EPC Project Management PDF
EPC Project Management PDF
Eni
Design Basis, Key Deliverables & Battery Limits: how to approach a Front End
Engineering Design
Balance between engineering freezing and early procurement: Long Lead Items
strategy
Fast Track: Basic, FEED & Detail Design phases in overlap aiming at Project goals
Conclusions
2 eniprogetti
Eni
3 eniprogetti
Design Basis, Key Deliverables & Battery Limits: how to approach a Front End
Engineering Design
4 eniprogetti
Oil and Gas Project Development Phases
Project expenditure
Capital Risk
Difficulty to implement
changes
Personnel involved
Stakeholders’ e pectatio s
Time
5 eniprogetti
Project Development Phases Key Activities -> Key Deliverables (es. for process
and piping and layout engineering)
Support to Construction
and commissioning Red-marked and as-built
Feasibility
Preparation of process specifications, design criteria, for all Process Flow Diagrams
processes , utilities and transportation systems. Preliminary Battery Limits Table
engineering, safety and constructability. Preliminary P&I Ds
Equipment Data Sheets Design Criteria
Preliminary Plot Plan
Identification and analysis of the main process and Technology selection report
utilities for each generated concept alternative Preliminary Heat & Material balance
6 Block Flow Diagram
Preliminary Site Plan
eniprogetti
How Design Basis, Key Delivery and B.L. can affect a Project
What if…
… Desig Bases are not finalized
Example: the pressure of the Sea Water Make-up (rely upon information) was significantly different from the reality.
Technical resolution: lower the pumps with an additional basin (groundwater level very high).
Impact: additional costs and delay in schedule
7
Note: Lesson Learnt not related with ENI projects
eniprogetti
Why Basic-FEED is the most important part of a Project?
value
$ BOQ &
Construction
strategy
Material
Selection & Peak
Take-off Construction
Cost
Project Cost
Curvet
Availability of
Peak Information
Material
Cost time
During Basic – FEED project costs can be properly evaluated by finalization of material
8 selectio a d MTOs, owi g to that this phase is the ost i porta t for the go/ o go eniprogetti
final assessment
Design approach – Key points
The Basic - FEED engineering shall be tailor fit to allow the correct definition of
the i vest e t cost a d to support the go / o go decisio gate 3 (key
deliverables fit for purpose to the activities and not vice-versa);
In Basic – FEED phase, the key deliverables allow to fix the material selection
and estimate material take-offs which are the input for the procurement and
construction strategy based on the project drivers;
9 eniprogetti
Balance between engineering freezing and early procurement: Long Lead
Items strategy
10 eniprogetti
Long Lead Items definitions
11 eniprogetti
Critical Path
The critical path is the sequence of activities that represents the longest path through a project, which
determines the shortest possible project duration [PMBOK 6.6.2.2 Critical Path Method]
Appling Critical Path method for all the systems of a project, even material with a rather short
delivery can result to be critical, owing to that we can split LLI in two categories:
EARLY PROCUREMENT
TIE-INS EARLY COMMISSIONING
Shut- Shut-
UNIT 10 down Production down
UNIT 20 Plant to be disinvested Dismantling
Dismantelling
Dismantelling
Shut-
UNIT 30 down Production
FEED TIE-INS
Detail Design &
TIE-INS INSTAL. Commissioning
INSTAL. Procurement Dismantling
Feasibility Study TIE-INS Shut- Construction
down
Tie-ins shall be planed in an early stage of the project, with a dedicated engineering,
13 construction and commissioning team. The project schedule incorporates the production eniprogetti
plan in terms of turn-around or critical milestones.
Bulk Material for Early Commissioning System
During the engineering phase it is important to verify that the delivery of bulk material
14 fits the Mechanical Completion dates (additional specific MTOs can be envisaged). eniprogetti
Long Lead Items strategy – Key points
The critical path developed for all the project systems allows us to recognize
critical delivery items which do not have the longest delivery such as tie-ins or
bulk material for early commissioning system, which shall be focused since the
start of the project with a dedicated integrated team (engineering,
construction and commissioning);
For a revamping project, the integration of the production plan in the project
baseline allows to execute tie-ins during turn-around, minimizing the number
of shut-downs and avoiding unnecessary loss of production;
15 eniprogetti
Fast Track: Basic, FEED & Detail Design phases in overlap aiming at Project
goals
Tom Peters
16 eniprogetti
Project objectives and Fast-Track Projects
FEED
17 eniprogetti
Possible outcomes when implementing a Fast-Track in a project
Not linear
Relying approach in
upon preliminary Design based
decision making
information on assumptions
Overdesign Increased
material interface
management
Higher
Increased Risk
possibility of Which it the greatest
inconsistencies
objective?
