Major Equipment Life Cycle Cost Analysis PDF
Major Equipment Life Cycle Cost Analysis PDF
Major Equipment Life Cycle Cost Analysis PDF
2014
Recommended Citation
O'Connor, Edward Patrick, "Major equipment life cycle cost analysis" (2014). Graduate Theses and Dissertations. Paper 14216.
This Thesis is brought to you for free and open access by the Graduate College at Digital Repository @ Iowa State University. It has been accepted for
inclusion in Graduate Theses and Dissertations by an authorized administrator of Digital Repository @ Iowa State University. For more information,
please contact [email protected].
Major equipment life cycle cost analysis
by
Edward P. O’Connor
MASTER OF SCIENCE
Ames, Iowa
2014
TABLE OF CONTENTS
LIST OF TABLES .......................................................................................................................... v
LIST OF FIGURES ....................................................................................................................... vi
NOMENCLATURE ..................................................................................................................... vii
ACKNOWLEDGMENTS ............................................................................................................. ix
ABSTRACT ...................................................................................................................................... x
CHAPTER 1. INTRODUCTION ................................................................................................... 1
Background ................................................................................................................................. 1
Equipment life......................................................................................................................... 1
Life cycle cost analysis ........................................................................................................... 4
Public agency financial constraints ......................................................................................... 7
Research Motivation ................................................................................................................. 10
Problem Statement .................................................................................................................... 11
Thesis Organization .................................................................................................................. 12
CHAPTER 2. OVERALL APPROACH TO RESEARCH METHODOLOGY AND
VALIDATION .............................................................................................................................. 14
Methodology ............................................................................................................................. 14
Software analysis .................................................................................................................. 14
Benchmarking survey ........................................................................................................... 15
Minnesota case study analysis .............................................................................................. 16
Equipment data ..................................................................................................................... 18
Deterministic and stochastic equipment LCCA model ......................................................... 18
Equipment economic life calculation.................................................................................... 20
Determining historical fuel cost sampling ranges ................................................................. 21
CHAPTER 3. IMPACT OF FUEL VOLATILITY ON EQUIPMENT ECONOMIC LIFE ....... 23
Abstract ..................................................................................................................................... 23
Introduction ............................................................................................................................... 23
Background ............................................................................................................................... 24
Methodology ............................................................................................................................. 27
Deterministic and stochastic models ..................................................................................... 27
Optimal economic life cycle analysis ................................................................................... 29
Results ....................................................................................................................................... 31
Deterministic equipment example ........................................................................................ 31
Stochastic equipment example.............................................................................................. 33
iii
LIST OF TABLES
LIST OF FIGURES
NOMENCLATURE
CF Consumption Factor
EF Engine Factor
F Future Worth
FC Fuel Cost
FP Fuel Price
i Interest Rate
IC Initial Cost
LC Life Cycle
MV Market Value
viii
N Years of Calculation
P Present Worth
SV Salvage Value
TC Tire Cost
TF Time Factor
ACKNOWLEDGMENTS
I would like to thank Dr. Gransberg for all the support and guidance that he has offered
grateful for the opportunity that he gave me, and I owe a great deal of my success to him.
I would also like to thank the members of my thesis committee, Dr. Jahren and Dr.
Rouse, for supporting me in the classroom and with my research. I have learned a lot from both
of them, and I greatly appreciate all they have done for me.
x
ABSTRACT
Managing a public agency’s equipment fleet is rife with conflicting priorities. One of the
most important aspects is the economic trade-off between the capital cost of replacing a piece of
equipment and the ownership costs of operating and maintaining the machine in question if
retained for another year. Therefore, determining life cycle costs and the economic life is vital
for fleet managers to optimize equipment funds. Currently, most public agencies apply
deterministic methods to make fleet management decisions. These methods do not account for
uncertainty within the input parameters, such as volatility in fuel prices that potentially impact
the replace-or-retain decision. Thus, the objective of this study is to develop a stochastic
equipment life cycle cost analysis (LCCA) model to optimize equipment economic life based on
A public agency does not have financial flexibility; consequently, the constraints on the
use of available funding can affect the replacement and repair cycles for its equipment fleet.
Public sector financial constraints have the potential to put an agency’s fleet into continuous
decline if needed repairs cannot be made and old equipment cannot be replaced when it reaches
the end of its economic life. This research will show that from the public perspective, there is a
predisposition to retain a piece of equipment for as long as possible before replacing it because
of the administrative burden required to get purchase authority. Thus, it is essential for the fleet
manager to have a tool that will provide the accurate information to assist in making major
equipment repair and replacement decisions. The public fund authorization process may require
the agency to identify the need to replace a given piece of equipment a year or more in advance
of the need, making the results of this research both timely and valuable for implementation.
xi
literature review, national survey, case study analysis, and a software content analysis. Data
from the Minneapolis Public Works Fleet Services Division (MPWFSD) was obtained during the
case study analysis to utilize in this thesis. Also, a viable equipment LCCA model, the Peurifoy
and Schexnayder model (PSM), was used in the analysis in addition to the use of engineering
economics. The model utilizes stochastic inputs to quantify uncertainty and determine a given
CHAPTER 1.
INTRODUCTION
The objective of this research is to develop a stochastic equipment LCCA model to determine
the economic life of equipment for a public agency’s fleet. The MPWFSD equipment fleet data
was utilized in the LCCA. This thesis has three main areas of focus:
Stochastic Equipment LCCA Model to Calculate the Economic Life that Varies from
Deterministic Methods
Background
In order to develop an effective and reliable equipment LCCA model the stages of
equipment life had to be established. Also, the equipment LCCA methods had to be examined to
determine the most applicable LCCA method. Therefore, this section presents the fundamental
information from the literature as a basis upon which the analyses were performed. The content
within this chapter is used to complement and support the information found in Chapters 3, 4,
and 5.
Equipment Life
Equipment life can be mathematically defined in three different ways: physical life, profit
life, and economic life (Mitchell 1998). Physical and economic life both must be defined and
calculated when considering equipment life because they provide two important means to
(Douglas 1975). The concepts of depreciation, inflation, investment, maintenance and repairs,
2
downtime, and obsolescence are all integral to a replacement analysis (Gransberg, Popescu, and
Ryan 2006). Combining these concepts and processes allows the equipment manager to properly
Figure 1 shows the relationship between the three stages of each life cycle (Douglas
1978). The graph shows that over the physical life of the machine, it takes some time for the
new machine to earn enough to cover the capital cost of its procurement. It then moves into a
phase where it earns more than it costs to own, operate, and maintain. A machine finishes its life
in a stage where the costs of keeping it going and the productive time lost to repairs it is greater
than what it earns during the periods when it is operational. Thus, an equipment fleet manager
needs tools to identify the point in time where retaining a given piece of equipment is no longer
profitable, and the machine can be replaced by either purchasing a new piece or by leasing an
equivalent piece.
Economic Life
+
Profits
Profit Life
$
0 Physical Life
2 4 6 8 10 12 14
Age at Replacement (years)
Figure 1 also graphically illustrates three different definitions for the useful life of a given
machine: economic life, profit life, and physical life. These are explained in the following
sections.
Physical life
For this research, the physical life of equipment will be identified as the service life. This
time period ends when equipment can no longer be operated. This stage is greatly impacted by
the repair and maintenance attention that the machine has received over its lifespan (Gransberg et
al. 2006). A piece of equipment that has not been given adequate maintenance throughout its
lifespan will deteriorate faster than a machine that was been given substantial preventative
maintenance. Thus, the service lives will vary depending on the piece of equipment and the
Profit life
Profit life is the time period where equipment is generating a profit (Gransberg et al.
2006). This is the most desired stage of the equipment life because after this point in time the
equipment will operate with a loss (Douglas 1978). “Increasingly costly repairs exacerbate this
as major components wear out and need to be replaced” (Gransberg et al. 2006). Thus, this is a
critical stage in the equipment life to maximize on profitability and efficiencies. Also, the
equipment fleet manager must be able to determine this time period to implement a replacement
plan for a new machine while the components are useful (Gransberg et al. 2006).
4
Economic life
Economic life is based on decreasing ownership costs with the increase in operating costs
(Mitchell 1998). The time period where these costs are equivalent is called the economic life.
When the operating costs exceed the ownership costs, a piece of equipment is costing more to
operate than to own. To maximize profits, the replacement of a piece of equipment should occur
before the economic life is reached. “The proper timing of equipment replacement prevents an
erosion of profitability by the increased cost of maintenance and operation as the equipment ages
The economic life will be the primary tool applied in the research to determine the
replacement time period. The usage of engineering economics will be utilized to calculate the
optimal economic life based on principles laid down by Park (2011) and Peurifoy and
Schexnayder (2002). Of the equipment life cycle cost models proposed Peuifoy and
Schexnayder (2002), one will be extended by incorporating stochastic inputs to the economic life
determination calculation.
replacement analysis, and replacement models. The decision to repair, overhaul, or replace a
piece of equipment in a public agency’s fleet is a function of ownership and operating costs.
This research explores the impact of commodity price volatility, as well as normal variation, in
the costs of tires and repair parts. The accuracy of the life cycle costs can be improved by
implementing stochastic functions. Thus, this research employed a stochastic model to better
depict life cycle costs and compute optimal economic life to improve equipment fleet decisions.
5
Life cycle costs for equipment have two components: ownership costs and operating
costs. Ownership costs include initial costs, depreciation, insurance, taxes, storage, and
investment costs (Peurifoy and Schexnayder 2002). Operating costs include repair and
maintenance, tire, tire repair, fuel, operator, and any other consumable equipment cost
(Gransberg et al. 2006). The MPWFSD provided equipment fleet data which was used in the
research to evaluate equipment life and answer the research questions in a quantitative manner.
Stochastic Modeling
that phenomenon” (Pinsky and Karlin 2011). A deterministic phenomenon or model predicts a
single result from a set of conditions (Pinsky and Karlin 2011). A stochastic phenomenon does
not always lead to the same outcome but to different results regulated by statistical regularity
(Haldorsen and Damselth 1990). The prediction of a stochastic model is built by articulating the
Pinsky and Karlin (2011) hold that stochastic modeling has three components:
3. A connection or equation which links the elements of the system under study together.
model because phenomena are not naturally stochastic (Pinsky and Karlin 2011). This allows
A critical part of the stochastic models is the probability functions used to determine the
outcome of a phenomenon. The equally likely approach, originated in 1812, “was made to
define the probability of an event A as the ratio of the total number of ways that A could occur to
the total number of possible outcomes of the experiment” (Pinsky and Karlin 2011). This
approach is the basis for the utilization of the distributions of probabilities in the stochastic
models.
The stochastic process utilizes random variables within a model to determine the most likely
outcome. The random variables are generated using Monte Carlo simulations. Monte Carlo
simulations perform iterations, using random variables, on the output of a stochastic model. The
results are then obtained from the simulation based on statistical data. The equipment LCCA
model proposed in this thesis is a stochastic process applied to the economic life of equipment
The PSM to calculate life cycle costs for equipment was employed for this research. R.L.
2006). Thus, the model was selected for the equipment LCCA. The parameters of the model are
explained below.
The PSM equipment LCCA model utilizes cost factors that are separated into ownership
and operating costs. The initial cost is defined as the purchase amount of a piece of equipment
minus the tire cost (Peurifoy and Schexnayder 2002). Taxes, insurance, and storage costs are
calculated as a single percentage of initial costs. Ownership costs are determined by computing
the equivalent uniform annual cost (EUAC) of the initial costs and the estimated salvage value.
7
The PSM operating costs include the fuel costs; repair and maintenance costs; filter, oil,
and grease (FOG) costs; tire cost; and tire repair costs. Fuel costs include a function “of how a
machine is used in the field and the local cost of fuel” (Peurifoy and Schexnayder 2002). To
calculate the fuel costs, a consumption rate is multiplied by the fuel price, engine horsepower,
time, and engine factor. The time factor is based on the production rate in an hour, and engine
The repair and maintenance costs are calculated as a percentage of the annual
depreciation. This method uses the straight-line method for depreciation. The percentage for the
repair and maintenance cost is a function of the machine type and work application. Also, the
equipment ownership cost model and contained all the elements necessary to allow it to be
transformed into a stochastic LCCA model for use in this research. However, the PSM was
originally developed for use in private industry by construction contractors (Peurifoy and
Schexnayder 2002), and as a result must be adapted for application to public agency equipment
fleet management decisions. For example, since public agencies do not pay sales or property
taxes, the tax component was dropped from the PSM to adapt it to the final deterministic model
for the public sector. The subsequent paragraphs in this section will discuss the other
adjustments made to make the PSM fully applicable to the typical public agency’s financial
environment.
8
Private contractors operate with access to requisite funding when it is time to repair or
replace a specific piece of equipment. This is not the case in the public sector. The major source
of funding for public equipment fleet expenses comes from tax revenues that feed capital budgets
(Antich 2010). Public purchases of capital equipment must often gain approval from an
appropriate authority and be paid for from tax revenues that were collected for this purpose.
