This document contains exercises from Chapter 13 of a project management fundamentals course. It includes a project network with budget and status information to develop status reports for different periods of the project. Based on the data provided, the project is assessed to be 74.75% complete at the end of period 8 and expected to come in $31,000 under budget. A second exercise provides labor hour data for a nanotechnology project over 6 periods and calculates schedule variance, cost variance, schedule performance index, and cost performance index for each period. At the end of period 6, the project is assessed to be on budget but behind schedule.

Uploaded by

lulu
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
156 views

Running Head: Chapter 13 Exercises

This document contains exercises from Chapter 13 of a project management fundamentals course. It includes a project network with budget and status information to develop status reports for different periods of the project. Based on the data provided, the project is assessed to be 74.75% complete at the end of period 8 and expected to come in $31,000 under budget. A second exercise provides labor hour data for a nanotechnology project over 6 periods and calculates schedule variance, cost variance, schedule performance index, and cost performance index for each period. At the end of period 6, the project is assessed to be on budget but behind schedule.

Uploaded by

lulu
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 7

RUNNING HEAD: CHAPTER 13 EXERCISES

WBS 8.4 Chapter 13 Exercises

Benjamin Srock

Fundamentals of Project Management

PMGT-501

Robert W. Erickson, Ph.D.

July 25, 2016


RUNNING HEAD: CHAPTER 13 EXERCISES

Benjamin Srock
PMGT 501
Chapter 13: Exercises 4 and 6

4. Given the following project network, baseline, and status information, develop status
reports for periods 2, 4, 6, 8, and complete the performance indexes table. Calculate the EACf
and the VACf . Based on your data, what is your assessment of the current status of the project?
At completion?

Budget
ID 1 2 3 4 5 6 7 8 9 10 11 12
$000
A 40 10 10 10 10
B 32 8 4 8 4 8
C 48 12 12 12 12
D 18 6 2 2 2 6
E 28 8 8 12
F 40 20 20
Total 206 18 14 18 14 20 26 22 26 2 6 20 20
Cumulative 18 32 50 64 85 110 132 158 160 166 186 206
RUNNING HEAD: CHAPTER 13 EXERCISES

Status Report Ending Period 2 ($000)


Task % Complete EV AC PV CV SV
A 75% 30 25 20 5 10
B 50% 16 12 12 4 4
Cumulative Totals 46 37 32 9 14

Status Report Ending Period 4 ($000)


Task % Complete EV AC PV CV SV
A 100% 40 35 40 5 0
B 100% 32 24 24 8 8
Cumulative Totals 72 59 64 13 8

Status Report Ending Period 6 ($000)


Task % Complete EV AC PV CV SV
A 100% 40 35 40 5 0
B 100% 32 24 32 8 0
C 75% 36 24 24 12 12
D 0% 0 0 6 0 -6
E 50% 14 10 8 4 6
Cumulative Totals 122 93 110 29 12

Status Report Ending Period 8 ($000)


Task % Complete EV AC PV CV SV
A 100% 40 35 40 5 0
B 100% 32 24 32 8 0
C 100% 48 32 48 16 0
D 33% 6 20 10 -14 -4
E 100% 28 20 28 8 0
Cumulative Totals 154 131 158 23 -4

Performance Indexes Summary


Period EV AC PV SPI CPI PCI-B
2 46 37 32 1.44 1.24 22%
4 72 59 64 1.13 1.22 35%
6 122 93 110 1.11 1.31 59%
8 154 131 158 0.97 1.18 75%

(BAC − EV)
EAC𝑓 = + AC
EV
(AC)

(206 − 154)
EAC𝑓 = + 131
(154/131)

(52)
EAC𝑓 = + 131 = (44) + 131 = 𝟏𝟕𝟓
(1.18)
RUNNING HEAD: CHAPTER 13 EXERCISES

VAC𝑓 = (BAC − EAC𝑓 ) = (206 − 175) = 𝟑𝟏

Based on your data, what is your assessment of the current status of the project? At completion?
At the end of period 8, the project is 74.75% complete (EV/BAC) and $23,000 under budget. At
this point, the project should have amassed an actual cost of $154,000, when it actually cost
$131,000. This savings is a good sign as it indicates we are getting $1.18 worth of work for
every $1.00 we spend. Based on this current rate of operation, the project should come in
$31,000 under budget. The downside is that while there is a substantial savings, the project does
appear to be behind schedule.

