Acs 03 Usfd
Acs 03 Usfd
Acs 03 Usfd
“4.1.1c) Sensitivity setting of the equipment and probes– Check once every 3 days
The sensitivity of the USFD equipment shall be set up once every 3 dayswith the help of standard rail
pieces as mentioned below:
Sensitivity (gain) setting: For the sensitivity setting of ultrasonic equipment and the probes, the following
sequence is to be maintained:
i) Place the testing trolley on the standard rail piece having artificial flaws as shown in Fig.
3 for need based criteria. Check the alignment of probes to make sure that 700 Central
probe & 00 probe travel centrally in line with the axis of the rail head & web. 700 GF & 700
NGF probes shall be aligned towards GF & NGF respectively at appropriate positions.
ii) Set the acoustic barrier of the normal probe at right angle to the longitudinal direction of
rail.
iii) Open the water nozzle and regulate water flow on the probes at an optimum speed.
iv) While testing on single line section and ‘D’ marked rails on double / multiple line section,
additional gain of 10db is to be employed.”
2. Para 5.1.2 is revised as follows :
“5.1.2 During testing
(i) Conduct test as per procedure mentioned in Chapter 6.
(ii) Maintain proper alignment of all probes during testing, otherwise false echoes may appear.
(iii) Ensure adequate supply of water for coupling.
(iv) Check proper functioning of 70o probes by touching the probe bottom with fingers. Noise
pattern should appear on the screen.
(v) Look out for back wall echo corresponding to normal probe throughout testing
(vi) Lift the machine at crossings/change of rail table height at joints to protect the probes.
(vii) Mark the locations found defective as per classification.”
A thermit welding done in-situ shall be joggled fish-plated with two clamps and supported on
wooden blocks of 300-450 mm length untill tested as good by USFD.”
“8.14 Action to be taken after detection of defects in AT welds : Action to be taken for defects
in AT welds shall be same as at para 6.4. In addition, following shall also be applicable
for welds classified as defective (DFWO/DFWR) in Initial acceptance test & periodic
testing of AT welds using hand probing :
The frequency of testing of AT welds with above listed probes shall be as under:
In case of welds on major bridges & bridge approaches (100m either side) and in tunnels & on tunnel
approaches (100m either side), the minimum frequency of testing shall be once in a year.
Due to unusually high weld failure or other abnormal development in some sections, Chief
Engineer may order testing of welds early, as per need.
The testing interval of USFD testing of defective AT welds should be reduced by 50% of normal
testing interval of AT welds as provided in para8.15.1 to avoid fractures of defective welds.
8. Below Para 8.16, New clause b) (iii) under Note ‘Guidelines for the operators’, is added
as given below :
“ b) (iii) The defect signal observed at the collar from one end of testing shall be confirmed from other
end also. If defect is confirmed from both the ends the welds must be marked as defective.”
9. Fig.3 and Fig.22 (c) are revised and are enclosed at Annexure-1-A and Annexure-1-B.
10. New para 6.3.1 and 6.3.2 are added as given below :
“6.3.1: Defect at any location which is detected by two or more probes and are considered
to be classified asOBS/OBSW based on peak pattern of individual probe, should be
classified as IMR/IMRW and action shall be taken accordingly as per Para 6.4.
6.3.2: In case two or more OBS/OBSW defects are located within a distance of 4.0 metre
from each other, such OBS/OBSW defects shall be classified as IMR/IMRW and
action shall be taken accordingly as per Para 6.4.”
11. A new Para 10.6 is added at the end of chapter 10 as follows:
10.6Guidelines for USFD testing of tongue rail of point & crossing in service.
10.6.1 For purpose of USFD testing of tongue rails of points and crossings, the tongue rail can be
demarcated in three zones as under:
a. Zone-1: Where full width of Rail head is available. This zone shall be covered in normal rail
testing.
b. Zone-2: Region where scanning by 700 probe is easily feasible i.e. up to width of rail head of points
and crossings, where 700 probe of 20 mm crystal size can be suitably placed over it.
c. Zone-3: Rest portion of tongue rail of points and crossing.
10.6.2 The USFD testing of tongue rails of points and crossings, shall be done as given below.
The sensitivity setting for the probes shall remain same as used for through periodic rail
testing.
a. Zone-1 : This part of tongue rail of point & crossings where full width of rail head is available,
shall be covered in normal rail testing using double rail tester. In some of the switches in which
guide roller of double rail tester hinder the movement of trolley up to full width of rail head part,
lower dia of guide roller shall be used.
b. Zone-2 : This part of tongue rail shall be tested manually using 70˚/2 MHz , Single crystal probe
having crystal size 20 dia. or 20x20 mm square crystal.
c. Zone-3 : This part of the tongue rail shall be examined visually.
10.6.3 Classification of defects : The defect classification shall be made as per provisions given
in Item 1(A), 2(A) , 3 (A) and 4(A) of Annexure-II-A of ‘Manual for Ultrasonic testing of
rails & welds, (Revised-2012)’
However, in zone-2 provisions given in Item 2(A) and 3 (A) of Annexure-II-A of ‘Manual for
Ultrasonic testing of rails & welds, (Revised-2012)’ shall be applicable.
10.6.4 Action to be taken after detection of defects: SE/JE (P.Way)/USFD shall impose speed
restriction of 30 Kmph or stricter immediately and to be continued till flawed tongue rail is
replaced which should be done within 3 days of detection.
5Ø FBH
15
SLICE FROM RAIL HEAD RAIL HEAD WIDTH
300
25
20
40
20° 25
90°
Fig. 3
APPROX. 100
1.25m
1.5m LONG ALUMINIUM / WOODEN HOUSING FOR TEST PIECE HAVING TOP TABLE
WIDTH EQUAL TO RAIL HEAD WIDTH
1. The slice from rail head for sensitivity setting shall be from rail of same sectional weight which is to be tested (i.e. for testing on 60Kg/52Kg, 90R rails etc. the
sensitivity testing piece shall be from 60Kg, 52Kg, 90R rails respectively).
2. In case of machines having provision of variable shift of gauge face probes following shall be ensured:
a) Maximum shift of probe shall be limited to the extant up to which there is no loss of acoustic coupling depending on rail top profile.
b) The sensitivity setting shall be done at the shift level with which actual testing is to be carried out.
c) The shift of probe shall not be altered during testing without fresh setting at altered shift .
ALL DIMENSIONS ARE IN mm.
FIG. 3 - SENSITIVITY SETTING BLOCK FOR 70 ° 2MHz (CENTRE, DRAWING IS NOT TO SCALE
Annexure‐1 B
HEIGHT OF RAIL
TX TX RX RX
Rig.
FLAW
Fig. 22 (c): AT Weld Testing using 45° tandem probe
Fig. 22(c)