1.5 Guidelines For Preparing Inspections & Test Plans (Itp) Agrarian Reform Communities Project
1.5 Guidelines For Preparing Inspections & Test Plans (Itp) Agrarian Reform Communities Project
1.0 OBJECTIVE
The purpose of this Work Instruction is to describe the method to be used by all LGUs
for preparing an Inspection and Test Plan. It also describes the approval process.
2.0 SCOPE
This Work Instruction applies to all LGUs and to all sub-projects undertaken during the
construction of sub-projects implemented under the ARCP.
3.0 DEFINITIONS
The document that list inspections and tests to be carried out for a specific trade, work
section or operation. It identifies points in the manufacturing, installation and construction
process at which tests and inspections occur.
A ‘hold’ point is mandatory. It defines a point beyond which work may not proceed without
the inspection or test being verified by another party. This ‘other party’ might be ARCWG
and DARPO, it could also be a representative of a government agency.
A ‘witness’ point provides another party with the opportunity to verify the inspection or test,
at their option. Notification to DARPO representative is required.
Surveillance (S)
Where the LGU performing the work verifies its own quality often with the aid of checklists,
the output for this inspection is an inspection record.
Work Area
A single section of the total work usually defined by location, which for any trade or activity
will be completed before moving onto another area. Example: a room, a building, a length of
pipeline between manholes, etc.
The LGU is responsible for ensuring that all required Inspection and Test Plans are
prepared.
3.1 The Plans for their own work, in the final analysis the LGU are responsible.
3.2 The LGU LPO Head is made responsible for preparing an d submitting Inspection
and Test Plans prior to approval and final acceptance by the DARPO and CPMO
1.5 GUIDELINES FOR PREPARING INSPECTIONS & TEST PLANS (ITP)
Agrarian Reform Communities Project
.
4.0 RESPONSIBILITIES
5.0 DETAILS
5.1.1 Read the contract documents (including the technical specifications) and prepare
a list of any discrepancies, ambiguities and missing information regarding
materials standards and/or workmanship.
5.1.2 Contact the DARPO/RI Engineer and resolve the issues listed as a result of 5.1.1.
5.1.3 Examine the scope of work and divide it into separate ITP. As a general guide it
is normally convenient to document a separate ITP for each trade or work section.
5.1.4 Review the contract documentation and note the quality requirements. Include
any references to tests, approvals and hold and witness points.
5.1.5 Prepare an ITP reflecting the requirements of the contract documents and using
the notes from 5.1.4.
5.1.8 Approve and issue the draft ITP for acceptance prior to commencing the work
described in each plan. Incorporate any amendments required and issue the final
edition to ARCWG, DARPO and APO/CPMO
5.1.9 Decide how best to divide the works by location and indicate these locations
either on a schedule (with reference to grids and levels) or by marking up
drawings.
5.1.10 Train Project Engineers in the use of the ITP. Formalize a procedure for
notification of appropriate party for Witness and Hold points.
5.1.11 Carry out inspections and tests in accordance with the approved ITP. Where
Hold or Witness points are designated record results on checklists or forms.
5.2.1 Record the following particulars of the contract either on the Inspection and Test
Plans or on a separate cover sheet:
The characteristics to be verified will frequently determine the stage at which the
inspection or test must take place. Such further work might also cover up or deny
access for the purposes of verifying certain characteristics.
Indicate the contractual document number and item that requires the operation or
the inspection or the test. It is a reference for all parties involved.
For many operation, the methods employed will be self-evident and determined
by the characteristics being examined. In other cases, however, the precise
manner in which the operation is carried out may need to be described.
The LGU might have internal procedure for performing certain operation and
tests, the reference number should be indicated in this column.
The stage/frequency (timing, how often) will often be determined by the type of
the inspection and/or test and the characteristics under consideration. The
frequency shall be stated in a unit which is measurable. Such unit may be for
example: per batch, per 1000 m2, once a day, every truck, etc.
1.5 GUIDELINES FOR PREPARING INSPECTIONS & TEST PLANS (ITP)
Agrarian Reform Communities Project
The “Inspection By” section of the ITP indicates the person or organization
responsible for performing the inspection/test and the parties involved.
An H in the DARPO box indicates that the DARPO must be notified in advance
and that the Contractor cannot proceed with the following work until authorized by
the DARPO or his representative.
Hold and Witness points applicable to the DARPO representative are included in
the Specification.
This may be in the form of a special schedule that lists all such required points.
Alternatively, they may be indicated from the wording in the Specification e.g.,
“shall be approved by the DARPO Representative” or “ as directed by the DARPO
Representative” are “hold” points, 24 hours notice of intention must be given
“would be a typical witness point.”
The approval requirements of authorized bodies (Codes and Standards) are hold
points.
It is the LGU’s responsibility to identify the hold and witness points that are
required for the Sub-Contractors and employees who are doing the work. The
LGU should do this to the extent that is necessary to be confident that the work is
being carried out to the standards required by the Specification.
The LGU should note that the DARPO, APO and APO/CPMO will retain the
option to inspect the work at any stage. When preparing the ITP, Surveillance(s)
should therefore be shown in the DARPO and APO/CPMO,s column against all
selected inspection or test points which are not otherwise covered by “HOLD” or
“WITNESS” points.
1.5 GUIDELINES FOR PREPARING INSPECTIONS & TEST PLANS (ITP)
Agrarian Reform Communities Project
5.3.8 Output/Records
Records are essential to quality assurance in that they offer the documented
evidence necessary to provide the confidence that the product or work is in
accordance with the specification.
The records, which will be in various forms, will include the checklists. The
Records column indicates the form or checklist number used to record the
inspection results. Other examples of records include: test certificates, certificate
of compliance, survey data, written approvals.
5.4.1 The LPO Head must review and approve the Inspection and Test Plans prior to
issue for final acceptance by DARPO.
5.4.2 The LGU submits his ITP to the DARPO for review and approval. The ITP must
be approved by Provincial Project Manager, (PARO II).
5.4.3 Once approved, the DARPO issues a copy of the ITP to the LGU, ARCWG,
DARPO and APO/CPMO.
5.4.4 The LGU Project Engineer is responsible for implementation of the ITP.