Piping Checklist
Piping Checklist
Piping Checklist
60% model review is one of the reviews planned in all the EPC projects execution at different
stages- 30%, 60% and 90% of design completion.
60% 3D model review is an intermediate review which take place when the final structural
steel, final equipment and the majority of the major piping runs, duct-work, instrument and
electrical trays have been MODELLED. The primary purpose of these reviews is to review the
routings to insure that process integrity has not been compromised, that the pipe, duct-work and
tray runs are in accordance with the minimum criteria established for the project and to observe
any potential interference in the operability or maintainability, created by the routing of these
items.
Below is the piping check point which shall be reviewed prior to 60% 3D model review:
PROJECT NAME : PROJECT NO. :
DOCUMENT NO. :
General:
3 Pipe supports locations & types are correct. Supports for stress critical systems shall be based on
stress analysis calculations.
4 Utility stations locations are shown by volume box and the locations are checked.
5 Foam powder & Water Spray Systems are modeled and checked.
7 Access and egress, operation and maintenance of valve and instruments are checked.
9 All equipment are modeled as per latest vendor drawings & checked.
10 All mechanical handling equipment’s like cranes, monorails, davits, eye pads, EOT’s etc… are
modeled and checked.
11 All structural steel, e.g. pipe racks, technological structures, shelters, platforms, stair cases /ladders,
pipe supports designed by civil etc… are modeled as Civil design and checked.
15 All Instrument items like junction boxes, panels, cabinets, SIV vessels Inclusive of supports) are
modeled and checked.
16 All Electrical items like junction boxes, panels, cabinets, lighting poles, flood lights, masts etc…
(Inclusive of supports) are modeled and checked.
17 All Telecom items like junction boxes, panels, cabinets, CCTVs, PAGA speakers, telecom tower,
etc… are modeled and checked.
18 All above ground cable tray routing is modeled and checked. Outline of drops to equipment/all users
is shown in the model.
24 Interdisciplinary model review is conducted and all the comments are resolved.
Process related:
25 All line numbers, line size, pipe class & flow direction are checked as per P&IDs.
26 All tags for equipment, valve, SP item and Instrument are checked as per P&IDs.
27 All in-line & on-line components are located and sequence of branch connections are as per P&IDs.
28 The special requirements such as slope, no pocket, removable spool etc. and design related P&ID
notes are taken care.
29 Ensure the hydro test vents and drains are provided where necessary (for all lines that will be hydro
tested).
32 The requirement of symmetrical piping and minimum piping are properly taken care as per process
requirement, if applicable.(esp. for air cooler piping)
33 The requirement of straight length for inlet pipes at column inlets, knock out drums/vessels and
cyclones etc. are taken care as per Process/Mechanical requirement.
34 The straight length requirement for suction & discharge of pumps/ Compressors, if any is checked.
35 The suction line for compressor is routed with a slope towards the knock out drum.
36 The length / no. of elbows on suction line between tank/vessel and pump should be minimum.
Pockets may be avoided if possible. High points shall be below the LL level in the tank (i.e. Fully
flooded line).
37 All the vapor lines branch off from the top of the main line.
38 All valves required for emergency operations are operable from grade.
39 Lines are provided with drain connection between two valves, especially when the second valve is a
check valve.
40 The hot lines which are near to the operating platform or near the reach of the person are insulated for
personnel protection. The limits of insulation modeled are checked.
41 The routing of flare header is free of any pocket and kept continuously sloping towards knock-out
drum as per process requirement.
Layout related:
42 Ensure all vertical lines rising or dropping from rack to unit are maintained same back of pipe from
rack.
43 Arrangement of piping entering and leaving the plant are logically grouped together at the battery limit.
44 The PSV outlet lines are self draining to flare header and ensure no pocket in PSV inlet lines.
45 The personnel access/ingress paths are free from hazards posed by blow out panels, rupture discs
and relief valve discharge stacks.
46 Removable spool shall be of minimum length and shall not have any instruments, vents, drains and
other tapping/connected piping.
47 The area for large filters, strainers etc. are located within curbed areas to contain the spillage during
cartridge/element replacement operations.
48 The handling & removal of all valves, blinds etc. for maintenance are reviewed with respect to
arrangement and access space.
49 Ensure that the design has been done effectively to reduce the number of flanges required for
internally lined pipes and Galvanized pipes greater than 2”.
50 Operation and maintenance access for all valves, Instrumentation, spec. blinds/spacer & spade are
provided.
51 Platforms requirement for accessibility, operation, maintenance are taken care. Also ensure proper
access is provided by proper selection of ladders or stairways.
52 Proper size cut outs are provided on platform/floor openings for piping.
54 Ensure there is no interference with adjacent lines/structure due to expansion of piping in hot
condition.
56 The flat side up (FSU) eccentric reducer is used in pump suction line to avoid pocket formation which
may cause the cavitations of the pump.