18 eniprogetti
How to mitigate risks in fast-track projects
Re-cycling
Design
Feasibility Study inputs/outputs
FEED
Detail Design & D
Procurement
Final alignment
ENGINEERING MATERIAL
Final alignment mitigates risk When procurement cycle
of further phases for critical is long, procurement can
aspects be start with preliminary
data, updating more
consolidated information
during the vendor
ENGINEERING MATERIAL alignment before PO
TEAM
Preliminary information Material check/re-rated
If the approach is aligned
evaluated from Basic (used is re-consolidated both in
since the beginning with a
for detail design) are Basic and Detail Design
common goal, all the team
always re-checked when to avoid reworks during
is aimed to support
more information are construction and
unavoidable project changes
available commissioning
and reworks activities
19 eniprogetti
Case Study
Feasibility Study
FEED
Detail Design & D
Procurement
Project Organization
Engineering Approach: Re-cycling Design
1. Process and Layout for critical circuit
2. 3D Model Review 30% and 60%
3. Material Selection
4. Vendor design
5. Design Philosophy – Operating manual
20 eniprogetti
Case Study Organization Chart
OWNER
FEAS.
PRE-
FEASIBILI
LICENSOR
TY FEASIBIL. CNT
BASIC -
BASIC –FEED
FAST-TRACK
FEED
CONTRACTOR
DETAIL ENG.
CONTRACTOR
DETAILED
ENG.
CONSTRUCTION CONSTRUCTION
CONSTRUCTION
CONTRACTOR CONTRACTOR
2) PROCESS SCENARIOS
(DESIGN CASES AND
TRANSIENTS)
PUMP
FV s Valves Flow PSVs Valves Flow
DISCHARGE
Case
File by FVA FVB FVC PSVA PSVB PSVC
A B C IN OUT IN OUT IN OUT IN OUT IN OUT IN OUT
EST9 4 SA 1 351 351 351 351 351 351 351 351 351 351 351 351 351 351 351
EST9
EST9
4
4
SA
SA
2
3
380 380 380 380 380 380 380 380 380 380 380 380 380 380
5 5 5 5 5 5 5 5 5 5 5 5 5 5
380
5
3) STRESS
EST9 4 SA 4 351 351 250 351 351 351 351 250 250 351 351 351 351 250 250
EST9
EST9
4
4
SA
SA
5
6
250 351 351 250 250 351 351 351 351 250 250 351 351 351
351 250 351 351 351 250 250 351 351 351 351 250 250 351
351
351
CRITERIA
EST9 4 SA 7 351 351 351 351 351 351 351 351 351 250 250 250 250 250 250
CEER 4 CEER 1
x x x x x x x x x
351 351 250 351 351 351 351 250 250 250 250 250 250 250
x x x x x x
250
WITH
4
CEER
CEER 4
4
CEER
CEER
2
3
351 250 351 351 351 250 250 351 351 250 250 250 250 250
250 351 351 250 250 351 351 351 351 250 250 250 250 250
250
250 PRELIMINARY
1) PRELIMINARY CEER
CEER
CEER
4
4
CEER
CEER
CEER
4
5
6
351 351 250 351 351 351 351 250 250 351 351 351 351 250
351 250 351 351 351 250 250 351 351 351 351 250 250 351
250 351 351 250 250 351 351 351 351 250 250 351 351 351
250
351
351 CRITICAL
CEER 4 CEER 7 351 351 351 351 351 351 351 351 351 351 351 351 351 351 351
CEER
4
4
CEER
CEER
temperature , piping not anchored to the pumps.
5) STRESS
CALCULATION
22 eniprogetti
#2: 3D Model Review 30% AND 60%
23 eniprogetti
#3: Material Selection (Piping)
Vendor
Material requisition
Follow-up &
Purchase Order
Material Requirements
24 eniprogetti
#4: Vendor design
Process DataSheet
Material Requisition
Mechanical and
Material Check
Vendor
Follow-up
25 eniprogetti
#5: Design Philosophy – Operating manual
Updated Control
Philosophy
26 eniprogetti
Fast Track – Key points
The Fast Track with parallelization of phases which traditionally are developed
sequentially is a possible strategy to meet Project Objectives when the
schedule is challenging;
To mitigate the risk associated to fast track (more interfaces, reworks,
designing by conservative assumptions rather that consolidated data etc.)
project team needs to be integrated with an interface management plan and
dedicated engineering methods such as re-cycling and final alignment need to
be set-up in the engineering execution plan.
27 eniprogetti
Conclusions - Key Factors for Basic-FEED Projects
28 eniprogetti