Chiller Modelos - YK PDF
Chiller Modelos - YK PDF
Chiller Modelos - YK PDF
R134A
035-19569-101 (0109)
Table of Contents
1 SUPPLIER INFORMATION 1-1 4 INSTALLATION 4-1
1.5 About this Manual 1-2 4.5 Rigging Unit to Final Location 4-1
1.6 Misuse of Equipment 1-2 4.6 Locating and Installing Isolator Pads 4-1
1.8 Safety Labels 1-3 4.7 Installing Optional Spring Isolators 4-2
GB I-i
035-19569-101 (0109)
6.2 Checking the Oil Level in the Oil Reservoir 6-1 9.2 Dimensions -
Evaporator Compact Water Boxes 9-4
6.3 Start-up Procedure 6-1
9.3 Nozzle Arrangements -
6.4 Chiller Operation 6-4 Evaporator Compact Water Boxes 9-5
6.5 Operating Log Sheet 6-4 9.4 Dimensions -
Condenser Compact Water Boxes 9-7
6.7 Stopping the System 6-7
9.5 Nozzle Arrangements -
6.8 Prolonged Shutdown 6-7
Condenser Compact Water Boxes 9-8
6.9 Start-up after Prolonged Shutdown 6-7
9.6 Dimensions -
Evaporator Marine Water Boxes 9-9
7 MAINTENANCE 7-1 9.8 Nozzle Arrangements -
Evaporator Marine Water Boxes 9-10
7.1 Inspections 7-1
9.8 Dimensions -
7.2 Oil Return System 7-2 Condenser Marine Water Boxes 9-11
7.3 Oil Charge 7-3 9.8 Nozzle Arrangements -
Condenser Marine Water Boxes 9-12
7.4 Refrigerant Charge 7-3
9.9 Unit Weights 9-13
7.5 Condenser and Evaporator 7-5
9.10 Process and Instrumentation Diagram 9-15
7.6 Compressor 7-7
I-ii GB
035-19569-101 (0109)
1 SUPPLIER INFORMATION
1.1 Introduction For warranty purposes, the following conditions must
be satisfied:
York YK chillers are manufactured to the highest design
and construction standards to ensure high performance, The initial start of the unit must be carried out by trained
reliability and adaptability to all types of air conditioning personnel from an Authorised York Service Centre.
installations.
Only genuine York approved spare parts, oils and
The units are intended for cooling water or glycol refrigerants must be used.
solutions and are not suitable for purposes other than
those specified in this manual. All the scheduled maintenance operations detailed in
this manual must be performed at the specified times
This manual and the Control System Operating by suitably trained and qualified personnel.
Instructions contain all the information required for correct
installation and commissioning of the unit, together with Failure to satisfy any of these conditions will automatically
operating and maintenance instructions. The manuals void the warranty.
should be read thoroughly before attempting to operate
or service the unit. 1.3 Safety
All warranty claims must specify the unit model, serial ■ Correct utilisation of the machinery in accordance
number and order number. with the procedures detailed in the manuals.
The unit warranty will be void if any modification to the The owner must comply with the Governmental
unit is carried out without prior written approval from Standards and Regulations for the commissioning and
York International. in-service inspections of the unit, in particular those
relating to pressure equipments.
GB 1-1
035-19569-101 (0109)
1-2 GB
035-19569-101 (0109)
GB 1-3
035-19569-101 (0109)
Refrigerant Data:
Safety Data R134a
Toxicity Low.
In contact with skin Liquid splashes or spray may cause freeze burns. Unlikely to be hazardous
by skin absorption. Thaw affected areas with water. Remove contaminated
clothing carefully — may adhere to skin in case of freeze burns. Wash
affected areas with plenty of warm water. If symptoms occur (irritation or
blistering) obtain medical attention.
In contact with eyes Vapour has no effect. Liquid splashes or spray may cause freeze burns.
Immediately irrigate with eyewash solution or clean water for at least 10
minutes. Obtain immediate medical attention.
Ingested Highly unlikely to occur — but should this occur freeze burn will occur. Do not
induce vomiting. Provided patient is conscious, wash mouth with water and
give about 250 ml (0.5 pint) to drink. Obtain immediate medical attention.
Inhalation High atmospheric concentrations may have an anaesthetic effect, including
loss of consciousness. Very high exposures may cause an abnormal heart
rhythm and prove suddenly fatal.
At higher concentration there is a danger from asphyxiation due to reduced
oxygen content of atmosphere. Remove patient to fresh air, keep warm and
at rest. Administer oxygen if necessary. Apply artificial respiration if breathing
has ceased or shows signs of failing. In event of cardiac arrest apply external
cardiac massage. Obtain immediate medical attention.
Further medical advice Symptomatic and supportive therapy is indicated. Cardiac sensitisation has
been described which may, in the presence of circulating catecholamines
such as adrenalin, give rise to cardiac arrhythmia’s and subsequent arrest
following exposure to high concentrations.
Long term exposure A lifetime inhalation study in rats has shown that exposure to 50,000 ppm
resulted in benign tumours of the testis. This is not considered to be of
relevance to humans exposed to concentrations at or below the occupational
exposure limit.
Occupational exposure limits Recommended limit: 1000 ppm v/v - 8 hr TWA.
Stability Not specified.
Conditions to avoid Use in presence of naked flames, red hot surfaces and high moisture
levels.
Hazardous reactions May react violently with sodium, potassium, barium and other alkali and
alkaline earth metals. Incompatible materials: Magnesium and alloys
containing more then 2% magnesium.
Hazardous decomposition products Halogen acids by thermal decomposition and hydrolysis.
General precautions Avoid inhalation of high concentrations of vapours. Atmospheric
concentrations should be minimised and kept as low as reasonably
practicable below the occupational exposure limit. The vapour is heavier than
air and collects at low level and in confined areas. Ventilate by extraction
at lowest levels.
Respiratory protection Where doubt exists on atmospheric concentration, approved breathing
apparatus should be worn. This should be self contained or of the long
breather type.
Storage Keep containers dry and in a cool place away from fire risk, direct sunlight,
and all sources of heat such as radiators. Keep at temperatures not
exceeding 45°C.
Protective clothing Wear overalls, impervious gloves and goggles/face protection.
1-4 GB
035-19569-101 (0109)
Spill/leak procedure Ensure suitable personal protective clothing and respiratory protection is
worn. Provided it is safe to do so, isolate the source of the leak. Allow small
spillage’s to evaporate provided there is suitable ventilation.
Large spillage’s: Ventilate area. Contain spillage’s with sand, earth or
any suitable absorbent material. Prevent liquid from entering drains,
sewers, basements and work pits since vapour may create a suffocating
atmosphere.
Disposal Best to recover and recycle. If this is not possible, destruction is to be in
an approved facility which is equipped to absorb and neutralise acids and
other toxic processing products.
Fire extinguishing data Non-flammable at atmospheric conditions.
Containers Fire exposed containers should be kept cool with water sprays. Containers
may burst if overheated.
Fire fighting protective equipment Self contained breathing apparatus and protective clothing must be worn
in fire conditions.
GB 1-5
035-19569-101 (0109)
1-6 GB
035-19569-101 (0109)
2 PRODUCT DESCRIPTION
2.1 General (Figures 2.1 and 2.2) In operation, a liquid (water or brine to be chilled) flows
through the evaporator, where boiling refrigerant absorbs
The York YK Millennium™ Centrifugal Liquid Chiller is heat from the liquid. The chilled liquid is then piped to fan
primarily used for large air conditioning systems, but may coil units or other air conditioning terminal units, where
be used on other applications. The chiller is completely it flows through finned coils, absorbing heat from the
factory-packaged including evaporator, condenser, air. The warmed liquid is then returned to the chiller to
compressor, motor, lubrication system, graphic control complete the chilled liquid circuit.
centre (OptiView), and all interconnecting unit piping
and wiring. The initial charge of refrigerant and oil is The refrigerant vapour, which is produced by the boiling
supplied for each unit. action in the evaporator, flows to the compressor
where the rotating impeller increases its pressure and
The chiller is controlled by a modern state of the art temperature and discharges it into the condenser.
microprocessor control centre that monitors its operation. Water flowing through the condenser tubes absorbs
The control centre is programmed by the operator to suit heat from the refrigerant vapour, causing it to condense.
job specifications. Automatic timed start-ups and shut- The condenser water is supplied to the chiller from an
downs are also programmable to suit nighttime, week- external source, usually a cooling tower. The condensed
ends, and holidays. The operating status, temperatures, refrigerant drains from the condenser into the liquid
pressures, and other information pertinent to operation return line, where the variable orifice meters the flow
of the chiller are automatically displayed and read on of liquid refrigerant to the evaporator to complete the
a graphic display. Other displays can be observed by refrigerant circuit.
pressing the keys as labelled on the control centre.
The chiller with the graphic control centre (OptiView) is The major components of a chiller are selected to handle
compatible with an electro-mechanical starter, YORK the refrigerant, which would be evaporated at full load
Solid State Starter (optional), or Variable Speed Drive design conditions. However, most systems will be called
(optional). upon to deliver full load capacity for only a relatively small
part of the time the unit is in operation.
GB 2-1
035-19569-101 (0109)
GB 2-3
035-19569-101 (0109)
2-4 GB
035-19569-101 (0109)
To provide the required amount of oil under the necessary a motor support.
pressure to properly lubricate these parts, a motor driven
submersible oil pump is located in a remote oil sump. Motor drive shaft is directly connected to the compressor
shaft with a flexible disc coupling. This coupling has
Upon pressing of the COMPRESSOR START switch on all metal construction with no wearing parts to assure
the control panel, the oil pump is immediately energized. long life, and no lubrication requirements to provide low
After a 50 second pre-lube period, the compressor motor maintenance.
will start. The oil pump will continue to run during the
entire operation of the compressor, and for 150 seconds For units utilising remote electro-mechanical starters,
during compressor shutdown. a terminal box is provided for field connected conduit.
Motor terminals are brought through the motor casing into
The submerged oil pump takes suction from the the terminal box. Jumpers are furnished for three-lead
surrounding oil and discharges it to the oil cooler where type of starting. Motor terminal lugs are not furnished.
heat is rejected. The oil flows from the oil cooler to the oil Overload/overcurrent transformers are furnished with
filter. The oil leaves the filter and flows to the emergency all units.
oil reservoir where it is distributed to the compressor
bearings. The oil lubricates the compressor rotating For units furnished with factory packaged Solid State
components and is returned to the oil sump. Starters, (optional) see Options Section.
There is an emergency oil reservoir located at the 2.6 Graphic Control Centre (OptiView)
highest point in the lubrication system internally in the
compressor. It provides an oil supply to the various The graphic control centre is factory-mounted, wired
bearings and gears in the event of a system shutdown and tested. The electronic panel automatically controls
due to power failure. The reservoir, located on the top of the operation of the unit in meeting system cooling
the compressor, allows the oil to be distributed through requirements while minimizing energy usage. For
the passages by gravity flow, thus providing necessary detailed information on the Graphic Control Centre, refer
lubrication during the compressor shutdown. to Form 160.54-O1
GB 2-5
035-19569-101 (0109)
Stub-out water nozzle connections with Victaulic grooves 2.9 Options and Accessories
are welded to the water boxes. These nozzle connections
are suitable for Victaulic couplings, welding or flanges, 2.9.1 Service Isolation Valves
and are capped for shipment. Plugged ¾" drain and vent
If the chiller is equipped with optional service isolation
connections are provided in each water box.
valves on the discharge and liquid line, these valves
must remain open during operation. These valves are
2.8 Refrigerant Flow Control
used for isolating the refrigerant charge in either the
evaporator or condenser to allow service access to the
Refrigerant flow to the evaporator is controlled by a
system. A refrigerant pump-out unit will be required to
variable orifice.
isolate the refrigerant.
A level sensor senses the refrigerant level in the condenser
Isolation of the refrigerant in this system must be
and outputs an analog voltage to the microprocessor
performed by a qualified service technician.
that represents this level (0% = empty; 100% = full).
Under program control, the microprocessor modulates
2.9.2 Hot Gas Bypass
a variable orifice to control the condenser refrigerant
level to a programmed setpoint. Other setpoints affect Hot gas bypass is optional and is used to eliminate
the control sensitivity and response. These setpoints compressor surge during light load or high head
must be entered at chiller commissioning by a qualified operation. The control panel will automatically modulate
service technician. Only a qualified service technician the hot gas valve open and closed as required.
may modify these settings. Adjustment of the hot gas control valve must be
performed by a qualified service technician following
While the chiller is shut down, the orifice will be in the Hot Gas Set-up procedure.
the fully open position causing the sensed level to be
approximately 0%. When the chiller is started, after the Changes in chilled water flow will require re-adjustment
vane motor end switch (VMS) opens when entering of the hot gas control to insure proper operation.
SYSTEM RUN, if actual level is less than the level
setpoint, a linearly increasing ramp is applied to the 2.9.3 Solid State Starter
level setpoint. This ramp causes the setpoint to go from
The optional Solid State Starter is a reduced voltage
the initial refrigerant level (approximately 0%) to the
starter that controls and maintains a constant current
programmed setpoint over a period of 15 minutes.
flow to the motor during start-up. It is mounted on the
chiller. Power and control wiring between the starter and
If the actual level is greater than the setpoint when the
chiller are factory installed. Available for 380-600 volts,
VMS opens, there is no pulldown period, it immediately
the starter enclosure is IP54 with a hinged access door
begins to control to the programmed setpoint.
with lock and key. Electrical lugs for incoming power
wiring are provided.
While the chiller is running, the refrigerant level is
normally controlled to the level setpoint. However,
anytime the vanes fully close (VMS closes), normal
2.9.4 Variable Speed Drive
level control is terminated, any refrigerant level setpoint An optional 400V – 3-Ph – 60/50Hz Variable Speed Drive
pulldown in effect is cancelled and the outputs to the level can be factory packaged with the chiller. It is designed to
control will be opposite that which is supplied to the vane vary the compressor motor speed and pre-rotation vane
motor (i.e., when a close pulse is applied to the vane position by controlling the frequency and voltage of the
motor, an open pulse is applied to the level control, etc.). electrical power to the motor. Operational information
When the VMS opens, if the refrigerant level is less than is contained in Form 160.00-O1 (VSD 658 HP and 900
the level setpoint, a refrigerant level setpoint pulldown HP) or 160.00-O4 (VSD OptiSpeed 292 HP and 419
is initiated as described above. Otherwise, the level is HP). The control logic automatically adjusts motor speed
controlled to the programmed setpoint. and compressor pre-rotation vane position for maximum
part load efficiency by analysing information fed to it by
sensors located throughout the chiller.
2-6 GB
035-19569-101 (0109)
2.10 Nomenclature
YK ER ER Q7 5 CS G S
Model Special Modifications
GB 2-7
035-19569-101 (0109)
2-8 GB
035-19569-101 (0109)
Refrigerant and oil charges are shipped separately Form 1 – Factory Assembled Unit (complete with
(unless optional condenser isolation valves are motor, refrigerant and oil charges)
ordered).
1. The motor/compressor assembly mounted, with
Chillers can also be shipped dismantled when required all necessary interconnecting piping assembled.
by rigging conditions, but generally it is more economical Graphic control centre (OptiView) is mounted on the
to enlarge access openings to accommodate the factory unit. Complete unit factory leak tested, evacuated
assembled unit. Chillers shipped dismantled MUST and charged with R134a.
be field assembled under the supervision of a York
representative. An optional Solid State Starter or Variable Speed
Drive can be factory mounted and wired.
FIELD ASSEMBLED UNITS ONLY
2. Miscellaneous material – Four (4) vibration isolation
Use Form 160.73-N3 in conjunction with this manual. pads (or optional spring isolators and brackets).
This instruction will be furnished with all units that are to
be field assembled. Extra copies may be ordered from Form 2 – Factory Assembled Unit (complete with
the York Publication Distribution Centre. motor, refrigerant and oil charges shipped separately).
A York authorised representative must check the 1. The motor/compressor assembly mounted, with
installation, supervise the initial start-up and operation all necessary interconnecting piping assembled.
of all newly installed chillers. Graphic control centre (OptiView) is mounted on the
unit. Complete unit factory leak tested, evacuated
The York Warranty may be voided if the and charged with holding charge of nitrogen.
following restrictions are not adhered to:
An optional Solid State Starter or Variable Speed
CAUTION Drive can be factory mounted and wired.
GB 3-1
035-19569-101 (0109)
Units shipped dismantled MUST be re- 3.3 Inspection, Damage and Shortage
assembled by, or under the supervision of, a
York representative. (See Form 160.73-N3) The unit shipment should be checked on arrival to see
NOTE that all major pieces, boxes and crates are received.
Each unit should be checked before unloading, for any
Form 7 – Split Shells visible signs of damage. Any damage or signs of possible
damage must be reported to the transportation company
Shipped as four major assemblies. Unit first factory immediately for their inspection.
assembled, refrigerant piped, wired and leak tested;
then dismantled for shipment. Compressor/motor York will not be responsible for any damage in shipment
assembly removed from shells and skidded. or at job site or loss of parts.
Evaporator and condenser shells are separated at When received at the job site all containers should
tube sheets and are not skidded. Refrigerant lines be opened and contents checked against the packing
between shells are flanged and capped, requiring no list. Any material shortage should be reported to York
welding. immediately.
All compressor wiring attached. All wiring harnesses Chiller Data Plate
on shells are removed. All openings on compressor
and shells are closed and charged with dry nitrogen A unit data plate is mounted on the control panel
(1.4 to 2 kPag). assembly of each unit, giving unit model number; design
working pressure; water passes; refrigerant charge;
Miscellaneous packaging of control centre, tubing, serial numbers; and motor power characteristics and
water temperature controls, wiring, oil isolators, solid connection diagrams.
state starter (option), etc.; refrigerant charge shipped
separately. Additional information may be found on the motor
data plate. This information should be included when
Units shipped dismantled MUST be re- contacting the factory on any problem relating to the
assembled by, or under the supervision of, a motor.
York representative. (See Form 160.73-N3)
NOTE
3-2 GB
035-19569-101 (0109)
3.4 Rigging Do not lift the unit with slings around motor/
compressor assembly or by means of eye
The complete standard chiller is shipped without skids. bolts in the tapped holes of the compressor
(When optional skids are used it may be necessary to CAUTION motor assembly. Do not turn a unit on its side
remove the skids so riggers skates can be used under for rigging. Do not rig vertically.
the unit end sheets to reduce overall height.)
The rigging and operating weights and overall dimensions
Each unit has four (4) lifting holes (two in each end) in are given in Section 9 as a guide in determining the
the end sheets which should be used to lift the unit. clearances required for rigging. (Add 150 mm to overall
height for optional skidded unit.).
Care should be taken at all times during rigging and
handling of the chiller to avoid damage to the unit and
its external connections. Lift only using holes shown.
GB 3-3
035-19569-101 (0109)
3-4 GB
035-19569-101 (0109)
GB 4-1
035-19569-101 (0109)
When ordered, 4 spring type isolator assemblies will be After the unit is levelled (and wedged in place for optional
furnished with the unit. The 4 assemblies are identical spring isolators) the piping connections may be made;
and can be placed at any of the 4 corners of the unit. chilled water, condenser water and refrigerant relief. The
piping should be arranged with offsets for flexibility, and
While the unit is still suspended by the rigging, the adequately supported and braced independently of the
isolators should be bolted to the unit by inserting the cap unit to avoid strain on the unit and vibration transmission.
screw(s) through the hole(s) in the mounting bracket into Hangers must allow for alignment of pipe. Isolators (by
the tapped hole in the top of the isolator levelling bolt(s). others) in the piping and hangers are highly desirable,
Then the unit can be lowered onto the floor. and may be required by specifications, in order to
effectively utilise the vibration isolation characteristics
The levelling bolts should now be rotated one (1) turn of the vibration isolation mounts of the unit.
at a time, in sequence, until the unit end sheets are
clear of the floor by the dimension shown in Figure .2 Check for piping alignment – Upon completion of piping,
and the unit is level. Check that the unit is level, both a connection in each line as close to the unit as possible
longitudinally and transversely (see Levelling the Unit). should be opened, by removing the flange bolts or
If the levelling bolts are not long enough to level unit coupling and checked for piping alignment. If any of the
due to an uneven or sloping floor or foundation, steel bolts are bound in their holes, or if the connection springs
shims (grouted, if necessary) must be added beneath are out of alignment, the misalignment must be corrected
the isolator assemblies as necessary. by properly supporting the piping or by applying heat to
anneal the pipe.
After the unit is levelled, wedge and shim under each
corner to solidly support the unit in this position while If the piping is annealed to relieve stress, the
piping connections are being made, pipe hangers inside of the pipe must be cleaned of scale
adjusted and connections checked for alignment. Then before it is finally bolted in place.
the unit is filled with water and checked for leaks. The NOTE
4-2 GB
035-19569-101 (0109)
LD08525
LD08527 LD08528
UNIT WEIGHT 13,081 TO 24,281 Kgs. UNIT WEIGHT 24,281 TO 45,570 Kgs.
Condenser See
Centreline Centreline Dimensions
of Vessels
Evaporator
Centreline
See
Dimensions
GB 4-3
035-19569-101 (0109)
4-4 GB
035-19569-101 (0109)
Foreign objects which could lodge in, or block flow For proper operation of the unit, condenser refrigerant
through the evaporator and condenser tubes must be pressure must be maintained above evaporator pressure.
kept out of the water circuit. All water piping must be If operating conditions will fulfill this requirement, no
cleaned or flushed before being connected to the chiller attempt should be made to control condenser water
pumps, or other equipment. temperature by means of automatic valves, cycling of
the cooling tower fan or other means, since chillers are
Permanent strainers (supplied by others) are required designed to function satisfactorily and efficiently when
in both the evaporator and condenser water circuits to condenser water is allowed to seek its own temperature
protect the chiller as well as the pumps, tower spray level at reduced loads and off-peak seasons of the
nozzles, chilled water coils and controls, etc. The year. However, if entering condenser water temperature
strainer should be installed in the entering chilled water can go below the required minimum, condenser water
line, directly upstream of the chiller. temperature must be maintained equal to or slightly
higher than the required minimum. Refer to Figure 4.3
Water piping circuits should be arranged so that the for a typical water piping schematic.
pumps discharge through the chiller, and should be
controlled as necessary to maintain essentially constant
chilled and condenser water flows through the unit at all
load conditions.
GB 4-5
035-19569-101 (0109)
4.10 Stop Valves transit may cause the nuts to loosen. If water pressure
is applied before tightening is done, the gaskets may be
Stop valves may be provided (by others) in the damaged and have to be replaced.
evaporator and condenser water piping adjacent to
the unit to facilitate maintenance. Thermometer wells Fill the chilled and condenser water circuits, operate
and pressure taps should be provided (by others) in the pumps manually and carefully check the evaporator
the piping as close to the unit as possible to facilitate and condenser water heads and piping for leaks. Repair
operating check. leaks as necessary.
4.11 Flow Switches (Field Installed) Before initial operation of the unit both water circuits
should be thoroughly vented of all air at the high
A flow switch or pressure differential control in the chilled points.
or condensed water lines is an accessory furnished for
connection to the control panel. If a flow switch is used, 4.14 Refrigerant Relief Piping
it must be directly in series with the chiller and sensing
only water flow through the chiller. The flow switch can Each unit is equipped with pressure relief valves located
be paddle type (field installed) or thermal type (factory on the condenser and on the evaporator for the purpose
mounted). A differential pressure switch that senses of quickly relieving excess pressure of the refrigerant
pressure drop across the unit can also be supplied. charge to the atmosphere as a safety precaution in case
of an emergency, such as fire. The pressure relief valve
4.12 Drain and Vent Valves is set at design pressure of the system and has discharge
capacity required by relevant standard.
Drain and vent valves (by others) should be installed
in the connections provided in the evaporator and Refrigerant relief vent piping (by others), from the relief
condenser liquid heads. These connections may be valves to the outside of the building, is required by code
piped to drain if desired. in most areas and should be installed on all chillers. The
vent line should be sized in accordance with EN13136,
4.13 Checking Piping Circuits and Venting Air or local code. The vent line must include a dirt trap in
the vertical leg to intercept and permit clean out and to
After the water piping is completed, but before any trap any vent stack condensation. The piping MUST be
water box insulation is applied. Tighten and torque (to arranged to avoid strain on the relief valves, using a
maintain between 41 and 82 Nm) the nuts on the liquid flexible connection, if necessary.
head flanges. Gasket shrinkage and handling during
4-6 GB
035-19569-101 (0109)
Compressor lubricant piping and system external piping On units shipped disassembled, after installation of the
are factory installed on all units shipped assembled. control panel, control wiring must be completed between
On units shipped dismantled, the lubricant piping to oil unit components and control panel, solid state starter, or
sump and oil cooler and system oil return connections variable speed drive, when used, using wiring harness
should be completed, under the supervision of the York furnished. Refer to Form 160.73-N3.
representative, using material furnished. See Form
160.73-N3. Field wiring connections for control modifications (by
others) if required, are shown on Form 160.73-PW7.
4.16 Control Panel Positioning
(See Figure 4.5) No deviations in unit wiring from that shown on drawings
delivered shall be made without prior approval of the
On units with H9 and K1-K7 compressors, the control York representative.
panel is placed in a position above the evaporator for
shipping. For units with P and Q compressors the control 4.18 Power Wiring
panel is not adjustable. To move the control panel into
position for operation, proceed as follows: Chiller with Electro-Mechanical Starter
1. While supporting the control panel, remove the A 115 V, 1 Ø, 50 Hz supply of 15 amperes must be
hardware between the support arms and the supplied to the control panel, from the control transformer
evaporator. (2 kVA required) included with the compressor motor
starter. DO NOT make final power connections to control
2. Swing the control panel into a vertical position. centre until approved by York representative.
3. Slide the control panel down the guide rails to the Oil Pump – 3 Phase Starter
proper position. Tighten securely.
Separate wiring or a fused disconnect switch should be
4. Discard unused hardware. supplied by the installer.
GB 4-7
035-19569-101 (0109)
4-8 GB
035-19569-101 (0109)
CAUTION
GB 5-1
035-19569-101 (0109)
5-2 GB
035-19569-101 (0109)
To prevent overheating of the oil in the event of a control 6.3 Start-up Procedure
centre component failure, the oil heater thermostat
(1HTR) is set to open at 82°C. 6.3.1 Pre-Starting
Prior to starting the chiller, observe the graphic control
centre (OptiView). Make sure the display reads SYSTEM
READY TO START.
GB 6-1
035-19569-101 (0109)
6.3.2 Start-up
1. If the chilled water pump is manually operated, start 1. The control centre display message will read
the pump. The control centre will not allow the chiller SYSTEM PRELUBE for the first 50 seconds of the
to start unless chilled liquid flow is established through starting sequence.
the unit. (A field supplied chilled water flow switch is
required.) If the chilled liquid pump is wired to the 2. The oil pump will start to circulate oil for a 50 second
graphic control centre the pump will automatically pre-run to establish oil flow and adequate lubrication
start. to all bearings, gears, and rotating surfaces within
the compressor. The high and low oil pressure
2. To start the chiller, press the compressor START (3) transducers (OP) and the oil temperature sensor
switch. This switch will automatically spring return (RT3) will sense any malfunction in the lubrication
to the RUN (I) position. When the start switch is system.
energised, the control centre is placed in an operating
mode and any fault will be shown by a display 3. The anti-recycle timer software function will operate
message. after the 50 seconds of pre-run time. At this time,
the timer will be initiated and will run for 30 minutes
Any faults which occur during STOP/RESET after the compressor starts. If the chiller shuts down
are also displayed. during this period of time, it cannot be started until
the timer completes the 30 minute cycle.
CAUTION
When the chiller starts, the following automatic 6. For display messages and information pertaining
sequences are initiated: (Refer to Figures 6.2 and 6.3, to operation, refer to the Graphic Control Centre
Chiller Starting & Shutdown Sequence). (OptiView )Operating Instructions (160-54-OI).
6-2 GB
035-19569-101 (0109)
** Not for all shutdowns. Refer to Graphic Control Centre Operating Instructions.
** Not for all shutdowns. Refer to Graphic Control Centre Operating Instructions.
GB 6-3
035-19569-101 (0109)
After the compressor reaches operating speed, the pre- An accurate record of system operating conditions
rotation vanes will begin to open under the control of the (temperatures and pressures) recorded at regular
microprocessor which senses the leaving chilled liquid intervals throughout each 24 hour operating period
temperature. The unit capacity will vary to maintain the should be kept. An optional status printer is available
leaving CHILLED LIQUID TEMPERATURE SETPOINT. for this purpose using automatic data logging after
The pre-rotation vanes are modulated by an actuator programming the DATA LOGGER function.
under the control of the microprocessor. The vane control
routine employs proportional plus derivative (rate) control The record of readings serves as a valuable reference
action. A drop in chilled liquid temperature will cause for operating the system. Readings taken when a system
the actuator to close the pre-rotation vanes to decrease is newly installed will establish normal conditions with
chiller capacity. When the chilled liquid temperature which to compare later readings.
rises, the actuator will open the pre-rotation vanes to
increase the capacity of the chiller. For example, an increase in condenser water temperature
difference (leaving condenser water temperature minus
However, the current draw (A) of the compressor motor entering condenser water temperature) may be an
cannot exceed the setting of the % CURRENT LIMIT at indication of dirty condenser tubes.
any time during the unit operation. The microprocessor
40% to 100% three-phase peak current limit software 6.6 Maintenance and Service
function, plus the 3-phase 100% solid state overload
If the system is malfunctioning or the unit is stopped by
current limiter (CM-2), on Electro-Mechanical Starter
one of the safety controls, consult Section 8. After repair
applications, or the Solid State Starter current limit
or adjustment the compressor cannot be started or the
function will override the temperature control function
particular fault continues to affect the performance of the
and prevent the pre-rotation vanes from opening beyond
unit, please call the nearest York Office. Failure to report
the % CURRENT LIMIT setting.
constant troubles could damage the unit and increase
the cost of repairs.
If the load continues to decrease, after the pre-rotation
vanes are entirely closed, the chiller will be shut down by
6.6.1 Normal and Safety System Shutdowns
the Leaving Chilled Liquid – Low Temperature Control.
Normal and safety system shutdowns have been built into
6.4.1 Condenser Water Temperature Control the unit to protect it from damage during certain operating
conditions. The system will be stopped automatically
The unit is designed to use less power by taking
by controls that respond to high temperatures, low
advantage of lower than design temperatures that are
temperatures, and low and high pressures, etc.
naturally produced by cooling towers throughout the
operating year. Exact control of condenser water such
as a cooling tower bypass, is not necessary for most
installations. The chiller requires only that the minimum
condenser water temperature be no lower than the value
determined by referring to the formula below:
Where:
6-4 GB
035-19569-101 (0109)
GB 6-5
035-19569-101 (0109)
6-6 GB
035-19569-101 (0109)
The graphic control centre (OptiView) can be programmed If the chiller is to be shut down for an extended period of
to start and stop automatically (maximum, once each time (for example, over the winter season), the following
day) whenever desired. To stop the chiller, proceed as paragraphs detail the procedure to be followed.
follows:
1. Test all system joints for refrigerant leaks with a
1. Push the compressor STOP/RESET(O) switch. The leak detector. If any leaks are found, they should be
compressor will stop automatically. The oil pump will repaired before allowing the system to stand for a
continue to run for shutdown period. The oil pump long period of time.
will then stop automatically.
During long idle periods, the tightness of the system
2. Stop the chilled water pump (if not wired into the should be checked periodically.
graphic control centre, in which case it will shut off
automatically simultaneously with the oil pump.) (The 2. If freezing temperatures are encountered while the
actual water pump contact operation is dependent system is idle, carefully drain the water from the
upon the position of the microprocessor board jumper cooling tower, condenser, condenser pump, and the
J54.) chilled water system, chilled water pump and coils.
3. Open the switch to the cooling tower fan motors, if Open the drains on the evaporator and condenser
used. liquid heads to assure complete drainage. (If a
Variable Speed Drive is fitted, drain its water cooling
4. The compressor sump oil heater (thermostatically system. If a Solid State Starter is fitted drain water
controlled) is energised when the unit is stopped. from starter cooling loop).
GB 6-7
035-19569-101 (0109)
6-8 GB
035-19569-101 (0109)
7.1.2 Daily
1. Check graphic control centre (OptiView) displays.
GB 7-1
035-19569-101 (0109)
COMPRESSOR
SOLENOID VALVE
CONDENSER
EVAPORATOR
SOLENOID VALVE
STOP VALVE
c. Lubricate ball bearings. 3. The nozzle of the eductor should be checked for any
foreign particles that may be obstructing the jet.
4. Inspect and service electrical components as
necessary. 4. Assemble the new filter-drier.
5. Perform chemical analysis of system. 5. Open condenser stop valve and check dehydrator
connections for refrigerant leaks.
7-2 GB
035-19569-101 (0109)
The nominal oil charge for the compressor is 75.7 litres, 4. As soon as oil charging is complete, restore the power
of York “K” oil. Only York “K” refrigeration oil must be supply to energise the oil heater. This will keep the
used in the centrifugal compressor. Since oil absorbs concentration of refrigerant in the oil to a minimum.
moisture when exposed to the atmosphere, it should be
kept tightly capped until used. When the oil reservoir is initially charged with
oil, the oil pump should be started manually to
7.3.1 Oil Charging Procedure fill the lines, passages, oil cooler and oil filter.
CAUTION This will lower the oil level in the reservoir. It will
The compressor oil level must be maintained between
then be necessary to add oil to bring the level
the oil reservoir’s upper and lower sight glasses. If the
back to the centre of the upper sight glass.
oil level falls into the lower sight glass, it is necessary to
add oil to the compressor oil reservoir. The oil should be
charged into the oil reservoir using the an oil charging 7.4 Refrigerant Charge
pump(Part No. 070-10654). To charge oil into the oil
The refrigerant system is pressure tested and evacuated
reservoir, proceed as follows:
at the factory.
1. The unit must be shut down.
7.4.1 Checking The Refrigerant Charge
2. Immerse the suction connection of the oil charging The refrigerant level should have been observed
pump in a clean container of new oil and connect the and the level recorded after initial charging. With
pump discharge connection to the oil charging valve the correct charge the level should visible in the
(A) located on the oil reservoir cover plate. (figure sight glass.
7.2). Do not tighten the connection at the charging
valve until after the air is forced out by pumping a few The refrigerant charge should always be
strokes of the oil pump. This fills the lines with oil and checked and trimmed when the system is shut
prevents air from being pumped into the system. down.
NOTE
3. Open the oil charging valve and pump oil into the
system until oil level in the compressor oil reservoir The refrigerant charge level must be checked after the
is about midway in the upper sight glass. Then, pressure and temperature have equalised between the
close the charging valve and disconnect the hand condenser and evaporator. This would be expected
oil pump. to be 4 hours or more after the compressor and water
pumps are stopped.
GB 7-3
035-19569-101 (0109)
7-4 GB
035-19569-101 (0109)
GB 7-5
035-19569-101 (0109)
Condenser trouble due to fouled tubes is usually If the tubes are fouled with a hard scale deposit, they
indicated by a steady rise in head pressure, over a period may require acid cleaning. It is important that before acid
of time, accompanied by a steady rise in condensing cleaning, the tubes be cleaned by the brushing process
temperature, and noisy operation. These symptoms may described above. If the relatively loose foreign material is
also be due to foul gas build-up. Purging will remove the removed before the acid cleaning, the acid solution will
foul gas revealing the effect of fouling. have less material to dissolve and flush from the tubes
with the result that a more satisfactory cleaning job will
Tube Fouling be accomplished with a probable saving of time.
Fouling of the tubes can be due to deposits of two types Acid cleaning should only be performed by an expert.
as follows: Please consult your local water treatment representative
for assistance in removing scale build-up and preventative
1. Rust or sludge - which finds its way into the tubes maintenance programs to eliminate future problems.
and accumulates there. This material usually does
not build up on the inner tube surfaces as scale, 7.5.4 Tube Leaks
but does interfere with the heat transfer. Rust or
Evaporator and condenser tube leaks may result in
sludge can generally be removed from the tubes by
refrigerant leaking into the water circuit, or water leaking
a thorough brushing process.
into the shell depending on the pressure levels. If
2. Scale - due to mineral deposits. These deposits, refrigerant is leaking into the water, it can be detected
even though very thin and scarcely detectable upon at the liquid head vents after a period of shutdown. If
physical inspection, are highly resistant to heat water is leaking into the refrigerant, system capacity and
transfer. They can be removed most effectively by efficiency will drop off sharply.
circulating an acid solution through the tubes.
If a tube is leaking and water has entered the system,
the evaporator and condenser should be valved off from
7.5.3 Tube Cleaning Procedures
the rest of the water circuit and drained immediately to
Brush Cleaning of Tubes prevent severe rusting and corrosion. The refrigerant
system should then be drained and purged with dry
If the tube consists of dirt and sludge, it can usually be nitrogen to prevent severe rusting and corrosion. If a
removed by means of the brushing process. Drain the tube leak is indicated, the exact location of the leak may
water sides of the circuit to be cleaned (cooling water or be determined as follows:
chilled water) remove the heads and thoroughly clean
each tube with a soft bristle bronze or nylon brush. DO 1. Remove the heads and listen at each section of tubes
NOT USE A STEEL BRISTLE BRUSH. A steel brush for a hissing sound that would indicate gas leakage.
may damage the tubes. This will assist in locating the section of tubes to be
further investigated. If the probable location of the
Improved results can be obtained by admitting water into leaky tubes has been determined, treat that section
the tube during the cleaning process. This can be done in the following manner (if the location is not definite,
by mounting the brush on a suitable length of 1/8" pipe all the tubes will require investigation).
with a few small holes at the brush end and connecting
the other end by means of a hose to the water supply. 2. Wash off both tube heads and the ends of all tubes
with water.
The tubes should always be brush cleaned
before acid cleaning. 3. With nitrogen or dry air, blow out the tubes to clear
them of traces of refrigerant laden moisture from the
NOTE
circulation water. As soon as the tubes are clear,
a cork should be driven into each end of the tube.
Pressurise the dry system with 350 to 690 kPag of
nitrogen. Repeat this with all of the other tubes in the
suspected section or, if necessary, with all the tubes
in the evaporator or condenser. Allow the evaporator
or condenser to remain corked up to 12 to 24 hours
before proceeding. Depending upon the amount of
leakage, the corks may blow from the end of a tube,
indicating the location of the leakage. If not, it will be
necessary to make a very thorough test with the leak
detector.
7-6 GB
035-19569-101 (0109)
4. After the tubes have been corked for 12 to 24 hours, 2. Oil Changing - The oil in the compressor must be
it is recommended that two men working at both changed annually or earlier if it becomes dark or
ends of the evaporator carefully test each tube – one cloudy. However, quarterly oil analysis can eliminate
man removing corks at one end and the other at the the need for an annual change provided the analysis
opposite end to remove corks and handle the leak indicates there is no problem with the oil.
detector. Start with the top row of tubes in the section
being investigated. Remove the corks at the ends 7.7 Compressor Motor
of one tube simultaneously and insert the exploring
tube for 5 seconds – this should be long enough to 1. Check motor mounting screws frequently for
draw into the detector any refrigerant gas that might tightness.
have leaked through the tube walls. A fan placed at
the end of the evaporator opposite the detector will 2. Check motor winding insulation annually for
assure that any leakage will travel through the tube deterioration of windings.
to the detector.
3. For the lubrication instructions, refer to the motor
5. Mark any leaking tubes for later identification. manual
7.6 Compressor
GB 7-7
035-19569-101 (0109)
1. All electrical controls should be inspected for With the main disconnect switch and compressor motor
obvious malfunctions. starter open, test the motor as follows:
2. It is important that the factory settings of controls 1. Test the insulation, using a megohm meter (megger),
(operation and safety) are not changed. If the settings between phases and each phase and ground (see
are changed without York approval, the warranty will be figure 7.4); these readings are to be interpreted using
invalidated. the graph shown in figure 7.5.
For information covering the graphic control centre 2. If readings fall below shaded area, remove external
(OptiView) operation, refer to manual 160.54-O1. leads from motor and repeat test.
7-8 GB
035-19569-101 (0109)
8 TROUBLSHOOTING
GB 8-1
035-19569-101 (0109)
8-2 GB
035-19569-101 (0109)
9 TECHNICAL DATA
9.1 Dimensions
P and Q Compressors
COMPRESSOR
OPTIVIEW
MOTOR
CONTROL CENTER
J2 H2
B4,5
EVAP
CONDENSER
E C D
G2 F2 A
(EVAP) (EVAP) (SHIPPING WIDTH) M
P8 COMPRESSOR Q5 COMPRESSOR
EVAPORATOR-CONDENSER SHELL CODES EVAPORATOR-CONDENSER SHELL CODES
G-E H-F J-J L-L C-C D-D E-E F-F
A 2108 2108 2299 2299 A 1676 1676 2134 2134
B 3200 3200 3327 3327 B 2403 2403 2578 2578
C 610 610 641 641 C 445 445 495 495
D 445 445 508 508 D 394 394 445 445
E 3658 4877 3658 4877 E 3658 4877 3658 4877
P9 COMPRESSOR Q6 COMPRESSOR
EVAPORATOR-CONDENSER SHELL CODES EVAPORATOR-CONDENSER SHELL CODES
H-F J-J L-L E-E F-F
A 2108 2299 2299 A 2134 2134
B 3124 3264 3264 B 2515 2515
C 610 641 641 C 495 495
D 445 508 508 D 445 445
E 4877 3658 4877 E 3658 4877
GB 9-1
035-19569-101 (0109)
H Compressors
178
H9 COMPRESSORS
EVAP.-COND.SHELL CODES
K-K M-M
A 2299 2616
B 3150 3315
C 641 724
D 508 584
E 4267 4267
NOTES:
1. All dimensions are approximate. Certified dimensions are available on request.
2. For all water boxes (compact shown above), determine overall unit length by adding water box depth to tube sheet length.
3. Water nozzles can be located on either end of unit. Add 13 mm to nozzle length for flanged connections.
4. To determine overall height, add dimension "M" for the appropriate isolator type.
5. Use of motors with motor hoods may increase overall unit dimensions.
9-2 GB
035-19569-101 (0109)
K Compressors
COMPRESSOR
MOTOR
OPTIVIEW
CONTROL CENTER
J2 H2
B1,5
EVAP
CONDENSER
E C A D
G2 F2 M
(EVAP) (EVAP) (SHIPPING WIDTH)
7”
NOTES:
1. All dimensions are approximate. Certified dimensions are available on request.
2. For all water boxes (compact shown above), determine overall unit length by adding water box depth to tube sheet length.
3. Water nozzles can be located on either end of unit. Add 13 mm to nozzle length for flanged connections.
4. To determine overall height, add dimension "M" for the appropriate isolator type.
5. Use of motors with motor hoods may increase overall unit dimensions.
6. Tubesheets are provided with jacking point notches on P and larger shells.
GB 9-3
035-19569-101 (0109)
G
F
F F
9-4 GB
035-19569-101 (0109)
A to K Evaporators
1-PASS
FRONT
OF NOZZLE
EVAP. UNIT EVAP. ARRANGEMENTS
NO. OF EVAPORATOR
A H PASSES IN OUT
A H
AA AA 1
H A
M C C M
COMPRESSOR END FLOOR LINE MOTOR END
2-PASS
FRONT
EVAP. OF EVAP.
UNIT NOZZLE
B J ARRANGEMENTS
NO. OF EVAPORATOR
DD C K DD PASSES IN OUT
BB BB C B
2 K J
M C C M
FLOOR LINE MOTOR END
COMPRESSOR END
3-PASS
FRONT
EVAP. OF EVAP.
UNIT NOZZLE
F N ARRANGEMENTS
NO. OF EVAPORATOR
DD G P DD PASSES IN OUT
BB BB G N
3 P F
M C C M
FLOOR LINE
COMPRESSOR END MOTOR END
GB 9-5
035-19569-101 (0109)
1 PASS
FRONT
OF
UNIT
SHELL 1 PASS
CODE IN OUT
A H
A H
M–Z
AA AA H A
M C C M
COMPRESSOR END FLOOR MOTOR END
LINE
2 PASS
FRONT
OF
UNIT SHELL 2 PA SS
CODES IN OUT
B C J K B C
C B
AA AA M–Z
J K
K J
M C C M
EE EE FLOOR EE EE
3 PASS
FRONT
OF
UNIT
SHELL 3 PA SS
CODES IN OUT
? ?
F N
M–Z
AA AA N F
M C C M
FLOOR
COMPRESSOR END LINE MOTOR END
9-6 GB
035-19569-101 (0109)
H H
J
H
H H
GB 9-7
035-19569-101 (0109)
FRONT
OF UNIT
1-PASS
NOZZLE
P Q ARRANGEMENTS
NO. OF COND.
CC CC PASSES IN OUT
FLOOR P Q
COND. COND. 1
LINE Q P
M D D M
COMPRESSOR END MOTOR END
FRONT
OF UNIT
2-PASS
S U
NOZZLE
ARRANGEMENTS
R T
DD DD NO. OF COND.
PASSES IN OUT
BB BB
FLOOR R S
2
COND. LINE COND. T U
M D D M
FRONT
OF UNIT 3-PASS
NOZZLE
W Y
ARRANGEMENTS
V X NO. OF COND.
DD DD PASSES IN OUT
V Y
BB BB 3
FLOOR X W
COND. LINE COND.
M D D M
COMPRESSOR END MOTOR END
9-8 GB
035-19569-101 (0109)
1-PASS
FRONT OF UNIT FRONT OF UNIT
C C C C
IN 1 6 OUT 1 6 IN
OUT
P P
COMPRESSOR END M MOTOR END FLOOR LINE COMPRESSOR END MOTOR END FLOOR LINE
M
2-PASS
FRONT OF UNIT FRONT OF UNIT
R C C R
8 OUT 3 OUT
IN
IN P P
7 2
Q Q
COMPRESSOR END MOTOR END FLOOR LINE COMPRESSOR END M MOTOR END FLOOR LINE
M
4 10
OUT OUT
IN
P IN P
9 5
Q Q
COMPRESSOR END M MOTOR END FLOOR LINE COMPRESSOR END MOTOR END FLOOR LINE
M
GB 9-9
035-19569-101 (0109)
EVAPORATOR
1-PASS
IN OUT
1 6
6 1
EVAPORATOR
2-PASS
IN OUT
EVAP SHELL 1-PASS 2-PASS 3-PASS
2 3
CODE F I F G I F I
7 8
A 483 222 432 165 197 432 197
C,D 578 270 524 178 241 524 241
E,F 654 308 559 191 260 559 260
G,H 660 302 572 286 260 572 260
J,K,L 686 314 597 241 268 597 267
M,N 762 343 660 308 292 660 292
P,Q 762 343 660 343 292 660 292
QT,QV 813 368 711 343 318 711 318
R,S,W 813 371 762 368 346 762 346
EVAPORATOR X,Z 838 371 762 394 346 762 346
3-PASS
IN OUT
5 10
9 4
NOTES:
1. All dimensions are approximate. Certified dimensions are available upon request.
2. Standard water nozzles are Schedule 40 pipe size, furnished as welding stub-outs with Victaulic grooves, allowing the option of welding, flanges,
or use of Victaulic couplings. Factory-installed, class 150 (ANSI B16.5, round slip-on, forged carbon steel with 1.6 mm raised face), water flanged
nozzles are optional (add 13 mm to nozzle length). Companion flanges, nuts, bolts, and gaskets are not furnished.
3. One-, two-, and three-pass nozzle arrangements are available only in pairs shown and for all shell codes. Any pair of evaporator nozzles
may be used in combination with any pair of condenser nozzles. Compact water boxes on one heat exchanger may be used with Marine
Water Boxes on the other heat exchanger.
4. Water must enter the water box through the bottom connection to achieve rated performance.
5. Add dimension "M" as shown on the unit dimensions page for the appropriate isolator type.
9-10 GB
035-19569-101 (0109)
IN 11 OUT 16 OUT 11 IN 16
S S
CL CL CL
FLOOR FLOOR
M LINE M M LINE M
COMPRESSOR END MOTOR END COMPRESSOR END MOTOR END
18 OUT 13 OUT
IN
IN
S 17 12 S
T T CL
CL
FLOOR U FLOOR
M U M M M
LINE LINE
COMPRESSOR END MOTOR END COMPRESSOR END MOTOR END
20 OUT
OUT 14
IN IN
15 S S 19
T T
CL CL CL CL
FLOOR FLOOR U
M U M M LINE M
LINE
COMPRESSOR END MOTOR END COMPRESSOR END MOTOR END
GB 9-11
035-19569-101 (0109)
J (2-PASS
H RETURN HEAD)
CONDENSER
2-PASS
IN OUT
12 13
17 18
NOTES:
1. All dimensions are approximate. Certified dimensions are available upon request.
2. Standard water nozzles are Schedule 40 pipe size, furnished as welding stub-outs with Victaulic grooves, allowing the option of welding,
flanges, or use of Victaulic couplings. Factory-installed, class 150 (ANSI B16.5, round slip-on, forged carbon steel with 1.6 mm raised face),
water flanged nozzles are optional (add 13 mm to nozzle length). Companion flanges, nuts, bolts, and gaskets are not furnished.
3. One-, two-, and three-pass nozzle arrangements are available only in pairs shown and for all shell codes. Any pair of evaporator nozzles
may be used in combination with any pair of condenser nozzles. Compact water boxes on one heat exchanger may be used with Marine
Water Boxes on the other heat exchanger.
4. Condenser water must enter the water box through the bottom connection for proper operation of the sub-cooler to achieve rated performance.
5. Add dimension "M" as shown on the unit dimension page for the appropriate isolator type.
9-12 GB
035-19569-101 (0109)
GB 9-13
035-19569-101 (0109)
9-14 GB
PT ZT
042 040
GB
1 YORK CLIENT YORK
CUSTOMER
OY TE
040 13 010 +12 °C
YORK CLIENT YORK
CUSTOMER TE TE
031 091 YORK CLIENT
PSV PSV CUSTOMER
031 032 11
9.10 Process and Instrumentation Diagram
PSH
030
PT
030
8 INSTRUMENTATION
PW LCV Expansion valve
030 6 LT Level transmitter
TE
094 MPH Oil motor pump
S32
+32 °C
OH Oil heater
OY Solenoid valve
SG
3-4 030 PRV Prerotation vanes
WATER
TCV PT Pressure transducer
030
+27 °C
PT PSH High pressure cut out
041 7
TE PSV Safety valve
CLIENT YORK 093
CUSTOMER LT PW Pressure tapping
OH TSH
030 040 040 SG Sight glass
VALVES SG SG TE Temperature sensor
041 042 MPH
S10 Service valves for TE 8 040 TCV Thermostatic valve
TE
032 040 LCV TSH Temperature safety
S31 refrigerant charging / 030
S32 removing ZSL PRV closed position switch
S31
ZT Bearing proximity probe
The P & I Diagram may vary according to the compressor and the options. This one is only an example based on a chiller with H5 compressor and without any options.
035-19569-101 (0109)
9-15
035-19569-101 (0109)
9-16 GB
035-19569-101 (0109)
10 SPARE PARTS
GB 10-1
035-19569-101 (0109)
10-2 GB
035-19569-101 (0109)
Never discard used compressor oil, as it Reference should be made to Section 4 for unit
contains refrigerant in solution. Return installation instructions, Section 9 for unit weights and
used oil to the oil manufacturer. Section 3 for handling.
WARNING
Isolate all sources of electrical supply to the unit Residual solution, refrigerant, oil and glycol or
including any control system supplies switched by the similar fluids may remain in some parts of the
unit. Ensure that all points of isolation are secured in system. These should be mopped up and disposed
the "OFF" position. The supply cables may then be of as described above.
disconnected and removed. For connection points refer
to Section 4. It is important to ensure that whilst components are
being removed the remaining parts are supported in a
Remove all refrigerant from the unit into a suitable safe manner.
container using a refrigerant reclaim or recovery unit.
This refrigerant may then be re-used, if appropriate, Only use lifting equipment of adequate
or returned to the manufacturer for disposal. Under capacity.
NO circumstances should refrigerant be vented to
WARNING
atmosphere. Drain the oil from the unit into a suitable
container and dispose of according to local laws and
regulations governing the disposal of oily wastes. Any After removal from position the unit parts may be
spilt oil should be mopped up and similarly disposed disposed of according to local laws and regulations.
of.
GB 11-1
035-19569-101 (0109)
11-2 GB
www.johnsoncontrols.com