Electric Line Specification & Handling
Electric Line Specification & Handling
Electric Line Specification & Handling
1.0 Purpose/Scope
This Section provides information to the Wells Group PE’s on electric line design, use, and operation.
2.0 Definitions
ASH – Alaska Safety Handbook
PE – Wells Group Production Engineer
GPB –Greater Prudhoe Bay
DSO – Drill site operator
SSV – Surface Safety Valve
WOA – Western Operating Area
EOA – Eastern Operating Area
5.0 Procedure/Process
There are multiple electric line sizes in use today. In Alaska, a typical logging truck will contain a split
drum of two wire types. The drum will contain a single conductor 0.23” diameter and a 7 conductor 0.39”
diameter wire. All conductors are double layered, reverse lay, steel wire strands with internal copper
conductors.
The smaller 0.23" single conductor line is typically used for production logging, neutron logging,
perforating, etc. The 0.23” E-line can operate at 3500 psi whp and higher without problems if the
flowtubes have been properly sized and the correct temperature range grease is used. A trailer-mounted
high pressure grease pump can be called out on location to assist in the grease seal at higher pressures.
The larger 0.39” 7 conductor line is used for USIT logging, running the CNT-G tool, setting whipstocks,
patches, straddles and other jobs that require either 7 conductors or higher strength cable. The well pressure
should be less than 1500 psi to obtain an effective seal on 0.39” line. At pressures over 1000 psi, line
speeds while running in the hole must be slowed and flowtubes kept tight to maintain a seal. Be aware that
a third party 60 or 90 ton crane may be required for this size line due to the increased max working tension
and the doubling effect of the upper sheave. Most E-line boom trucks are only rated for 9000 - 10,000 lbs.
In certain circumstances a shooting bridle can be rigged by attaching a short length of 0.23” line to the end
of the 0.39” line. This configuration allows flexibility in setting the proper weak point and making use of
the stonger cable.
A third cased hole line size option is the 0.32” wire. This intermediate sized, single conductor wire
provides an additional 2,000 lbs. of working tension over the 0.23” wire with much better pressure control
performance than the 0.39” wire. Depending on the wellbore fluid composition and the flowtube
configuration this size wire can be considered for wellhead pressures between 2,000 psi and 2,500 psi.
Again, crane limitations should always be considered and addressed when using a larger, heavier, and
stronger wire.
A new addition to Schlumberger’s suite of tools, the Electronically Controlled Release Device (ECRD),
which can electrically disconnect the electric line tools instead of tension disconnected weak point has
effectively lengthened the distance the 0.39” line can be run. This allows for deployment of tractor drive
units for extended reach.
Open hole conductor line is 0.46” diameter, extra strength, and uses 7 electrical conductor wires. This size
line is not used for pressure work as it is difficult to maintain a seal using flowtubes, thus it should never be
used in cased hole work unless special circumstances exist.
The published breaking strength for each size of the E-lines used is listed below.
The maximum operating tension allowed by the E-line company is 50% of the published breaking strength.
conductor covered with a bonded composite Teflon insulator, which prevents the passage of well pressure.
The following armor numbers may vary or change with new developments in E-lines, but the idea is the
same.
An inner wrap of 12 strands surrounds the insulator with torque in one direction and an outer wrap of 18
strands surrounds the inner wrap with torque in the other direction. The opposite torque between the outer
and inner armor packages maintains balance, keeping the strands tightly packed together, maintaining the
round shape of the E-line in addition to holding the insulated conductor package in place.
To assist in providing a seal in high pressure gas wells, the voids between the wire strands are packed with
a blocking material during manufacture. This construction is known as a high temperature double blocked
18/12 E-line. Other strand combinations are in use. Refer to the latest E-line data sheet, but see picture
below for a general illustration of the concept.
Listed below are the most common operational reasons for damaging E-line with a brief description of its
most common cause.
Insulator conductor package damage can occur if more than, 3500 lb., or approximately 60% of the E-line
breaking strength is pulled.
Wire strand damage will occur, stranding, if more than, 4350 lb., 75% of the breaking strength of the E-
line is pulled.
E-line crush at the drum flange is common if the RIH weight is less than 25% of the OOH weight while
operating around maximum pulls.
Bird caging occurs when running into the well with lower tension above the E-line than below it, i.e. the
E-line is run into the hole faster than the tool. It can also occur if the pack-off is too tight. Bird caging is
also a primary concern in high GOR wells where gas jetting may occur. In such wells, the E-line should
not be left stationary where it may be exposed to a gas jet.
Stranding, or a broken armor wire, can be initiated by mechanical damage in the well, armor hardening
due to well fluids or by a combination of both.
Stranding due to corrosive fluids can occur when inappropriate or inadequate amounts of corrosive fluid
inhibitors are used to treat the cables that are operating in this environment. To eliminate the effects of
these fluids, inhibitors are usually mixed in the grease supply system and when injected through the grease
injection system the line will have minimal effects while operating in this environment.
Oval E-line occurs when the line is spooled across a sheave that has a groove outside the tolerance for the
E-line or the sheave diameter is too small.
“Milking” the E-line usually occurs when the line wiper or pack-off assemblies are over pressured when
pulling out of hole to a point where the E-line is squeezed, forcing a severe reduction in diameter which
loosens the strands. The loose strands will be in the well where they cannot be seen.
Flowtubes that fit too tightly can have a similar effect when RIH but the loose strands will be above the
pack-off and easily seen.
Kinked, or bent E-line, usually occurs when there is no weight on the line, such as RIH too fast or having
the tools “blown up hole”, and is one of the most common occurrences.
Repairing a loose strand in the cable is an option. Minor kinks can be taken out by running the line on and
off the drum under controlled conditions. Broken strands can be shimmed or soldered but the line cannot
be used with flowtubes again. Open hole E-line is commonly spliced without problem.
New conductor line from the manufacturer will require “seasoning,” which consists of using flow tubes on
the high side of the tolerance, running into the well for a 1000 feet at approximately 5000 ft/hr and pulling
out at about 2000 ft/hr for 500 feet. This may vary depending on depth deviation and or local procedure.
This is repeated every 1000 feet all the way to bottom. After 5 runs to bottom the line is usually seasoned
and smaller flowtubes can be used. This is a time consuming procedure but is necessary in order to prolong
the life of the conductor line and extend its useful life.
During this procedure, torque in the armor wires is balanced and the line diameter reduces as the length
increases.
Excessive pressure on the line with the pack-off or line wiper should be avoided at all costs as this will
deform, or “milk”, the line beyond repair.
The armor will seat less on each subsequent run until the length increase is minimal. However, during the
first few runs it should be monitored closely for open strands or high wires.
Whenever the line is to run deeper than the depth that the line has originally been seasoned for, as described
above, it is necessary to season the amount of line that has not been run in the hole. Be sure that the line at
the deepest depth reached is measured and recorded for future determination of flow-tube size to use when
going this deep again, or deeper.
The Fleet Angle is defined as the angle of a line from the center of the bottom sheave to the center of the
drum. Ideally, this angle should be less than 1.25.
Example:
After shooting a 3-3/8” perforation gun on 0.23” monocable across the interval from 11,378’ MD to 11,403’
MD in a naturally producing well with a high GOR the tool string became stuck in the XN nipple at 10,973’
MD while pulling out of the hole. The wellhead pressures after perforating were unchanged from initial
pressures which were 2,600/300/0. The wellbore is basically vertical with minor dog-leg severities.
Information Required:
50% of E-line breaking strength as given by table above. 2,900 lbs.
Weak point configuration and breaking strength (SWP) as given by crew. 9x3 = 1,990 lbs.
Tool weight (WT) as recorded by crew at surface. 640 lbs.
Pick-up weight (WPU) closest to stuck point as recorded by crew. 1,800 lbs.
Calculations:
To determine the maximum safe working surface tension, as defined above, the values for #1 and #2 have
to be evaluated and compared to determine which one is the least amount of tension.
#1 is simply given as a line/material specification from the table and is equal to 2,900 lbs.
#2, or 75% of SWP at depth has to be calculated using the process that follows:
It must be noted and understood that this value of 1,492 lbs. is the maximum allowed tension at the weak
point, not the maximum allowed surface tension. To get 1,492 lbs. of tension to the weak point down-hole,
more tension at surface will need to be applied to overcome the line weight and the friction between the
line and the wellbore. Tool weight is not a consideration when stuck as the weak point is not supporting
any of the tool weight given that it is being held up by the restriction, or the XN nipple in this example. To
determine the line weight (WL) and the wellbore friction (f) the following equation is used:
WPU = WT + WL + f
(WL + f) = WPU - WT = 1,800 – 640 = 1,160 lbs.
This indicates that 1,160 lbs. of surface tension is required to support the weight of the line in the hole and
overcome the friction associated with the pressure control equipment, as well as, the down-hole friction due
to wellbore geometry. In the case of a stuck tool-string, as in this example, any amount of tension above
1,160 lbs. will be applied to the weak point. Consequently our maximum allowed surface tension due to
the weak point limitation can be calculated by simply adding the weight of the line and friction to the
maximum allowed tension on the weak point.
Now that the values for both #1 and #2 are known for the given situation it is evident that 2,652 lbs. is less
than 2,900 lbs. and is therefore, our maximum safe working tension.
BP Confidential and © 2009 BP America Inc.
Control Tier: 4 – ADW Revision Date: 6/18/2010
Document Number: UPS-US-AK-ADW-WLS-ADW-DOC-00074-4 Print Date: 3/24/2019
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE CONTROLLED
VERSION OF THIS DOCUMENT CAN BE FOUND AT http://eportal.bpweb.bp.com/hse
RP: Electric Line Specification and Handling Page 7 of 9
Assuming that the crew was unsuccessful in freeing the stuck tool-string while staying under the maximum
safe working tension of 2,652 lbs, the Wireline Operations Team Lead would need to be notified, apprised
of the situation, and would have to give permission to pull surface tension over 2,652 lbs.
