EI6002 Power Plant Instrumentation Question Bank
EI6002 Power Plant Instrumentation Question Bank
EI6002 Power Plant Instrumentation Question Bank
com
VALLIAMMAI ENGINEERING COLLEGE
SRM Nagar, Kattankulathur – 603 203
DEPARTMENT OF
ELECTRONICS AND INSTRUMENTATION ENGINEERING
QUESTION BANK
VI SEMESTER
Regulation – 2013
Prepared by
INSTRUMENTATION ENGINEERING
QUESTION BANK
SUBJECT : EI 6002 POWER PLANT INSTRUMENTATION
SEM / YEAR: VI/III
INSTRUMENTATION ENGINEERING
QUESTION BANK
SUBJECT : EI 6002 POWER PLANT INSTRUMENTATION
SEM / YEAR: VI/III
PART - B
1. Distinguish between sub critical and supercritical boilers with 2 Understand
example. (16)
2. Discuss in detail with a schematic diagram the hydro power 2 Understand
plant generation. (16)
3. Describe about the layout of thermal power plant, also 1 Remember
discuss its advantages and disadvantages. (16)
4. i) Describe in detail the need of combine cycle power 1 Remember
generation? (4)
ii) Explain any two types of combined cycle power 4 Analyze
generation unit with neat sketch and working.(12)
5. With a block diagram explain the operation of nuclear 4 Analyze
power plant and also mention the important parameters to
be monitored in each blocks. (16)
6. What is meant by cogeneration? Also explain the topping 4 Analyze
cycle and bottoming cycle operation of cogeneration
system. (16)
7. i) Describe the various operations involved in thermal 1 Remember
power plant. (10)
ii) Describe the importance of instrumentation in power 1 Remember
generation. (6)
8. i) Describe briefly the importance of instrumentation in 1 Remember
nuclear power plant. (6)
ii) Illustrate the schematic diagram and explain the 3 Apply
operations of Pressurized water Nuclear Reactor &
Boiling water reactor. (10)
9. Discuss the various role of instrumentation system in 2 Understand
thermal power plant. Also list the desirable qualities of
measurement requirements. (16)
10. i) Compare and evaluate the performance 4 Analyze
characteristics of thermal and nuclear power plants
based on each component. (8)
ii) Describe in detail the basic instrumentation 1 Remember
required in thermal plant. (8)
11. i) Illustrate with a neat sketch, the process of electric 3 Apply
power generation using Wind Energy. (8)
ii) Explain with a neat sketch, the process of electric 3 Apply
INSTRUMENTATION ENGINEERING
QUESTION BANK
SUBJECT : EI 6002 POWER PLANT INSTRUMENTATION
SEM / YEAR: VI/III
PART - A
Q.No Questions BT Level Competence
1. Write the two types of feed water heaters in a steam power 6 Create
planting terms of uses.
2. List various methods of feed water flow measurement in 1 Remember
power plant.
3. Examine the suitability of float type in boiler drum level 3 Apply
measurement.
4. Classify the types of turbine speed measurement. 3 Apply
5. Give the need of vibration monitoring in turbine. 2 Understand
6. Discuss the principle of Dall tube? 6 Create
7. Point out the significance of Stagnation point? 4 Analyze
8. Demonstrate the principle of steam purity measurement. 3 Apply
9. What is pulverized coal? 1 Remember
10. Analyze the importance of drum level measurement? How 4 Analyze
is it taken care of?