This creates a constraint on expenditures that is often referred to as the “color of money,” where
it is possible to have surplus funds that were designated for one purpose in the public coffers
while at the same time have insufficient funds to make purchases for another specific purpose
(Lang 2008). The most common situation is a strict separation of capital expenditures for the
purchase of new pieces of equipment from operations and maintenance expenses, which are
designated to pay for routine expenses such as fuel and repair parts (Lang 2008). Often major
capital expenses must pass through an appropriations process where the governing authority
reviews and approves a specific sum of money to purchase a specific item. This process may
require the agency to identify the need to replace a given piece of equipment a year or more in
advance of the need, making the results of this research both timely and valuable for
implementation.
The City of Minneapolis, whose equipment fleet records are used in the subsequent
analysis, provides an excellent example of the constraints faced by public agency equipment fleet
managers. Its operating budget is established to “ensure maintenance of capital assets and
infrastructure in the most cost-efficient manner” (COM 2014). Within that budget, the
equipment fleet will be repaired and replaced from current revenues “where possible” (COM
2014). Minneapolis maintains a five-year capital improvement program (CIP) that provides
funding for capital projects (COM 2014). Equipment fleet is not “the [appropriate] asset nature
9
to fund through the City’s CIP process” (COM 2014). Thus, Minneapolis maintains a separate
five-year funding plan to address major equipment purchases (COM 2014). Theoretically, to get
the purchase of a piece of equipment into this budget, the equipment fleet manager is required to
make replacement decisions at least five years in advance of the need to provide the time for the
City to appropriate the necessary funding. While private contractors often have long-term
equipment replacement plans of their own, they are not constrained to executing deviations from
that plan because they are in full control of what and when available financial resources are
expended. Minneapolis’ five-year plan for equipment forces its equipment fleet manager to
make decisions in conditions of greater uncertainty than that faced by its private-sector
counterpart. Thus, using a stochastic LCCA model to inform these decisions is more appropriate
for the public sector because of the length of the decisions’ time horizon.
Some public agencies avail themselves of other funding mechanisms to partially support
their fleet operations. Examples are grant acquisitions, purchasing of used parts, and leasing
agreements (Antich 2010). Private contractors normally have an immediately available line of
credit upon which they can draw to finance large purchases whether planned or unexpected (The
Bond Exchange 2010). A public agency does not have the same financial flexibility;
consequently, the constraints on the use of available funding can affect the replacement and
repair cycles for equipment fleet. For example, the City of Macomb, Michigan deferred all
vehicle and equipment purchases for one year in 2010 due to budget deficits. As a result, in
2011 they were faced with substantially higher maintenance and repair costs (Antich 2010).
While choosing the null option of not spending money on the equipment fleet may have been an
unavoidable fiscal reality, the consequence was that the decision effectively extended the service
life of the equipment scheduled to be replaced in 2010 beyond its economic life. The result
10
unacceptably high repair costs and could end up being disposed of at a salvage value far below
the unit’s possible market value if it had been repaired the previous year (Antich 2010).
The other issue is purely mechanical as experience has shown that idle equipment
deteriorates if it is not operated as designed. Things like gaskets and seals dry out causing fluid
to leak or the gasket to blow when the machine is operated for the first time after a long period of
being idle (Moss 2014). Thus, the public sectors financial constraints have the potential to put an
agency’s fleet into a virtual demise if needed repairs cannot be made, and old equipment cannot
be replaced when it reaches the end of its economic life. One can infer from this discussion that
from the public’s perspective, there is a strong tendency to keep a piece of equipment for as long
as possible before replacing it because of the administrative burden required to get purchase
authority. Therefore, it is critical that the fleet manager have a tool that will provide the most
accurate information to assist in making major repair and replacement decisions. Developing
Research Motivation
Managing an agency’s major equipment fleet is rife with conflicting priorities. One of the
most important is the economic trade-off between the capital cost of replacing a piece of
equipment and the ownership costs of operating and maintaining the machine in question if
retained for another year. Therefore, determining life cycle costs and the economic life is vital
Many studies have been completed on equipment replacement optimization. For example,
Fan and Jin (2011) applied a decision tree to determine the significant factors in the economic
11
life determination of construction equipment. The utilization of EUAC was used to find the
replacement age of equipment within the North Carolina Department of Transportation (DOT)
fleet (Kauffman et al. 2012). Previous studies do not have a stochastic function that models
volatility in commodity pricing for input variables like diesel fuel to determine the economic life
of equipment. This research has developed a robust method permitting equipment fleet
managers to maximize the cost effectiveness of the fleet by optimizing the overall life cycle
Problem Statement
The effective management of equipment fleet is a vital part of a public agency. A public
agency’s equipment fleet decisions are often made years in advance of actual purchases and
usually involve a mandate to minimize costs (COM 2014). Therefore, the need to accurately
determine the life cycle costs and replacement age is significant. Additionally, fleet management
software based on basic engineering economic theory oversimplifies this complex relationship
by failing to account for non-financial input parameters, such as the agency’s sustainability
goals, volatility of fuel prices, actual annual usage rates for seasonal equipment, etc.
Deterministic equipment LCCA models only provide results based on discrete input
parameters while a stochastic model utilizes a distribution of values to improve the accuracy of
the output (Pinsky and Karlin 2011). By taking into account operating costs and non-financial
parameters, better decisions may be made by fleet managers with an expanded understanding of
how each input parameter impacts the final decision. A stochastic equipment LCCA model will
be proposed for use by equipment fleet managers to sell, purchase, or repair pieces of equipment
How does uncertainty in the input variables to the classic LCCA methodology impact
The primary research question is addressed by answering the following three specific
questions:
1. How does volatility in fuel costs and variation in interest rates impact equipment
economic life?
2. How does uncertainty in other input parameters impact equipment life cycle cost and,
3. Can stochastic models be used to determine equipment economic life in a manner that is
Thesis Organization
This thesis contains three journal papers in chapters 3, 4, and 5. Each paper is related to
equipment LCCA, but each is intended to provide the answers to one of the three specific
questions detailed in the previous section. Chapter 1 provides complementary information that is
needed to understand the concepts that were utilized throughout this thesis. Chapter 2 contains
the research methodology and supplemental information that was completed for this thesis.
Chapter 3 discusses the influence of fuel volatility and interest rate variation within the
stochastic equipment LCCA model. Chapter 4 determines which equipment LCCA input
parameters have the greatest impact on equipment life cycle costs by utilizing a sensitivity
analysis of the stochastic model. Finally, Chapter 5 applies a stochastic equipment LCCA model
to determine the economic life that is different than the deterministic methods.
13
Chapter 6 contains the conclusion and limitations of the thesis based on the previous
chapters. Chapter 7 encompasses the recommendations for future research related to the work
that has been completed in this thesis. After Chapter 7, the appendices contain supplemental
CHAPTER 2.
OVERALL APPROACH TO RESEARCH METHODOLOGY AND VALIDATION
Figure 2 displays the research methodology that was employed for this study. This is the overall
approach in the development of the stochastic model and economic life determination used to
Methodology
The research steps and instruments are detailed within each paper in Chapters 3, 4, and 5.
This chapter contains the stochastic model that was developed based on the PSM to calculate
equipment life cycle costs (2002). The use of engineering economics is detailed to explain the
economic life calculation based on the works of Park (2011). Additionally, the statistical F-test
is defined because it was applied to determine the historical fuel price range in Chapters 4 and 5.
Software Analysis
Current LCCA and fleet management software is extensive and diverse. Each platform
has unique abilities for varying applications. This research conducted an analysis of twenty-
eight individual, commercial products to differentiate between software packages. The purpose
of this research effort was to determine if any existing packages would serve as viable software
15
programs for use by the Minnesota Local Road Research Board (LRRB) members. Each piece
of software was analyzed on its features, capabilities, and functionality. Based on this analysis, a
determination of the viability of the software and its ability to satisfy the needs articulated in the
The primary research instrument was a formal content analysis of the features,
capabilities, and functions found in the marketing and specification literature available on the
Internet. A content analysis can be used to develop “valid inferences from a message, written or
visual, using a set of procedures” (Neuendorf 2002). Based on the equipment LCCA
capabilities, the most viable software programs were Fleet Maintenance Pro, Fleet & Equipment
The programs were found to have the highest capabilities to apply to the LCCA of the equipment
fleet.
Benchmarking Survey
An online survey was distributed to benchmark the usage of LCCA and other parameters
in agency fleet management programs. The questionnaire was developed from the literature
review and assembled in accordance with the thirteen-point protocol established by Oppenheim
The survey was distributed by the City of Minneapolis to solicit a substantial amount of
management. The main objective of the survey was to gather information about input
parameters, fleet data, budget information, and the decision-making processes for equipment.
The survey results were found to be inconclusive based on the limited number of respondents
The case study analysis for this research involved three agencies: the City of Eagan, the
City of Minneapolis, and Dodge County. The candidates were selected by the research team
because they comprise three different levels of equipment fleet sizes and practices. Minneapolis
is a large city; Eagan is a small city, and Dodge is a county. The case studies were conducted
through structured interviews of the stakeholders in each agency. The objective of the case
City of Eagan: Eagan utilizes a vehicle rating policy to determine repair and replacement
decisions. The policy is based on the age of the vehicle and a rating system. Once the piece of
equipment reaches a certain criteria, the vehicle is evaluated and reviewed to determine if a
replacement is required. The repair decisions for pieces of equipment are related to the rating
system as well. Pieces of equipment are repaired and maintained until they reach the minimum
major equipment fleet decisions. The utilization of the M5 software program, minimum cost
method, and maximum number of hours are some of the components that aid in equipment
decisions. The replacement evaluation has three major sets of information that are analyzed
including equipment life cycle, equipment utilization, and the business need of the equipment.
The repair process is specified by 50% to 60% of the original value of a piece of equipment. If a
piece of equipment is above the optimal range of 50% to 60% of the initial value then the
equipment is repaired. Utilization and agency need are vital in the repair and replacement
Dodge County: Dodge County does not utilize any formal decision making techniques to
make equipment fleet decisions. The replacement process is based on the needs and allowable
budget. Also, repairs for both light and heavy pieces of equipment are performed on an as-
The City of Minneapolis and the City of Eagan have the most dynamic equipment fleet
replacement and repair policies. Dodge County’s absence of overall structure within the
equipment fleet management is mostly due to the lack of data recording and policy
implementation. The City of Minneapolis and the City of Eagan are the most significant case
18
studies for this research project. Therefore, the data used for this research is from the City of
Minneapolis. Chapters 3, 4, and 5 all use equipment fleet data that was provided from the City
of Minneapolis.
Equipment Data
Two options were evaluated when deciding on the data to use for this thesis. The first
option was to use data gathered from the MPWFSD, and the second option was obtaining data
from the literature review. The MPWFSD provided historical equipment fleet data dating back
to 2009. Some of the data was able to be utilized in this thesis, such as service lives, acquisition
costs, and salvage values. However not all the data was able to be exploited such as the repair,
maintenance, tire, tire repair, and depreciation cost. Regression analysis was performed to
determine if the data could be employed; however, with the lack of historical data, this option
was found to be inapplicable. The quality of the data from the MPWFSD was not consistent, and
the data for the equipment had to be derived from the literature review.
The equipment LCCA model was built on the components of the PSM and engineering
economics. The model was employed in all the papers found in Chapters 3, 4, and 5. The model
Where:
LCC = Life cycle cost
Operating Cost = R&MC + FC + TC + TRC
R&MC = Repair and maintenance cost
FC = Fuel cost
19
TC = Tire cost
TRC = Tire repair cost
The operating costs are based on Equations 2 through 6 (Peurifoy and Schexnayder 2002,
Atcheson 1993). Equation 3 is used to calculate the repair and maintenance costs at a constant
rate each year, while Equation 4 is used to calculate the repair and maintenance costs in a given
year. Equation 4 is used in the economic life determination because it may be applied
Where:
IC = Initial Cost
SV = Salvage Value
N = Useful Life
𝑌𝑒𝑎𝑟 𝐷𝑖𝑔𝑖𝑡
Years R&MC = ((𝑆𝑢𝑚 𝑜𝑓 𝑌𝑒𝑎𝑟𝑠 𝐷𝑖𝑔𝑖𝑡) 𝑥 𝑇𝑜𝑡𝑎𝑙 𝑟𝑒𝑝𝑎𝑖𝑟 𝐶𝑜𝑠𝑡) + 𝑅&𝑀𝐶 (4)
Where:
Year Digit = Year taken in ascending order
Sum of Years Digit = Sum of years’ digit for the depreciation period
Total Repair Cost = Repair Factor x (List Price – Tire Cost)
Repair Factors given by Table 1
FC = TF x EF x CF x hp x FP (5)
Where:
TF = Time factor, based on the minutes of productivity within an hour utilized as a
percent
EF = Engine factor, based on the percent of horsepower utilized
CF = Consumption factor, units of gallon of fuel per flywheel horsepower hour
(gal/fwhp-hr)
hp = Engine horsepower
FP = Fuel price, units of $/gal
TRC = % of TC (6)
The ownership costs for the model utilize Equations 7 and 8 (Peurifoy and Schexnayder 2002,
Park 2011).