57 In general, on straight pipe run the eccentric reducer is used with its flat side down (FSD).
58 Placement of valves in pipe racks has been avoided. If unavoidable they are to be provided with
access.
59 For routing of jacketed sulphur piping, cross is used where the direction change is envisaged. Also
ensure proper space for rodding from two directions.
60 Ensure that the valves and instruments located on sulphur pits are safely accessible in case of fire for
shutdown.
61 Provision of tundish where drain is to be collected from the open drain system is checked.
62 Ensure the discharge of process and hydrocarbon lines should not be let to open at grade; This
should be connected to closed drain system.
63 Ensure the Relief valve piping should be as short as possible when discharging into a closed system.
64 The valve pits, sumps, catch basins and trenches, culverts and any other pits etc. are properly located
and checked.
65 The dyke, curb walls, bund walls and fire separation walls etc. are properly located and checked.
67 The piping for Pumps in parallel and Fin fan coolers is checked for symmetry to have same
performance.
69 Location of suction air filters is checked so that the air quality is clean and free from obstacle.
70 Hand wheel/lever location/orientation to be checked for plug/ball valves for interference with operating
access, platforms, structures etc.
71 Check the distance of snuffing steam isolation valve for fired heaters, it is to be located 15m away
from heater.
74 The adequate clearance availability for the maintenance and removal of rotors/shafts/internals etc
(including the installation of temporary rigging beams, hoists, chain falls, etc.) should be checked.
75 The bottom of monorails/ hoists/EOT/HOT hook elevation should not be lower than the usable
openings of roll-up doors, forklift access aisles etc.
76 The Crane/Hoist hook limits have been considered when setting crane/monorail elevations. (The
compressor/blower/pump shelter sizes to checked w.r.to available operation & maintenance space.)
78 Adequate lay down areas are identified and located for use with cranes, gantries and monorails.
79 The requirement of breakup flanges should be checked for piping running over equipments (esp.
compressors, chemical injection package, blowers).
80 Fire proofing requirement to be checked as per HSE. Fire proofing if required, shall be modeled and
checked for clearances and interferences.
81 The pumps with a vertical suction line and the elevated strainer are properly located and ensured the
opening of such strainer does not result in spilling the flammable liquid.
82 Access around the pumps is to be checked for obstruction due to hook up around the pumps like seal
oil lines, casing drains to closed drain network etc.
83 All Cryogenic service valves stem are to be checked for the stem in Vertical position or at less than 45
degree angle to vertical.
86 The Control valves, ESDV, & PSV are modeled and checked as per vendor drawings along with
correct size and orientation of actuators. Maintenance access is checked for Control valves, ESDV,
PSV & actuators of valves.
87 All inline/online Instrument connections are checked as per the Inst. Hook-up drawings.
88 The instrument orifice tapping orientations are checked as per Instrument Standards as per type of
fluid (e.g. gas & liquid).
90 The suction of the air blower of buildings and the inlet for HVAC is taken from a non-hazardous area.
91 Check that tracing around the suction and discharge lines can be dismantled to allow pump removal.
92 The clearance for removal of strainer basket is checked. Also checked for requirement of breakup
flanges, if any for strainer drain lines.
93 Instrument and electrical push buttons on poles are checked so as they are not obstructing the
accessibility of the pump.
94 The piping with instrument connections is properly positioned for easy accessibility. If needed for
access, the necessary platform and walkways are provided.
95 In case ultrasonic flow meter is used, then adequacy of space available around the flow meter is
checked for installation of the flow meter sensor so that it does not touch adjacent line.
96 Electrical, Instrumentation and Telecommunication JB are locations are checked so that they are not
causing obstruction in the walkway.
97 Sample cabinet and coolers are properly located and checked, wherever applicable.
100 The electrical main cable trays are properly shown and checked.
101 The underground electrical/instrumentation cable trenches etc. are properly shown and checked.
102 The underground electrical conduits are properly shown and checked (esp. where crossing is
expected).
103 Electrical transformers as a block are shown. Bus duct between Generator and the Switchboard are
shown.
104 Electrical Panel, Junction Boxes, Push Button stations are shown and checked.
105 Instrument main & branch cable trays of 150 mm and above along with, trenches, junction boxes,
transmitter boxes etc. are located and shown and checked.
Stress and supporting related:
106 The appropriate secondary supports are provided and span is checked as per the support
specification.
107 Stress group comments for stress critical lines are incorporated and checked.
108 The routings of two-phase lines are to be without pocket to the maximum extent possible. Also ensure
proper supporting of these lines.
110 Ensure civil structural & foundation is modeled for non standard secondary supports (by civil)
111 Ensure that correct types of primary supports are selected like clamp type shoes shall be used for
Stainless steel, Alloy steel and galvanized pipes. Clamp type shoes shall be used for Carbon steel
pipes requiring PWHT.
