12 Unsignalized Intersection Analysis: 12.1 Purpose
12 Unsignalized Intersection Analysis: 12.1 Purpose
12 Unsignalized Intersection Analysis: 12.1 Purpose
12.1 Purpose
This chapter presents commonly used unsignalized intersection deterministic analysis procedures
and identifies specific methodologies and input parameters to be used on ODOT projects.
Simulation procedures are covered in APM v1 Chapter 8. Software settings are covered in
Appendix 12/13. Topics covered include:
• Turn Lane Criteria
• Unsignalized Intersection Capacity Analysis
• Traffic Signal Warrants
• Estimating Vehicle Queue Lengths at Unsignalized Intersections
For software-specific settings and parameters for unsignalized intersection analysis, refer to
Appendix 12/13.
Purpose: A left turn lane improves safety and increases the capacity of the roadway by reducing
the speed differential between the through and the left turn vehicles. Furthermore, the left turn
lane provides the turning vehicle with a potential waiting area until acceptable gaps in the
opposing traffic allow them to complete the turn. Installation of a left turn lane must be
consistent with the access management strategy for the roadway.
The criterion is not met from zero to ten left turn vehicles per hour, but indicates that careful
consideration be given to installing a left turn lane due to the increased potential for rear-end
collisions in the through lanes. While the turn volumes are low, the adverse safety and operations
impacts may require installation of a left turn. The final determination will be based on a field
study.
Evaluation Guidelines
1. The evaluation should indicate the installation of a left turn lane will improve the overall
safety and/or operation of the intersection and the roadway. If these requirements are not met,
the left turn lane should not be installed or, if already in place, not allowed to remain in
operation.
2. Alternatives Considered: List all alternatives that were considered, including alternative
locations. Briefly discuss alternatives to the left turn lane considered to diminish
congestion/delays resulting in criteria being met.
3. Access Management: Address access management issues such as the long term access
management strategy for the state roadway, spacing standards, other accesses that may be
located nearby, breaks in barrier/curb, etc.
4. Land Use Concerns: Include how the proposed left turn lane addresses land use concerns
and transportation plans.
5. Plan: Include a plan or diagram of proposed location of left turn lane.
6. Operational Requirements: Consider storage length requirements, deceleration distance,
• Northbound: The northbound advancing volume is 40 + 200 + 300 + 15 = 555, and the
southbound opposing volume is 515 vehicles (the opposing left turns are not counted as
opposing volumes). The volume for the y-axis on Exhibit 12-1 is determined using the
equation:
To determine if the northbound left turn volume criterion is met, use the 45 mph
curve in Exhibit 12-1, 535 for the y-axis and 15 left-turns for the x-axis. The
volume criterion is not met in the northbound direction.
• Southbound: The southbound advancing volume is 90 + 250 + 200 + 15 = 555, and the
northbound opposing volume is 540 vehicles (the opposing left turns are not counted as
opposing volumes). The volume for the y-axis on Exhibit 12-1 is (555/2+ 540/2) = 548.
To determine if the southbound left turn volume criterion is met, use the 45 mph curve in
Exhibit 12-1, 548 for the y-axis and 40 left-turns for the x-axis. The volume criterion is
met in the southbound direction.
Not all intersections that meet the siting criteria below should have a right turn lane
installed. Refer to APM Chapter 10 for modal considerations for right turn lanes,
and to Chapter 14 for multimodal analysis procedures such as MMLOS. The need
for other evaluations such as per the Traffic Manual and HDM should be
coordinated with Region Roadway/Traffic or Traffic-Roadway Section.
Purpose
The purpose of a right turn lane at an unsignalized intersection is to improve safety and to
maximize the capacity of a roadway by reducing the speed differential between the right turning
vehicles and the other vehicles on the roadway.
1. A right turn lane should be installed, if criterion 1 (Volume) or 2 (Crash) or 3 (Special Cases)
are met, unless a subsequent evaluation eliminates it as an option; and
2. The Region Traffic Engineer must approve all proposed right turn lanes on state highways,
regardless of funding source; and
3. The right turn lane complies with Access Management Spacing Standards; and
4. The right turn lane conforms to applicable local, regional and state plans.
Note: If there is no right turn lane, a shoulder needs to be provided. If this intersection is in a
rural area and is a connection to a public street, a right turn lane is needed.
1. Adequate trial of other remedies with satisfactory observance and enforcement has failed to
reduce the accident frequency; and
2. A history of crashes of the type susceptible to correction by a right turn lane; and
3. The safety benefits outweigh the associated improvements costs; and
4. The installation of the right turn lane minimizes impacts to the safety of vehicles, bicycles or
pedestrians along the roadway.
1. Railroad Crossings: If a railroad is parallel to the roadway and adversely affects right turns,
a worst case scenario should be used in determining the storage requirements for the right
turn lane design. The right turn lane storage length depends on the amount of time the
roadway is closed, the expected number of vehicle arrivals and the location of the crossing or
other obstruction. The analysis should consider all of the variables influencing the design of
the right turn lane and may allow a design for conditions other than the worst case storage
requirements, providing safety is not compromised.
Evaluation Guidelines
1. The evaluation should indicate the installation of a right turn lane will improve the overall
safety and/or operation of the intersection and the roadway. If these requirements are not met,
the right turn lane should not be installed or, if already in place, should be reevaluated for
continued use.
2. Alternatives Considered: List all alternatives that were considered, including alternative
locations. Briefly discuss alternatives to the right turn lane considered to diminish
congestion/delays resulting in criteria being met.
3. Access Management: Address access management issues such as the long term access
management strategy for the state roadway, spacing standards, other accesses that may be
located nearby, breaks in barrier/curb, etc.
4. Land Use Concerns: Include how the proposed right turn lane addresses land use concerns
and transportation plans.
5. Plan: Include a plan or diagram of proposed location of right turn lane.
6. Operational Requirements: Consider storage length requirements, deceleration distance,
desired alignment distance, etc. For signalized intersections, installing a right turn lane must
be consistent with the requirements in the Traffic Signal Guidelines.
The southbound outside lane has 600 through vehicles and 90 right turning vehicles for a total of
690 vehicles. Using the 45 mph curve in Exhibit 12-2, along with 690 approaching vehicles and
90 right turning vehicles we find that the vehicular volume criterion is met.
Refer to OHP Action 1F.1 for clarification on how the OHP mobility targets are
applied at different segment and intersection facilities. Different OHP v/c ratio
targets apply to mainline versus minor approaches. HDM v/c ratios apply to all
approaches as they do not specify minor or mainline.
If operational performance measure targets or criteria indicate a need, such as where the minor
approach exceeds the v/c ratio target, the analyst needs to investigate multiple traffic control type
solutions from lowest impact to highest. Potential solutions that could be considered range from,
but are not limited to additional channelization, changes to lane alignments/designations,
conversion to all-way stop, realignment, roundabout, and j turns as well as more intensive
solutions such as signals and grade separations. Supplemental operational measures and
considerations also come into play. Volume to capacity ratio is just one factor. Other operational
factors to be investigated include multimodal considerations, safety and crash history, Level of
Service and delay, sight distance, conflict points, functional area adequacy, and availability of
alternate routes. The decision making process may involve an intersection control evaluation
and/or a design exception process. For further guidance on solution development, refer to
Chapter 10.
For a sketch planning level estimation of future traffic control needs, the Planning & Preliminary
Engineering Applications Guide (PPEAG) provides a graphical method as shown in Exhibits
12-3 and 12-4. Refer to the PPEAG for guidance on appropriate use of this method.
For two-way stop control, the HCM employs a procedure for analyzing unsignalized
intersections that is primarily based on an established hierarchy of intersection movements
(based on assigned ROW) and a gap acceptance model. The major components of the gap
acceptance model include the critical gap and follow-up time; where the critical gap is the
minimum time interval in the major street traffic stream that allows intersection entry for one
minor street vehicle and the follow-up time is the time between the departure of one vehicle from
the minor street and the departure of the next vehicle using the same major street gap under a
condition of continuous queuing on the minor street. A simplified planning level analysis method
is available in the PPEAG, including a simplified spreadsheet tool.
At two-way stop intersections, the controlling movement (usually a minor street left turn) often
controls the overall intersection performance. Therefore, the v/c ratio for that movement will
typically be the one reported and evaluated against the adopted mobility standard. This is
especially important to recognize when analyzing two-way stop-controlled intersections where
the very low v/c ratios for the unimpeded, high-volume major street movements will overshadow
the higher v/c ratios for the lower-volume minor street movements. In these situations the
unimpeded v/c ratio is often very low, even though the minor street movements are near or over
capacity. However, as there may be times when the mainline v/c ratio is near the mobility
standard, it should always be acknowledged before deferring to minor street movements. For
ODOT facilities, the mainline through movement v/c ratio should be reported, as programs
generally only report out minor v/c and mainline left.
The analyst should also check for heavy traffic flows that may occur in the opposite direction of
peak hour volumes. For example, a high volume right turn movement in the pm peak period can
be an indicator of a paired high volume left turn movement in the am peak period.
A right turn flare is where, on the stop controlled approach at a two-way stop controlled
intersection, a shared lane allows right-turning vehicles to complete their movement while other
vehicles are occupying the lane (see Exhibit 12-5). Current analysis
procedures/processes/software differ as to how a right turn flare on the minor street is analyzed
at unsignalized intersections.
The HCM 6, HCS and Vistro provide a method for directly coding and evaluating the capacity of
a flared right turn lane.
Synchro/SimTraffic and SIDRA do not allow directly for a flare, so in some cases it may be
appropriate to code in a separate (short) turn lane. However, Synchro and SIDRA both see the
If SimTraffic is being used, it may still be appropriate to include a scenario with a short turn lane
with an appropriate length taper measured from field conditions or from design guidance (i.e.,
HDM). This will reflect the impact of a flare in SimTraffic when modeling driver behavior and
vehicle characteristics for determining measures such as queuing and stop delay.
Engineering judgment is needed to determine when a right turn flare should be coded. There is
not a single way to analyze/report the v/c ratios since the factors above vary widely across
analysis areas. The analyst should observe operations in the field to understand existing usage.
Considerations include:
• Purpose: What is the purpose of the analysis – broad versus specific? Plan versus
project? What measures are needed? What is the correct effort for the work?
• Physical Conditions: Width, length, curbed section or not, available sight distance. A
flare may be created by a large radius to accommodate trucks. Are there other constraints
such as parking?
• Volumes: Total, turn moves
• Characteristics: Drivers, vehicles, traffic flow volumes, bicycles, pedestrians
• Operations – Are vehicles observed using/creating a flare? Is access to the flare blocked
by queues?
There are three ways to handle right turn flares for reporting v/c ratio:
1. The most conservative is to not code any flare (the outside lane is a full shared lane).
2. The most correct mathematical way is to input the data (directly or by importing) into the
HCM/HCS/Vistro unsignalized processes, and coding the flare to account for the partial
increase in capacity.
3. A third approach is to code the intersection both ways in HCM/HCS/Vistro and see if the
values are different enough to warrant reporting the difference (perhaps as a range).
When the decision is made to include the effects of a flare on an unsignalized intersection, the
analyst must use the HCM/HCS/Vistro process to report v/c ratios.
There is a limitation of the HCM unsignalized intersection methodology for shared left turn
approaches. Major street left turns are always treated as exclusive turn lanes regardless of how
they are coded. This can result in very low shared left turn v/c ratios (like 0.01) on an approach
that should be over capacity.
Shared major left turn vehicles are approximated in the HCM methodology by adjusting the
potential for a "queue-free state" in the case of delaying through movement vehicles. This
calculation ratchets down the through lane capacity (1700 for an unstopped lane) to reflect the
The resulting reported HCM v/c is the left turn volume divided by the capacity of the shared lane
for the lefts only. The v/c of the major street (non-stopped) left turn only reflects the left turn
volume regardless if it is in a shared or an exclusive lane (v/c = volume of left turns / shared lane
capacity). Other through movements and the stopped movements use the total lane volume
divided by the shared lane capacity to obtain v/c.
In most cases this won't make a difference as the minor approaches will tend to control.
However, in cases of small minor leg movements and a high volume on the mainline, the major
through or the major left will control.
To calculate the correct shared approach v/c requires that you add the through v/c (volume of
through vehicles divided by 1700) to the left turn v/c.
Software programs that follow HCM 2010/6th Edition report out a value for the v/c ratio for the
major left turn movement. However, this v/c is only of the left turn and does not include the
through movement.
Divide the major street flow rate (pcph) by 1700 pcph to obtain the v/c of the through movement.
In this case the northbound major street flow rate is 191 pcph.
Add the major left to the through movement to obtain the total reportable v/c:
An unsignalized intersection acceleration lane is an added lane for vehicles turning from a side
street at an at-grade intersection that allows the turning vehicle to accelerate from the turning
speed to highway speed, typically on rural limited access highways. The v/c ratio of intersection
acceleration lanes is performed using segment analysis. The worst v/c ratio is reported out of
either the upstream segment before the merge point, or of the downstream segment after the
merge point. Refer to Chapter 11 for segment v/c ratio calculation procedures. Additional
analysis of intersection acceleration lane operations may be performed using microsimulation.
Refer to Chapter 10 for general considerations on intersection acceleration lanes. An engineering
study, Roadway Design Exception, and State Traffic-Roadway Engineer approval is required for
A right turn acceleration lane is created in Synchro by coding a minor stop controlled approach
right turn movement with one Add Lane, entering the curb radius, and designating the sign
control as Free, Stop or Yield as appropriate. If the acceleration lane is a drop lane, a bend node
is coded at the end of the lane drop. This will draw an add lane on the departure side of the
intersection that will merge with the through travel lanes downstream. In the simulation window,
the lane alignment for through traffic is coded as L-NA so through vehicles do not enter the right
turn acceleration lane. Likewise, right turning traffic is coded as R-NA so right turn vehicles turn
into the acceleration lane and not the through lane. See Exhibit 12-6.
This coding does not provide a v/c ratio of the right turn acceleration lane. The v/c ratio analysis
is performed using segment analysis for a two-lane highway. The worst v/c ratio is reported out
of either the upstream segment before the merge point, or of the downstream segment after the
merge point. For a multilane highway a merge analysis would be performed.
A median acceleration lane is shown in Exhibit12-7. The acceleration lane drops downstream of
the intersection.
A left turn add lane is shown in Exhibit 12-8. This differs from the median acceleration lane in
that the added lane does not drop downstream of the intersection. This design requires a barrier
separating the through lane from the add lane.
A median acceleration lane or left turn add lane can be created in Synchro by coding the
movement as an Add Lane. Synchro provides a v/c ratio for the left turn into the median
acceleration lane using a non-HCM methodology. The segment downstream of the merge point
still needs to be evaluated using segment analysis, unless it is a left turn add lane where there is
no merge point.
For simulation of an add lane, Synchro includes a Lane Alignment setting to establish whether
vehicles are allowed to enter the added lane as they pass through an intersection or where
through movements need to stay in their own lane. For a median acceleration lane, to prevent
through vehicles from entering the median acceleration lane the movement is coded as R-NA.
The left out movement is coded as L-NA to force those vehicles to turn into the median
acceleration lane only. See Exhibits 12-9 and 12-10.
Synchro provides a TWLTL feature. With this feature Synchro assumes two-stage left turn out
from the minor approach at an intersection, as shown in Exhibit 12-11. This is coded by inputting
a Median Width and checking the TWLTL option. Two vehicles can be stored in the median.
This does not model driveway operations along a TWLTL. Synchro allows coding of TWLTL
operation at four-leg intersections – this configuration is only allowed at minor crossroads.
Under low volume conditions, two-way stop control (TWSC) is sufficient at most intersections.
However, in some circumstances AWSC may be justified, for example as a safety treatment or as
an interim improvement such as prior to installation of a roundabout or traffic signal. An
Intersection Traffic Control Study is required for multi-way stop installation. The ODOT Traffic
Manual contains guidance on the engineering study required for AWSC as well as the approval
process. AWSC requires approval of the State Traffic-Roadway Engineer.
The MUTCD contains threshold criteria for AWSC based on crashes or volumes. These are
guidelines rather than mandatory requirements. They should not be regarded as an absolute
minimum that must be met in order to consider AWSC.
For AWSC intersection operational analysis, the HCM procedure is based on an analysis of each
approach independently. The procedure determines the capacity of each approach, which is used
to calculate v/c ratios. The highest v/c ratio approach will be the one reported and evaluated
against the adopted mobility standard. Some programs report out only degree of saturation,
which should be assumed equivalent to v/c ratio. A simplified planning level analysis method is
available in the Planning & Preliminary Engineering Applications Guide. Refer to Chapter 10 for
guidance on the consideration of AWSC as a solution.
The HCM does not include methods for analysis of certain unsignalized intersections with
unusual configurations. These configurations can be analyzed using microsimulation, but
simulation does not produce a v/c ratio. SIDRA is the only program able to compute v/c ratios
for configurations such as allway stops with more than 4 legs, or non-standard stop sign
placement such as where the mainline turns at an intersection.
An HCM based workaround procedure to obtain an approximate v/c ratio can be done for a 4-leg
two-way stop intersection where the stop signs have non-standard placement by moving the
volumes to mimic an HCM analyzable configuration. An example is shown in Exhibit 12-12. In
this example, the highest volumes occur between the SB and EB approaches which are not
stopped, as shown in the Existing configuration. The WB and NB approaches are low volume
and are stopped. The workaround to analyze this configuration is to model the approaches having
the major flow as if they were opposite each other. This was done in the Adjusted for Analysis
configuration shown in Exhibit 12-12, where the EB and NB approaches were switched with
each other. Note that Exhibit 12-12 shows turn movements rather than actual lane configurations.
All movements still go to the same departure leg as in the Existing configuration. In other words,
the directional approach and departure volumes on each leg of the intersection remain
unchanged. The Adjusted for Analysis configuration can then be analyzed using HCM TWSC
methodology. Vistro version 6 or higher is able to automatically re-sort TWSC movements in
order to perform this type of workaround analysis as well.
The v/c ratios resulting from this method should be considered as approximate only. This method
can also be used as a way to estimate preliminary signal warrants. It should be noted that the
resulting volumes are only for approximating the analysis and should not be shown on flow
diagram figures.
WB WBR SB WBR
WBT WBL
EBL NBT
WBL WBT
EBT NBR
EBR EB NBL
EB
LEGS SWITCHED
The workaround described above does not work for T intersections where the stem leg is not
stopped while the other two legs are stopped. The v/c ratio for such a configuration can be
obtained using SIDRA, or can be approximated by analyzing the intersection under all-way stop
control, or by taking the average v/c ratio between AWSC and TWSC.
12.3.4 Roundabouts
Roundabouts are a safe and efficient intersection option with more free flow than a stop sign or
signal provides. Roundabouts can be a gateway or transition feature, roadway connection point,
or key element of an access management project. Research has shown roundabouts generally
reduce crashes and vehicle delay as compared to signals. Roundabouts have fewer conflict points
and severe injury crashes in comparison to other intersection designs.
For roundabouts on state highways, refer to the ODOT Traffic Manual and HDM for roundabout
guidelines, standards, siting criteria and the approval process. The State Traffic-Roadway
Engineer has been delegated the authority to approve the installation of roundabouts on State
Highways, which is divided into two phases: Conceptual Approval and Design Approval.
Unlike traffic signals, there are no roundabout warrants because roundabouts are intersection
designs and not traffic control devices. As such the decision to convert an intersection to a
roundabout is an engineering design decision and not a traffic control device decision.
Roundabout automobile capacity analysis generally follows the current HCM method. For
further information, refer to Roundabouts: An Informational Guide (1), Second Edition, also
Studies have shown that U.S. drivers use roundabouts more conservatively than international
drivers. Therefore, U.S. roundabout capacities are generally lower than international values.
Exhibit 12-13 (HCM 6 Exhibit 22-12) shows a single lane roundabout with an entry flow
conflicting with a circulatory flow. Please note the subscripts: “c” is for circulatory, “e” is for
entry, and “ex” is for exiting flow. Entry vehicles yield to circulatory vehicles.
Bicycles that enter the roundabout as a vehicle should be included in the intersection volumes for
each movement (including U-turns).
Use HCM 6 Equation 22-8 to find the demand flow rate for each movement.
𝑉𝑉𝑖𝑖
𝑣𝑣𝑖𝑖 =
𝑃𝑃𝑃𝑃𝑃𝑃
Where:
𝑣𝑣𝑖𝑖 = demand flow rate for movement (veh/h)
𝑉𝑉𝑖𝑖 = demand volume recorded for movement, include bicycles as a vehicle (veh/h)
𝑃𝑃𝑃𝑃𝑃𝑃 = peak hour factor
Step 2: Passenger car equivalents (bicycle, medium trucks, and heavy trucks)
Flow rates in vehicles per hour (veh/h) are converted to equivalent passenger cars per hour (pc/h)
using vehicle factors. The bicycle equivalent factor should be 1.0, rather than 0.5 as suggested in
HCM 6 (Exhibit 12-14).
1
𝑓𝑓𝐻𝐻𝐻𝐻 =
1 + 𝑃𝑃𝑚𝑚 (𝐸𝐸𝑚𝑚 − 1) + 𝑃𝑃ℎ (𝐸𝐸ℎ − 1)
Where:
𝑓𝑓𝐻𝐻𝐻𝐻 = heavy vehicle adjustment factor
𝑃𝑃𝑚𝑚 = proportion of demand volume that consists of medium trucks (decimal)
𝑃𝑃ℎ = proportion of demand volume that consists of heavy vehicles (decimal)
𝐸𝐸𝑚𝑚 = passenger car equivalent for medium trucks (Passenger Car Equivalents given)
𝐸𝐸ℎ = passenger car equivalent for heavy vehicles (Passenger Car Equivalents given)
𝑣𝑣𝑖𝑖
𝑣𝑣𝑖𝑖,𝑝𝑝𝑝𝑝𝑝𝑝 =
𝑓𝑓𝐻𝐻𝐻𝐻
Where:
𝑣𝑣𝑖𝑖,𝑝𝑝𝑝𝑝𝑝𝑝 = demand flow rate for movement (passenger cars per hour; pc/hr)
𝑣𝑣𝑖𝑖 = demand flow rate for movement (veh/hr)
𝑓𝑓𝐻𝐻𝐻𝐻 = heavy vehicle adjustment factor
The circulating flow rates in front of each entry are summed in terms of passenger car
equivalents. See HCM 6 Equation 22-11 below.
Where:
𝑣𝑣𝑐𝑐 = Circulating flow rates in front of specified entry; in passenger car equivalents
𝑣𝑣𝑊𝑊𝑊𝑊𝑊𝑊,𝑝𝑝𝑝𝑝𝑝𝑝 = Flow rates of a specified movement
This step is for a multi-lane roundabout approach with more than one entry lane.
For approaches with multiple lanes, lane utilization must be estimated. If field data are not
available, HCM 6 Exhibit 22-9 provides guidance on potential default values for different lane
configurations.
For approaches with movements that may use more than one lane, follow HCM 6 Exhibit 22-14
to determine the assumed lane assignment.
Using the assumed lane assignment, assign flow rates to each lane using the formulas provided in
HCM 6 Exhibit 22-15.
For single lane roundabouts without a capacity and headway study (i.e. Bend, Oregon) one
should use HCM 6 Equation 22-1 to find the capacity for each entry lane using the circulatory
flow rate calculated in Step 3.
𝐶𝐶 = 1,380𝑒𝑒 (−𝐵𝐵×𝑉𝑉𝑐𝑐 )
Where:
𝐶𝐶 = Entry capacity (pc/h) for single-lane roundabout
𝑉𝑉𝑐𝑐 = Circulating (conflicting) flow (pc/h)
𝐵𝐵 = Coefficient, 0.00102 for single lane roundabouts
The City of Bend, Oregon has more roundabouts than any city in Oregon. Therefore, Bend
drivers have become accustomed to roundabouts which operate at a higher capacity. A study of
single-lane roundabouts in Bend (City of Bend Roundabout Operational Analysis Guidelines,
Kittelson & Associates, Inc., 2009) developed a locally calibrated capacity equation. Rather than
the HCM equation, the Bend capacity equation is to be used for all single-lane roundabouts to be
built in the Bend area. The local calibration of headways and capacities better match Bend
driving habits.
For a Type 1 Yielding Bypass lane as shown in Exhibit 12-15, the capacity of the bypass lane
should also be calculated. The exiting flow is used as the circulating or conflicting flow and the
bypass lane volume must yield as the entry flow. Use of the single or multilane capacity equation
(HCM 6 Step 5, Equation 22-6 or 22-7) depends on the number of opposing exit lanes. No
calculation is necessary if the bypass lane is a Type 2, non-yielding bypass entering an add-lane.
The capacity of an add-lane is expected to be high.
Step 6A: The following procedure is for analysis of single lane roundabouts; for two entry lanes,
see Step 6B below. For one entry lane, use one of the following three equations, similar to HCM
6 Exhibit 22-18, to find the entry capacity adjustment factor for pedestrians.
1. If the conflicting flow rate exceeds 881 pcph, or if the number of conflicting
pedestrians per hour is less than 40, the entry capacity adjustment factor for pedestrians is
1.0
2. If the number of conflicting pedestrians per hour is equal to or greater than 40, but less
than 101, use the following formula to calculate the entry capacity adjustment factor for
pedestrians.
3. If either of the above two conditions are not met, use the following formula to calculate
the entry capacity adjustment factor for pedestrians.
Else
1,119.5 − 0.715𝑣𝑣𝑐𝑐,𝑝𝑝𝑝𝑝𝑝𝑝 + 0.00073𝑣𝑣𝑐𝑐,𝑝𝑝𝑝𝑝𝑝𝑝 𝑛𝑛𝑝𝑝𝑝𝑝𝑝𝑝
𝑓𝑓𝑝𝑝𝑝𝑝𝑝𝑝 =
1,068.6 − 0.654𝑣𝑣𝑐𝑐,𝑝𝑝𝑝𝑝𝑝𝑝
Where:
𝑓𝑓𝑝𝑝𝑝𝑝𝑝𝑝 = entry capacity pedestrian adjustment factor
𝑣𝑣𝑐𝑐 = conflicting flow (pc/h)
𝑛𝑛𝑝𝑝𝑝𝑝𝑝𝑝 = conflicting pedestrians (p/h)
An adjustment factor for pedestrians of 1.0 is recommended if there are fewer than 40
pedestrians crossing a leg in an hour. Less than 40 pedestrians crossing a leg in an hour do not
have a significant effect on single lane roundabout operation.
If the hourly number of passenger car equivalent vehicles circulating in front of an entrance is
over 881, then the adjustment factor for pedestrians is a factor of 1.0. If that is not the case and
the number of pedestrians crossing at a crosswalk is greater than 40 and less than or equal to 101,
then the second equation determines the adjustment factor for pedestrians.
Step 6B: If considering more than one entry lane, see HCM 6 Step 6 including Exhibits 22-20
and 22-21 for the entry capacity adjustment factor for pedestrians.
Step 7A: A weighted average of the heavy vehicle adjustment factor is created for each entry
lane with HCM 6 Equation 22-15.
Where:
𝑓𝑓𝐻𝐻𝐻𝐻𝐻𝐻 = averaged heavy vehicle adjustment factor for entry lane
𝑓𝑓𝐻𝐻𝐻𝐻𝐻𝐻 = heavy vehicle adjustment factor for movement i
𝑣𝑣𝑖𝑖,𝑃𝑃𝑃𝑃𝑃𝑃 = demand flow for movement i (pc/h)
The entry lane flow rate is converted back to vehicles per hour with HCM 6, Equation 22-13, a
rearrangement of Equation 22-9.
Where:
𝑣𝑣𝑖𝑖,𝑃𝑃𝑃𝑃𝑃𝑃 = demand flow rate for lane i (pc/hr)
𝑣𝑣𝑖𝑖 = demand flow rate for lane i (veh/hr)
𝑓𝑓𝐻𝐻𝐻𝐻,𝑒𝑒 = heavy vehicle adjustment factor
Step 7B: The capacity of a lane is converted back to vehicles per hour in Equation 22-14.
ci = ci , PCE f HVe f ped
The decision to build a roundabout is determined by the State Traffic-Roadway Engineer (with
consultation from Region Traffic). Considerations for further study may include highway
classification, traffic characteristics, and system continuity.
HCM 6 states the delay to be similar to unsignalized intersections, per United Sates roundabout
data. The HCM makes a good point about delay at peak hour or design hour:
At higher volumes, it is likely that motorists may make stops before the crosswalk as well as the
yield/stop that HCM 6 describes as resembling STOP control.
3600
3600 �(𝑥𝑥 � 𝑐𝑐 � 𝑥𝑥
𝑑𝑑 = + 900𝑇𝑇 �𝑥𝑥 − 1 + 2
− 1) + � + 5 × 𝑚𝑚𝑚𝑚𝑚𝑚[𝑥𝑥, 1]
𝑐𝑐 450𝑇𝑇
Where:
𝑑𝑑 = average control delay (s/veh)
𝑥𝑥 = volume-to-capacity ratio of the subject lane
𝑐𝑐 = capacity of the subject lane (veh/hr)
𝑇𝑇 = time period (h) (T = 0.25 for a 15-min analysis)
The delay is calculated for each lane on each approach.
The delay from Step 9 and the v/c ratio from Step 8 are used with Exhibit 12-16 (HCM 6 Exhibit
22-8) to determine the LOS of each lane on each approach.
The average control delay of a roundabout is calculated in HCM 6 equations 22-18 and
22-19. For a single lane roundabout with single entry lanes, these equations will reduce to
an average of approach (HCM 6 Equation 22-19):
∑ 𝑑𝑑𝑖𝑖 𝑣𝑣𝑖𝑖
𝑑𝑑𝑖𝑖𝑖𝑖𝑖𝑖𝑖𝑖𝑖𝑖𝑖𝑖𝑖𝑖𝑖𝑖𝑖𝑖𝑖𝑖𝑖𝑖𝑖𝑖 =
∑ 𝑣𝑣𝑖𝑖
Where:
𝑑𝑑𝑖𝑖𝑖𝑖𝑖𝑖𝑖𝑖𝑖𝑖𝑖𝑖𝑖𝑖𝑖𝑖𝑖𝑖𝑖𝑖𝑖𝑖𝑖𝑖 = average control delay for entire intersection (s/veh)
𝑑𝑑𝑖𝑖 = control delay for approach i (s/veh)
𝑣𝑣𝑖𝑖 = flow rate for approach i (veh/h)
With the average intersection delay, the intersection LOS is found from Exhibit 12-16
(HCM 6 Exhibit 22-8).
