Section 8 - Special Conditions of Contract
Section 8 - Special Conditions of Contract
Section 8 - Special Conditions of Contract
Table of Clauses
Bidding Document for Grid S/S Construction of 05 Nos. 132/33/11kV GIS sub-station DESCO
Section 8 - Special Conditions of Contract 8-2
1. Definitions
5.1 The Contract shall be interpreted in accordance with the laws of: The People’s Republic
of Bangladesh
7. Scope of Facilities
7.3 The Contractor agrees to supply spare parts for a period of years: 5 years
8.1 The Contractor shall commence work on the Facilities within 21 days from the Effective
Date for determining Time for Completion as specified in the Contract Agreement.
8.2 The Time for Completion of the whole of the Facilities shall be 540 days from the
Effective Date as described in the Contract Agreement.
Bidding Document for Grid S/S Construction of 05 Nos. 132/33/11kV GIS sub-station DESCO
Section 8 - Special Conditions of Contract 8-3
13. Securities
13.3.1 The amount of performance security, as a percentage of the Contract Price for the Facility or for
the part of the Facility for which a separate Time for Completion is provided, shall be: Ten
percent(10%) of the contract price
13.3.2 The performance security shall be in the form of a Bank Guarantee issued by a bank
acceptable to the Employer as per form included in Section 6 (Employer’s Requirements,
Bank Guarantees and Certificates).
If the Institution issuing the security is located outside Bangladesh, It shall have a
correspondent financing institution located in Bangladesh to make it enforceable.
14.1(a) Income Tax, surcharge and all taxes of similar nature and VAT levied on the Contractor in
Bangladesh in connection with the execution of this Contract, except the personnel taxes and
other taxes on its expatriate and local personnel, shall be paid by the Employer.
To facilitate payment of such taxes by the Employer, the Contractor shall submit to the income
tax authorities through the Employer all statutory statements and returns with necessary
documents and information well before the dates fixed for submission of such returns and the
Contractor shall also comply with all requirements in the course of the proceedings before the
tax authorities. If, for the Contractor's failure to submit such statement/returns in time, any
interest, penalty or any other levy is imposed by the tax authorities, the Employer shall not be
liable to pay such amount which will be the liability of the Contractor. The Employer will not be
liable for payment of tax, VAT etc., if an arbitrary assessment is made for the failure of
submission of proper documents by the Contractor.
(b) The Contractor's final payment shall not be released until full compliance of this provision through
fulfillment of the rules and regulations of the Tax Authorities of Bangladesh of the Contract by
the Contractor.
14.2(a) The Contractor shall, at his cost and expense secure, any work permits, labor permits, tax
clearances, tax exemption certificate and any other authorization which may be required by the
Government of Bangladesh to permit imported personnel of Contractor and its sub Contractors
to perform their work at site. The Contractor shall withhold from the pay roll of all local
employees and remit to appropriate authorities such taxes or assessments as may be required
by Bangladesh Law.
(b) The Contractor shall be liable to the Employer for customs duties and taxes, paid by the
Employer and for the other lawful tax which may be or may become payable, on the
Contractor's equipment tools and supplies imported for the Works and subsequently sold within
Bangladesh, to a party, or parties other than the Employer. For the selling of anything by the
Contractor, permission of the Employer shall be obtained by the Contractor
c) The Employer will be responsible for the payments of all such Customs and Import Duties and
VAT levied on the imported Plant, except materials for civil works such as reinforcement steel
bars, cement etc. which are available in Bangladesh, required for the project upon submission
by the Contractor of necessary documentation as detailed 14.2(d). Consequently, all bid prices
shall be exclusive of Customs and Import Duties and VAT on the imported Plant required for this
Bidding Document for Grid S/S Construction of 05 Nos. 132/33/11kV GIS sub-station DESCO
Section 8 - Special Conditions of Contract 8-4
project.
The materials for civil works such as reinforcement steel, cement, sand, bentonite slurry and
retrder are normally available in Bangladesh and can be procured locally by the Contractor. In
cases where these materials are required to be imported for the work, all customs and import
duties shall be borne by the Contractor.
(d) In order for the Employer to obtain the necessary import permits and satisfy the requirements of
the customs authorities for the imported Plant required for this Contract the following
documentation is required.
Within 60 days of the signing of the contract the Contractor shall submit a detailed delivery
schedule of Plant he is to provide under the contract indicating the type of equipment and the
name of the manufacturer. 6 (six) copies of the schedule are to be submitted to the Employer
On behalf of the Government of Bangladesh the Ministry of Commerce annually issue a schedule
of import protected items. The Contractor shall be responsible for advising the Employer of any
Plant the Contractor intends to ship under the Contract which is import protected. This advice is
to be received by the Project Manager at least 4 (four) months before the Contractor reaches
Bangladesh in order to permit the Employer to obtain the necessary import permissions
(e) Import license and permits for the Plant shall be obtained by the Employer at no cost to the
Contract, no import and export customs duties levied on food of any sort or personal effects
imported for consumption by the Contractor’s personnel shall be paid by the Employer.
(f) If, however, after payment of Customs and Import duties by the Employer, goods are
discovered to have arrived into Bangladesh in such a badly damaged condition due to the
Contractor’s negligence that they have to be replaced, the Contractor will be responsible for
the payment of the Customs and Import duties levied on all the replacement portions/part(s) of
the imported Plant.
Bidding Document for Grid S/S Construction of 05 Nos. 132/33/11kV GIS sub-station DESCO
Section 8 - Special Conditions of Contract 8-5
(g) The Contractor will be responsible for payment of all costs, with the exception of those costs
that are specifically to the account of the Employer as described in SCC 14.2(c), related to
clearances of Plant and Contractor's Equipment at the port of entry. The Contractor shall
perform all necessary Customs formalities in respect of clearance of materials from the port in
consultation with DESCO.
h) It is the Contractor's responsibility to ensure all negotiable shipping documentation and all
necessary import information is forwarded to the Employer so that it is received by him in
Bangladesh at least 14 (fourteen) days before arrival of the ship in the Bangladesh port.
Demurrage and any other charges resulting from the lack of documents or incorrect
documentation received in Bangladesh shall be to the Contractor's account
20.3.2 The text “fourteen (14) days” is replaced by “twenty eight (28) days” in both places.
20.3.8 Drawings are to be submitted for approval on paper prints, folded to A4 size with the project
title block and drawing numbers fully visible.
20.3.9 The Contractor shall be mention Employer's drawing numbers to all drawings prior to
submittal. Following award of the contract the Employer and Contractor will review the
numbering system, familiarize each other with requirements, and agree on the numbering
system to be applied.
Comprehensive cross references are to be included on drawings and the Contractor shall
include the Employer's drawing number in the cross references. At each and every issue of
a drawing the revision shall be raised, and details given in revision boxes on the drawing.
Comprehensive details of revisions are to be given and phrases such as "REVISED",
"UPDATED", "MODIFIED" or similar are not acceptable. Reference to any drawing in
communications shall include the Employer's drawing number.
20.3.10 The Contractor shall submit four (04) copies of drawings of the plant and works for formal
approval to the Employer. A Program of drawing submittal shall be agreed with the
Contractor following contract award. Drawings issued in accordance with this Program shall
take account of the time periods necessary for postage, and approval by the Employer, to
ensure that approved drawings are available prior to manufacture. For site construction
works, 4 copies of "Construction Issue" drawings are to be submitted and made available,
on site, at least 21 days prior to the commencement of the works.
Where appropriate, the drawings shall be accompanied by supporting calculations. The
Contractor shall ensure that drawings of a specific aspect of the Works are fully co-ordinate
and submitted together in a logical sequence.
Should the Contractor revise a drawing for any reason following approval by the Employer
the revised drawing is to be resubmitted for re Approval by the Employer, the original
approval automatically being void
20.3.11 During construction of the Works on the site, the Contractor shall ensure that all
departures, modifications and corrections to the approved drawings are recorded. All
such changes to the drawings are to be marked in red to show the "as-built" state and
one set of "as-built" drawings are to be available on the site at all times.
Bidding Document for Grid S/S Construction of 05 Nos. 132/33/11kV GIS sub-station DESCO
Section 8 - Special Conditions of Contract 8-6
Employer's Representative. These drawings shall be issued by the Contractor prior to the
issue of the Completion Certificate.
22. Installation
22.2 Labor:
The Contractor shall ensure equal opportunity for men and women for same nature of
work.
The Contractor shall ensure mandated provisions of labor law and provide equal pay for
work of equal value.
The Contractor shall not engage any children as labor during the execution of the
contract. Child means a child below the statutory minimum age specified under
applicable national, provisional or local law of Bangladesh.
(d) The Contractor shall throughout the contract (including the Defect Liability Period):
(ii) provide male or female condoms for all Site staff and labor as appropriate; and
(iii) provide for STI and HIV/AIDS screening, diagnosis, counseling and referral to a
dedicated national STI and HIV/AIDS program, (unless otherwise agreed) of all
Site staff and labor.
The Contractor shall include in the program to be submitted for the execution of the
Facilities under Sub-Clause 18.2 an alleviation program for Site staff and labor and
their families in respect of Sexually Transmitted Infections (STI) and Sexually
Transmitted Diseases (STD) including HIV/AIDS. The STI, STD and HIV/AIDS
alleviation program shall indicate when, how and at what cost the Contractor plans to
satisfy the requirements of this Sub-Clause and the related specification. For each
component, the program shall detail the resources to be provided or utilized and any
Bidding Document for Grid S/S Construction of 05 Nos. 132/33/11kV GIS sub-station DESCO
Section 8 - Special Conditions of Contract 8-7
25.2.2 The Guarantee Test of the Facilities shall be successfully completed within 15
(fifteen) days from the date of Completion.
26.2 Applicable rate for liquidated damages: 0.5% of the Contract Price per week in the
Proportions of currencies in which the Contract Price is payable.
The maximum amount of Liquidated Damages for the uncompleted Works or any part
thereof is ten percent (10%) of the final Contract price of the whole of the Works.
26.3 No bonus will be given for earlier Completion of the Facilities or part thereof.
27.10 The critical components covered under the extended defect liability : No Extended
Defect liability required.
42. Termination
42.1.2(e) The contract shall be terminated in case of breach of any of the conditions stipulated in
SCC 22.2.1(e), 22.2.4(c) and 22.2.16
45.1 The DB shall be appointed within 28 days after the Effective Date.
The DB shall be comprise of 3(three) suitable qualified person (the member).
List of potential DB members to be decided later on.
45.2 Appointment (if not agreed) to be made by: The President of Institution of Engineers,
Bangladesh.
45.3 The text “GCC sub-clauses 44.7 & 44.8” is replaced by “GCC Sub-Clauses 45.4 & 45.5”.
Bidding Document for Grid S/S Construction of 05 Nos. 132/33/11kV GIS sub-station DESCO
Section 8 - Special Conditions of Contract 8-8
45.4 The text “GCC sub-clause 44.4” is replaced by ”GCC Sub-Clause 45.3”
Bidding Document for Grid S/S Construction of 05 Nos. 132/33/11kV GIS sub-station DESCO