112 All foundation including footing/ piling wherever applicable is located and shown (for equipments, pipe
support and platforms, etc).
115 Small bore branches with long runs are checked for proper supporting and requirement of stiffeners at
branch–off locations.
Piping Checklist for 90% 3D Model Review
90% 3D model review is a final review in 3 sets of model reviews, 30%, 60% and
90%. 90% 3D model review held when the 3D model has basically been completed. This
occurs when all equipment, piping, valves, instruments, electrical, structural and other items
have been modeled in 3D environment. In this review, the items to be reviewed will include
such things as the location and orientation of valve hand wheels for operability, the location
of local instruments for maintainability.
Agreement on the location of all these critical items should precede the start of piping
isometrics EXTRACTION or the preparation of instrument location plan drawings, if
required.
Below is the piping check point which shall be reviewed prior to 90% 3D model review:
PROJECT NAME : CLIENT :
2 Inter discipline model review is conducted and comments of the same are incorporated.
7 All Steel Structures are completed and checked with respect to IFC drawings
8 All Buildings are completed and checked with respect to IFC drawings
9 All Foundations are completed and checked with respect to IFC drawings
10 All Online, Off-line and equipment mounted Instruments are completed and checked with respect to
approved vendor drawings.
11 All Telecom items including CCTV’s, PAGA speakers are shown and checked
17 All Utility Stations are identified, located and checked for the maximum length of hose with proper
access.
18 All Safety showers and eye baths are identified, located and checked with proper access.
19 Location of mobile and portable /manual firefighting equipment are shown and checked.
20 All Sample connections are identified and modeled and checked for proper access.
21 The minor access platforms, if any are located and checked for proper access.
22 The offline instruments including analyzer enclosures/panels etc. are modeled at proper locations
and checked.
23 The fire and gas detectors are shown and location of each is checked by HSE for function and by
piping for obstruction.
24 The cable routing inside the building is complete and checked so that it is not obstructing any
movement of crane or walkways.
25 All the instrument stands and supports are checked so that they are not obstructing the walkways
on the platforms especially in case of platforms located on vertical vessels and columns.
26 Location of junction boxes is checked so that they are not obstructing the walkways.
27 Junction boxes/fire boxes are modeled with volume for door opening and does not enter into the
hard standing/access areas located for crane/walkways, etc.
28 Cable conduits are checked so that they are not coming out in the middle of the road/ walkways.
29 Ensure that arrangement of small bore piping has been done in such a way that the pipe support is
provided to prevent the breakage due to vibration.
31 Ensure that cooling water lines branch off from the header from top.
32 Ensure that there are no valves installed with the stem pointing below the horizontal plane in
downward direction.
33 Ensure that the vents from an analyzer house/cabinet are located and routed to atmosphere at safe
height from grade.
34 The vents of seal chambers of reciprocating compressors are properly routed and supported.
35 Unloading and storage of chemicals and additives is reviewed for any environmental impact.
36 Vendor trim piping around equipment is put in the model and checked.
38 Check that the Siren/safety alarm system is installed at top of highest building and at the centre of
plant area.
39 The proper lighting poles and fixtures etc. are shown and checked.
40 The safety equipment like wind socks, breathing apparatus are strategically located as per escape
and safety equipment layout.
41 The routing of branch cable trays to the instrument and support for the same is properly shown and
checked.
42 The parking area, traffic barriers, boulders, etc. as applicable is modeled and checked.
43 Steam tracing manifolds and steam jacketing details are shown in model and checked.
44 All design change notices (DCNs) are taken care with respect to completeness.
Instructions for filling the check list for 90% model review:
1. This list is not intended for use in milestone reviews, it is for ensuring that the model is
ready for the mile stone review and therefore it is required to be completed and signed
before proceeding for milestone review.
2. Many check points in the check list do not specify the criteria or basis for checking. The
points are listed with the intention to cover the full scope of model and that there are no
miss-outs before proceeding for mile stone review. Separate check prints of points need to
be maintained by Area Designers, Lead Designers and Area engineers to support the
readiness of the model review.
3. This check list is to be prepared by piping Lead Designer for each area or WBS
separately.
4. Though this check list is prepared by piping Lead Designer and checked by piping Area
Engineer, it requires input from many disciplines. In such cases the piping lead designer
has to obtain the confirmation from the designer of the respective discipline.
5. The Model Manager is the approver for the list.
6. The signed copy is to be preserved for record.
Checklist for Piping Isometrics: P&ID, Layout,
Drafting Related
ere is a checklist for Piping Isometrics
Sr.
Check Points
No.