AP = P[(i(1+i)N)/((1+i)N-1] (8)
Where:
IC = (list price – tire cost)
SV = % of the initial cost
N = Year of calculation
i = Interest rate
P = Present worth
The economic life calculation is used in Chapters 3 and 5. The EUAC takes into account
the operating and ownership cost differently than the life cycle cost calculations, shown in
Equations 9 through 12 (Park 2011). The ownership costs utilize the market value of the vehicle
in a given year, displayed by Equation 11 (Park 2011). The operating costs must also be
21
calculated, using Equation 10, on an annual basis in a given year to properly calculate the EUAC
(Park 2011).
PF = P[F(1+i)-N] (12)
Where:
IC = (list price – tire cost)
SN = Market value at the end the ownership period of N years
N = Year of calculation
i = Interest rate
P = Present worth
F = Future worth
The statistical F-test was applied to determine the historical fuel cost sampling ranges for
Chapters 4 and 5. “The F-test evaluates the ratio of two variances as evidence to test the null
hypothesis that two population variances are equal” (LeBlanc 2004). The data used for the F-test
must be obtained from “unbiased study design” to create a population variance and a normal
distribution (LeBlanc 2004). A major assumption of the test is that both populations under
investigation have a normal distribution (LeBlanc 2004). The F-test uses Equation 13 to
determine the ratio (LeBlanc 2004). This equation is based on the variances, S, within two
populations.
The larger of the two variances is placed in the numerator and the smaller in the
denominator (LeBlanc 2004). The null hypothesis is true if the ratio is calculated to be 1.0, but
the larger the ratio the “stronger the evidence that the two population variances are unequal”
(LeBlanc 2004).
The F-test may be employed for a one or two-tailed test, with the p-value determining the
significance of the data. The p-value represents the area on the right and left end of a normal
distribution for a two-tailed test (LeBlanc 2004). If p ≤ 0.05, “the probability associated with the
random-variation explanation for the observed difference between the two sample variances is
sufficiently low to reject this explanation” (LeBlanc 2004). Thus, if the p-value was greater than
0.05 the null hypothesis could be rejected and the two samples do not have significantly similar
data. This logic will be employed to determine the appropriate choice, in months, for the
CHAPTER 3.
IMPACT OF FUEL VOLATILITY ON EQUIPMENT ECONOMIC LIFE
O’Connor, E.P. and D.D. Gransberg, “Impact of Fuel Volatility on Equipment Economic Life,”
(to be submitted for publication in the Journal for Construction Engineering and Management,
ASCE, in 2014).
Abstract
Diesel fuel prices are currently more volatile than in any time in the past two decades. As
a result, its impact on public agency equipment fleet management decisions is more prominent
than ever before. Therefore, the purpose of this research is to quantify the impact of fuel
volatility on the economic life of equipment and provide guidance on how to factor this major
operating cost into public agency fleet repair, overhaul, and replacement decisions. The authors
demonstrate the impact using both deterministic and stochastic equipment economic life cost
models. An example utilizing a 2002 Sterling LT9500 dump truck is provided to demonstrate
the difference between the two models. When the stochastic model is used, the equipment
management decision can be enhanced by associating a confidence level with the economic life
determination. The researchers find that a 50% increase in fuel costs creates a 32% increase in
the life cycle cost, which reduces the economic life of the truck. It was also concluded that the
life cycle cost model is most sensitive to the interest rate used and the fuel costs.
Introduction
Equipment replacement decisions are critical to the success of public agency fleet
management. If a piece of equipment is not replaced at the end of its economic service life, the
maintenance, repair, and fuel consumption costs will outweigh the value of its purpose (Jensen
24
and Bard 2002), eating more than its fair share of the agency’s limited operations budget. The
issue is exacerbated by the fact that in most cases purchases of new equipment are made using
the agency’s capital budget, which typically requires approval from authorities in the fleet
manager’s chain of command (Gransberg et al. 2006). Therefore, if a machine is selected for
replacement before it literally stops running, the fleet manager must be able to justify the
purchase to those individuals. To do so often requires a means to demonstrate the business case
for buying a new machine rather than keeping the old one for another year.
The purpose of this paper is to demonstrate the usage of a deterministic and stochastic
model to quantify equipment life cycle costs, economic life, and the impact of fuel volatility.
The usage of commercial software will be employed to perform Monte Carlo simulations to
calculate the stochastic life cycle costs. Also, a sensitivity analysis will be performed to
determine the impact of fuel fluctuation. An example using a dump truck from the MPWFSD
equipment fleet will be used to demonstrate the fuel impact and the difference between the
Background
Past research has provided a number of options to base the replacement decision on
accepted financial terms that are easily understood by nontechnical personnel with limited fleet
management expertise or experience. According to Fan and Jin (2011), the most widely
accepted approach is called the “cost minimization method” which was first proposed by Taylor
(1923). Schexnayder (1980) describes it as “the most appropriate analysis method” and proposes
that it “yields an optimum replacement timing cycle and a corresponding equivalent annual
cost.” The method was adapted for public transportation agencies by Gillerspie and Hyde
25
(2004). All three models use life cycle cost analysis based on engineering economics to identify
a point in a given machine’s life where the cumulative cost of operating and ownership is at its
minimum. Figure 3 graphically illustrates the basis of this theory. It shows that as a piece of
equipment ages, its capital value decreases while its operation and maintenance costs increase.
The theoretical optimum service life is the point where cumulative costs are at the minimum and
Each of the models described above are deterministic models that require the analyst to
develop single values for each input variable. Thus, the economic life is really a snapshot based
on the values used at the time of the analysis. While all models are merely mathematical analogs
for real conditions, assuming a given cost for a significant variable like fuel prices makes the
output used by the decision-maker highly dependent on the quality of the assumptions used in
the analysis. Two key input variables are the interest rate used in the model and the values used
26
for operating costs that are highly volatile, like fuel prices. According to Schexnayder (1980),
“because the analysis process incorporates [engineering economics] procedures it was necessary
to establish the correct interest rate factor.” The interest rate assumption issue was validated by
several other studies (Pittenger et al. 2012, Gransberg 2009, Gransberg and Kelly 2008,
Gransberg and Scheepbouwer 2010), and in each case the value of allowing the interest rate to be
Diesel fuel prices are also an input variable that fluctuate within a wide range and are
“considered as a significant input to the annual operating costs” (Richardson 2007). Therefore,
understanding the impact of fuel prices is vital to optimize the life cycle equipment fleet
management decisions. Figure 4 depicts the monthly diesel fuel prices from January 2011 to
March 2014 (U.S. Department of Energy 2014). The quantities shown in the figure were used
for the creation of the stochastic model. The fuel prices are shown to fluctuate from three to four
dollars with no certain pattern. Thus, this volatility impacts the life cycle costs and equipment
decisions substantially. The fluctuation in the fuel costs directly impacts the life cycle costs of
equipment because life cycle costs will increase along with the fuel prices, which directly impact
the calculated economic life of the equipment. By allowing the fuel price input variable to vary
over its historic range, a better life cycle cost may be achieved. Consequently, making fuel costs
a stochastic input will allow for a more realistic calculation in the economic life determination.
27
4.5
4
3.5
3
Fuel Price 2.5
($/gal) 2
1.5
1
0.5
0
Date
Methodology
The methodology for this study is based on the deterministic and stochastic models to
calculate equipment life cycle costs. A stochastic economic life determination is applied to
further examine replacement ages and aid the public agency’s equipment fleet managers.
Both models were developed using equipment ownership cost inputs prescribed by
Peurifoy and Schexnayder (2002) and engineering economic LCCA to determine the economic
life of equipment. The overall goal of the model was to optimize the life cycle costs and the
economic life of equipment for a pubic agency’s fleet. To accomplish this the fuel volatility,
interest rate fluctuation, and changing market values were made to be stochastic inputs for the
28
model. Monte Carlo simulations were then run to produce probability distributions which allow
The PSM was determined to be the most thorough and applicable method that could be
applied in the development of the model. The method was adapted to apply to a public agency.
For example, since public agencies don’t pay sales or property taxes, that component was
dropped in the formulation of the final deterministic model illustrated in the remainder of this
paper.
The input parameters utilized in the PSM to formulate the deterministic and stochastic
models consist of solely cost variables. The costs are analyzed on an annual basis for all the
parameters. Therefore, the final output for the life cycle cost is an annual amount. Since most
agency budgets are based on the fiscal year, using EUAC analysis provides output in a form that
correlates with the purpose for conducting the analysis: to determine the required equipment
replacement capital budget (Pittenger et al. 2012). The model uses Equation 1 to determine the
The operating costs for the deterministic and stochastic models are based on Equations 2
through 6 (Peurifoy and Schexnayder 2002, Park 2011). Equation 4 is used to calculate the
repair and maintenance cost in a given year, while Equation 3 is used to calculate the repair and
maintenance costs at a constant rate each year. The ownership costs for the deterministic and
For this study, Equation 5 used a 50-minute productive hour for the time factor, which
equates to 0.83. Also, for Equation 5, 0.04 gal/fwhp-hr was used for the consumption factor and
1.0 was used for the engine factor. For Equation 3, 37% was used for the repair and maintenance
29
factor, and 16% was used for the tire repair factor in equation 6 (Peurifoy and Schexnayder
2002).
Figure 5 summarizes the stochastic LCCA model based on the adapted public sector
version of the PSM. The stochastic inputs are the fuel costs within the operating costs and the
interest rate used in the ownership costs. The deterministic inputs include the initial cost,
salvage value, useful life, depreciation, tire cost, and tire repair costs.
Fuel Cost
Stochastic
Parameters
Interest Rate
Initial Cost
Annual Life Cycle Peurifoy/Schexnayder
Costs Method
Salvage Value
Useful Life
Deterministic
Parameters
Depreciation
Tire Cost
The determination of the economic life for equipment fleet is a critical component of the
LCCA. The economic life, or the optimal time to sell a piece of equipment, requires the usage of
EUAC calculations. To properly use the EUAC, the ownership costs and operating costs must
be calculated on an annual basis in the correct year. The life cycle costs must also be calculated,
30
using Equation 9, on an annual basis in a given year to properly calculate the EUAC (Park 2011).
Additionally, Equations 10 and 11 are utilized for the operating and ownership costs within the
Schexnayder (1980) found that in the private sector that “the proper interest rate is the
cost-of-capital rate for the particular firm making the analysis.” Public agencies may or may not
be able to determine its own cost-of-capital. However, if the replacement equipment will be
funded by the sale of municipal bonds or some other financial instrument, then that rate would be
appropriate. Therefore, the need to evaluate life cycle cost using a stochastic interest rate is no
longer necessary.
The calculation of the EUAC is done over the entire life span for a piece of equipment.
The lowest EUAC in a given year will be the optimal economic life. This will be the point in
time in which the piece of equipment has the lowest combined operating and ownership costs.
Figure 6 summarizes the stochastic inputs that were utilized during the economic life
calculations. Since the interest rate is a stochastic input, all the calculations for the economic life
employ a stochastic function. Additionally, the market value has been applied stochastically
Results
The results contain the output from the deterministic and stochastic equipment example.
A sensitivity analysis quantified the impact of fuel volatility associated with the LCCA.
Additionally, the stochastic model is compared with the deterministic model to illustrate the
discrepancies.
A 2002 Sterling LT9500 dump truck was employed in an example to demonstrate the
deterministic method. The data for the dump truck was derived from the records furnished by
the MPWFSD. Table 2 shows the information that was used during the formation of the model
for the dump truck. The dump truck was chosen for this demonstration because it is a typical
Table 2. Deterministic LCCA for the 2002 Sterling LT9500 Dump Truck
Parameters 2002 Sterling LT9500 Dump Truck
Initial Cost $96,339
Annual Usage in Hours 1000
Annual Initial Cost (AIC) $11,265
Tire Cost $3,240
Salvage Value (12%) $11,561
Annual Salve Value (ASV) $1,456
Useful Life 14
Sum of Years Digit 105
Change in Market Value 10.60%
Interest Rate 7.38%
Depreciation $6,056
Tire Repair Costs $518
R&MC $2,241
Fuel Price $3.54/gal
Fuel Costs $50,523
Total Operating Costs $56,522
Ownership Costs $9,809
Annual Life Cycle Cost $66,330
32
Figure 7 depicts the plot of the annual life cycle costs for the 2002 Sterling LT9500 dump
truck versus varying fuel prices. As fuel prices increase, the annual life cycle cost of the dump
truck increases. The figure shows the drastic impact of the fuel pricing to the life cycle costs of a
piece of equipment. This figure stresses the importance of accurately calculating the fuel costs to
120,000
100,000
80,000
Annual Life
60,000
Cycle Cost ($)
40,000
20,000
0
0.0 1.0 2.0 3.0 4.0 5.0 6.0 7.0
Fuel Price ($/gal)
Figure 8 shows the optimal economic life of the dump truck. The plot consists of the
annual costs versus replacement age of the dump truck with the associated cost parameters. The
economic life of the dump truck is depicted by the dashed line at year 12, this is the optimal
point where the R&MC are increasing while the ownership costs are decreasing.
