Rencana Anggaran Biaya: NO Vulome SAT Spesifikasi Harga Satuan Jumlah Harga A. Persiapan Uraian
Rencana Anggaran Biaya: NO Vulome SAT Spesifikasi Harga Satuan Jumlah Harga A. Persiapan Uraian
Rencana Anggaran Biaya: NO Vulome SAT Spesifikasi Harga Satuan Jumlah Harga A. Persiapan Uraian
HARGA
NO URAIAN VULOME SAT SPESIFIKASI JUMLAH HARGA
SATUAN
A. PERSIAPAN
1 Papan Nama Proyek 1.00 Ls By Owner -
2 Pagar Pengaman Proyek 1.00 Ls By Owner
3 Listrik dan Air Kerja 1.00 Ls 8,000,000 8,000,000
4 Pembersihan Lokasi 1.00 Ls 4,000,000 4,000,000
5 Mobilisasi Alat dan Bahan 1.00 Ls 15,000,000 15,000,000
6 Perataan Tanah 1.00 Ls 20,000,000 20,000,000
TOTAL 47,000,000
B PEKERJAAN DUDUKAN CONTEINER
1 Floor Hardener 7.20 m3 With Wiremesh 4,500,000 32,400,000
TOTAL 32,400,000
C PEKERJAAN STRUKTUR CONTEINER KNOCK DOWN LANTAI BAWAH
1 Bottom
- Bottom Side Raill Baja UNP 150.75.6,5 1421.20 kg Setara Gunung Garuda 23,000 32,687,600
- Cross Member CNP 100.50.20.2,3 390.40 kg Setara Gunung Garuda 20,000 7,808,000
- Corner Casting Container 16.00 bh 750,000 12,000,000
- Plat Cross Member 100x50x12 33.91 kg 23,000 779,976
- Baut 16mm 128.00 bh 8,000 1,024,000
2 Side - -
- Corner Raill Baja UNP 150.75.6,5 1047.20 kg Setara Gunung Garuda 23,000 24,085,600
- Corner Post Plat 150x3500x2 98.91 kg 23,000 2,274,930
- Corner Post Plat 200x3500x2 98.91 kg 23,000 2,274,930
- Corner Post Plat 200x6000x2 113.04 kg 23,000 2,599,920
- Corner Post Plat 200x3000x2 113.04 kg 23,000 2,599,920
- Corner Post Plat 200x8000x2 100.48 kg 23,000 2,311,040
- Baut Spandek 210.00 bh 3,000 630,000
2
- Spandek 0,5 Colorbond 161.00 m 120,000 19,320,000
3 Top
- Top Side Raill Baja UNP 150.75.6,5 1421.20 kg Setara Gunung Garuda 23,000 32,687,600
- Baut Spandek 40.00 bh 3,000 120,000
2
- Spandek 0,5 Colorbond 18.00 m 120,000 2,160,000
- Corner Casting Container 16.00 bh 750,000 12,000,000
TOTAL 157,363,516
D PEKERJAAN STRUKTUR CONTEINER KNOCK DOWN LANTAI ATAS
1 Bottom
- Bottom Side Raill Baja UNP 150.75.6,5 411.40 kg Setara Gunung Garuda 23,000 9,462,200
- Cross Member CNP 100.50.20.2,3 97.60 kg Setara Gunung Garuda 20,000 1,952,000
- Corner Casting Container 4.00 bh 750,000 3,000,000
- Plat Cross Member 100x50x12 3.77 kg 23,000 86,664
- Baut 16mm 32.00 bh 8,000 256,000
HARGA
NO URAIAN VULOME SAT SPESIFIKASI JUMLAH HARGA
SATUAN
2 Side - -
- Corner Raill Baja UNP 150.75.6,5 261.80 kg Setara Gunung Garuda 23,000 6,021,400
- Corner Post Plat 150x3500x5 82.43 kg 23,000 1,895,775
- Corner Post Plat 200x3500x5 109.90 kg 23,000 2,527,700
- Corner Post Plat 200x3000x2 37.68 kg 23,000 866,640
- Corner Post Plat 200x8000x2 100.48 kg 23,000 2,311,040
- Baut Spandek 40.00 bh 3,000 120,000
2
- Spandek 0,5 Colorbond 56.00 m 120,000 6,720,000
3 Top
- Top Side Raill Baja UNP 150.75.6,5 411.40 kg Setara Gunung Garuda 23,000 9,462,200
- Baut Spandek 40.00 bh 3,000 120,000
2
- Spandek 0,5 Colorbond 24.00 m 120,000 2,880,000
- Corner Casting Container 4.00 bh 750,000 3,000,000
TOTAL 50,681,619