P&ID RELATED
1 Following items are checked with the P&ID (IFD or later issue):
b) Tag nos. of equipment, instruments, special items, actuated and manual valves (if applicable).
h) Sequence of branch connections (as agreed with Process in case of any changes).
i) Piping spec break, if any (preferably be at flange joints/valves, each iso to contain only one spec).
n) Specific requirements mentioned in applicable P&ID notes (if any) are complied
LAYOUT RELATED
2 High point vents and low point drains are provided, as per project requirements, for lines that will be
hydro-tested.
3 Drains are provided wherever liquid stagnation can occur in the lines e.g. downstream of a check valve.
4 Adequate pipe spool lengths are provided for wafer type butterfly and check valves to prevent the
interference of the valve disc with adjacent piping items.
5 The platform/grade/building wall/dyke or bund wall/floor penetrations and limits of road crossings are
properly shown wherever applicable.
6 The insulation limits are specified appropriately (esp. for personal protection)
7 The electrical tracing requirement and its limits are specified appropriately.
8 The wrapping and coating requirement and its limits are specified appropriately for u/g lines.
9 Minimum distance between welds is 50mm or five times the wall thickness whichever is greater, unless
otherwise indicated in Project specifications.
10 Unions are provided in galvanized piping where threaded in-line items need to be removed for
maintenance. Also, unions are provided at regular intervals (e.g. 24m) in straight pipe runs.
11 Full couplings are provided where applicable for small bore piping.
12 For piping below 2”, WN flanges are not directly welded to SW fittings. Also, PE pipes are not directly
welded with swaged reducers (couplings are used in between).
13 Appropriate break-up flanges are provided in piping with internal lining and hot-dip galvanized piping
(based on tub size). Spool configuration is made with one elbow or one tee only to ensure proper
galvanizing.
14 Lifting lugs are provided for removable spools wherever required as per project requirements.
15 There is adequate clearance between pipe support and the adjacent piping component (e.g. flange,
drain valve) to allow for flange bolt removal, valve operation, etc.
16 The valve stem orientation angle is indicated wherever the stem is not in the vertical and horizontal
planes.
17 The piping interfaces with equipment/package nozzles/terminal points are checked (w.r.t. size, rating,
flange face type and nozzle/TP nos.).
18 The straight length requirement for suction & discharge piping for compressors and certain pumps is as
required by Vendor/project specs.
19 Straight lengths and branch configuration of upstream/downstream lines for anti-surge valves is as per
Compressor Vendor’s recommendation.
20 The F/F dimensions of all valves, special items and in-line instrument items are as per approved vendor
drawings.
21 The instrument connections are checked with Piping-Instrument interface drawings/Instrument hook-up
drawings.
22 The rotameters are installed in vertical run with flow in upward direction.
23 The orifice tapping orientation is done considering liquid or gas flow as applicable and the BOM is as
per the piping-instrument interface diagram.
24 The straight length requirement (u/s & d/s) has been provided for flow meters (e.g. flow orifices, flow
nozzles, venture meters) and is as per Project standards/Vendor requirements.
25 The line configuration for lines containing magnetic flowmeters or vortex type flowmeters is such that
they are always flooded.
26 Line configuration allows easy removal of spectacle blinds/spacers & blinds and valves in case of RTJ
flange joints.
27 Flanged spools are provided in the case of conical strainers to enable removal.
28 Orientation of valve handwheel / lever is checked in model for proper access and commented
accordingly
29 Line routing is visually checked in model for general requirement like access to in line items,
supporting, clearances, obstructions, consistency and aesthetic requirement, etc.
30 Branches like drains, drip legs, etc. are located with sufficient clearance from the supports, steel or
other obstructions so that they do not clash during expansion/contraction.
31 Drip leg size and dimension is checked with Standard drawing for steam lines.
DRAFTING RELATED
33 The drawing border conforms to the Project specifications or Company standards, as applicable.
34 The isometric numbering is as per the approved project format and the line number matches with
isometric number.
36 Pipe class printed at the bottom of the drawing matches with that in the line number.
37 Line data (e.g. process parameters, P&ID no., PWHT & testing requirements, insulation & painting
specs, etc.) match with the Line List, if given in the isometric
38 Applicable reference documents (e.g. Line List, Isometric Index, Pipe Supports Spec, etc.) are
mentioned.
40 The “Cont. on …” description correctly appears at each end of the line isometric which is continued in
another sheet.
41 The isometric print is readable (if required, the isometric should be split into more sheets).
42 Isometric number change is made preferably at a flange joint/valve (not at a weld joint).
43 Dimensions and elevations are adequately given. At least one elevation is mentioned and WP
elevations for sloped lines are marked.
44 There are no HOLDs in the isometric (issue of any isometrics with HOLD requires approval by
HOD/PEM).