For multilane approaches and approaches with bypass lanes, the full Equation 22-18 is
used, which calculates a weighted average delay for the approach. An overall intersection
delay and LOS can also be determined using Equation 22-19.
The 95th percentile queue of a roundabout entry lane is calculated in HCM 6 Equation
22-20.
3600
�(1 � 𝑐𝑐 � 𝑥𝑥 𝑐𝑐
𝑄𝑄95 = 900𝑇𝑇 �𝑥𝑥 − 1 + − 𝑥𝑥)2 + �� �
150𝑇𝑇 3600
Where:
𝑄𝑄95 = 95th percentile queue (veh)
𝑥𝑥 = volume-to-capacity ratio of the subject lane
𝑐𝑐 = capacity of the subject lane (veh/hr)
𝑇𝑇 = time period (h) (T = 0.25 for a 15-min analysis)
Start analysis of a single lane roundabout with existing and future volumes. If an entry
lane exceeds the mobility standard, then analyze a bypass lane for that approach. The
bypass lane volume is subtracted out of the roundabout entry lane volume. This affects
flow rate calculations of Steps 1 through 5. This may also affect capacity, v/c, delay,
LOS, or 95th percentile queue. If a bypass lane merges into an existing lane (Yielding
Type 1), then calculate the capacity of the bypass lane (HCM 6 Chapter 33, Example
Problem 1). If not due to a heavy right turn movement, then a multilane roundabout
should be considered (not all of the circulating lanes must have more than one lane). If a
multilane roundabout entry lane exceeds the mobility standard, then again consider a
bypass lane. A flow chart showing this process is shown in Exhibit 12-17.
R
Heavy thru, left, or Partial multilane O
conflicting volume roundabout U
causes mobility std to Yes meets mobility Yes N
be exceeded? standard? D
A
N N B
o o O
U
Full multilane roundabout meets future mobility T
standard? Yes
A
L
N
o T
Full multilane E
roundabout meets R
Caused by heavy mobility standard N
right turn volume? Yes with bypass Yes A
lane(s)? T
N I
o N V
o
E
The MUTCD warrants are part of the Traffic-Roadway Section (TRS) signal
approval process. For more information contact TRS. For all other
applications/projections, only the ADT-based Preliminary Signal Warrant process
can be used.
Traffic signal warrants must be met and the State Traffic-Roadway Engineer’s approval
obtained before a traffic signal can be installed on a state highway. However, approval of
a signal depends on more than just a warrant analysis. Meeting a warrant is necessary to
install a signal, but it does not mean a signal should be recommended or guarantee its
installation. Considerations to be evaluated include safety concerns, alternatives to
signalization, signal systems, delay, queuing, bike and pedestrian needs, railroads, access,
consistency with local plans, local agency support and others. The engineering
investigation, conducted or reviewed by the Region Traffic Engineer, must demonstrate a
reduction in delay, improvements in safety, improved connectivity or some other
"benefit" and why a signal is the best solution as compared to other alternatives, such as
listed in MUTCD Section 4B.04a. During the consideration, the Region Traffic Engineer,
input from Traffic-Roadway Section (TRS) must be obtained prior to reaching any
conclusions. Coordination with TRS should occur early in the project process to allow
sufficient time to develop and evaluate alternatives to signalization if deemed necessary.
Once the investigation and recommendation is reviewed, TRS will act on the request.
If preliminary signal warrants are met, project analysts need to forward a copy of the
PSW form and analysis to Region Traffic and coordinate with Region Traffic to initiate
the traffic signal engineering investigation as outlined in the Traffic Manual. If Region
Traffic supports the concept of a signal installation, they will forward the analysis to
TRS.
Introduction
The single most important criterion for preliminary signal warrant analysis is engineering
judgment. In the following procedures only the fundamental parameters of volumes and
approach lanes are provided.
Background
There are 9 traffic signal warrants found in the MUTCD, listed in Part 4. The signal
warrants are:
OAR 734-020-0460 (1) stipulates that only MUTCD Warrant 1 Condition A and
Condition B may be used to project future needs for traffic signals beyond three years
from the present time. Condition A deals primarily with high volumes on the intersecting
minor street. Condition B addresses high volumes on the major street and the delays and
hazards to vehicles on the minor street trying to either access or cross the major street.
The preliminary warrant is considered satisfied if either Condition A or Condition B is
met for either 100% of the thresholds or 70% of the thresholds when the major-street
speed exceeds 40 mph or in an isolated community with a population of less than 10,000.
The 80% and 56% thresholds that may apply after adequate trial of other remedial
measures are not used for preliminary signal warrants. MUTCD Warrant 3, Peak Hour
cannot be used to project needs for future traffic signals.
Analysis
In MUTCD Warrant 1 the eighth highest hour of an average day is used to determine
whether a warrant is met. At the analysis stage in TPAU, ADT is used for preliminary
signal warrant analysis. A conversion factor of 5.65% is applied to the ADT to reach the
eighth highest hour. The conversion factor of 5.65% was developed based on a study of
1991 to 1994 manual counts and as agreed on by TPAU and TRS. This factor was used to
convert MUTCD hourly volumes to ADT volumes (divided the MUTCD volume by the
factor .0565). This equals the target ADT volume to meet MUTCD Warrant 1. As an
example, for Condition A to be met the MUTCD requires a minimum total of 500
vehicles per hour on both approaches of the major street, where the major and minor
streets both have only one lane for moving traffic (at 100%, assuming no reductions). To
convert this to ADT volumes, the following calculations are made:
500
ADT = = 8,850
0.0565
If the 85th percentile speed of major street traffic exceeds 40 mph in either an urban or
rural area or when the intersection lies within the built-up area of an isolated community
(typically non-MPO) having a population of less than 10,000, reduce the target volume
for the warrants to 70 percent of the normal requirements, as shown in the preliminary
traffic signal warrant analysis sheet in Exhibit 12-18.
