2018 ASME International Pipeline Conference - Breathing New Life To Aging Pipeline Infrastructure With Tite Liner™

Download as pdf or txt
Download as pdf or txt
You are on page 1of 47

IPC-2018-78594

BREATHING NEW LIFE TO AGING PIPELINE INFRASTRUCTURE


USING UNIQUE WIRELINE INSPECTION TECHNIQUES AND PIPE-
LINING TECHNOLOGY

Alex Gutierrez Clay Goudy


United Pipeline de Mexico Q-Inline
An Aegion Company A Quanta Services Company
Introduction

§ Breathing new life into existing Pipeline Infrastructure


§ The Challenge
§ The Strategy
• Tethered Inspection
• Carbon Fiber Re-inforcement
• Pipeline Liner
§ Lessons Learned
Breathing New Life

§ In 2014, Mexico’s Energy Reform opened up market to private investment

§ More than 14 billion USD of pipeline investments expected by 2023

§ Nearly 8,000 km of pipelines in strategic markets are out of service

§ In 2016, United approached with high profile CO2 pipeline rehab project

§ 56km. CO2 pipeline system in bad shape - 10 months execution window

§ Dilemma and Opportunity – New system vs rehabilitation


The Challenge

§ Pipeline system issues


• CO2 pipeline provides feedstock to Urea plant
• Documented Leaks (air tests) in locations with difficult access
• Indications of internal and external corrosion
• ROW through environmentally sensitive areas and populated areas
• New construction would not meet 10 month execution window

§ Pipeline integrity assessment to determine Fitness for Purpose

§ Pipelines were un-piggable

§ Land access was a significant challenge


The Challenge

§ Project Specifics:
• 12 and 18 inch pipelines x 28 kilometers
• 18 kilometers of environmentally protected marsh and swamp
• 8 kilometers of populated areas
• 2 kilometers through petrochemical facility and pipe racks
• Humid CO2 transport at 400 psi pressure
• Internal and external corrosion indications

§ Rehabilitation and repair strategy required pin-point accuracy

§ Interactive Pipeline Liner – corrosion barrier + structural integrity


The Challenge
The Challenge
The Challenge
The Challenge
The Challenge
The Strategy

§ Tethered ILI inspection to provide exact location of anomalies

§ CIS-DCVG surveys to evaluate coating and CP system

§ Pin-point repairs with steel replacement and FRP reinforcement

§ HDPE & PA-12 pipe liner installation with leak detection features

§ New automated CP system installation

§ Hydro-testing and commissioning


Tethered Inspection

§ Technology: Tethered Hi-Res Triax Sensor MFL and Caliper tool


§ Total Length: 56 kilometers in 12 and 18 inch diameters
§ Sections: 26 sections of 2,600 – 11,500 feet in length
§ Assessment Guidelines: ASME B31G and Modified 31G

§ Data sent from the field with 24 hour data analysis turn-around
§ More than 18,000 indications with 600 indications requiring repair
§ Tethered tool pulled with skid-wireline provided high quality data

§ Pin-Point accuracy minimized land access issues


Tethered Inspection
Tethered Inspection
Tethered Inspection
Tethered Inspection
Tethered Inspection
Tethered Inspection
Tethered Inspection
Tethered Inspection
Tethered Inspection
Tethered Inspection
Tethered Inspection
Tethered Inspection
Tethered Inspection

Classification of wall thickness loss anomalies


800

1
700
10

600

500

12 inch pipeline 400

300
685
0
8

0
20
1

1
12
18 2
200
381 0 4
0
3 10 4

0 277
0 33 0
1 1 1 0
0
3 12 0 212
100 0 2 198
184
3 162 0
3 159
1
6 0 1 0 112 0 111 117
89 5 95 96
81 5 2 0 0 1 0 0 0 80
0 72 0
58 48 3 7 0 0 1
0 40 42 36 33
10 21 19 4 12 16
0
KM 0 - 1

KM 1 - 2

KM 2 - 3

KM 3 - 4

KM 4 - 5

KM 5 - 6

KM 6 - 7

KM 7 - 8

KM 8 - 9

KM 9 - 10

KM 10 - 11

KM 11 - 12

KM 12 - 13

KM 13 - 14

KM 14 - 15

KM 15 - 16

KM 16 - 17

KM 17 - 18

KM 18 - 19

KM 19 - 20

KM 20 - 21

KM 21 - 22

KM 22 - 23

KM 23 - 24

KM 24 - 25

KM 25 - 26

KM 26 - 27

KM 27 - 28

KM 28 - 29
<IMA 40% IMA-LM 40-80% LM 80% o Mayor

SECCION EL POLVORIN-PAJARITOS
SECCION COSOLEACAQUE-LA PERA

18 inch pipeline
Tethered Inspection
Tethered Inspection
Tethered Inspection
FRP Reinforcement

§ Tyfo FRP system meets ASME-PCC-2 and ISO-24817 standards


§ Fast and cost-effective solution for wall loss repairs
§ Pin-point accuracy of ILI data allowed for localized reinforcement
FRP Reinforcement
Pipeline Liner

§ Two thirds of wall loss indications due to internal corrosion

§ Humid CO2 a source of integrity concerns

§ Plastic Liner eliminates concerns

§ Interactive system complements steel strength

§ Pressurized Groove Design allows for real time leak detection

§ PA-12 liner installed in river crossing - eliminate permeation

§ Significant flow improvement expected


Pipeline Liner

Interactive Liner Gap Spanning


§ Purpose: reinforce steel pipelines in areas with localized corrosion
§ Bridge areas of reduced wall thickness assuming a worst case scenario
§ 400 psi operating pressure - interactive liner spans upto 4 inch holes
Pipeline Liner

Flow Improvement
§ Reduction in friction coefficient of liner vs bare steel = improved flow
§ Flow improvement resulted in increased flow transport capacity
§ Hazen Williams flow calculation (water) shows a 21-26% improvement
§ For gas, Darcy-Weisbach model for laminar flow showed a similar result
§ Observed system improvement from 2,200TPD to 2,710TPD = 23%
Pipeline Liner

Active Liner Monitoring


§ Purpose: Detect pinhole anomalies
§ Annular space pressure – 10 to 15 psi
§ Annular space pressure real time monitoring with wireless sensors
Pipeline Liner
Pipeline Liner
Pipeline Liner
Pipeline Liner
Pipeline Liner
Pipeline Liner
Pipeline Liner
Pipeline Liner
Pipeline Liner
Pipeline Liner
Pipeline Liner
Lessons Learned

§ Success of project = Tethered ILI inspection + solid rehab strategy

§ 56 kilometers of pipeline put back into service in 10 months

§ Rehabilitation = utilization of key asset at a fraction of cost & time

§ Pemex Logistics has more than 874 out of commission pipelines

§ Cost effective strategy to obtain access to strategic markets

§ An observed 22% improvement in flow capacity a big bonus


Questions?

You might also like