Notes:
The following documents are to be used for checking isometrics:
1. Issued For Design (or later issue) P&IDs and Line Lists (and any Process DCNs issued
thereafter)
2. Approved Vendor drawings review of equipment & package mechanical drawings
3. Issued For Design Instrument-Piping Interface drawings
4. Approved vendor drawings of in-line instrument items including control
valves, Pressure safety relief valve, motor operated valves and emergency shutdown
valves
5. Approved vendor drawings for manual valves and SP items.
6. Approved Pipe Support specification and Piping Material specification
7. Issued For Construction Civil and Structural drawings wherever applicable
In case approved drawings are not available at the time of isometrics issue, it should be
brought to the notice of the Lead engineer and the isometrics shall not be issued.
Checklist for Nozzle Orientation
Further to my post related to requirements for preparation and issue of nozzle orientation, here is
a checklist for the nozzle orientation.
SL DESCRIPTION
NO.
Check Points
1 Vessel modelling is completed and nozzle orientation is extracted from model & checked
against latest vendor drawing.
2 30% Model review is completed and review tag related to subject vessel are closed.
3 Plant “North” is indicated. Nozzle orientation angle shall be w.r.t. north as ‘0’ degree(clock
wise).
4 Any P&ID notes regarding particular nozzle location/ elevation/ orientation are taken into
consideration.
5 All nozzles are shown as per P&ID and are designated with nozzle tag number, size and
rating. Any mismatches are commented and resolved.
6 All nozzles are shown as per Mechanical Data Sheet(MDS) and are designated with nozzle
number, size and rating. Any mismatches are commented and resolved.
7 All level instrument nozzles are shown as per Level Sketches. Any mismatches are
commented and resolved.
8 Vessel dimensions OD (or ID & thk) and height/ length are shown.
9 Holds & notes are clearly listed & identified with cloud.
10 All reference drawings (P&ID / MDS / Level Sketches / Vendor GA) including revision number
are listed in reference drawing section .
11 Nozzles projected above platforms have minimum clearance of 150 mm between bottom of
flange and top of grating.
12 Inlet and outlet nozzles shall be located sufficiently away to avoid vortex flow.
13 All nozzle projections are shown with respect to TAN line for all dish end nozzles.
14 All nozzle projections (exclusive of dish end nozzles) are shown with respect to vessel centre
line for all shell nozzles.
17 Proper access and approach ladder is provided for all Nozzles/ Instruments as per project
specification and all Platform dimensions, location & ladder location are shown.
18 Side entry from ladder has been provided to the top and intermediate platforms.
19 All valves are accessible from ladder for size less than or equal to 3” and from platform for
sizes greater than 3” unless otherwise specified in relevant project specifications/ client
operation and maintenance requirements.
20 Maximum height of ladder, without mid landing is checked with respect to project
specifications.
22 For Instrument nozzles that require access, check the possibility of combining the nozzles for
common access and also check for any obstruction in the surrounding.
24 Nozzle schedule table (showing sl.no, nozzle name, rating, size, nozzle function, nozzle
projection from vessel center line etc.) shall be shown.
25 Manhole location shall be shown. Manhole cover can be opened without any hindrance.
Manhole davit orientation is marked and manhole envelope angle are shown. Sideways
location is preferred manhole location.
26 Manhole height from platform shall be as per project specifications/ client requirements.
28 Minimum 750 mm clear space is available on all vessel Platforms for ease of access even after
installing all Stand pipe, valves, Instruments.
Horizontal Vessel
1 One plan view with minimum two elevation views (front view & side view) are shown, if nozzles
are on both Dish end, Both views are required, The views are clearly marked with A-A, B-B
etc.
4 Proper access, clearances are provided for bottom nozzles, boot mounted nozzles and
nozzles are clash free with equipment support.
Vertical Vessel
1 One elevation view and multiple plan views at every platform elevation are shown.
3 Based on Drop zone area, Pipe davit radius is marked. Pipe davit orientation is shown in the
plan view of the top platform. Drop zone area to be accessible from common access.
4 Platform width, start angle and end angle are shown clearly.
6 When there are two platforms one above the other(typically in columns etc.), ensure adequate
headroom is available and space is not obstructed due to structural bracings.
Pig Launcher
1 Kicker line connection shall be shown on side/ top of major barrel near to end closure.
2 Balance line connection shall be shown on side/ top of minor barrel near to pig trap valve
location.
10 Drain shall be shown on bottom of major barrel near to reducer and also on bottom of minor
barrel near to pig trap valve.
Pig Receiver
1 Kicker line connection shall be shown on side/ top of major barrel near to reducer.
2 Balance line connection shall be shown on side/ top of minor barrel near to reducer.
3 Vent connection shall be shown on top of major barrel near to end closure and also on top of
minor barrel near to pig trap valve.
4 Pig signaler shall be located on top of minor barrel after near to pig trap valve.
8 Pressure indicator connections shall be shown on the top of major barrel near to end closure
and also on minor barrel near to pig trap valve location.
