C Chart
C Chart
Submitted by,
J. NELSON (3510920075)
V. NITTYANANDAM (3510920078)
If analysis of the control chart indicates that the process is currently under
control (i.e. is stable, with variation only coming from sources common to the
process) then data from the process can be used to predict the future
performance of the process. If the chart indicates that the process being
monitored is not in control, analysis of the chart can help determine the sources
of variation, which can then be eliminated to bring the process back into
control. A control chart is a specific kind of run chart that allows significant
change to be differentiated from the natural variability of the process.
The control chart can be seen as part of an objective and disciplined approach
that enables correct decisions regarding control of the process, including
whether or not to change process control parameters. Process parameters should
never be adjusted for a process that is in control, as this will result in degraded
process performance.
History
The control chart was invented by Walter A. Shewhart while working for Bell
Labs in the 1920s. The company's engineers had been seeking to improve the
reliability of their telephony transmission systems. Because amplifiers and other
equipment had to be buried underground, there was a business need to reduce
the frequency of failures and repairs. By 1920 they had already realized the
importance of reducing variation in a manufacturing process. Moreover, they
had realized that continual process-adjustment in reaction to non-conformance
actually increased variation and degraded quality. Shewhart framed the problem
in terms of Common- and special-causes of variation and, on May 16, 1924,
wrote an internal memo introducing the control chart as a tool for distinguishing
between the two. Dr. Shewhart's boss, George Edwards, recalled: "Dr. Shewhart
prepared a little memorandum only about a page in length. About a third of that
page was given over to a simple diagram which we would all recognize today as
a schematic control chart. That diagram, and the short text which preceded and
followed it, set forth all of the essential principles and considerations which are
involved in what we know today as process quality control." Shewhart stressed
that bringing a production process into a state of statistical control, where there
is only common-causevariation, and keeping it in control, is necessary to predict
future output and to manage a process economically.
Dr. Shewhart created the basis for the control chart and the concept of a state of
statistical control by carefully designed experiments. While Dr. Shewhart drew
from pure mathematical statistical theories, he understood data from physical
processes typically produce a "normal distribution curve" (a Gaussian
distribution, also commonly referred to as a "bell curve"). He discovered that
observed variation in manufacturing data did not always behave the same way
as data in nature (Brownian motion of particles). Dr. Shewhart concluded that
while every process displays variation, some processes display controlled
variation that is natural to the process, while others display uncontrolled
variation that is not present in the process causal system at all times.
In 1924 or 1925, Shewhart's innovation came to the attention of W. Edwards
Deming, then working at the Hawthorne facility. Deming later worked at
the United States Department of Agriculture and then became the mathematical
advisor to the United States Census Bureau. Over the next half a
century, Deming became the foremost champion and proponent of Shewhart's
work. After the defeat ofJapan at the close of World War II, Deming served as
statistical consultant to the Supreme Commander of the Allied Powers. His
ensuing involvement in Japanese life, and long career as an industrial consultant
there, spread Shewhart's thinking, and the use of the control chart, widely in
Japanese manufacturing industry throughout the 1950s and 1960s.
Chart details
A control chart consists of:
Upper and lower warning limits, drawn as separate lines, typically two
standard errors above and below the center line
Division into zones, with the addition of rules governing frequencies of
observations in each zone
Annotation with events of interest, as determined by the Quality Engineer
in charge of the process's quality
Chart usage
If the process is in control, all points will plot within the control limits. Any
observations outside the limits, or systematic patterns within, suggest the
introduction of a new (and likely unanticipated) source of variation, known as
a special-cause variation. Since increased variation means increased quality
costs, a control chart "signaling" the presence of a special-cause requires
immediate investigation.
This makes the control limits very important decision aids. The control limits
tell you about process behavior and have no intrinsic relationship to
any specification targets or engineering tolerance. In practice, the process mean
(and hence the center line) may not coincide with the specified value (or target)
of the quality characteristic because the process' design simply can't deliver the
process characteristic at the desired level.
Control charts limit specification limits or targets because of the tendency of
those involved with the process (e.g., machine operators) to focus on
performing to specification when in fact the least-cost course of action is to
keep process variation as low as possible. Attempting to make a process whose
natural center is not the same as the target perform to target specification
increases process variability and increases costs significantly and is the cause of
much inefficiency in operations. Process capability studies do examine the
relationship between the natural process limits (the control limits) and
specifications, however.
The purpose of control charts is to allow simple detection of events that are
indicative of actual process change. This simple decision can be difficult where
the process characteristic is continuously varying; the control chart provides
statistically objective criteria of change. When change is detected and
considered good its cause should be identified and possibly become the new
way of working, where the change is bad then its cause should be identified and
eliminated.
The purpose in adding warning limits or subdividing the control chart into zones
is to provide early notification if something is amiss. Instead of immediately
launching a process improvement effort to determine whether special causes are
present, the Quality Engineer may temporarily increase the rate at which
samples are taken from the process output until it's clear that the process is truly
in control. Note that with three sigma limits, one expects to be signaled
approximately once out of every 370 points on average, just due to common-
causes.
Choice of limits
The success of Shewhart's approach is based on the idea that no matter how well
the process is designed, there exists a certain amount of nature variability in
output measurements.
When the variation in process quality is due to random causes alone, the process
is said to be in-control. If the process variation includes both random and
special causes of variation, the process is said to be out-of-control.
In its basic form, the control chart is a plot of some function of process
measurements against time. The points that are plotted on the graph are
compared to a pair of control limits. A point that exceeds the control limits
signals an alarm.
An Example
Daily samples of 10 bars are taken, during a stable period of the process. For
each sample, the weights are recorded, and their mean/average is computed. The
sample means are estimates of the process mean.
It has been shown that Shewhart-type charts are efficient in detecting medium to
large shifts, but are insensitive to small shifts. One attempt to increase the
power of Shewhart-type charts is by adding supplementary stopping rules based
on runs. The most popular stopping rules were suggested by the "Western
Electric Company" ("WECO"). These rules supplement the ordinary rule: "One
point exceeds the control limits". Here are the most popular Western Electric
rules: