Data Analysis and Interpretation: CCL Project A
Data Analysis and Interpretation: CCL Project A
CCL Project A: -
Capital expenditure
Expenses/year
Year Production
1st Nil
2nd – 5th 2 Million Tons/year
6th – 17th Equal
18th 3 Million Tons/year
19th 2 Million Tons/year
20th 2 Million Tons/year
Coal Grade Production % Non Power % Power %
G9 50 60 40
G10 50 60 40
G1 0 0
G2 3450 3450
G3 3210 3210
G4 3000 3000
G5 2750 2750
G6 1900 2280
G7 1600 1920
G8 1420 1700
G9 1100 1320
G10 980 1180
G11 810 970
G12 760 910
Capital Present
Year exp S & W Spares Contractor P&F Admin exp Transportation Others TOTAL PV @ 6% value
1 81 8 3 12 12 0 0 10 126 0.94340 118.8679
2 0 8 3 12 12 3.1 10.4 10 58.5 0.89000 52.0648
3 0 8 3 12 12 3.1 10.4 10 58.5 0.83962 49.1177
4 0 8 3 12 12 3.1 10.4 10 58.5 0.79209 46.3375
5 0 8 3 12 12 3.1 10.4 10 58.5 0.74726 43.7146
6 0 8 3 12 12 36.8125 123.5 10 205.3125 0.70496 144.7372
7 0 8 3 12 12 36.8125 123.5 10 205.3125 0.66506 136.5445
8 0 8 3 12 12 36.8125 123.5 10 205.3125 0.62741 128.8156
9 0 8 3 12 12 36.8125 123.5 10 205.3125 0.59190 121.5242
10 0 8 3 12 12 36.8125 123.5 10 205.3125 0.55839 114.6454
11 0 8 3 12 12 36.8125 123.5 10 205.3125 0.52679 108.1561
12 0 8 3 12 12 36.8125 123.5 10 205.3125 0.49697 102.0340
13 0 8 3 12 12 36.8125 123.5 10 205.3125 0.46884 96.2585
14 0 8 3 12 12 36.8125 123.5 10 205.3125 0.44230 90.8099
15 0 8 3 12 12 36.8125 123.5 10 205.3125 0.41727 85.6697
16 0 8 3 12 12 36.8125 123.5 10 205.3125 0.39365 80.8205
17 0 8 3 12 12 36.8125 123.5 10 205.3125 0.37136 76.2458
18 0 8 3 12 12 4.65 15.6 10 65.25 0.35034 22.8599
19 0 8 3 12 12 3.1 10.4 10 58.5 0.33051 19.3350
20 0 8 3 12 12 3.1 10.4 10 58.5 0.31180 18.2406
NPV of total cash inflow NPV of total cash Outflow Net Present Value Rs.(cr)
18383.725 1656.7995 16726.925
Internal rate of return is calculated on the basis of trail and errors. By taking various
discounting factor, so that the appropriate percentage of internal rate of return can be judged
out.
Suggestions: Any project which has a payback period of 3 to 5 years is considered as a good
project.
Cash Outflow for calculating Payback period of the project is 1656.7994 Rupees (crores).
Cumulative Cash flow of the payback is the subtraction of all the cash inflow from the cash
Outflow in a row one by one.
Capital expenditure
Revenue expenditure/year
Year Production
1st Nil
2nd – 6th 1 Million Tons/year
6th – 15th Equal
G1 0 0
G2 3450 3450
G3 3210 3210
G4 3000 3000
G5 2750 2750
G6 1900 2280
G7 1600 1920
G8 1420 1700
G9 1100 1320
G10 980 1180
G11 810 970
G12 760 910
Present
Year L & R P&M HEMM Wages POL Contractor Electricity Transportation Others TOTAL DF @ 6 % value
1 15 20 5 3 0.005 2 0.005 5 10 60.01 0.9434 56.6132075
2 3 3 0.005 2 0.005 5 10 23.01 0.8900 20.4788181
3 1 3 0.005 2 0.005 5 10 21.01 0.8396 17.6404011
4 3 0.005 2 0.005 5 10 20.01 0.7921 15.8497942
5 3 0.005 2 0.005 5 10 20.01 0.7473 14.952636
6 3 0.005 2 0.005 5 10 20.01 0.7050 14.1062604
7 3 0.005 2 0.005 5 10 20.01 0.6651 13.3077928
8 3 0.005 2 0.005 5 10 20.01 0.6274 12.5545216
9 3 0.005 2 0.005 5 10 20.01 0.5919 11.8438883
10 3 0.005 2 0.005 5 10 20.01 0.5584 11.1734795
11 3 0.005 2 0.005 5 10 20.01 0.5268 10.5410184
12 3 0.005 2 0.005 5 10 20.01 0.4970 9.94435697
13 3 0.005 2 0.005 5 10 20.01 0.4688 9.38146884
14 3 0.005 2 0.005 5 10 20.01 0.4423 8.8504423
15 3 0.005 2 0.005 5 10 20.01 0.4173 8.34947387
Discount rate 6% is taken to calculate the present value of cash inflow per year of the project
Step 3:- Calculation of Net Present value of the Project
Net Present Value = Present value of cash Inflow – Present value of cash outflow
NPV of total cash inflow NPV of total cash Outflow Net Present Value Rs.(cr)
1726.2593 235.5876 1490.6718
By Trial and Error method, at 42.09% discount factor the Total cash inflow is equal to total
cash outflow of the project.