33
80,000
70,000
60,000
Ownership
50,000 Costs
Annual Cost ($)
40,000
Operating Costs
30,000
20,000
Annual
10,000 Equivalent
- Costs
0 2 4 6 8 10 12 14
Replacement Age (yrs.)
Figure 8. Economic Life of the Dump Truck Using Deterministic Model
After the creation of the deterministic model, input values for the variables of interest are
allowed to vary within their historic ranges in the stochastic model. The first priority was to
create probability distributions for the stochastic inputs. Utilizing the 2002 Sterling LT9500
dump truck, the fuel prices, interest rate, and market value were made to be stochastic inputs.
After creating distributions for the stochastic inputs, the stochastic model was created. The
model ran Monte Carlo simulations to calculate the expected life cycle costs. Table 3
summarizes the parameters of the stochastic model and the output. The fuel cost, interest rate,
market value, and annual life cycle costs are shown in Table 3 by the output that was calculated
in the simulation. The market value was only utilized in the economic life calculations.
34
Table 3. Stochastic LCCA for the 2002 Sterling LT9500 dump truck
Parameters 2002 Sterling LT9500 dump truck
Initial Cost $96,339
Annual Usage in Hours 1000
Annual Initial Cost (AIC) $11,049
Tire Cost $3,240
Salvage Value (12%) $11,561
Annual Salve Value (ASV) $1,300
Useful Life 14
Sum of Years Digit 105
Change in Market Value 10.78%
Interest Rate 7.05%
Depreciation $6,056
Tire Repair Costs $518
R&MC $2,241
Fuel Costs $50,813
Total Operating Costs $56,812
Ownership Costs $9,749
Annual Life Cycle Costs $66,560
Figure 9 shows the model’s sensitivity to both interest rates and fuel prices. This diagram
depicts the relationship between the input values and the impact to the annual life cycle costs.
According to this simulation, the interest rate is shown to have a higher financial impact than the
fuel prices in the calculation of the life cycle costs for the dump truck.
Interest Rate
$42,646.39 $66,855.14
Fuel Prices
$58,533.62 $68,641.29
Baseline = $63,553.18
$65,000
$50,000
$70,000
$60,000
$40,000
$45,000
$55,000
Figure 9. Input Sensitivity for the 2002 Sterling LT9500 dump truck
35
Figure 10 shows the economic life of the dump truck using the output from the stochastic
model. The yellow triangle specifies the optimal economic life (i.e. the replacement age) of the
2002 Sterling LT9500 dump truck. The figure shows that as the level of confidence increases
both the EUAC and the economic life increase. With a 90% confidence, an economic life of
fourteen years was determined, which is equal to the service life of the dump truck.
82000
Lowest EUAC
81000
80000
79000
78000
90%
EUAC ($) 77000 85%
80%
76000
75%
70%
75000
74000
73000
72000
1 2 3 4 5 6 7 8 9 10 11 12 13 14
Life (yrs.)
Figure 10. Economic Life of the dump truck using the Stochastic Model
Figure 10 provides the equipment fleet manager with information not available in a
deterministic model’s output. The range of 70% confidence to 90% confidence translates to an
36
economic life between 11 and 14 years. Thus, if the equipment fleet manager wants to be
completely sure that a piece of equipment has achieved its maximum economic life, then the
truck would be retained in the fleet for 14 years. However, that desire to get the most value out
of each capital equipment investment would be offset by the potential loss if the equipment had
been replaced with the most current technology at an earlier point in its service life. Therefore,
the best way to interpret the output shown in Figure 10 is to use it as a trigger point to begin a
detailed evaluation of the costs and benefits of retaining the current piece of equipment for
another year or replacing it with a comparable new machine. Taking this approach to decision-
making would then trigger the fleet manager to begin an annual retain-replace analysis starting in
year 11 and repeat it in years 12 and 13 with a replacement occurring in year 14 if the analysis
Implementing the proposed model would allow the fleet manager to be able to forecast
several years in advance the need for equipment replacement for the entire fleet. The manager
would be able to generate a rational annual equipment replacement budget for the agency over a
period of 3 to 5 years with relatively increased confidence that the decisions can be justified.
The change from deterministic to stochastic modeling is evident in the fuel costs and life
cycle costs displayed in Table 4. The fuel cost for the deterministic model used a unit price of
$3.54/gal, while the stochastic model used a statistic distribution of the historical fuel costs.
Additionally, the deterministic model utilized a fixed interest rate which the stochastic model did
not. Based on the confidence levels, the life cycle costs differ. For example, the stochastic
model determined a life cycle cost of $68,467 with an 80% confidence, and the cost only
37
increases as the confidence increases. Thus, the costs are separated by a larger quantity when the
The economic life of the dump truck was determined to be 12 years for the deterministic
model. Whereas, the stochastic model demonstrated that the truck’s economic life could be as
much as 14 years. The value added by the stochastic analysis directly relates to public agency
funding constraints discussed in Chapter 2 and provides quantified justification for potentially
retaining a piece of equipment past the point identified in the deterministic model.
Conclusions
Deterministic and stochastic models were developed to calculate life cycle costs and the
optimal economic life of equipment. An example was demonstrated, using a dump truck to show
the usage of the models and to determine the impact of fuel volatility. This was achieved by
applying the PSM and basic engineering economics principals to find the optimal life cycle cost
solutions. The deterministic and stochastic models were then compared to examine the impact of
the inputs.
When the stochastic model was applied to a piece of equipment, the sensitivity of the
model’s input variables were determined. The interest rate was found to have a greater impact
on economic life output than fuel prices. Thus, the assumption of selecting an arbitrary interest
rate with which to evaluate all alternatives is faulty. One author describes the issue in this
38
The confidence levels associated with the stochastic model demonstrates a difference
from the deterministic calculations. The deterministic model determined an economic life of 12
years while the stochastic model determined a range from 11 to 14 years, with 14 years being the
most certain time frame. Once again, this proves that allowing fuel prices to range
probabilistically in the analysis provides a means to quantify the certainty of the equipment
replacement decision.
To put the above analysis in the perspective of the public agency fleet manager, the
interest rate chosen for the calculation is less important than the impact of fuel prices because the
funding for the replacement alternative comes from the capital expense budget and the funding
for fuel consumption comes from the agency’s operations and maintenance budget.
Additionally, many agencies have mandated interest rates that must be used in LCCA (Gransberg
and Scheepbouwer 2010), which effectively forces the fleet manager to use a deterministic rate
in order to receive approval to purchase the new equipment. Therefore, the results argue that the
fuel price is probably the most critical input when determining the economic life of equipment
since fuel will be funded from the operations and maintenance budget. The capital budget will
either contain funding for a purchase or not, but the operations and maintenance budget must
purchase the fuel that the equipment fleet needs for the given fiscal year. Hence, with the
increasing cost of diesel fuel, the issue of upgrading to a more fuel-efficient model of equipment
using the latest technology has become an increasingly important element of the replace/repair
decision. Therefore, employing the stochastic inputs allows the analyst to determine the impact
CHAPTER 4.
EQUIPMENT LIFE CYCLE COST ANALYSIS INPUT VARIABLE SENSITIVITY
ANALYSIS USING A STOCHASTIC MODEL
O’Connor, E.P. and D.D. Gransberg, “Equipment Life Cycle Cost Analysis Input Variable
Sensitivity Analysis using a Stochastic Model,” (to be submitted for publication in the
Abstract
Deterministic life cycle cost models force the analyst to select a discrete value for every
input variable even when past history has shown most of the inputs will vary over time. The
important issue is the sensitivity of the model’s output to the values assumed for the input
variables. To improve equipment LCCA models, each variable’s sensitivity must be known.
This paper presents a comprehensive stochastic sensitivity analysis. Data from the MPWFSD
equipment fleet was used to determine the impact of nine stochastic input variables. The authors
find that the engine and time factors had the greatest impact on the output of the equipment life
cycle costs.
Introduction
associated with equipment fleet. The input parameters utilize a fixed quantity to calculate the
costs; however, fluctuation within an input is not taken into account. “In the deterministic
model, each variable has a single ‘best’ value that is used” (Gransberg et al. 2006). This may not
reflect the actual costs associated with a piece of equipment, especially with volatile inputs. A
stochastic model is employed for a more accurate analysis. “[A] stochastic model predicts a set
of possible outcomes weighted by their likelihood or probabilities” (Pinsky and Karlin 2011).
40
This paper will illustrate the usage of an equipment LCCA model with a large number of
the input variables being stochastic. The usage of a sensitivity analysis will identify the most
vital input parameters to the model. The MPWFSD equipment fleet data was applied to the
study to use actual information from a public agency. Therefore, managers will be able to make
equipment fleet decisions with the identification of the essential equipment characteristics.
These decisions are especially critical to public agencies because they must minimize the costs of
owning, operating, and maintaining equipment due to the lack of profit motive within public
A sensitivity analysis will be applied to the stochastic model using the Monte Carlo
simulations. The analysis will determine the most sensitive inputs to the model by highlighting
“the parameters that have the greatest influence on the results of the model” (McCarthy et al.
1995). Additionally, the analysis will allow for a more accurate depiction of the actual life cycle
costs because a “sensitivity analysis can highlight model parameters that ought to be the most
accurately measured so as to maximize the precision of the model” (McCarthy et al. 1995).
Background
Most common stochastic models utilize Monte Carlo simulations (Gransberg et al. 2006).
Monte Carlo simulations use “random samples from known populations of simulated data to
track a statistic’s behavior” (Mooney 1997). The first step in creating a simulation would be to
define the data to be analyzed and, more importantly, the deterministic and stochastic variables
(Mooney 1997). The next step is to create probability distributions for the stochastic or random
variables. Next, an output variable must be created using a logarithm or mathematical equation
41
utilizing the stochastic functions. Finally, the output variable is used to run the Monte Carlo
simulations.
The common assumption is that repair and maintenance costs are the most influential
parameters to equipment life cycle costs (Peurifoy and Schexnayder 2002). This is due to the
uncertainty associated with the cost item. Equipment may need routine maintenance, minor
repairs, or complete overhauls whose costs are hard to predict for each type of equipment.
Additional influential cost parameters to equipment life cycle costs are depicted in Table 5.
The following input variables that were portrayed as stochastic in the model: annual
usage, engine factor, time factor, fuel price, interest rate, salvage value, tire repair factor, repair
and maintenance cost, and tire cost. Each was selected to determine the uncertainty associated
with the inputs and to determine the impact of each parameter on the model.
The engine factor is a parameter that affects fuel efficiency and fuel cost. Engine factors
“depend on the engine horsepower, engine type, fuel type, and operating conditions” (Atcheson
1994). Atcheson (1994) categorizes operating conditions in three degrees: low, medium, or high.
Under standard conditions a gasoline engine will operate with a 0.06 gal/fwhp-h, and a diesel
engine will operate with a 0.04 gal/fwhp-h (Peurifoy and Schexnayder 2002). These are
deterministic factors utilized in the model, but the engine factor was made stochastic to account
The MPWFSD portrays salvage values as a percentage of capital cost, and the analysis
uses this value to maintain consistency with the other data provided by the MPWFSD. The
MPWFSD maintains equipment fleet data on a variety of both construction equipment and
administrative vehicles. Administrative vehicles and construction equipment use percentages for
salvage values shown in Table 6. The percentages for the construction equipment reflect values
from only loaders, dump trucks, and bobcats. The administrative vehicles’ salvage values are
The tire repair factor is associated with the tire repair cost. Tire costs include the
replacement of the tires, while tire repair cost takes into account the repairs on the tires
(Gransberg et al. 2006). The tire costs were obtained from dealers within Minnesota to provide
an accurate depiction of the costs associated with the MPWFSD’s equipment fleet. The tire
repair factors and annual usage for the stochastic model range from 12% to 16% (Gransberg et
al. 2006, Atcheson 1993, Peurifoy and Schexnayder 2002). Additionally, the annual usage for
the equipment ranges from 1,560 hours to 2,600 hours (Atcheson 1993, Peurifoy and
Schexnayder 2002).
The interest rate was characterized by a range of values found in the literature in addition
to Minnesota municipal bond rates to establish a relationship with a public agency. Table 7
displays the source for each of the interest rate values utilized within the stochastic model.
