Rate Analysis
Rate Analysis
Total A 4,164.00
Add : 2% Electrical Charges 83.28
Add : 2% Water charges 83.28
Add : 5% over head charge 208.20
Add : Contractor profit 10% 416.40
Rate for 10 Sqm Rs. 4,955.16
Rate for 1 Sqm Rs. 495.52
Rate for 1 Sft Rs. 46.04
As per BOQ M-Sand 1 Sft = Rs. 43
01.10.2018
G IN CM 1:6
Amount
480.00
400.00
50.00 5.00 0.46
50.00
100.00 10sq.m
324.00
2,160.00
375.00
225.00
4,164.00
01.10.2018
RATE ANALYSIS FOR INNER WALLS PLASTERING IN CM 1:6
Data for 10 Smt 15 mm thick(RIVER SAND)
Sl.No Description Unit Qty Rate Amount
Materials
1 Cement Bag 1.20 400.00 480.00
2 Sand Cft 10.00 100.00 1,000.00
3 Stageing L.S 50.00
4 Tools and plants L.S 50.00
5 Arpita mesh above elecrical pipes(For 10 Sqm) Rft 25.00 4.00 100.00
6 Arpith mesh corner beeding Rft 18.00 18.00 324.00
Labours
7 Labour cost ( 10.76x10=108Sft) Sft 108.00 20.00 2,160.00
8 Bull fixing
Mason Nos 0.50 750.00 375.00
Helper Nos 0.50 450.00 225.00
TOTAL AMOUNT A 4,764.00
Total A 4,764.00
Add : 2% Electrical Charges 95.28
Add : 2% Water charges 95.28
Add : 5% over head charge 238.20
Add : Contractor profit 10% 476.40
Rate for 10 Sqm Rs. 5,669.16
Rate for 1 Sqm Rs. 566.92
Rate for 1 Sft Rs. 52.68
As per River Sand 1 Sft = Rs. 53
10sq.m