1
Note that the value of 8,850 calculated in the analysis example is the same as the value on the worksheet
for this scenario.
• Include only the through and through/turn lanes in the number of approach lanes.
• For the ADT, count total volume approaching from both directions, including all
turn movements.
• Include only the through, through/turn and left turn lanes in the number of
approach lanes. However, in cases of where a minor street approach is just a right
turn lane, code this as a lane in the worksheet. The right turn discount is applied
normally as described below.
• For the ADT, count the highest approaching volume (one direction only, do not
include the ADT approaching from both directions) including some or none of the
right turn volume as discussed in the following scenarios and examples:
o Scenario # 1 – Shared Left-Through-Right Lane: Some of the right
turns are included in the minor street approach ADT if the right turn
demand is greater than 85% of the capacity of the shared lane. Use
unsignalized capacity analysis to calculate the capacity of the shared lane.
The right turn discount is 85% of the shared lane capacity (85% of the
capacity is used because once the v/c exceeds 0.85, drivers suffer longer
delay and begin to take unsafe gaps). Subtract the right-turn discount from
the total right turn volume to determine the number of right turns in the
warrant. If the remainder is less than or equal to zero, do not include any
of the right turns in the approach ADT.
Example Application: Right Turn Discounts (Only for the minor road.)
The diagram below shows a typical unsignalized intersection, the peak hour volumes, the
ADT volumes and lane configurations. The peak hour volumes are 10% of the ADT. The
85th percentile speed is 35 mph and the intersection is located in a city with a population
of 60,000.
The figure below shows the Preliminary Signal Warrant Analysis for this example. The
preliminary signal warrant is not met because the Minor Street ADT is less than the
warrant volume in Condition A and the Major Street ADT is less than the warrant volume
in Condition B.
1 Meeting preliminary signal warrants does not guarantee that a signal will be installed. When preliminary
signal warrants are met, project analysts need to coordinate with Region Traffic to initiate the traffic signal
engineering investigation as outlined in the Traffic Manual. Before a signal can be installed, the
engineering investigation must be conducted or reviewed by the Region Traffic Manager who will forward
signal recommendations to headquarters. Traffic signal warrants must be met and the State Traffic
Engineer’s approval obtained before a traffic signal can be installed on a state highway.
The diagram below shows a typical unsignalized intersection with a separate right turn
lane on the eastbound approach, the peak hour volumes, the ADT volumes and lane
configurations. The peak hour volumes are 10% of the ADT. The 85th percentile speed is
35 mph and the intersection is located in a city with a population of 60,000.
The form below shows the Preliminary Signal Warrant Analysis for this example. The
preliminary signal warrant is not met since the Minor Street ADT is less than the warrant
volume in Condition A and the Major Street ADT is less than the warrant volume in
Condition B.
1 Meeting preliminary signal warrants does not guarantee that a signal will be installed. When preliminary
signal warrants are met, project analysts need to coordinate with Region Traffic to initiate the traffic signal
engineering investigation as outlined in the Traffic Manual. Before a signal can be installed, the
engineering investigation must be conducted or reviewed by the Region Traffic Manager who will forward
signal recommendations to headquarters. Traffic signal warrants must be met and the State Traffic
Engineer’s approval obtained before a traffic signal can be installed on a state highway.
The diagram below shows a typical unsignalized intersection with a shared through-right
lane on the eastbound approach, the peak hour volumes, the ADT volumes and lane
configurations. The peak hour volumes are 10% of the ADT. The 85th percentile speed is
35 mph and the intersection is located in a city with a population of 60,000.
1 Meeting preliminary signal warrants does not guarantee that a signal will be installed. When preliminary
signal warrants are met, project analysts need to coordinate with Region Traffic to initiate the traffic signal
engineering investigation as outlined in the Traffic Manual. Before a signal can be installed, the
engineering investigation must be conducted or reviewed by the Region Traffic Manager who will forward
signal recommendations to headquarters. Traffic signal warrants must be met and the State Traffic
Engineer’s approval obtained before a traffic signal can be installed on a state highway.
PSWs are used to project signalization needs. MUTCD warrants are limited to 3 years or
less and are for actual approval of installation of a traffic signal. This requires an
engineering study including an evaluation of the full set of 9 MUTCD signal warrants.
Provisions for this evaluation are found in the ODOT Traffic Signal Policy and
Guidelines, OAR 734-020-0400 thru 734-020-0500 and ODOT Traffic Manual.
Estimates of queue lengths should be based on the anticipated arrival patterns, duration of
interruptions and the ability of the intersection to recover from momentary heavy arrival
rates. The average queue length and the 95th percentile queue length should be shown in
the report. The 95th percentile queue length shall be used for design purposes. A queue
blockage or spillback condition is considered a problem when the duration exceeds 5
percent of the peak hour. The average vehicle length, including buffer space between
vehicles, to be used in analysis shall be 25-feet, unless a local study indicates otherwise,
with all queue length calculations rounded up to the next 25-foot increment. Queue
lengths subject to over-capacity conditions can only be adequately assessed through the
use of simulation software. The 25-foot average does not apply to microsimulation,
where vehicle lengths differ by vehicle type. Refer to Chapter 15 for microsimulation
guidance.
The minimum storage length for urban or rural left turn lanes at unsignalized
intersections on state highways is 100 feet. Left Turn Lane layouts/dimensions are
available in HDM Chapter 8 Figure 8-9 and Traffic Line Manual (TLM) Section
310.
TPAU Models
At unsignalized intersections, the movements of interest are often the major street left
turns and all minor street movements. The most common methodologies used for
estimating queue lengths for these movements include the Highway Capacity Software
(HCS) 2 and the Two-Minute Rule.
2
Highway Capacity Software, McTrans, University of Florida, Gainesville, Florida.
Poisson regression models were developed to improve the queue length estimations.
Model validation shows that the refined models are predicting queue lengths better than
other methods. The HCM methodology was found to consistently under estimate the
queue length. A Two-Way Stop Queue Length Calculator is available on the Planning
Section website under Tools. Exhibit 12-19 summarizes the developed models, and
applicable ranges of input data for each model type. When the range of independent
variables exceeds the limiting value, use queue length models with caution.