43
Methodology
The stochastic equipment LCCA model was developed using equipment cost inputs
prescribed by the Peurifoy and Schexnayder (2002) and engineering economics. The following
input variables for the model were made stochastic: fuel prices, interest rates, repair and
maintenance factors, tire costs, tire repair factors, engine and time factors, salvage values, and
annual usage. Monte Carlo simulations were then run to produce probability distributions which
allow the development of the probability output. Based on the output, a sensitivity analysis was
The PSM was selected as a widely accepted equipment ownership cost methodology and
used as the basis for the stochastic model. The PSM was developed for construction contractors
and needed to be adapted for application by a public agency. For example, since public agencies
do not pay sales or property taxes, that component was dropped in the formulation of the model.
The equipment costs were calculated on an annual basis using Equations 1 through 8.
Equation 1 was employed to determine the annual life cycle costs, and Equations 2 through 8
The stochastic model that was employed for this research includes nine stochastic inputs
that range from direct quantities to factors within an equation. Table 8 shows the stochastic
44
parameters that were applied for the analysis. The values that utilized a deterministic variable
were the initial cost, useful life, depreciation, and fuel consumption factors.
The selection of historical fuel data is a significant issue within the stochastic model to
ensure accuracy. Applying an abundance of historical fuel data may disrupt the model and take
into account economic influences that are not present in this research. Also, the selection of only
a few data points may not correctly quantify the fuel prices. Thus, finding the most appropriate
time period for the data is vital to the accuracy of the model.
The historical fuel data was assessed every sixth month to determine a variation within
the data points. The F-test and the P-value determination were used to define the most
appropriate time period for the fuel data. Tables 9 and 10 show the mean, standard deviation,
variance, and P-value for each specified month for gasoline and diesel fuel prices. The P-value
is used to determine an appropriate time period for the fuel price sample population by
calculating the significance to the null hypothesis. “P-values simply provide a cut-off beyond
which we assert that the findings are ‘statistically significant’ (Davies and Crombie 2009). The
45
null hypothesis is the assumption that there is no difference between two sample populations
Tables 9 and 10 show that the cut-off point where adding additional data points does not
increase the statistical significance of the sample is in the 42nd month. By convention, five
percent significance was applied to the study to determine the statistical significance (Davies and
Crombie 2009). Thus, any P-value less than five percent is found “unlikely to have arisen by
chance, and we reject the idea that there is no difference between the two treatments (reject the
null hypothesis)” (Davies and Crombie 2009). For the diesel prices the 45-month time period
was found to be the cut-off range, and for the gasoline prices the 47-month time period was
found to be the most significant. Consequently, the 45- and 47-month ranges were applied for
Results
Various types of equipment from the MPWFSD equipment fleet were employed in the
stochastic model to determine the most sensitive variables. The following pieces of equipment
were applied to the model: 2008 Ford F250, 2007 Chevrolet Impala, 2006 Ford Escape XLT,
2005 Sterling LT9513 tandem dump truck, 2006 Volvo L90F Art loader 2.5 yard, and a 2006
Volvo L150E Art loader 5 yard. The Chevrolet Impala, Ford F250, and Ford Escape are grouped
into the administrative vehicles, and the Sterling dump truck and the two Volvo loaders are
The determination of the most sensitive inputs to the stochastic model used a sensitivity
analysis within a commercial software. Figure 11 displays the sensitivity analysis output for the
2008 Ford F250. The range in the values is represented in dollar amounts, where a wider the
range represents a more volatile input. The sensitivity of each variable is related to the mean of
the annual life cycle cost associated with the piece of equipment. For the 2008 Ford F250 the
time factor was the most fluctuating input to the stochastic model with a range from $9,645 to
$35,495. Therefore, the time factor variable alone could make the annual costs vary by about
$25,000.
47
$3 5,000
$5,000
$2 0,000
$4 0,000
$10,000
$3 0,000
$2 5,000
$1 5,000
Next, a ranking system was employed to further examine the sensitivity analysis. Since
there are a total of nine input variables for the construction equipment and eight variables for the
administrative vehicles, each stochastic input will be ranked with one being the most sensitive
and eight or nine being the least sensitive. This will allow the determination of the most
sensitive variable to each piece of equipment. Table 11 displays the ranking for each machine.
Table 11. Sensitivity Ranking of each Variable within the Sensitivity Analysis
Piece of Equipment
Input Variable 2008 2007 2006 2005 Dump 2006 Volvo 2006 Volvo
Ford Chevrolet Ford3
1 2
Truck4 Loader5 Loader6
Time Factor 1 1 1 2 2 1
Engine Factor N/A N/A N/A 3 1 2
Interest Rate 5 4 5 1 4 4
Salvage Value 3 6 4 4 5 5
Annual Usage 2 2 2 9 6 9
Tire Costs 4 7 8 7 3 3
Tire Repair Costs 9 8 6 8 9 8
R&MC 8 5 7 6 7 7
Fuel price 7 3 3 5 8 6
1
F250, 2Impala, 3Escape XLT, 4Sterling LT9513, 5L90F Art 2.5yd., 6L150E Art 5yd.
48
The ranking from each piece of equipment was averaged to find the most significant
input factors. Table 12 contains the results from the average ranking for each stochastic input
factor. These results are directly related to Table 11 and the sensitivity analysis that was
performed.
Table 12. Ranking of the Input Variables from the Sensitivity Analysis
Input Variable Average Ranking of Input Variables
Time Factor 1.2
Engine Factor 1.7
Interest Rate 4.2
Salvage Value (%) 4.5
Annual Usage 4.3
Tire Costs 5.2
Tire Repair Costs 7.8
R&MC 7.0
Fuel price 6.0
The results from Tables 11 and 12 indicate that the time and engine factors are the most
sensitive variables to the stochastic life cycle cost model for the construction equipment. The
two factors are utilized in the same calculation and have a major impact on the life cycle costs.
For the administrative vehicles, the time factor and annual usage are the most sensitive to the
model. Once again, the annual usage is applied in the same calculation as the time factor so they
may influence each other. The time factor is vastly unknown due to variability with idle time
and productivity. Thus, the engine and time factors displayed significant uncertainty due to such
The percent of total horsepower used, which is a component of the engine factor, may
vary extensively from project to project within an agency’s fleet. Also, the amount of total
horsepower may vary depending on the usage of a machine. For example, if a dump truck is
49
hauling heavy material this may cause more usage of the engine horsepower. Thus, the
uncertainty associated with the input is considerable and is evident in the sensitivity analysis.
The two sedans displayed inputs that were closely related when ranking the sensitivities.
However, the repair and maintenance costs were one of the least influential inputs to the model
for all pieces of equipment. The results contradict the common assumption about repair and
maintenance costs, “repair cost normally constitutes the single highest operating cost” (Atcheson
1993). Also, both of the Volvo loaders exhibited tire costs as the third most influential input due
to the relative high cost of tires for that piece of equipment when compared to the cost of the
Within the stochastic model, fuel costs are a function of annual usage, fuel price, engine
factor, horsepower, time factor, and the fuel consumption factor. Thus, the size of the engine
and the time factor directly impact fuel costs and are related to fuel efficiency because the
consumption factor goes down as an engine’s fuel efficiency increases. The engine and time
factors are variables that a fleet manager may not directly control. Therefore, applying the inputs
deterministically would allow for the analysis of the other variables that managers may
influence.
Table 13 displays an example of the impact that the engine and time factor, along with
the annual usage, have on equipment costs. In this example, the fuel costs were calculated with
varying horsepower, either 400 hp or 300 hp, and a varying combined factor consisting of the
engine and time factor. Additionally, the fuel consumption factor and annual usage were applied
uniformly for all the pieces of equipment. The results displayed by Machines B and D show that
the fuel costs are drastically lower when applying a piece of equipment with less horsepower and
50
a lower combined factor consisting of the engine and time factor. Therefore, this further
Conclusions
Based on the results obtained from the Monte Carlo simulation, the time and engine
factors were the most sensitive input variables to the equipment taken from the MPWFSD. The
uncertainty associated with each factor was one of the major reasons that discrepancy occurred
during the simulations. The sensitivity of the time and engine factors is not vital for a fleet
manager since they cannot control the input of each element. Thus, each factor has a major
impact on the LCCA but is not significant in equipment fleet decisions concerning repairs and
overhauls.
Equipment fleet managers may use the sensitivity results of the time and engine factor to
efficiency should be a high priority due to the costs associated with the time factor, engine factor,
and annual usage. Equipment that is able to perform well in all work conditions, has a lower
For a public agency’s equipment fleet manager, the influence of the time and engine
factors are not essential to fleet decisions. Idle time, working conditions, and engine efficiency
are not variables that an equipment fleet manager can influence. Thus, employing the inputs as
51
deterministic is the most practical solution. Inputs such as the repair and maintenance
uncertainty are more vital to equipment decisions because the fleet manager can control those
inputs more closely. These inputs should remain stochastic within the model to optimize the
results. Consequently, the study identified variables to be deterministic and stochastic within an
CHAPTER 5.
OPTIMIZING PUBLIC AGENCY EQUIPMENT ECONOMIC LIFE USING
STOCHASTIC MODELING TECHNIQUES
O’Connor, E.P. and D.D. Gransberg, “Optimizing Public Agency Equipment Economic Life
Using Stochastic Modeling Techniques” (to be submitted for publication in the Journal for
Abstract
Public agency funding constraints force equipment fleet managers to identify the need to
replace a given piece of equipment a year or more in advance to be able to obtain authorization
models do not account for uncertainty within input parameters. This research proposes a
model, taking into account the variation within the input variables. Using the MPWFSD’s
equipment fleet data, an optimal replacement age was determined based on confidence levels
ranging from 70% to 90%. A trigger point was formulated by analyzing the sensitivity between
the change in market value and the repair and maintenance costs. Using the stochastic model,
along with a sensitivity analysis, an economic life was determined that was different than that
Introduction
A public agency’s equipment fleet consists of many different types of machines, for
example the Texas Department of Transportation’s (TxDOT’s) fleet ranges from compact sedans
to motorized ferries (TxDOT 2008). Also, many agencies have “a uniform process in [their]
approach to determine equipment replacement criteria” (TxDOT 2008). The methods for
53
determining a replacement age are based on deterministic approaches that do not account for
uncertainty with inputs that affect equipment LCCA (West et al. 2013). To take into account
uncertainty, a stochastic approach has been employed to define a viable economic life of
The maintaining and monitoring of the equipment fleet is a vital role of the equipment
fleet managers, especially when the fleet becomes older (Antich 2010). This issue is stressed
due to the budget constraints in public agencies andalso typically means more maintenance and
employed in public agencies to ensure equipment fleet is in operating condition (Antich 2010).
Therefore, not only is the funding different for private and public entities’ equipment fleet but
the maintenance and repair costs are drastically different to manage. As a result, the PSM has
been modified to be implemented for public agency usage to aid in equipment fleet decisions.
For this research the MPWFSD’s equipment fleet data was utilized. To determine the
economic life of the equipment, a stochastic model was used. The EUAC was applied to
calculate the economic life of equipment based on the work completed by Park (2011). The
calculation of the life cycle costs was based on the PSM. Additionally, Monte Carlo simulations
were used to make the model stochastic and determine the sensitivity of the input parameters.
Background
using dynamic programming, based on the Bellman and Wagner approaches, was employed to
determine the replacement age of vehicles (Fan et al. 2013). The Florida Department of
replacement age of the equipment (2009). Fan and Jin (2011) applied a decision tree to
determine the significant factors in the economic life determination of construction equipment.
Research completed by Mitchell (1998, 2011) applied cumulative cost models to aid
managers with determining repair costs for equipment. His work focused on the private sector
and used regression models to analyze the repair costs for an equipment fleet. Also, the use of
regression models was employed by Ghadam (2012) to determine the economic life of earth
moving equipment. Soft computing methods using LCCA tools were applied to transportation
Additionally, LCCA for infrastructure systems were established with the optimal service life and
The utilization of EUAC was employed to determine the optimal disposal age, or
economic life, of six equipment classes for the North Carolina DOT (Kauffman et al. 2012). The
research included the following varied input parameters to the EUCA model: interest rate, initial
market value (MV), MV decline rate, mileage decline, cost per mile, and annual cost increase
rate (Kauffman et a. 2012). A sensitivity analysis was performed for each of the varied
parameters and was evaluated based on mean, standard deviation, coefficient of variation, and
Barringer (1997) performed Monte Carlo simulations to calculate life cycle costs for the
American Petroleum Institute (API) pumps. The work included failure costs found by Monte
Carlo simulations and net present value (NPV) calculations to determine the life cycle costs
(Barringer 1997). Barringer’s work was completed using commercial software, similar to this
research, but it was finalized for process equipment not construction equipment. Also, Barringer
completed research based on reliability principles and computing life cycle costs in 2001.