Prior to calling for permission to pull tension over the safe working value, it is a good idea to determine
what surface tension would be necessary to break the weak point in this particular situation as the Wireline
Operations Team Lead will likely want to know and it will help to facilitate a plan forward with appropriate
contingencies. Using basically the same thinking and calculations from above, the surface tension required
to break, or pull out of, the weak point can be calculated as follows:
After discussing the situation and developing a plan with the Team Lead, attempt to free the tool-string as
planned. If unable to do so, confirm with the Team Lead that permission is given to pull out of the weak
point at tension in excess of 2,900 lbs or activate the Electronic Release Sub (ERS)/ECRD, if available, to
leave the tool-string down-hole. Pulling out of the weak point or electronically releasing it should always
be a deliberate act, of which the Team Lead is aware. And in preparation to leave a tool-string down-hole,
always prepare a dimensioned tool sketch for fishing purposes before doing so.
Pull of greater than 3500 lb. on the E-line should never occur given that this is the yield strength of the
conductor line, but if it is necessary due to operational problems, all supervisors should be made aware. In
addition, a 3,500 lb tension on the wire represents a 7,000 lb hook load on the crane which is at or near the
maximum load allowed on most standard cranes in a common boom configuration when rigged up over a
well. Always be sure to verify maximum hook load for the crane as configured over the well and determine
the appropriate maximum surface tension to ensure that the crane is not over-loaded.
For the calculation New Line values are used and therefore, as the outer armor wears, the quantity
of strands calculated may require increasing.
From empirical testing it is known that on a properly constructed weak point with even
distribution of the selected armor on new cable, there is a breaking strength variance of up to
12%.
Well bore temperature decreases armor wire strength by 2% at 100, 8% at 200, 10% at 250 and
12% at 350 degrees Fahrenheit.
Weak point selection should be calculated so that the weight of the E-line plus drag plus pull out
should be less than 3500 lb., which is the insulator conductor package yield strength. Anything
higher than this will likely damage the conductor.
1.) Given a 15,000 feet deep well, 30 degrees deviation, gas filled casing, 4000 psi surface
pressure with a tool weight of 150 lbs we can calculate the required string weight and E-line head
weak point strength.
2.) The E-line weight in air is 95 lbs. per 1000 feet. Buoyancy is normally ignored.
Maximum E-line weight = 15 x 95 = 1425 lbs.
3.) Drag on the tool string is a constant which is usually ignored however, drag on the E-line
should always be considered since it increases with depth, deviation and well direction.
4.) Drag best guess estimate = 150 lbs.
5.) The required tool string weight for 4000 psi. WHP is calculated using a factor of 0.038
pounds sinker bar weight per wellhead psi. plus ~50 pounds to overcome grease injector friction.
6.) Minimum tool string weight = (4000 x 0.038) + 50 = 202 lbs.
7.) The rule of thumb is to choose a weak point that will allow the maximum pull on the cable
to be within the manufacturers working specification which, for this E-line is 2,900 lbs.
8.) To calculate the maximum available breaking strength of the weak point we subtract the
sum of the drag plus the E-line weight from the working specification.
9.) Maximum available breaking strength within working spec. = 2900 - (1425 + 150) = 1325
lbs.
10.) Each armor strand has a breaking strength of 212 lbs. so we can calculate the number of strands to
be used by dividing the required weight by 212 and rounding to the nearest whole strand. When
this is completed the pull out plus E-line weight plus drag should be summed and checked to
ensure that it is less than the conductor/insulation yield by an acceptable factor.
11.) Number of armor strands = 1325 / 212 = 6.25 (6 strands).
12.) Pull to conductor/insulator yield = 3500 – {(6 x 212) + 1425 + 150} = 653 lbs.
13.) Given that the 12% variance on this weak point breaking strength = 0.12 x (6x12) = 153 lbs, this
653 lbs available extra tension is more than adequate to ensure conductor/insulator yield is not
reached.
Revision Log
Revision Date Approving Custodian/ Author Revision Details
Authority
1/09/1993 J. Rathert S. Adcock Original Issue
2/26/2005 Doug Cismoski Jim Moore No revisions necessary
May 21, 2010 Jerry Bixby Scott Bundy / Ron Doc reviewed for technical
Doshier accuracy: Mod sec 5.2, 5.3.
June 18, 2010 Jerry Bixby Jason Dahlem Doc reviewed for tech acc.
Add sect 5 para 5, add
corrosive fluids pg 3, mod
safe working tension pg 5,
add example pg 6.
August 3, 2010 Andy Kirk Chris Tzvetcoff Add BP Confidentiality
Statement
October 15, 2010 Dan Kara Aras Worthington Document reviewed during
"SOP in conformance with
ADWOP project Oct 2010".
Change document
classification to RP from
SOP due to content.
<< Revision date >> << Approving << Author’s Name << Brief Description of
Authority’s Name >> >> Revision >>
(or, see attached e-mail )
Approving Authority signature Date