Exhibit 12-19 TPAU Two-way Stop Controlled Intersection Queue Length Models
Lane
Queue Length Model Equation1
Group
MJL2 Queue Length = e (0.3925+0.0059*VOL+0.00104*CONVOL+0.49*Signal-0.81*LT)
3
Development of Queue Length Models at Two-way STOP Controlled Intersection: A
Surrogate Method (accessed on January 23, 2014)
As the HCM method was found to consistently underestimate queue lengths, and two-
minute rule consistently overestimates queue lengths, neither method should be used for
two-way stop control queue length estimation. Either simulation or the models in Exhibit
12-19 may be used. Example 12-7 and Example 12-8 outline the step by step process of
queue length estimation using developed models. The queues in this methodology
represent the maximum queues for the peak 15-minute period which are considered to be
an acceptable approximation of the 95th percentile queue length.
This procedure estimates the number of vehicles in queue. This number is multiplied by
the appropriate average vehicle storage length obtained from Exhibit 12-20 to determine
the queue length.
This example demonstrates the application of the TPAU queue length estimation models
at a three- legged Stop- controlled intersection.
(Source: Example Problem 1 of HCM 6 Chapter 32)
Data
• Volume (peak 15-min) and lane configuration is show below:
Step 4: Compute Conflicting Flow Rates (CONVOL) as per HCM 6 Equations 20-4
through 20-29
WB MJL
Vc,MJL = Vc,4
Vc,4 = V2 + V3
Vc,4 = 240+40 = 280 veh/h
NB MNLR
Vc,MNLR = vc,7 + vc,9
NB MNLR
VOL = 160 veh/h is within the range (0, 300]
CONVOL = 1140 veh/h is within the range (0, 3000]
QL = e (-0.6319+0.0173*VOL+0.00066*CONVOL-0.000007913* VOL* CONVOL)
QL = e (-0.6319 + 0.0173*160 + 0.00066*1140 -0.000007913* 160* 1140)
QL = 4.2 ≈ 5 vehicles
This example demonstrates the application of the TPAU queue length estimation models
at a four-legged two-way STOP controlled intersection.
(Source: Example Problem 3 of 2010 HCM Chapter 32, Page 32-7)
Data
• Volumes and lane configurations as shown below:
• Major street with two lanes in each direction, minor street with one lane on each
approach that flares with storage for one vehicle in the flare area, and median
storage for two vehicles at one time available for minor-street through and left-
turn movements;
• Level grade on all approaches;
Step 4: Compute Conflicting Flow Rates (CONVOL) as per HCM 6 Equations 19-4
through 19-29
EB MJL
vc, 1 = v5 + v6 + v16 = 300 + 100 + 0 = 400 veh/h
WB MJL
vc, 4 = v2 + v3 + v15 = 250 + 50 + 0 = 300 veh/h
NB MNLTR
vc,NB = vc,7 + vc,8 + vc,9
vc,7 = vc,I,7+ vc,II,7 (two-stage gap acceptance)
vc,I,7 = 2(v1 + v1u) + v2 + 0.5v3 + v15
= 2(33+0) + 250 + 0.5(50) + 0 = 341 veh/h
vc,II,7 = 2(v4 + v4u) + 0.5v5 + 0.5v11 + v13
= 2(66+0) + 0.5(300) + 0.5(110) + 0 = 337 veh/h
vc,7 = vc,I,7+ vc,II,7 = 341 + 337 = 678 veh/h
vc,8 = vc,I,8+ vc,II,8 (two-stage gap acceptance)
vc,I,8 = 2(v1 + v1u) + v2 + 0.5v3 + v15
= 2(33+0) + 250 + 0.5(50) + 0 = 341 veh/h
vc,II,8 = 2(v4 + v4u) + v5 + v6 + v16
= 2(66+0) + 300 + 100 + 0 = 532 veh/h
vc,8 = vc,I,8+ vc,II,8 = 341 + 532 = 873 veh/h
vc,9 = 0.5v2 + 0.5v3 + v4U + v14 + v15
WB MJL
VOL = 66 veh/h is within the range (0, 300]
CONVOL = 300 veh/h is within the range (0, 2000]
SIGNAL = 0 ; LT = 1
QL= e (0.3925 + 0.0059 * VOL + 0.00104 * CONVOL + 0.49 * Signal - 0.81 * LT)
QL= e (0.3925 + 0.0059 * 66 + 0.00104 * 300 + 0.49 * 0 - 0.81 * 1)
QL = 1.3 ≈ 2 veh
NB MNLTR
VOL = 231 veh/h is within the range (0, 300]
CONVOL = 1701 veh/h is within the range (0, 3000]
QL= e (-0.7844 + 0.01636 * VOL + 0.0006 * CONVOL - 0.0000043 * VOL* CONVOL)
QL= e (-0.7844 + 0.01636 * 231 + 0.0006 * 1701 - 0.0000043 * 231* 1701)
QL = 10.2 ≈ 11 veh
Summary
Maximum QL for
EB LT = 2 veh
WB LT = 2 veh
NB approach = 11 Veh
SB approach = 5 Veh
Estimates from other queue length models are presented below:
Simulation
If simulation is being performed as part of the analysis, queue lengths should be taken
from the simulation results. If simulation is not being done, it should be considered
especially if the v/c ratios are approaching 0.90. If the effort to do a simulation analysis is
not desired, the TPAU queue length estimation models should be used. Refer to APM
version 1 Chapter 8 for simulation procedures.
Two-Minute Rule
The Two-Minute Rule is a rule of thumb methodology that shall only be used for sketch
planning level analysis or for lane groups not addressed in the TPAU method. This
method estimates queue lengths for major street left turns and minor street movements by
using the queue that would result from a two-minute stoppage of the turning demand
volume. This method does not consider the magnitudes and impacts of the conflicting
flows on the size of the queue. The calculation of the 95th percentile queue using the two-
minute rule methodology shall use the following equation:
References
(1) Robinson, Bruce W., et al. Roundabouts: An Informational Guide. No. FHWA-RD-
00-067. 2000.