55
Methodology
The calculation of the equipment life was performed using deterministic and stochastic
input variables. The usage of the PSM was employed to calculate the life cycle costs. The
method was altered to reflect public agency practices. This was done because the PSM is
operated by private entities, and public agencies operate with different constraints.
The input parameters utilized in the PSM to formulate the stochastic model consist of
solely cost variables. The costs are analyzed on an annual basis for all the parameters. The
stochastic and deterministic LCCA models use Equation 2 through 6 to determine the operating
costs for the equipment (Peurifoy and Schexnayder 2002, Park 2011).
The determination of the economic life for an equipment fleet is a critical component of
the LCCA. The economic life, or the optimal time to sell a piece of equipment, requires the
usage of EUAC calculations. To properly utilize EUAC, the ownership costs and operating costs
must be calculated on an annual basis in the correct year, using Equations 9 through 12 (Park
2011).
The calculation of the EUAC is done over the entire life span for a piece of equipment.
In most instances the lowest EUAC in a given year will be the optimal economic life. This will
be the value used in the deterministic and stochastic evaluation of the equipment fleet. The
stochastic model will use confidence levels associated with the output. Also, the stochastic
economic life evaluation will use the same equations as the deterministic method but apply
stochastic inputs.
56
The last 47 months were used for the range of the diesel fuel prices, determined by the F-
test and P-value statistical assessment (see Table 9 from Chapter 4). Table 14 summarizes the
stochastic inputs that were applied to the economic life calculations. Other than the fuel prices
and the tire cost, the values displayed in Table 14 were obtained from the literature (Gransberg et
al. 2006, Atcheson 1993, Puerifioy and Schexnayder 2002, Park 2011).
Table 14. Stochastic Values for the Inputs used in the Economic Life Determination
Parameter Range of Values
Interest Rate 3% - 16%
Tire Cost Varied by Machine
R&MC 35% - 80%
Change in Market Value 8% - 15%
Diesel Fuel Prices $3.38/gal. - $4.13/gal.
Tire Repair Factor 12% - 16%
associated with the EUAC. The range for the confidence levels will be from 70% - 90%. Then a
sensitivity analysis will be applied to determine the sensitivity of the change in market value and
the repair and maintenance costs. When the sensitivity for the repair and maintenance costs
exceeds the sensitivity of the change in market value, it will be an indicator for equipment fleet
managers. Figure 12 shows an example of the trigger point based on the sensitivity analysis.
57
30,000
Trigger Point
25,000
20,000
Change in
10,000
Market Value
5,000
0
0 2 4 6 8 10
Life (yrs.)
Figure 12. Trigger Point Determination Based on Sensitivity Analysis
The trigger point in Figure 12 is identified by the dashed line at year 6. This is the point
in time when the sensitivity of the repair and maintenance costs intersects with the sensitivity of
the change in market value. The trigger point signifies that the repair and maintenance costs are
Results
The results for the research include deterministic and stochastic economic life
calculations, and a sensitivity analysis of the stochastic output. An example using a loader, from
the MPWFD equipment fleet, is provided to demonstrate the results that were obtained. Lastly,
the usage of the stochastic economic life is discussed and compared with the deterministic
method.
58
The deterministic economic life was calculated to compare the results with the stochastic
determination. Figure 13 displays the deterministic economic life of a 2006 loader, a piece of
equipment within the MPWFD fleet. The economic life of the loader was found to be 4 years
using the lowest EUAC. The variation between the two methods of calculating the economic life
97,500
Economic Life
97,000
96,500
EUAC ($)
96,000
95,500
95,000
0 1 2 3 4 5 6 7 8 9 10
Life (yrs.)
The stochastic determination of the economic life for the 2006 Volvo loader is depicted
in Figure 14. The confidence levels are shown with the optimal replacement age specified by the
lowest EUAC. The economic life for the loader varies from year 5 to 8 depending on the
confidence level.
59
119,000
Lowest EUAC
117,000
115,000
113,000 90%
EUAC ($) 85%
111,000
80%
109,000 75%
70%
107,000
105,000
103,000
0 1 2 3 4 5 6 7 8 9 10
Life (yrs.)
The stochastic economic life range for the loader supplies more detail than a
deterministic determination. Using the range of values for the input parameters provides a more
certain calculation of the economic life. Additionally, the range offers the fleet manager options
Sensitivity Analysis
Monte Carlo simulations were employed to determine the sensitivity of the inputs for the
economic life calculation. Based on the sensitivity results of the change in market value and
repair and maintenance costs, a trigger point for the machines was established. The sensitivity of
each variable is related to the mean of the annual life cycle cost associated with the piece of
60
equipment. The range in the values is represented in dollar amounts. The wider the range the
Figure 15 displays the results from the sensitivity analysis performed in the seventh year
of the 2006 Volvo loader. The results show that the change in market value is more sensitive
than the repair and maintenance costs given the year under investigation.
Interest Rate
$92,509.07 $122,161.35
Tire Cost
$92,375.17 $107,951.91
Baseline = $100,560.17
$125, 000
$105, 000
$110, 000
$95, 000
$115, 000
$120, 000
$100, 000
$90, 000
Figure 15. Sensitivity Analysis for the 2006 Volvo Loader in Year 7
Figure 16 contains the results from the sensitivity analysis performed in the eighth year of
the Volvo loader. The results indicate that the repair and maintenance costs are more sensitive
than the change in market value. This would indicate that the trigger point would be in year 8,
Interest Rate
$93,531.24 $121,947.17
Tire Cost
$93,026.68 $108,523.95
$105, 000
$115, 000
$120, 000
$125, 000
$90, 000
$110, 000
$95, 000
$100, 000
Figure 16. Sensitivity Analysis for the 2006 Volvo Loader in Year 8
Figure 17 contains the plot of the sensitivity fluctuations for the change in market value
and the repair and maintenance costs for the 2006 Volvo loader. The results correlate with the
30,000
Trigger Point
25,000
20,000 R&MC
Change in
Output 15,000
Mean ($) Change in
10,000 Market
Value
5,000
0
0 1 2 3 4 5 6 7 8 9 10
Life (yrs.)
Figure 17. Change in the Output Mean for 2006 Volvo Loader 5 yd.
62
The results displayed in Figure 17 indicate that the sensitivities of the two inputs intersect
at year 8, signifying the change in the sensitivity. The intersection of the two parameters is the
trigger point for equipment fleet managers. Fleet managers may use this information to aid in
equipment decisions.
Table 15 contains the results of the machines that were investigated within the MPWFD
fleet. The economic life is shown with the deterministic and the stochastic methods for
comparison. Also, the sensitivity analysis trigger year is displayed, and the service life of each
machine is displayed.
Since public agencies must make equipment replacement decisions years in advance, 5
years for the MPWFD, the economic life range allows fleet managers to plan the replacement
with certain levels of confidence. For example, if the fleet manager uses an 80% confidence
associated with the economic life for the 2006 loader 5 yd., the manager may plan the
replacement at year 2, because at 80% confidence the economic life would be at year 7.
Based on the results from Table 15, the sensitivity analysis of the economic life
determination may be used as a trigger point for equipment fleet managers. The sensitivity of
the maintenance and repair costs is higher than the market value at the trigger point. Indicated
by the shift in the two input parameters, the likelihood of a major failure for a piece of equipment
increases as the machine ages. Therefore, implementing the trigger point would allow fleet
63
managers to identify the correct age to implement preventative maintenance steps or support a
replacement decision.
The budget constraints within a public agency’s equipment fleet result in strict
replacement policies. This results in keeping equipment past the optimal economic life,
increasing the repair and maintenance costs during the service life of equipment. The fleet
manager has to manage these costs and identify the correct maintenance strategy at the correct
time period. By having a trigger point within the service life of the fleet, it allows for the
Conclusions
A stochastic equipment LCCA model was applied to determine the economic life of
equipment within a public agency. Using the PSM and engineering economics with stochastic
functions, the optimal replacement age was determined. The results displayed a different output
than traditional deterministic methods. The model accounts for uncertainty within input
parameters, different than deterministic methods that only have discrete input values.
Accounting for the uncertainty within the input parameters allows the fleet managers to make
during the stochastic economic life determination. The outcomes displayed a change in the
sensitivity from year to year because of the change in market value and the repair and
maintenance costs. The variation between the two input variables occurred within the optimal
replacement age which is indicated from the confidence levels calculated. The sensitivity of the
change in market value becomes less over time while the repair and maintenance cost increases
64
over time. The point in time is an indicator that replacement of the equipment should be
considered because repair and maintenance costs are more uncertain. Therefore, the confidence
levels along with the sensitivity analysis provide a viable range to replace a piece of equipment.
Fleet managers may use this method as an indicator for replacement or as a trigger point
to implement preventative maintenance strategies. Since public agencies must make equipment
replacement decisions years in advance, the economic life range allows fleet managers to plan
the replacement with certain levels of confidence. Also, due to budget constraints, public
agencies must maximize the life of equipment fleet. By implementing a trigger point based on
the stochastic economic life determination, this may aid fleet managers more effectively than
deterministic methods.
65
CHAPTER 6.
CONSOLIDATED CONCLUSIONS AND LIMITATIONS
Conclusions
Deterministic and stochastic models were developed for public agencies to calculate
equipment fleet life cycle costs and the optimal economic life. This was achieved by modifying
the PSM to fit the public agency’s equipment fleet environment and applying basic engineering
economics principles to find optimal life cycle cost solutions. When the stochastic model was
applied to a piece of equipment using fluctuating interest rates and fuel prices, the sensitivity of
the model’s input variables was determined. The interest rate was found to have a greater impact
on economic life output than fuel prices for a dump truck illustrated in Chapter 3. The fuel
volatility did impact the life cycle costs when applying the stochastic confidence levels.
Therefore, allowing fuel prices to range probabilistically in the analysis provided a means to
With the increasing cost of diesel fuel, the issue of upgrading to a more fuel-efficient
model of equipment using the latest technology has become an increasingly important element of
the replace/repair decision. Therefore, employing the stochastic inputs allows the analyst to
determine the impact of the most sensitive component of the model. This was illustrated in
Chapter 4, where common input values were made stochastic to determine their impact on the
public sector-adapted PSM equipment LCCA model. Based on Monte Carlo simulation
sensitivity analysis results, the time factor and engine factor were the most sensitive input
variables to the LCCA model. This leads to the conclusion that when deciding to replace a piece
of equipment, engine efficiency should be a high priority due to the costs associated with the
Applying that conclusion to the public sector, one must realize that once a given piece of
equipment is added to public agency’s equipment fleet, the equipment fleet manager can no
longer influence many of the model’s variables. These include the equipment’s idle time, its
working conditions, and its engine efficiency. While accounting for uncertainty was shown to
add value to the overall decision, making all the input variables stochastic introduces a level of
complication that is not necessary. Therefore, it is concluded that employing the inputs as
deterministic is the most practical determination. Inputs such as the repair and maintenance
uncertainty are more critical to equipment decisions because the fleet manager can control those
inputs more closely. Consequently, the researchers determined which variables should be
included in the equipment LCCA model as deterministic values and those better portrayed as
stochastic variables to aid public agency equipment fleet managers, as shown in Chapter 4.
Finally, Chapter 5 contained a stochastic equipment LCCA model that produced different
output results than the deterministic methods for a public agency’s fleet. The stochastic model
accounted for uncertainty within input parameters, unlike deterministic methods that only use
discrete input value assumptions. A range for the optimal replacement age was formulated
within a 70% to 90% confidence level. Since public agencies must make equipment replacement
decisions years in advance, the economic life range allows fleet managers to plan the
replacement with certain levels of confidence. The usage of Monte Carlo simulations provided
for a sensitivity analysis performed in conjunction with the stochastic economic life
determination. The outcomes displayed a change in the sensitivity from year to year due to the
change in market value and the repair and maintenance costs. The variation between the two
input variables occurred within the economic life range developed by the confidence levels.
Therefore, the confidence levels along with the sensitivity analysis provide a trigger point that
67
signals when the equipment manager should consider replacing a piece of equipment as it nears
Limitations
The results of this research have several important limitations that must be considered
before attempting to generalize it. The PSM model used to generate the results of the research
has been altered to account for a public agency’s constraints on equipment fleet funding.
Additionally, since the equipment fleet data used in the analyses sprung from the MPWFD fleet,
the input parameters were altered to match. The proposed model and methodology is not
applicable to a LCCA of a private entity’s equipment as it is missing certain factors, such as tax
considerations. Additionally, the historical fuel prices were taken from the state of Minnesota,
and interest rates were taken from municipal bond rates in Minnesota. Consequently, applying
the same input parameters for equipment fleet outside of Minnesota would yield inaccurate
results.