6. The following labor hours’ data have been collected for a nanotechnology project for
periods 1 through 6. Compute the SV, CV, SPI, and CPI for each period. Plot the EV and the
AC on the summary graph provided (or a similar one). Plot the SPI, CPI, and PCIB on the index
graph provided (or a similar one). What is your assessment of the project at the end of period 6?

Schedule Information Baseline budget needs - labor hours (00)


ACT/ Total
DUR ES LF SL 1 2 3 4 5 6 7 8 9 10 11 12 13 14
WP PV
1 2 0 2 0 20 10 10
2 2 2 7 3 24 16 8
3 6 2 11 3 30 5 5 10 3 2 5
4 5 2 7 0 25 10 10 2 2 1
5 4 4 11 3 16 4 4 4 4
6 4 7 11 0 20 5 5 6 4
7 2 11 13 0 10 5 5
Total PV by period 10 10 31 23 16 9 7 14 5 6 4 5 5
Cumulative PV by period 10 20 51 74 90 99 106 120 125 131 135 140 145
RUNNING HEAD: CHAPTER 13 EXERCISES

Status Report Ending Period 1 ($000)


Task % Complete EV AC PV CV SV
1 50% 1000 500 1000 500 0
Cumulative Totals 1000 500 1000 500 0

Status Report Ending Period 2 ($000)


Task % Complete EV AC PV CV SV
1 100% 2000 1500 2000 500 0
Cumulative Totals 2000 1500 2000 500 0

Status Report Ending Period 3 ($000)


Task % Complete EV AC PV CV SV
1 100% 2000 1500 2000 500 0
2 0% 0 0 1600 0 -1600
3 10% 300 200 500 100 -200
4 20% 500 500 1000 0 -500
Cumulative Totals 2800 2200 5100 600 -2300

Status Report Ending Period 4 ($000)


Task % Complete EV AC PV CV SV
1 100% 2000 1500 2000 500 0
2 50% 1200 1000 2400 200 -1200
3 30% 900 800 1000 100 -100
4 40% 1000 1500 2000 -500 -1000
Cumulative Totals 5100 4800 7400 300 -2300

Status Report Ending Period 5 ($000)


Task % Complete EV AC PV CV SV
1 100% 2000 1500 2000 500 0
2 100% 2400 2000 2400 400 0
3 50% 1500 800 2000 700 -500
4 60% 1500 1500 2200 0 -700
5 25% 400 400 400 0 0
Cumulative Totals 7400 6200 9000 1600 -1200

Status Report Ending Period 6 ($000)


Task % Complete EV AC PV CV SV
1 100% 2000 1500 2000 500 0
2 100% 2400 2000 2400 400 0
3 80% 2400 2100 2300 300 100
4 80% 2000 1800 2400 200 -400
5 50% 800 600 800 200 0
Cumulative Totals 8800 8000 9900 1600 -300

Period SPI CPI PCI-B


1 1.00 2.00 7% SPI = EV/PV
2 1.00 1.33 14% CPI = EV/AC
3 0.55 1.27 19% PCIB = EV/BAC
4 0.69 1.06 35%
5 0.82 1.19 51%
6 0.89 1.10 61%
RUNNING HEAD: CHAPTER 13 EXERCISES

What is your assessment of the project at the end of period 6? It is important to first note the
critical path 1, 4, 6, & 7. At the completion of the 6th period, activity 4 should be completed but
is only 80% complete. Since the actual cost of activity 1 resulted in a savings of $500, perhaps
this savings can be utilized to crash this activity to get the project back on schedule. If nothing is
done, the project will not complete on time.