11. Quote the digital methods of measuring speed. 1 Remember
INSTRUMENTATION ENGINEERING
QUESTION BANK
SUBJECT : EI 6002 POWER PLANT INSTRUMENTATION
SEM / YEAR: VI/III
INSTRUMENTATION ENGINEERING
QUESTION BANK
SUBJECT : EI 6002 POWER PLANT INSTRUMENTATION
SEM / YEAR: VI/III
drum? (4)
ii) Explain the method of measuring drum level using 5 Evaluate
differential pressure method. (12)
8. Describe in detail about Electrical and non electrical 2 Understand
parameters measured in a power plant. (16)
9. List the parameters to be measured in Flue gas of Boiler. 1 Remember
(16)
10. i) How do you measure current, voltage, power in a 1 Remember
power plant? Explain their basic principles. (8)
ii) Describe about the flow control measurements 1 Remember
required in power plants. (8)
11. i) With suitable diagram, explain the principle of 5 Evaluate
Electromagnetic type flow meters. (12)
ii) Mention its advantages and limitations of 4 Analyze
Electromagnetic type flow meters. (4)
12. Describe the need of Fuel Analysis in Thermal Power plant. 2 Understand
Also explain the Fuel Analysis method in detail.(16)
13. i) Describe a primary and secondary element each in the 1 Remember
measurement of feed water flow.(8)
ii) Discuss the principle behind vortex flow meter. (8) 2 Understand
14. i) Discuss the operation of LP and HP heaters in a steam 2 Understand
power plant. (8)
ii) What are the basic impurities in feed water and how do 4 Analyze
you analyze them.(8)
INSTRUMENTATION ENGINEERING
QUESTION BANK
SUBJECT : EI 6002 POWER PLANT INSTRUMENTATION
SEM / YEAR: VI/III
PART - A
Q.No Questions BT Level Competence
1. Describe the concept of excess air. 1 Remember
2. List the two basic types of deaerator. 1 Remember
3. Analyze the stoichiometric condition of combustion in fuel. 4 Analyze
4. Evaluate the necessity for Steam temperature control. 5 Evaluate
5. Define Firing rate demand. 1 Remember
6. Design split-range control. 6 Create
7. Examine the need for "Air/fuel ratio" control. 3 Apply
8. Predict the role of attemperator. 2 Understand
9. List the methods of Trimming 1 Remember
10. Quite the need of deaerator control. 1 Remember
11. Examine the role of boiler control. 3 Apply
12. Give the function of a deaerator in power plant and its 2 Understand
importance.
13. Quote the Steam temperature control methods. 1 Remember
14. Give the requirements to be considered for firing due to 2 Understand
load change.
15. Combine the two methods of Furnace draft control. 6 Create
16. Differentiate the advantage of three element control with 2 Understand
single element control.
17. Examine the balanced draft in Boiler. 4 Analyze
INSTRUMENTATION ENGINEERING
QUESTION BANK
SUBJECT : EI 6002 POWER PLANT INSTRUMENTATION
SEM / YEAR: VI/III
INSTRUMENTATION ENGINEERING
QUESTION BANK
SUBJECT : EI 6002 POWER PLANT INSTRUMENTATION
SEM / YEAR: VI/III
INSTRUMENTATION ENGINEERING
QUESTION BANK
SUBJECT : EI 6002 POWER PLANT INSTRUMENTATION
SEM / YEAR: VI/III
INSTRUMENTATION ENGINEERING
QUESTION BANK
SUBJECT : EI 6002 POWER PLANT INSTRUMENTATION
SEM / YEAR: VI/III
12. Explain in detail about burners for gaseous fuel. (16) 5 Evaluate
INSTRUMENTATION ENGINEERING
QUESTION BANK
SUBJECT : EI 6002 POWER PLANT INSTRUMENTATION
SEM / YEAR: VI/III
PART - A
Q.No Questions BT Level Competence
INSTRUMENTATION ENGINEERING
QUESTION BANK
SUBJECT : EI 6002 POWER PLANT INSTRUMENTATION
SEM / YEAR: VI/III
ii) Explain the control system employed for oil coolers in 4 Analyze
turbine (6)
6. Describe briefly various methods of steam turbine 1 Remember
governing. (16)
7. i) Illustrate with neat block diagram explain Impulse 3 Apply
turbine. (8)
ii) Illustrate with neat block diagram explain Reaction 3 Apply
turbine. (8)
INSTRUMENTATION ENGINEERING
QUESTION BANK
SUBJECT : EI 6002 POWER PLANT INSTRUMENTATION
SEM / YEAR: VI/III
13. Discuss about oil coolers in turbine with neat sketch. (16) 2 Understand
14. Explain with the control diagram the boiler-turbine 4 Analyze