Oil & Gas Project demands on Engineering

Hervé Baron
SPE, Paris
June 11th, 2015

© 2015 – Hervé Baron


Oil & Gas Project demands on Engineering

 The Engineering of a Process Plant


• The role of Engineering
• The work process

© 2015 – Hervé Baron


Oil & Gas Project demands on Engineering

© 2015 – Hervé Baron


Oil & Gas Project demands on Engineering

 The Engineering of a Process Plant


• The role of Engineering
• The work process

© 2015 – Hervé Baron


Oil & Gas Project demands on Engineering

Utility Units Design


Process Design Utility consumption
Electrical power
generation & distribution
Process
Plant Layout
Flow Process Civil design
Diagrams, Equipment (UG networks)
Heat & sizing
Material Equipment design by Civil design
Balance vendors ( foundations)

Fluids composition & Material selection and


conditions specifications

Structural steel

© 2015 – Hervé Baron


Piping & Piping Routing design
Instrumentation
Diagrams Instrumentation &
Control design
Oil & Gas Project demands on Engineering

 The Engineering of a Process Plant

 Fast track execution


• From sequential to concurrent E/P/C
• Consequences for Engineering: Early quantity estimates and commitments
• Awareness and compliance with construction work sequence
• Knowledge and focus on fundamentals

© 2015 – Hervé Baron


From sequential to concurrent Project execution

ENGINEERING Drawings

Bill of
materials

PROCUREMENT

CONSTRUCTION

© 2015 – Hervé Baron


From sequential to concurrent Project execution

ENGINEERING PROCUREMENT CONSTRUCTION

ENGINEERING

© 2015 – Hervé Baron


PROCUREMENT

CONSTRUCTION
Oil & Gas Project demands on Engineering

 The Engineering of a Process Plant

 Fast track execution


• From sequential to concurrent E/P/C
• Consequences for Engineering: Early quantity estimates and commitments
• Awareness and compliance with construction work sequence
• Knowledge and focus on fundamentals

© 2015 – Hervé Baron


From sequential to concurrent Project execution

ENGINEERING

Fabrication + transport
Up to 7-9 months on large
projects
PROCUREMENT

© 2015 – Hervé Baron


From sequential to concurrent Project execution

ENGINEERING

QUANTITIES TO ERECT

© 2015 – Hervé Baron


CONSTRUCTION
Oil & Gas Project demands on Engineering

 The Engineering of a Process Plant

 Fast track execution


• From sequential to concurrent E/P/C
• Consequences for Engineering: Early quantity estimates and commitments
• Awareness and compliance with construction work sequence
• Knowledge and focus on fundamentals

© 2015 – Hervé Baron


Awareness and compliance with construction sequence

Process simulations

Process data
sheet

Equipment
selection &
purchase

Vendor data

© 2015 – Hervé Baron


Foundation
drawings
Awareness and compliance with construction sequence

Engineering must adjust its schedule to match the construction sequence…

© 2015 – Hervé Baron


Awareness and compliance with construction sequence

Engineering must adjust its schedule to match the construction sequence…


Undergrounds are installed first but usually designed last!

© 2015 – Hervé Baron


Oil & Gas Project demands on Engineering

 The Engineering of a Process Plant

 Fast track execution


• From sequential to concurrent E/P/C
• Consequences for Engineering: Early quantity estimates and commitments
• Awareness and compliance with construction work sequence
• Knowledge and focus on fundamentals

© 2015 – Hervé Baron


Oil & Gas Project demands on Engineering

 The Engineering of a Process Plant

 Fast track execution


• From sequential to concurrent E/P/C
• Consequences for Engineering: Early quantity estimates and commitments
• Awareness and compliance with construction work sequence
• Knowledge and focus on fundamentals
• Piping chain

© 2015 – Hervé Baron


The most likely critical path of an Oil & Gas Project

© 2015 – Hervé Baron


Elementary work in Piping

Drawing + matching
materials available

Pre-fabrication:
cutting,
 welding,
 NDE,
 blasting,
 painting (primer)

Erection:
 fit-up,
 welding,
 NDE,
 PWHT,
 supports,
 hydrotest,

© 2015 – Hervé Baron


 cleaning,
 re-instatement,
 painting,
 insulation
Oil & Gas Project demands on Engineering

 The Engineering of a Process Plant

 Fast track execution


• From sequential to concurrent E/P/C
• Consequences for Engineering: Early quantity estimates and commitments
• Awareness and compliance with construction work sequence
• Knowledge and focus on fundamentals
• Piping chain
• Integration of Equipment

© 2015 – Hervé Baron


Management of information from Vendors

© 2015 – Hervé Baron


Management of information from Vendors

Initial package layout Final Package layout

© 2015 – Hervé Baron


Management of information from Vendors

Electrical Process

Plant
Layout Instrumentation &
Vendor Control
Piping

© 2015 – Hervé Baron


Civil
Oil & Gas Project demands on Engineering

The last word: Engineering in a nutshell

© 2015 – Hervé Baron


Oil & Gas Project demands on Engineering

© 2015 – Hervé Baron


Oil & Gas Project demands on Engineering

To order:

http://www.editionstechnip.com/fr/c
atalogue-detail/1111/oil-gas-engineering-
guide-the.html

© 2015 – Hervé Baron

You might also like