9 Lifting lug(two nos.) location shall be shown either on major barrel or on major and minor barrel
depending upon the total length of pig receiver.
10 Drain shall be shown on bottom of major barrel near to end closure and also on bottom of
minor barrel near to pig trap valve.
Checklist for Nozzle Orientation
Further to my post related to requirements for preparation and issue of nozzle orientation,
here is a checklist for the nozzle orientation.
SL DESCRIPTION
NO.
Check Points
1 Vessel modelling is completed and nozzle orientation is extracted from model & checked against
latest vendor drawing.
2 30% Model review is completed and review tag related to subject vessel are closed.
3 Plant “North” is indicated. Nozzle orientation angle shall be w.r.t. north as ‘0’ degree(clock wise).
4 Any P&ID notes regarding particular nozzle location/ elevation/ orientation are taken into
consideration.
5 All nozzles are shown as per P&ID and are designated with nozzle tag number, size and rating.
Any mismatches are commented and resolved.
6 All nozzles are shown as per Mechanical Data Sheet(MDS) and are designated with nozzle
number, size and rating. Any mismatches are commented and resolved.
7 All level instrument nozzles are shown as per Level Sketches. Any mismatches are commented
and resolved.
8 Vessel dimensions OD (or ID & thk) and height/ length are shown.
9 Holds & notes are clearly listed & identified with cloud.
10 All reference drawings (P&ID / MDS / Level Sketches / Vendor GA) including revision number are
listed in reference drawing section .
11 Nozzles projected above platforms have minimum clearance of 150 mm between bottom of flange
and top of grating.
12 Inlet and outlet nozzles shall be located sufficiently away to avoid vortex flow.
13 All nozzle projections are shown with respect to TAN line for all dish end nozzles.
14 All nozzle projections (exclusive of dish end nozzles) are shown with respect to vessel centre line
for all shell nozzles.
17 Proper access and approach ladder is provided for all Nozzles/ Instruments as per project
specification and all Platform dimensions, location & ladder location are shown.
18 Side entry from ladder has been provided to the top and intermediate platforms.
19 All valves are accessible from ladder for size less than or equal to 3” and from platform for sizes
greater than 3” unless otherwise specified in relevant project specifications/ client operation and
maintenance requirements.
20 Maximum height of ladder, without mid landing is checked with respect to project specifications.
22 For Instrument nozzles that require access, check the possibility of combining the nozzles for
common access and also check for any obstruction in the surrounding.
24 Nozzle schedule table (showing sl.no, nozzle name, rating, size, nozzle function, nozzle
projection from vessel center line etc.) shall be shown.
25 Manhole location shall be shown. Manhole cover can be opened without any hindrance. Manhole
davit orientation is marked and manhole envelope angle are shown. Sideways location is
preferred manhole location.
26 Manhole height from platform shall be as per project specifications/ client requirements.
28 Minimum 750 mm clear space is available on all vessel Platforms for ease of access even after
installing all Stand pipe, valves, Instruments.
Horizontal Vessel
1 One plan view with minimum two elevation views (front view & side view) are shown, if nozzles
are on both Dish end, Both views are required, The views are clearly marked with A-A, B-B etc.
4 Proper access, clearances are provided for bottom nozzles, boot mounted nozzles and nozzles
are clash free with equipment support.
Vertical Vessel
1 One elevation view and multiple plan views at every platform elevation are shown.
3 Based on Drop zone area, Pipe davit radius is marked. Pipe davit orientation is shown in the plan
view of the top platform. Drop zone area to be accessible from common access.
4 Platform width, start angle and end angle are shown clearly.
6 When there are two platforms one above the other(typically in columns etc.), ensure adequate
headroom is available and space is not obstructed due to structural bracings.
Pig Launcher
1 Kicker line connection shall be shown on side/ top of major barrel near to end closure.
2 Balance line connection shall be shown on side/ top of minor barrel near to pig trap valve location.
8 Pressure indicator connections shall be shown on the top of major barrel near to end closure and
also on minor barrel near to pig trap valve location.
10 Drain shall be shown on bottom of major barrel near to reducer and also on bottom of minor
barrel near to pig trap valve.
Pig Receiver
1 Kicker line connection shall be shown on side/ top of major barrel near to reducer.
2 Balance line connection shall be shown on side/ top of minor barrel near to reducer.
3 Vent connection shall be shown on top of major barrel near to end closure and also on top of
minor barrel near to pig trap valve.
4 Pig signaler shall be located on top of minor barrel after near to pig trap valve.
8 Pressure indicator connections shall be shown on the top of major barrel near to end closure and
also on minor barrel near to pig trap valve location.
9 Lifting lug(two nos.) location shall be shown either on major barrel or on major and minor barrel
depending upon the total length of pig receiver.
10 Drain shall be shown on bottom of major barrel near to end closure and also on bottom of minor
barrel near to pig trap valve.
