En TN004-Dead Bus Synchronizing
En TN004-Dead Bus Synchronizing
En TN004-Dead Bus Synchronizing
Author:
Florian Blazak
Head of special projects
Engineering department
p. 2 | K O H L E R - S D M O
1.2 Synchronizing as many generators as possible in less than 15 seconds
For some applications, the voltage must be quickly In general, the power plant does not directly supply
available on the busbar. the load: changeovers switch when the power plant
voltage is available, or when the power plant is
started.
1 1 1 1
3
1 Power plant dead bus synchronizing
2 Changeover contact switching
3 Gradual loading
p. 3 | K O H L E R - S D M O
On large-scale power plants, live bus synchronizing can Using the dead bus synchronizing
take too much time. Indeed, the conventional live bus technique, the entire power plant
synchronizing technique for several generators in is available in 10 to 12 seconds,
parallel involves production equipment deployment since it is not necessary to synchronize
time which is difficult to reduce.
the generators individually.
For example, consider live bus synchronization for 10
generators:
With this method, the voltage will be quickly available
- Generator starting time after the starting
on the busbar. However, the power plant will receive
order: 10 seconds
a load impact at the changeover, which causes
- Time for synchronization between each
frequency and voltage drop according to the load
generator: 1 to 3 seconds
shedding plan. Because they comply with the G3
application class, KOHLER-SDMO generators can
Successively parallel 9 generators to the first one can
absorb these impacts very quickly.
take an average time of 25 seconds.
Note:
This time can be a little bit reduced if the
On a power plant with dead bus synchronizing, the
synchronization of all the generators is done
live bus synchronizing technique for individual
simultaneously, provided that no load is applied on
generators is still available and can be used for the
the plant during this sequence.
power management to adjust the number of
generators in operation according to the site
consumption.
p. 4 | K O H L E R - S D M O
For driven mechanical loads with a parabolic resistive
1.4 Starting loads with a high inrush torque (fans, pumps), the torque supplied by the
current asynchronous motor at nominal voltage is very high
compared to the torque required to drive this load.
Dead bus synchronizing can be used to directly start a The current impact is therefore very large.
load with a very high inrush current, such as an
asynchronous motor (6 to 7 times the nominal A reduced voltage supply lowers the motor torque
current). and therefore the current absorbed at start-up. This
technique prevents oversizing of the alternator to
This application is specific since it requires to supply support the peak current when the asynchronous
only this load. Otherwise, all the other connected machine is started.
loads would have to be shut down if the asynchronous
machine needed to be restarted later.
Applications where dead bus
synchronizing is optional
AVR with
programmable The dead bus synchronizing option is sometimes used
ramp on sites where it is not really necessary. It’s often the
case when the loads or the starting sequence are not
Voltage
established during the project phase.
variator
Examples of power plants on which dead bus
synchronization is optional:
- LV power plant with changeover: if the
changeover time is not a matter, the dead bus
Dead bus synchronizing is similar to starting with a soft synchronizing option is not necessary since
starter with a fixed frequency (generator frequency) the time will be sufficient for live bus coupling
and a voltage ramp provided by the voltage regulator. of the power plant before the changeover
The current impact on the generator is much lower than switches, thanks to the reactivity of our
for direct starting with nominal voltage. regulation modules.
- Production power plants (for any number of
generators).
For many production power plants, the
generators are started individually with
gradual increase of the load.
Figure 1
p. 5 | K O H L E R - S D M O
Power plant extension and
dead bus synchronizing
For power plant extensions, all of the voltage
regulators must be identical to enable dead bus
synchronizing.
In fact, different regulators have different excitation
ramp time, which causes exchanges in reactive power
between the machines and can lead to activate
electrical protections.
Copyright 2018
p. 6 | K O H L E R - S D M O