The range of historical fuel prices for the research has been determined for the present
time period. To apply the same fuel prices in the future may be inaccurate. The F-test and P-
value determination would have to be completed to determine the appropriate range for fuel
Another limitation within this thesis has to do with the repair and maintenance costs. The
costs do not take into account a major failure of a machine. This was not included in the cost
parameter as it is impossible to estimate the potential amount based on the data obtained. This
amount could vary substantially based on the type of machine being analyzed. Thus, the analysis
uses only routine repair and maintenance costs and not complete overhaul costs within the
models.
68
CHAPTER 7.
CONTRIBUTIONS AND RECOMMENDATIONS FOR FUTURE RESEARCH
Contributions
The main contribution of this thesis is the development of a stochastic equipment LCCA
method into the public sector. The uncertainty within the input parameters is not taken into
account when applying deterministic methods to calculate the life cycle costs and determine the
economic life. Stochastic models account for uncertainty, like volatility in fuel costs, and
quantify the impact of that uncertainty to equipment life cycle cost. This was demonstrated
using a public agency’s equipment fleet to accurately calculate life cycle costs and a replacement
age.
Chapter 3 demonstrated the impact of fuel volatility to the determination of the economic life
for equipment. The stochastic model was able to quantify the impact of fuel fluctuation to aid
equipment fleet managers in replacement decisions. Therefore, public agencies may use the
stochastic model as a decision tool to make more certain decisions within the equipment fleet.
Chapter 4 quantified the uncertainty of each input variable to the equipment LCCA. This
provided a rational method for deciding which of the input variables to make deterministic and
stochastic within an equipment LCCA model to optimize results. This research applied a
sensitivity analysis to determine the uncertainty with each variable. For example, the engine and
time factors were deemed deterministic because fleet managers cannot directly control these
variables. This approach was different than previous research, such as Kauffman (2012), because
Chapter 5 provided the stochastic model to determine the economic life of equipment for a
public agency. This method determined results that were different than traditional deterministic
69
equipment LCCA models. The results take into account uncertainty within each input,
calculating a more realistic depiction of the actual costs. A trigger point for equipment fleet
managers was discovered based the sensitivities of the change in market value and repair and
maintenance costs. Therefore, the research developed a robust tool to aid equipment fleet
Due to the nonexistence of stochastic modeling for equipment LCCA within public agencies
this research is the first of its kind. Thus, the expansion for this thesis is critical to increase the
knowledge of equipment fleet management. The following is a list of possible research projects
Using the stochastic equipment LCCA model, the development of a replacement time
period may be established for public agency’s equipment fleet. The time period could
replace current replacement plans, such as the 5-year replacement plan used by the
MPWFD. The adjusted replacement period would be based on the confidence levels
associated with the stochastic economic life determination. For example, the 70% to
90% economic life range is between year 11 and 14 for the dump truck illustrated in
Chapter 3. The three year range, from year 11 to 14, could be the determination of a
Applying the stochastic equipment LCCA for private entities. Adjusting the model for
the private sector, and using the confidence levels to develop an optimal replacement age.
Case study analysis using the stochastic equipment LCCA from this thesis for other
public agencies. Since this research has been adapted for the MPWFD, the model could
be analyzed for a different equipment fleet to justify the results obtained in this thesis.
70
BIBLIOGRAPHY
11. Fan, H. and Jin, Z. (2011). “A Study on the Factors Affecting the Economical Life of
Heavy Construction Equipment.” Proceedings of the 28th ISARC, Seoul, Korea, pp. 923-
928.
12. Fan, W., Gemar, M. and Machemehl, R. (2013). “Equipment Replacement Decision
Making: Challenges and Opportunities.” Journal of Transportation Research Forum,
Volume 52, No. 3, pp. 79-90.
13. Flintsch, G. and Chen, C. (2004). “Soft Computing-Based Infrastructure Life-Cycle Cost
Analysis Tools.” Computational Intelligence: pp. 1-15.
14. Florida Department of Management Servies; Division of Specialized Servies. (2009).
"Minimum Equipment Replacement Criteria."
http://www.dms.myflorida.com/content/download/96061/559801/DMS_Minimum_Equip
ment_Replacement_Criteria.pdf (Assessed April 15, 2014).
15. Furuta, H., Kameda, T., Fukuda, Y., and Frangopol, D. (2003). “Life-Cycle Cost
Analysis for Infrastructure Systems: Life-Cycle Cost vs. Safety Level vs. Service Life.”
Life-Cycle, Performance of Deteriorating Structures: pp. 19-25.
16. Ghadam, P., Ravanshadnia, M., Ramezani, S. (2012). "Determining Economic Life of
Earth Moving Equipment by Using Life Cycle Cost Analysis: Case Study."
http://www.academia.edu/2032383/Determining_Economic_Life_of_Earth_Moving_Equ
ipment_by_Using_Life_Cycle_Cost_Analysis_Case_Study(Assessed April 15, 2014)
17. Gillerspie, J.S. and Hyde A. S. (2004). “The Replacement/Repair Decision for Heavy
Equipment.” Report VTRC 05-R8, Virginia Transportation Research Council, November.
18. Gransberg, D., Popescu, R., Ryan, R. (2006). “Construction Equipment Management for
Engineers, Estimators, and Owners.” 1st Ed., Taylor & Francis Group, Florida.
19. Gransberg, D.D., (2009). “Life Cycle Cost Analysis of Surface Retexturing with
Shotblasting as a Pavement Preservation Tool.” Transportation Research Record No.
2108, Journal of the Transportation Research Board, National Academies, December, pp.
46-52.
20. Gransberg, D.D., and E. Scheepbouwer. (2010). “Infrastructure Asset Life Cycle Cost
Analysis Issues,” 2010 Transactions, AACE, Int‘l, Atlanta, Georgia, June, pp.
CSC.03.01- CSC.03.8.
72
21. Gransberg, D.D., and E.J. Kelly, (2008). “Quantifying the Uncertainty Due to
Construction Material Price Volatility Using Monte Carlo Simulation.” Cost
Engineering, Journal of AACE, International, Vol. 50 (6), June, pp. 14-21.
22. Haldorsen, H., Damsleth, E. (1990). “Stochastic Modeling (includes associated papers
21255 and 21299).” Society of Petroleum Engineers: Journal of Petroleum Technology,
Volume 42, No. 4. PA.
23. Jensen, P.A. and Bard, J.F. (2002). “Operations Research Models and Methods.” Wiley,
New York, 700pp.
24. Kauffman, P., Howard, E., Yao, J., Harbinson, D., Brooks, N., Williams, R., Gurganus,
C. (2012). “Criteria for Fleet Management: Identification of Optimal Disposal Points
with the Use of Equivalent Uniform Annual Cost.” Transportation Research Record:
Journal of the Transportation Research Board, No 2292, Transportation Research Board
of the National Academies, Washington, D.C., pp. 171-178.
25. Lang, J. (2008). “Financial Management.” American Public Works Association. On-line
Avaliable at: http://www.apwa.net/c/documents/education/institutes/ppt/finance.ppt
(Assessed November 29, 2014).
26. LeBlanc, D. (2004). “Statistics: Concepts and Applications for Science.” Jones and
Bartlett Publishers. Sudbury, MA.
27. McCarthy, M.A., Burgman, M.A., and Ferson, S. (1995). “Sensitivity analysis for models
of population viability.” Biological Conservation 73: 93-100.
28. Mitchell, Z. (1998). "A Statistical Analysis Of Construction Equipment Repair Costs
Using Field Data & The Cumulative Cost Model." Virginia Polytechnic Institute.
Blacksburg, Virginia.
29. Mitchell, Z., Hildreth, J., and Vorster, M. (2011). ”Using the Cumulative Cost Model to
Forecast Equipment Repair Costs: Two Different Methodologies.” J. Constr. Eng.
Manage. 137, SPECIAL ISSUE: Construction Engineering: Opportunity and Vision for
Education, Practice, and Research, 817–822.
30. Mooney, C. (1997). “Monte Carlo Simulation.” Sage Publications, Inc. Thousand Oaks,
CA.
31. Moss Motors. (2014). “Bringing a Car out of Storage.” Tech Articles, Moss Motors, Ltd.
On-line Available at:
73
http://www.mossmotors.com/SiteGraphics/Pages/out_of_storage.html (Assessed
November 29, 2014).
32. Municipal Bonds. (2014). “Byron Minn Indpt Sch Dist Sch Bldg-ser A.”
http://minnesota.municipalbonds.com/bonds/recent/(Accessed May 20, 2014)
33. Municipal Bonds. (2014). “Northern Mun Pwr Agy Minn Elec Ser A.”
http://minnesota.municipalbonds.com/bonds/recent/(Accessed May 20, 2014)
34. Municipal Bonds. (2014). “University Minn Ser A.”
http://minnesota.municipalbonds.com/bonds/recent/(Accessed May 20, 2014)
35. Municipal Bonds. (2014). “Wayzata Minn Indpt Sch Dist Alternative Facs-ser B.”
http://minnesota.municipalbonds.com/bonds/recent/(Accessed May 20, 2014)
36. Municipal Bonds. (2014). “Westonka Minn Indpt Sch Dist Sch Bldg-ser A.”
http://minnesota.municipalbonds.com/bonds/recent/(Accessed May 20, 2014)
37. Neuendorf, K.A. (2002). “The Content Analysis Guidebook.” Sage Publications,
Thousand Oaks, California, 300 pp.
38. Oppenheim, A. N. (1992). “Questionnaire Design, Interviewing and Attitude
Measurement. “ Pinter, London & NY.
39. Park, C. (2011). “Contemporary Engineering Economics.”5th Ed., Prentice Hall, New
Jersey.
40. Peurifoy, R. and Schexnayder, C. (2002). “Construction Planning, Equipment, and
Methods.” 6th Ed., McGraw-Hill, New York, NY.
41. Pinsky, M., and Karlin, S. (2011). “An Introduction to Stochastic Modeling.” 5th edition,
Elsevier Inc. Burlington, MA.
42. Pittenger, D.M., D.D. Gransberg, M. Zaman, and C. Riemer. (2012). “Stochastic Life
Cycle Cost Analysis for Pavement Preservation Treatments.” Transportation Research
Record No. 2292, Journal of the Transportation Research Board, National Academies,
pp. 45-51.
43. Richardson, S. (2007). “Economics of Commuter Rail Alternatives.” Transportation
Research Record: Journal of the Transportation Research Board, No 1887,
Transportation Research Board of the National Academies, Washington, D.C., pp. 99-
105.
74
APPENDIX A.
CASE STUDY RESULTS
The case study results were obtained from a structured interview questionnaire. Three
agencies were investigated for the case study analysis: City of Minneapolis, City of Eagan, and
Dodge County. This section contains the questionnaire that was applied and the results from
The following contains the questions that were used during the case study analysis.
CONDITIONS: This interview can either be conducted in person or via telephone. The following
protocol shall be followed during its administration:
1. The questionnaire shall be sent to the respondent at least 1 week prior to the interview via
email.
2. To maximize the quality and quantity of information collected, the primary respondent
should be encouraged to invite other members of his/her organization to be present
during the interview. Thus, a single transportation agency response can be formulated and
recorded.
3. The interviewer will set the stage with a brief introduction that emphasizes the purpose of
the research, the type of information expected to be collected, and the ground rules for
the interview.
4. Once the interviewees indicate that they understand the process at hand, the interview
will commence.
5. The interviewer will read each question verbatim and then ask if the interviewee
understood the question before asking the interviewee to respond.
6. Each question contains a specific response that must be obtained before moving to the
next question. Once that response is obtained, the interviewer can record as text
additional cogent information that may have been discussed by the interviewees in
working their way to the specific response.
7. Upon conclusion of the interview, the interviewer will ask the interviewees if they have
additional information that they would like to contribute and record those answers as text.
8. The interviewer will assemble a clean copy of the final interview results and return them
to the interviewee for verification.
76
STRUCTURED INTERVIEW:
1. Interviewee name:
A. Name of Agency:
Other: {explain}
9. Approximate average annual budget for equipment repair, rehabilitation, and maintenance:
1. Does your agency currently use a formal decision-making process to make equipment
maintenance, repair, and/or replacement decisions on individual pieces of equipment?
2. If yes, which methods are used? What process best describes your procedures?
3. If your agency utilizes a software-based analysis for fleet management decisions, what software
program is used?
3. How does your agency decide between replacing and repairing a piece of equipment?
4. How long in advance does your agency need to know when to buy a new piece of equipment?
7. What information do you need to make equipment management decisions based on the life cycle
of the equipment?
8. What are the major life cycle components that factor into replacement or maintenance decisions
for heavy equipment?
Other(s):
9. What are the major life cycle components that factor into replacement or maintenance decisions
for light equipment?
Other(s):
1. What are the most common pieces of heavy equipment that your agency owns (5-6)?
2. What are the most common pieces of light equipment that your agency owns (5-6)?
3. Which pieces of equipment would be most beneficial for Life Cycle Cost Analysis?
4. Is there anything you would like to add that you think would be valuable to the
researchers in this study?