Check List for Overall Piping Plot Plan
Project Name: Job No.:
Client:
Notes: 1. As a minimum, the checklist shall be completed for the IFA and IFC issues of the Unit plot plans.
DESIGN
1 Complete facility with future scope (if any) as per the Project scope is
covered in Drawing.
2 Plant North, True North, wind direction & wind rose (if applicable) are
shown. Angle between Plant and True North isshown.
3 Datum point for plant (relative) co-ordinate system is defined and is located
in the S-W corner of the plot (unless a different location is specified in
theProject documents).
5 The true geographical co-ordinates (UTM) of the datum point are indicated
either at the datum point or in thenotes.
8 Grade levels for all indicated areas are given and are checked with the Civil
grading plan.
9 Relation of plant grade levels with reference (datum) level (e.g. mean sea
level) is indicated.
12 Separate gates are provided for personnel, trailer tanker & vehicle
movement, if applicable.
13 Separate fencingis provided for restricted areas, e.g. flare stack, pig
launcher/receiver, metering station, etc., ifapplicable.
15 Main roads and secondary roads are located with centre line and
coordinates/locating dimensions. Road and shoulder widths are checked
as per projectrequirements.
17 Adequate access roads are provided around process units and tank farms.
18 All units/areas are indicated by the respective area code, name or tag, e.g.
UTA, Utility Area, Unit-109, etc.
22 Sterile zone radius is shown for flare stack and no other equipment is
located within this zone.
25 Major storm water drain trenches and major UG corridors (for UG piping,
pipelines, cable trenches, etc.) are shown, asapplicable.
26 Equipment list is given in the drawing (unless otherwise decided for the
Project). The list includes at least the major equipment and the same
equipmenttag nos. are indicated in the drawing.
27 Equipment and vendor package outlines are shown and their tag nos. are
checked with the project EquipmentList/PFDs/P&IDs.
DRAFTING
34 Drawing title, drawing number and revision number in the title block are as
per the TDR.
37 Drawing scale is stated in the title block and graphic scale (bar scale) is
shown.
39 All general notes are checked and the units for dimensions, coordinates &
levels are given in the notes.
43 Revision clouds, along with revision number triangles are marked properly,
if applicable.
44 “Hold” clouds, if applicable, are properly marked and the list of “Holds” is
indicated.
Name:
Designation:
Revision number:
Date:
Check List for Piping Layouts
roject Name: Job No.:
Client:
Notes:
1. This checklist is intended for checking of layout drawings extracted from 3D CAD models.
2. As a minimum, the checklist shall be completed for the first issue of the layout drawing.
3. Items like Fire and Gas detectors and other E, I & T items (e.g. JBs, switch boards, lighting fittings, etc.)
need not be shown in Piping Layouts.
DESIGN
2 Grade and paving levels and paving extents are shown. (Dimensions of
paving not required.)
5 All equipment nozzles and vendor package terminal points are clearly
identified and tagged.
6 All tie-in points and battery limits are clearly identified and tagged and
coordinates/elevations are indicated.
7 All lines are identified by line numbers and major locating dimensions &
elevation are given.
8 Flow directions and slope symbols are indicated as per the P&IDs.
9 All secondary pipe supports (standard & special) are indicated and tagged
and the locating dimensions marked.
10 All primary pipe supports are identified by appropriate symbols (e.g. guide,
axial stop, etc.).
13 Structural grid numbers of pipe racks, buildings and shelters are shown.
DRAFTING
19 Drawing title, drawing number and revision number in the title block are as
per the TDR.
22 Drawing scale is stated in the title block and graphic scale (bar scale) is
shown.
24 All general notes are checked and the units for dimensions, coordinates &
levels are given in the notes.
26 Reference drawing numbers and titles are listed and checked. List shall
include unit plot plan and piping key plan as a minimum.
28 Revision clouds, along with revision number triangles are marked properly,
if applicable.
29 “Hold” clouds, if applicable, are properly marked and the list of “Holds” is
indicated.
30 Key plan is shown and the applicable area/unit of the plot plan is
highlighted.
31 Match line co-ordinates and drawing limits are clearly marked and are
consistent with the Key Plan drawing. Continuation drawing numbers are
correctly written.
Name:
Designation:
Revision number:
Date:
Check List for Piping Unit Plot Plan
Project Name: Job No.:
Client:
Notes: 1. As a minimum, the checklist shall be completed for the IFA and IFC issues of the Unit plot plans.
DESIGN
3 Extents of paving areas are shown with curbing and drain sump, as
applicable (dimensions not required).
4 Unit/area code, name or tag (e.g. UTA, Utility Area, Unit-109, etc.) is
indicated.
5 Main roads and secondary roads are located with centre line and
coordinates/locating dimensions.
