Facilities For The Engineers: Republic of The Philippines

Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 1

Republic of the Philippines

DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS


LOWER KALINGA
DISTRICT ENGINEERING OFFICE
Cordillera Administrative Region
Bulanao, Tabuk City, Kalinga

CONTRACTOR'S STATEMENT OF WORK ACCOMPLISHED


AS OF: March 8, 2018 - June 5, 2018

CONTRACT ID NO. : 17PL0272 Payment Certificate No. 2


Construction of Two(2) Storey Four(4) Classrooms Workshop Building-1, Kalinga National High
PROJECT NAME :
School, Tabuk City, Kalinga Sheet 1 1
LOCATION : Tabuk City, KaLinga
CONTRACTOR : JQG CONSTRUCTION

Total Qty. Total


ORIGINAL CONTRACT Qty. Approved Balance of
Item No. Description Unit Approved in
in this Billing
Quantity to
Quantity
Cost of this Billing Cost to Date Balance to Cost
Prev. Billing this Date
Quantity Unit Cost Total Cost
Part I Facilities for the Engineers
A.1.1(8) Provision of Field Office for the Engineer (Rental Basis) mos. 6.00 7,500.00 45,000.00 0.75 5.25 5,625.00 5,625.00 39,375.00
0.75
Other General Requirements - - - - - -
B.3 Building Permit and Other LGU Permits l.s. 1.00 65139.07 65,139.07 1.00 1.00 - - 65,139.07 -
B.5 Project Billboard/Signboard set 1.00 3,252.85 3,252.85 1.00 1.00 - - 3,252.85 -
B.7 Occupational Safety and Health Program mos. 6.00 49,221.00 295,326.00 1.80 1.50 3.30 2.70 73,831.50 162,429.30 132,896.70
B.9 Mobilization/Demobilization l.s. 1.00 258,035.65 258,035.65 0.50 0.40 0.90 0.10 103,214.26 232,232.09 25,803.57
Earthworks - - - - - -
801(1) Clearing and Grubbing sq.m. 301.15 276.64 83,310.14 301.15 301.15 - - 83,310.14 -
Package Type Air Conditioning Unit(PACU) 2.0HP coiling
1200(4) set 8.00 78,093.48 624,747.84 - 8.00 - - 624,747.84
Capacity(Floor Standing type)
505(5) Stone Masonry Class "A" cu.m. 46.75 43,615.68 2,039,033.04 - 46.75 - - 2,039,033.04
803(1)a Structure Excavation (Common Soil) cu.m. 206.36 791.77 163,389.66 206.36 206.36 - - 163,389.66 -
804(1)a Embankment form Structure Excavation cu.m. 94.06 187.07 17,595.80 94.06 94.06 - - 17,595.80 -
804(1)b Embankment from Borrow cu.m. 651.50 929.26 605,412.89 179.49 179.49 472.01 - 166,792.88 438,620.01
804(4) Gravel Fill cu.m. 46.06 1,609.97 74,155.22 46.06 46.06 - - 74,155.22 -
Plain and Reinforced Concrete Works - - - - - -
900(1)c1 Structural Concrete (Stair and Sun Breaker) cu.m. 6.97 12,779.31 89,071.79 6.97 6.97 - 89,071.79 89,071.79 -
900(1)c2 Structural Concrete (Footing and Slab-on-Fill) cu.m. 67.86 4,599.00 312,088.14 67.86 67.86 - - 312,088.14 -
900(1)c3 Structural Concrete (Footing Tie Beam) cu.m. 23.58 7,823.90 184,487.56 23.58 23.58 - - 184,487.56 -
900(1)c4 Structural Concrete (Column) cu.m. 34.27 4,987.35 170,916.48 17.14 17.14 34.27 - 85,458.24 170,916.48 -
900(1)c5 Structural Concrete(Suspended Slab) cu.m. 25.68 8,478.75 217,734.30 25.68 25.68 - 217,734.30 217,734.30 -
900(1)c6 Structural Concrete (Beams, Girders) cu.m. 39.74 5,574.60 221,534.60 19.87 19.87 39.74 - 110,767.30 221,534.60 -
902(1)a1 Reinforcing Steel Bars (Deformed, G-40) kgs. 35,844.00 62.31 2,233,439.64 21,024.71 14,819.29 35,844.00 - 923,390.25 2,233,439.64 -
903(2) Forms and Falseworks sq.m. 690.85 386.58 267,068.79 690.85 690.85 - - 267,068.79 -
Finishing and Other Civil Works - - - - - -
1000(1) Soil Poisoning lit. 115.60 843.28 97,483.17 115.60 115.60 - - 97,483.17 -
1046(2)a1 CHB Non-Load Bearing (Including RSB) sq.m. 129.91 2,166.04 281,390.26 129.91 129.91 - 281,390.26 281,390.26 -
1046(2)a2 CHB Non-Load Bearing (Including RSB) sq.m. 383.18 1,485.27 569,125.76 383.18 383.18 - 569,125.76 569,125.76 -
1010(1) Frames set 16.00 8,650.64 138,410.24 - 16.00 - - 138,410.24
1010(2)b Doors (Wood Panel) sq.m. 14.62 3,604.67 52,693.07 - 14.62 - - 52,693.07
1009(1)a Jalousie Window (Glass) sq.m. 24.70 1,856.66 45,859.50 - 24.70 - - 45,859.50
1005(6) Steel Window l.s. 1.00 82,189.61 82,189.61 - 1.00 - - 82,189.61
1005(5) Grille Window sq.m. 26.80 3,051.95 81,792.26 - 26.80 - - 81,792.26

