MODULE 4:
TECHNIQUES IN PT ROUTE
PLANNING: TRANSIT SERVICES
Eden T Sorupia, PhD
1
Local Public Transport Route Planning & Management Training Course | Module 4
Route Identification Factors
• Road network configuration
• Passenger demand (passenger load
profile)
2
Local Public Transport Route Planning & Management Training Course | Module 4
Route Identification Factors
• Road network configuration
• Passenger demand (passenger load
profile)
3
Local Public Transport Route Planning & Management Training Course | Module 4
Specific Factors to be Considered
a) Route ends at activity centers
b) Two route ends are connected by a series of road links
c) Shortest path is desirable between route ends
d) Passenger demand includes both end-to-end and
intermediate areas along the route
e) Off-street terminals
4
Local Public Transport Route Planning & Management Training Course | Module 4 Image: ilerlawfirm.net
Specific Factors to be Considered
f) Turning points at route ends
g) Public Transport network should
minimize number of transfers
h) Road sections should be able to
accommodate type and volume
of transit vehicles
i) Appropriate transit vehicle to
serve passenger demand and be
compatible with road capacity
5
Local Public Transport Route Planning & Management Training Course | Module 4
Basic Concept on Road Network with
Functional Characteristics
Arterial Road: Predominantly
carries through traffic from
one region to another, forming
principal avenues of travel for
traffic movements
Collector/Secondary: Non-
arterial road that collects and
distributes traffic in an area, as
well as serving abutting
property
Local Road: Primary purpose is
Legend: to access abutting properties
Arterial, Main Thoroughfare
Collector, Secondary
Local Road
6
Local Public Transport Route Planning & Management Training Course | Module 4
Mobility vs Accessibility
Mobility is the ability and level of ease of moving goods and services.
Congestion Management System: increases the efficiency of
moving people while removing cars from the roads.
Manages Travel Demand by utilizing strategies that increase
volume and capacity
Examples: designated truck lanes, bus only lanes
7
Local Public Transport Route Planning & Management Training Course | Module 4
Mobility vs. Accessibility
•Accessibility refers to
the number of activity
sites connected by the
facility
8
Local Public Transport Route Planning & Management Training Course | Module 4
Example 1: Passenger Demand as Input to PT
Route Planning -- Corridor
9
Local Public Transport Route Planning & Management Training Course | Module 4
Trip Assignment
Pax Volume
From To (pax/day Section
AB BA BC CB CD DC
A B 3,200 3,200
C 1,000 1,000 1,000
D 200 200 200 200
B A 3,000 3,000
C 1,300 1,300
D 300 300 300
C A 800 800 800
B 600 600
D 350 350
D A 360 360 360 360
B 400 400 400
C 450 450
Total 4,400 4.160 2,800 2,160 850 1,210 10
Local Public Transport Route Planning & Management Training Course | Module 4
Trip Assignment
11
Local Public Transport Route Planning & Management Training Course | Module 4
Trip Assignment
Assume a Seasonality Factor (SF) of 1.16
Ave. One-Way Volume (pax/day)
AB : 4,965
BC : 2,877
CD : 1,195
Passenger Load Profile (pax/day):
4,965 2,877
A B C
1,195 D
15
Local Public Transport Route Planning & Management Training Course | Module 4
Exercise: Estimating Level of Supply
Route A to D
Factors to be Considered:
Passenger Volume (PV) : 1,195 pax/day Mode PPHPD Distance (km)
Route Length (RL) : 45km FilCab < 500
PUJ 501 - 1,000 15 - 35
UV Express 501 - 1,000 35 - 60
Desired Operating Characteristics Mini Bus 1,001 - 5,000 > 60
Bus > 5001 > 60
Mode to be used : Bus
Ave. Seating Capacity (ASC) : 50 passengers
Ave. Travel Speed (ATS) : 30 kph
Terminal Waiting Time (TWT) : 1 hr/route end
Ave. One-Way Travel Time (TRT) : RL /ATS 45/30 = 1.5 hrs
Ave. Time per Round Trip (TRP) : (TWT x 2) + (TRT x 2)
: (1*2) + (1.5*2) = 5 hrs per day
No. of Hours in Operation NOH) : 14 hrs
Ave. No. of Round Trips per Day (NRT) : NOH / TRP 14/5 = 2.8
Viable Load Factor (VLF) : 0.70 (assume)
16
Local Public Transport Route Planning & Management Training Course | Module 4
Exercise: Estimating Level of Supply
17
Local Public Transport Route Planning & Management Training Course | Module 4
Estimate of Number of Units & Fleet Size
NU = PV / (VLF x ASC x NRT)
Where NU = Desired number of units operating per day
PV = Passenger Volume 1,195
VLF = Viable Load Factor 0.70
ASC = Ave Seating Capacity Bus = 50
NRT = Ave Number of Round Trips per day 2.8 Round Up = 3
NU = 1,195/(0.70*50*3)
NU = 11.4 say, 11
18
Local Public Transport Route Planning & Management Training Course | Module 4
Alternative Procedure in Estimating NU and FS
19
Local Public Transport Route Planning & Management Training Course | Module 4
Exercise: Estimating Level of Supply
1.0 Route A to C
PV = ________ pax/day
RL = ________ km
Desired Characteristics
Mode to be used : ___________
ASC : ___________ pax
ATS : ___________ kph
TWT : ___________ hr
TRT : ___________
TRP : ___________
NOH : ___________ hrs.