Analysis of the project by using Payback period method:-
Cumulative cash flow of Payback is calculates by subtracting the cash outflow from the cash
Inflow one by one in a column until cash inflow reaches negative in number.
Payback period is calculated by adding all the years of payback period year column.
For the 15 year project the payback period is 3.40 year which means that all the initial cash
outlay can be recovered with the payback time period. So the project is viable for the
Organization.
Analysis of the project by using Profitability Index Ratio:-
1 56.61320755 0
2 20.47881808 105.0195799
3 17.64040114 99.0750754
4 15.8497942 93.46705226
5 14.95263604 88.1764644
6 14.10626041 83.18534377
7 13.30779284 174.3927542
8 12.55452155 164.5214663
9 11.84388826 155.2089304
10 11.17347949 146.4235193
11 10.54101838 138.1353955
12 9.944356965 130.3164109
Profitability Index
13 9.381468835 122.9400103
14 8.850442297 115.9811418 Total Cash Inflow/Total
15 8.349473865 109.4161715 Cash outflow
Total
235.58756 1726.2593 7.3275
Rs.Cr
Profitability index for the project is 7.3275 which is obtained by dividing total cash inflow into
total cash Outflow.
FINDINGS & SUGGESTIONS
Findings:-
CCL Project A
The total cash Outflow for the project of 20 years is 1656.7995 Crore Rupees.
The total cash Inflow for the project of 20 years is 18383.725 Crore rupees.
The Net Present value of the project is 16726.925 Crore Rupees which is positive in
number so the project is financially viable for the organization.
The Internal rate of return or opportunity cost of capital for the project is 39.02%
which is much higher than the company required rate of return which is 12% so this
also ensures a profitable investment in project.
The profitability Index of the investment is 11.0959 and accepted if ratio is (PI > 1).
It has been found that the Payback Period of the investment 5.5 years.
The Payback Period shows that the initial investment can be recovered within a short
period of time.
The investment is ideal because for 20 year project an investment should be
recovered within 8-10 years.
CCL Project B
The total cash Outflow for the project of 15 years is 235.5876 Crore Rupees.
The total cash Inflow for the project of 15 years is 1726.2593 Crore Rupees.
The Net Present value of the project is 1490.6718 Crore Rupees
Positive value of Net present value determines the greater feasibility of the project so
the investment can be done by the company.
The Internal rate of return or opportunity cost of capital for the project is 42% which
is much higher than the company required rate of return which is 12% so this also
ensures a profitable investment in project.
The Profitability Index ratio of the investment is 7.3275
For acceptance of the project the Profitability Index should be greater than 1 and the
ratio of investment is much higher than the accepted standards so it is a valuable
investment.
The Payback Period of the investment 3.4 years.
Since the capital invested in a project of 15 years are recovered within a short period
of 3.4 years so the proposal is viable for the company.
SUGGESTIONS
The company cash inflow is much higher than the cash outflow in all the years expect
in 1st year which is nil, so company can increase its profitability by focusing on 1st year.
The company can use its opportunity cost of capital for expanding their business by
investing in other future projects.
The company may plan and control its capital expenditure.
The company can use other capital budgeting techniques such as Profitability index,
Accounting rate of return and discounting payback period method for evaluation of
their investment.
The company cash inflow of the investment is lower in certain year so they can
maintain constant inflow by increasing their coal production.
Both the investments are valuable for the company and they can generate huge profits
in the future so the investment should be accepted by the organization.
The company should reduce the year of the project because long term projects more
than 10 years have higher unpredictability rate and chances of uncertainty of accurate
cash Inflow in future.
The company can increase its required rate of return which is now 12% to find out a
suitable investment with higher earnings.
LIMITATIONS