79
The following section contains the results for each of the case studies that was completed
for this thesis. Each of the case studies has three parts: replacement evaluation process, repair
City of Minneapolis
Replacement Evaluation Process: The replacement evaluation process for the City of
Minneapolis includes three major aspects including; equipment life cycle, equipment utilization,
and business need of equipment. The equipment life cycle requirement is based on 50% to 60%
of the initial value of the piece of equipment. If a piece of equipment is below or at the optimal
value than it would be considered for replacement. The equipment utilization factor is based on
the usage and need for certain tasks. For example, a police vehicle may be utilized more than a
snow plow in the summer. The business need is the least important factor in the replacement
evaluation process. An example of business need for the City of Minneapolis would be that a
specific type of excavator is needed to build ponds, and now the City needs a different type of
excavator to maintain the ponds. Therefore, the replacement of an excavator which is needed to
The replacement evaluation entails a ten-, five-, and two-year replacement plan. These
plans are developed to specify replacement needs and when the replacement will be executed.
The ten-year plan is a rough estimate of what will be replaced in the future. The five-year plan
has a firm idea of what pieces of equipment will be replaced. The five-year plan includes
changes due to accidents and repairs. The two-year plan includes the specific data for
replacement. The two-year plan finalizes and calculates all the replacement decisions that will be
made.
80
Repair Evaluation Process: The repair process is specified by 50% to 60% of the original value
of a piece of equipment. If a piece of equipment is above the optimal range of the initial value
then the equipment is repaired. This is standard for all pieces of equipment within the fleet.
Utilization of the equipment fleet is a major driving force in the determination between repairing
Equipment Life Cycle Information: The most vital pieces of information that are needed to
make equipment decisions based on the life cycle of equipment for the City of Minneapolis
include age, utilization, and fuel consumption. The major life cycle components that factor into
Acquisition Costs
Depreciation
Salvage Value
Up-fitting Costs
The major life cycle components that factor into replacement or maintenance decisions for light
Acquisition Costs
Annual Usage
Operator Costs
Purchase Price
Salvage Value
Safety Factors
The most common pieces of heavy equipment that the City of Minneapolis owns are dump
trucks, loaders (3yd and 5yd), skid steer loaders, and numerous others. The most common pieces
of light equipment include sedans, particularly the Ford Escape and Ford Focus.
City of Eagan
Replacement Evaluation Process: The City of Eagan utilizes a minimum replacement standard
for all pieces of equipment. The standard entails a specific age, mileage, or hour requirement that
must be met before a piece of equipment can be replaced. An example for a light piece of
equipment is a sedan that must reach 10 years old or 100,000 miles before it may be classified
for replacement consideration. An example of a heavy piece of equipment is a backhoe that must
After the minimum standards have been met, the replacement evaluation process includes
the following pieces of information: Vehicle Condition Index (VCI), age (years, mileage, or
operating hours), and operational considerations. The VCI takes into account the following
parameters: age, mileage or hours, reliability, maintenance and repair costs, condition, cost per
mile, and risk factor. These considerations will be reviewed by city employees to make the
replacement decision. Furthermore, deviations from this policy must be reviewed and approved
by city administrators.
82
The time frame for future replacement decisions for the equipment fleet is dictated by the
budget period. The budget period for the City of Eagan is from May through December which
Repair Evaluation Process: All pieces of equipment are repaired and maintained until they
reach the minimum standards set by the replacement evaluation process. This is true for both
Equipment Life Cycle Information: All information and data regarding decisions based on the
life cycle of equipment is generated from FleetFocus, an equipment fleet software program. The
major life cycle components that factor into replacement or maintenance decisions for both
Acquisition Costs
Purchase Price
Maintenance Costs
Tire Costs
The most common pieces of heavy equipment that the City of Eagan owns are snow plows and
fire trucks. The City currently has approximately 40 snow plows and 20 fire trucks within their
equipment fleet. The most common pieces of light equipment includes sedans and light pick-ups.
83
Dodge County
Replacement Evaluation Process: Pieces of equipment are replaced based on the needs of the
County and the allowable budget. Once a piece of equipment needs to be replaced, the County
Repair Evaluation Process: Pieces of equipment are repaired when they are broken or need
Equipment Life Cycle Information: The information that Dodge County needs to make
equipment management decisions based on the life cycle of equipment are repair costs and costs
to replace. The major life cycle components that factor into replacement or maintenance
Acquisition Costs
Annual Usage
Depreciation
Purchase Price
Maintenance Costs
Salvage Value
The most common pieces of heavy equipment that Dodge County owns are snow plows, loaders,
excavators, and graders. The most common pieces of light equipment light pick-ups.
84
APPENDIX B.
NATIONAL SURVEY RESULTS
An online survey was distributed to benchmark the usage of LCCA and other parameters
in agency fleet management programs. The following contains the questionnaire and results that
Survey Questionnaire
Response
Agency Name
City
Approximate number of
pieces of heavy
machinery and
equipment
Approximate number of
pieces of light vehicles
(pickup, vans, etc.)
Approximate average
annual budget for
equipment purchase
Approximate average
annual budget for
equipment repair,
rehabilitation, and
maintenance
2. Does your agency currently use a formal decision-making process to make equipment
maintenance, repair, and/or replacement decisions on individual pieces of equipment?
3. If yes, which methods are used? What process best describes your procedures?
4. Which of the following fleet management software programs are or have been utilized
by your agency? Please check all that apply.
Other(s):
86
5. Which of the parameters listed in the table does your agency collect and maintain in your
equipment fleet management database? For those parameters in your database, please
rate your sense of how reliable the data in the database is currently.
Data Reliability
Available Available Not
Parameters Totally Mostly Mostly Very Don’t
Electronically on Paper Available Reliable
Unreliable Unreliable Reliable Reliable Know
Purchase
Price
Acquisition
Costs
Annual
Usage in
Hours
Total
Expected
Life
Equipment
Horsepower
Salvage
Value
Maintenance
Costs
Insurance
Costs
Interest
Costs
Depreciation
Operator
Costs
Tire Cost
Tire
Maintenance
Cost
Tire Life
Expectancy
Oil Life
Expectancy
Oil Costs
Fuel Costs
Lubrication
Costs
87
6. Which of the following parameters do you use when making equipment fleet
management decisions, like purchases, major repairs, etc.? Please rate the impact on the
final decision for each parameter that you use. For example, if the original purchase
price for the piece of equipment carries the heaviest weight in a decision to invest in a
major repair or to purchase a new piece of equipment, then rate it as “highest impact.”
On the other hand if it is not considered, rate its impact as “none.”
Decision-making Impact
Parameter
None Little Some High Highest
Purchase Price
Acquisition Costs (i.e. plates,
licensing, etc.)
Annual Usage in Hours
Total Expected Life
Equipment Horsepower
Salvage Value
Maintenance Costs
Insurance Costs
Interest Costs
Depreciation
Operator Costs
Tire Cost
Tire Maintenance Cost
Tire Life Expectancy
Oil Life Expectancy
Oil Costs
Fuel Costs
Lubrication Costs
7. Would you be willing to allow the researchers to use the information in your database
and allow them to interview you on your program?
Yes No
If yes, please indicate the name, phone number and email address of your agency’s point
of contact.
88
Survey Results
The subsequent tables contain the results of the survey. Table 16 shows the agency
respondents and the corresponding equipment fleet information. The number of pieces of
equipment and budget are shown in the table. Also, the last column of the table shows if the
Table 17 corresponds to the methods utilized within the formal decision-making process
that the agency has in place. Since eight of the eleven respondents utilize a formal decision-
making process, Table 17 has the results of only those eight. The respondents were allowed to
pick more than one method, and the percent column is based on the total percent for that method,
Based on the results from Table 17, the life cycle cost analysis method is the most
prominent method utilized by the responding agencies. The second highest response rate was the
economic life of investment, and following that was output from software-based analysis.
Table 18 contains the results from the software programs that are being utilized by the
various agencies that responded to the survey. The respondents were allowed to pick more than
one software program, thus the percentages are not cumulative of all software programs. The
most prominent software programs were MS Excel and Faster as shown in the table.
91
Table 18. Fleet Management Software Programs that have been or are being Utilized
Software Results* %
MS Excel 5 36%
collectiveFleet 1 7%
None 2 14%
Other: 11 79%
Faster, CCGSystems 6 55%
Jetfleet 1 9%
Sungard 1 9%
RTA 1 9%
C.F.A. Computerized fleet
analysis 1 9%
PRECISION 1 9%
*Respondents picked more than one software if applicable
Table 19 shows the availability of the input data for the LCCA model. The parameters
are the input data for the model and the other columns are the availability based on electronically
availability, paper availability, or not available. A total of eleven agency responses are contained
in Table 19, and they were allowed to pick more than one availability option.
92
Table 20 contains the results of the reliability characteristics of the available data for the
LCCA model inputs. The parameters for the table are the LCCA model inputs, and the other
columns relate to the reliability. Each agency could pick one characteristic for a given
parameter. Most of the results for each data point were mostly reliable as shown.
93
Purchase Price 1 0 5 1 3 0 10
Acquisition Costs
(i.e. plates,
licensing, etc.) 1 1 4 2 2 0 10
Annual Usage in
Hours 0 0 6 1 2 0 9
Total Expected Life
(in hours or years) 0 0 6 1 2 0 9
Equipment
Horsepower 1 0 4 1 1 1 8
Salvage Value 1 5 1 1 2 0 10
Maintenance Costs 0 2 5 1 2 0 10
Insurance Costs 1 2 2 1 1 0 7
Interest Costs 0 1 3 1 0 1 6
Depreciation 1 1 3 1 1 1 8
Operator Costs 0 1 3 1 2 1 8
Tire Maintenance
Cost 0 1 5 1 2 0 9
Tire Life
Expectancy 1 1 3 1 1 1 8
Oil Life
Expectancy 1 2 3 1 2 0 9
Oil Costs 0 1 6 1 2 0 10
Fuel Costs 0 1 6 1 2 0 10
Lubrication Costs 0 2 5 1 2 0 10
Table 21 is the impact of the input data for the LCCA model. Each agency was to rank
the impact from no impact to highest impact. The parameters that received the most responses
with the highest impact were purchase price, annual usage in hours, and total expected life. The
parameters that received the most responses corresponding with no impact included acquisition
APPENDIX C.
SOFTWARE ANALYSIS
Table 22 contains the results of the content analysis and differentiates the capabilities of
each software program. A check in a capability column indicates that the software program
performs that certain task. This was completed to indicate which software programs are most apt
Fleetmatics x x x
FleetFocus (by
x x x x x x x
AssetWorks)
J. J. Keller's
Maintenance Manager™ x x x x x
Software
collectiveFleet™ x x x x x x x x x
MH Fleet by MH
x x
Equipment
Maintenance Connection x
eMaint X3 x x x x x x x x x
Maintenance
x x x x x x x x x
Coordinator
Maintenance5000 x x
Maintenance Pro x x x x x x x
Accruent 360Facility x x x x x x
Infor EAM x x x x x x
4Site x x x
Guide TI x x
ManagerPlus x x x x x
iMaint (Fleet) x x x x
Maintenance Assistant
x x x x x x x
CMMS
MSI Service Pro Repair
x x x x x
Center and Field Service
Fleetio x x
TATEMS x x x
FleetCommander x
Arsenault, Dossier Fleet
x x x x x x
Maintenance
RTA Fleet Management x x x
FleetWave/RoadBASE x x x x x
FleetWise VB x x x
97
Table 22. Software Capabilities Cont'd
Capability
Software Track
Cost Integrate MX Mobile
Customiz- Bar Fuel Risk Equipment History Vehicle Track Integration
Tracking/ with Mobile Wireless
able code Mgnt Mgnt Tracking Recording Maint Tires GPS
Control CAD Solution Handheld
History
Fleetmatics x x x x x x
TMT Fleet
Maintenance Software x x x x x x x
J. J. Keller's
Maintenance x x x x
Manager™ Software
collectiveFleet™
MH Fleet by MH
Equipment x
Maintenance
Connection
x x
eMaint X3
Maintenance
Coordinator
x x
Maintenance5000
x x
Maintenance Pro
Accruent 360Facility x x
x x
Infor EAM
x
4Site
Guide TI x x
x x
ManagerPlus
iMaint (Fleet) x x x x
Maintenance Assistant
CMMS x
Fleetio x x x x x
TATEMS x
FleetCommander x x x x x
Arsenault, Dossier
Fleet Maintenance
x x x x
RTA Fleet
Management x x x x
FleetWave/RoadBASE x
FleetWise VB x
98
Based on the results from Table 22, further examination of the software programs was
conducted. Table 23 depicts the results of the examined software programs premised on the life
cycle (LC) capabilities and the functionality for this project. The life cycle capabilities were
broken down into three categories: generates LC, could generate LC based on input data, and no
viable inputs to compute LC. Next, the software was categorized into definitely functional,
maybe functional, and not functional. The functionality is dependent on how applicable the