Page 1 of 2

1004(2)a Finishing Hardware (Locksets) set 16.00 4,331.34 69,301.44 - 16.00 - - 69,301.44
1004(2)g Finishing Hardware (Hinges) set 12.00 3,377.54 40,530.48 - 12.00 - - 40,530.48
1003(9) Carpentry & Joinery Works (Chalk Board) l.s. 1.00 88,937.10 88,937.10 - 1.00 - - 88,937.10
1021(1)c Cement Floor Finish (With Floor) sq.m. 584.99 297.17 173,841.48 584.99 584.99 - 173,841.48 173,841.48 -
1027(1) Cement Plaster Finish sq.m. 2,313.80 172.00 397,973.60 1,619.66 1,619.66 694.14 278,581.52 278,581.52 119,392.08
1051(1) Railing m. 74.10 368.40 27,298.44 - 74.10 - - 27,298.44
1038(1) Reflective Insulation sq.m. 316.61 628.81 199,087.53 - 316.61 - - 199,087.53
1018(1) Glazed Tiles & Trims sq.m. 71.55 1,155.91 82,705.36 - 71.55 - - 82,705.36
1018(2) Unglazed Tiles sq.m. 251.60 466.26 117,311.02 - 251.60 - - 117,311.02
1018(3) Granite Tiles sq.m. 378.00 413.29 156,223.62 - 378.00 - - 156,223.62
1003(1)a1 Ceiling sq.m. 325.88 494.38 161,108.55 - 325.88 - - 161,108.55
1032(1)a Painting Works (Masonry/Concrete) sq.m. 2,553.90 116.65 297,912.44 - 2,553.90 - - 297,912.44
1032(1)b Painting Works (Wood) sq.m. 133.27 303.13 40,398.14 - 133.27 - - 40,398.14
1032(1)c Painting Works (Steel) sq.m. 62.73 2,310.04 144,908.81 - 62.73 - - 144,908.81
1014(1)b1 Prepainted Metal Sheets, 0.5mm, Long Span sq.m. 316.61 479.08 151,681.52 316.61 316.61 - 151,681.52 151,681.52 -
1047(8) Structural Steel (Roof Framing) kgs. 9,442.70 109.11 1,030,293.00 9,442.70 9,442.70 - 1,030,293.00 1,030,293.00 -
1047(1) Metal Structure, Fire Scape l.s. 1.00 116,626.10 116,626.10 - 1.00 - - 116,626.10
1001(8) Sewer Line Works l.s. 1.00 74,690.41 74,690.41 - 1.00 - - 74,690.41
1001(9) Storm Drainage/Down Spout l.s. 1.00 92,925.50 92,925.50 - 1.00 - - 92,925.50
1002(28) Cold Water Lines l.s. 1.00 54,657.24 54,657.24 0.30 0.30 0.70 16,397.17 16,397.17 38,260.07
1001(6) Catch Basin, CHB/Septik Tank each 14.00 2,968.93 41,565.02 - 14.00 - - 41,565.02
1002(8) Plumbing Fixtures l.s. 1.00 120,057.90 120,057.90 - 1.00 - - 120,057.90
Part D Electrical - - - - - -
1100(30) Conduit, Boxes & Fittings l.s. 1.00 164,666.50 164,666.50 0.50 0.50 0.50 82,333.25 82,333.25 82,333.25
1101(42) Wires and Wiring Devices l.s. 1.00 22,299.35 22,299.35 0.50 0.50 0.50 11,149.68 11,149.68 11,149.68
1102(27) Power Load Center, Switch Gear & Panel Board l.s. 1.00 70,772.63 70,772.63 - 1.00 - - 70,772.63
1103(1) Lighting Fixtures l.s. 1.00 147,961.17 147,961.17 - 1.00 - - 147,961.17
1208 Fire Alarm System l.s. 1.00 27,047.41 27,047.41 - 1.00 - - 27,047.41
1003(17) Carpentry and Joinery, Furniture l.s. 1.00 74,298.99 74,298.99 - 1.00 - - 74,298.99
13,506,764.08 TOTAL: 4,203,886.28 7,362,540.12 6,144,223.98

WE HEREBY CERTIFY that the Statement of Work Accomplished


on this page is true and correct.

Prepared by: Submitted by: Recommending Approval: Approved:

JQG CONSTRUCTION ADOLFO R. CARBONELL ERNESTO O. VECALDO IRENEO S. GALLATO


Contractor Project Engineer Chief, Construction Section District Engineer
DPWH-LKDEO DPWH-LKDEO DPWH-LKDEO
Page 2 of 2

You might also like