NRT : ___________ per day
VLF : ___________ (assume)
Estimate
NU = ___________
Assume UR = ___________
FS = ___________
Estimate
NU = PV / (VLF x ASC x NRT)
Assume UR = ___________
Fleet Size (FS) = ___________
Estimate
NU = PV / (VLF x ASC x NRT) = 1,682/(0.70 x 24 x 6) = 16.68 (Round Up)
Assume UR = 0.8
Fleet Size (FS) = NU x (1/UR) = 21.25 (Round Up) = 22
24
Local Public Transport Route Planning & Management Training Course | Module 4
Example of Growth Rate Determination
Year 2010: Pop1 = 35,000 (base year population)
Year 2015: Pop2 = 39,800 (5 years from base year)
Route A to D
PV = 1,195 pax/day
r = 2.6%
n = 5 years
26
Local Public Transport Route Planning & Management Training Course | Module 4
Passenger Volume Forecasting
27
Local Public Transport Route Planning & Management Training Course | Module 4
Trip Generation Index/Trip Rates
Person-trips per 100 sqm of Residential Floor Area
Trip Rates (Person Trips/100 Sqm)
Time
In Out Total
06:00 - 07:00 0.300 0.274 0.574
07:00 - 08:00 0.689 0.722 1.411
08:00 - 09:00 0.604 0.743 1.347
09:00 - 10:00 0.844 0.871 1.715
10:00 - 11:00 0.694 0.840 1.534
11:00 - 12:00 1.058 1.091 2.149
12:00 - 13:00 1.293 1.267 2.560
13:00 - 14:00 1.189 1.248 2.437
14:00 - 15:00 0.692 0.930 1.622
15:00 - 16:00 0.975 0.989 1.964
16:00 - 17:00 1.283 1.131 2.414
17:00 - 18:00 1.287 1.399 2.686
18:00 - 19:00 1.355 1.693 3.048
19:00 - 20:00 1.126 1.225 2.351
Total 13.389 14.423 27.812
28
Local Public Transport Route Planning & Management Training Course | Module 4
Trip Generation Index/Trip Rates
Person-trips per SqM of Retail/Commercial GFA
Trip Rates (Person Trips/Sqm)
Time
In Out Total
06:00 - 07:00 - - -
07:00 - 08:00 - - -
08:00 - 09:00 - - -
09:00 - 10:00 - - -
10:00 - 11:00 0.0342 0.0083 0.0425
11:00 - 12:00 0.0421 0.0185 0.0606
12:00 - 13:00 0.0386 0.0287 0.0673
13:00 - 14:00 0.0422 0.0333 0.0755
14:00 - 15:00 0.0348 0.0332 0.0680
15:00 - 16:00 0.0368 0.0410 0.0778
16:00 - 17:00 0.0435 0.0408 0.0843
17:00 - 18:00 0.0476 0.0521 0.0997
18:00 - 19:00 0.0401 0.0465 0.0866
19:00 - 20:00 0.0341 0.0522 0.0863
Total 0.3940 0.3546 0.7486
29
Local Public Transport Route Planning & Management Training Course | Module 4
Trip Generation Index/Trip Rates
Person-trips per SqM of Office Area
Trip Rates
Time
In Out Total
06:00 - 07:00 0.0171 0.0222 0.0393
07:00 - 08:00 0.0183 0.0244 0.0427
08:00 - 09:00 0.0194 0.0238 0.0432
09:00 - 10:00 0.0219 0.0298 0.0517
10:00 - 11:00 0.0211 0.0281 0.0492
11:00 - 12:00 0.0221 0.0302 0.0523
12:00 - 13:00 0.0248 0.0312 0.056
13:00 - 14:00 0.0258 0.0336 0.0594
14:00 - 15:00 0.0263 0.0336 0.0599
15:00 - 16:00 0.0269 0.0364 0.0633
16:00 - 17:00 0.0295 0.0399 0.0694
17:00 - 18:00 0.0343 0.0468 0.0811
18:00 - 19:00 0.0375 0.0493 0.0868
19:00 - 20:00 0.0379 0.0522 0.0901
Total 0.3629 0.4815 0.8444
30
Local Public Transport Route Planning & Management Training Course | Module 4
Example: Computation of Generated Traffic
Residential Area: GFA = 33,762 SqM
AM Peak Index
In : 0.689 person trips/100 SqM of GFA
Out : 0.722 persons trips/100 SqM of GFA
Daily
In : 13.389 person trips/100 SqM of GFA
Out : 14.423 persons trips/100 SqM of GFA
31
Local Public Transport Route Planning & Management Training Course | Module 4
Example: Estimating No. of Units (NU)
VARIABLES Assume modal split:
Type of Mode: Minibus, ASC = 35 70% public and 30% private:
Route Length (RL) = 10 km
Ave Travel Speed (ATS) = 25 kph; PV = 0.70 * 4,695 = 3,287 pax/day
Terminal Waiting Time (TWT) = 30 mins;
No of Operating Hours (NOH) = 16 hrs NUMBER OF UNITS
NU = PV / (VLF x ASC x NRT)
Ave Time per Round Trip
= (RL/ATS x 2) + (TWT/60 mins x 2) NU = 3,287 / (0.7 x 35 x 9)
= (10/25 * 2) + (30/60 * 2) NU = 15 units
= (20/25) + 1
= 1.8 hrs
FLEET SIZE
Number of Round Trips (NRT)
NRT = NOH/Ave Time per Round Trip FS = NU * (1/UR)
NRT = 16/1.8 = 8.9 (Round Up) FS = 15 x (1/0.8) = 18.75
NRT = 9 FS = 19 units
32
Local Public Transport Route Planning & Management Training Course | Module 4
End