7 Road crossings, e.g. culverts, casing pipe, duct banks are shown wherever
applicable.
11 Hard stand areas for heavy equipment is properly marked and located (if
applicable).
12 Equipment list is given in the drawing and equipment tags marked in the
plot match with the list.
13 Equipment/packages and their tag nos. are checked with the Project
Equipment List/P&IDs.
17 Multiple equipment having tag nos. with suffixes like A/B/C (e.g. multi-bay
air-coolers, pumps, etc.) are clearly identified and tagged as per Project
Equipment List/P&IDs.
19 Piperacks are shown with the module breaks and tag nos. (as per Civil
drawings) and the locating coordinates, column to column dimensions and
widths are indicated.
20 Pipe rack TOS elevations are clearly marked, esp. in case of multi-tier
racks. Sectional details are provided wherever required and space
requirement for cable trays is marked.
32 Underground facilities (e.g. buried vessels, u/g storage pits, etc.) are
shown. Items like valve pits, OWS manholes, etc. are shown in model
extracteddrawings (dimensions/coordinates are not required).
34 HSE requirements (if any) for staircase/escape route for tech. structure and
pipe rack platforms are checked.
35 Sterile zone radius is shown for flare stack and no other equipment is
located within the sterile zone.
38 Dyke walls are shown around tanks (wherever applicable) with dimensions
and heights.
DRAFTING
42 Drawing title, drawing number and revision number in the title block are as
per the TDR.
44 Revision block contains initials of the originator, checker and approver (both
Discipline & Project).
45 Drawing scale is stated in the title block and graphic scale (bar scale) is
shown.
46 The drawing scale conforms to the Project specifications or Company
standards, as applicable.
47 All general notes are checked and the units for dimensions, coordinates &
levels are given in the notes.
49 Reference drawing numbers and titles are listed and checked. List shall
include overall plot plan and key plot plan as aminimum.
51 Revision clouds, along with revision number triangles are marked properly,
if applicable.
52 “Hold” clouds, if applicable, are properly marked and the list of “Holds” is
indicated.
53 Key plan is shown and the applicable area/unit of the plot plan is
highlighted.
55 Match line co-ordinates and drawing limits are clearly marked and are
consistent with the Key Plan drawing. Continuation drawing numbers are
correctlywritten.
Name:
Designation:
Revision number:
Date:
Check List for Piping Material Take-Off (MTO)
Check List for Piping Material Take-Off (MTO)
Notes:1. This check list is applicable exclusively for Detail design engineering.
2. Some of the check points listed here are specific to manual MTO, when MTO extracted from model, ensure
these are taken care in model.
3. Hydrotest vent/drain MTO shall be identified w.r.t appropriate line number.
4. Make sure all revision changes in P&IDs are captured by cloud clearly.
I General
1.01 Team for MTO has read and working as per guidelines
provided Guide – Piping Material Take-off.
1.03 Notes in the P&Ids including legends are fully read and
accounted for in the MTO as applicable.
1.24 MTO for equipment trims are taken. Ensure that line
number given for trim lines based on equipment tag
number and relevant piping specification.
1.27 MTO for safety Equipments piping like fire hydrant, fire
monitor, safety shower, eye wash, etc. is considered.
1.28 MTO for fire water rings, foam and deluge piping is
considered.
1.31 MTO is taken for deck drain funnel piping (open drain)
network.
1.46 For Hub end valves , mating hub, hub clamp with
fasteners & Seal ring are considered in MTO.
1.47 Insulating gaskets kit are taken at dissimilar metal
flanged joints as required by specifications and P&IDs.
1.56 Number of hydro test vent & drain & MTO are
considered based on the sketches prepared for MTO
and identified separately. For below 2″ pipe sizes with
CS/SS materials, ensure that 10 % of line count is
considered for hydrotest test vent & drain (i.e. 5%
each) in MTO/material cost If sketches are not
prepared.
1.60 Extra bolt lengths for flange connection with wafer type
valves, PSVs, insulating gaskets, restriction orifice,
spectacle blind, conical strainer etc. are considered.
2 Tie-in MTO
2.01 Tie-in materials are considered and separated from
new line MTO. Additional temporary materials like
blind flange, gasket, bolt, etc. are considered as
applicable.
3.06 MTO for the lines not modelled or captured as per line
list/highlighted P&IDs is manually added into the MTO.
Name:
Designation:
Revision number:
Date:
Definition of Percentage Completion
The following description is a definition of each percentage complete stage of the piping 3D
model. Company practice normal practice is to make 3D model reviews at 30, 60, 90 and 100%
completion.
Definitions
BASIC
30% Completion
60% Completion
90% Completion
100% Completion
Client’s final comments from 90% 3D model review incorporated
3D model updated to latest issue of PEFS’s, PEUFS’s, line tables, arrangement drawings and
final equipment drawings
All sprinkler mainheaders shown