wind Pressure Coeffs (WY) - lb-ft Units
Program ETABS Version 9.6.0.0 File:Model-3_For_Design_Report.LOG

BEGIN ANALYSIS 2019/03/30 08:52:44

MAXIMUM MEMORY BLOCK SIZE (BYTES) = 64.000 MB

ELEMENT FORMATION 08:52:44

NUMBER OF JOINT ELEMENTS FORMED = 723

NUMBER OF SPRING ELEMENTS FORMED = 0

NUMBER OF FRAME ELEMENTS FORMED = 708

NUMBER OF SHELL ELEMENTS FORMED = 640

EQUATION SOLUTION 08:52:45

TOTAL NUMBER OF EQUILIBRIUM EQUATIONS = 4557

APPROXIMATE "EFFECTIVE" BAND WIDTH = 377

NUMBER OF EQUATION STORAGE BLOCKS = 1

MAXIMUM BLOCK SIZE (8-BYTE TERMS) = 1655034

SIZE OF STIFFNESS FILE(S) (BYTES) = 12.644 MB

NUMBER OF EQUATIONS TO SOLVE = 4557

NUMBER OF STATIC LOAD CASES = 9


NUMBER OF ACCELERATION LOADS = 6

NUMBER OF NONLINEAR DEFORMATION LOADS = 0

JOINT OUTPUT 08:52:46

GLOBAL FORCE BALANCE RELATIVE ERRORS

PERCENT FORCE AND MOMENT ERROR AT THE ORIGIN, IN GLOBAL COORDINATES

LOAD FX FY FZ MX MY MZ

DEAD 1.03E-11 1.41E-13 4.63E-12 3.55E-12 7.17E-12 6.38E-12

LIVE 1.48E-11 1.97E-13 6.81E-12 5.20E-12 1.05E-11 9.14E-12

WX 7.10E-10 8.24E-12 7.38E-13 3.35E-12 3.84E-10 4.39E-10

WY 1.23E-11 1.72E-09 1.26E-13 1.24E-09 8.73E-12 1.18E-09

EQX 1.08E-09 1.25E-11 1.42E-12 4.95E-12 5.84E-10 6.68E-10

EQY 1.99E-11 2.88E-09 1.46E-13 2.07E-09 1.43E-11 1.98E-09

WALL 4.96E-12 7.83E-14 3.43E-13 3.94E-13 2.83E-12 3.08E-12

FINISH 1.48E-11 1.97E-13 6.81E-12 5.20E-12 1.05E-11 9.14E-12

TRIBUTAR 1.48E-11 1.96E-13 6.76E-12 5.23E-12 1.04E-11 9.15E-12

ELEMENT JOINT-FORCE OUTPUT 08:52:46

NUMBER OF JOINT ELEMENTS SAVED = 723

NUMBER OF FRAME ELEMENTS SAVED = 708

NUMBER OF SHELL ELEMENTS SAVED = 640


ELEMENT OUTPUT 08:52:46

ANALYSIS COMPLETE 2019/03/30 08:52:46

Program ETABS Version 9.6.0.0 File:Model-3_For_Design_Report.LOG

BEGIN ANALYSIS 2019/03/30 08:52:46

MAXIMUM MEMORY BLOCK SIZE (BYTES) = 64.000 MB

ELEMENT FORMATION 08:52:47

NUMBER OF JOINT ELEMENTS FORMED = 723

NUMBER OF SPRING ELEMENTS FORMED = 0

LOAD RE-SOLUTION 08:52:47

NUMBER OF STATIC LOAD CASES = 9

ELEMENT JOINT-FORCE OUTPUT 08:52:47


NUMBER OF JOINT ELEMENTS SAVED = 723

NUMBER OF FRAME ELEMENTS SAVED = 708

NUMBER OF SHELL ELEMENTS SAVED = 640

ANALYSIS COMPLETE 2019/03/30 08:52:47


ETABS Thu Kha Cho

ETABS v9.7.1 - File: Model-3_For_Design_Report - March 30,2019 8:53


Plan View - TIE - Elevation 432.5354 Longitudinal Reinforcing (ACI 318-05/IBC 2003) - Kip-in Units
ETABS Thu Kha Cho

ETABS v9.7.1 - File: Model-3_For_Design_Report - March 30,2019 8:54


Elevation View - 1 Rebar Percentage (ACI 318-05/IBC 2003) - Kip-in Units