Project Charter Sample Construction
Project Charter Sample Construction
Project Charter Sample Construction
(2) Project Scope Aimmal Corporation has its headquarters in Ajman, Arab Emirates. The project aims at
Abstract realizing new Aimmal offices in Abu Dhabi.
The offices will be located in the city centre. An underground parking lot will be built as well
as restaurants and a pied-a-terre for the Top Management of Aimmal.
(3) Project Manager (3) Level of Authority (4) Project Sponsor(s) (5) Type of Project Sponsor
Massimo Longo Full Decision And Spending Federico Lazzarin Aimmal CEO
Authority
(6) Product Description / The full complex is made of a tower in the city centre of Abu Dhabi. Besides the new
Deliverables offices of Aimmal, a two-floor underground parking lot will be built.
A restaurant will be built in the ground floor. A second restaurant will be located in the
first floor of the building. Both restaurants will function as a canteen for the employees
and as a restaurant for visitors.
At the last floor of the tower small pied-a-terre apartments will be located to host Aimmal
Management in case they need to attend evening meetings.
The internal lighting of the tower and the climate control has been designed by the
Novara snc. The whole system has been designed to have the lowest environment impact
thanks to computer controlled panels.
Particular attention will be given to the relationship management with the project
sponsor and local stakeholders. Project personnel will be trained in order to maintain
correct behaviours with all local project stakeholders.
(9) Pre-assigned Mario Bianchi. Skilled Team Leader with long experience in the arab countries.
Resources Livio Rossi. Project Planner with a deep knowledge of Primavera P6.
Two Liebherr cranes (280 HC-L 16/28 and 357 HC-L 18/32)
1. Value (40% at deliverable acceptance ,-5% for every $100K USD spent for rework
due to no-requirements adherence)
2. Quality (30% at deliverable acceptance, -3% for every $100K USD spent for rework
due to bad performance)
3. Budget (20% if no contingencies are used, 15% in case contingencies are used)
4. Schedule (10% if project delivers on time, +10%for any month earlier)
(21) High Level Process Project Technical Review meetings will be held on a monthly bases for lessons learned
Improvement Plan analysis.
Kanban Board will be used to enhance communication in project teams.
New excavator technologies will be applied to reduce time and reworks.
Computerized lighting and climate control systems will be developed within the agile/scrum
methodology.
(22) Organizational The project will be implemented within company ISO quality standards.
Process Definition All procurement will be done through informal RFI and formal RFQ according to company
quality standard.
Contract Manager will be on-site.
(23) Main Lessons Lessons from following projects have been analysed.
Learned Applied 1. City Tower construction in Hong Kong.
2. Lloyds Tower in London.
(24) Tools & Templates The Team Leader will receive Primavera P6 training in order to understand the work done
by the Planner.
Date: / / Date: / /