Opal Tower Investigation Final Report 2018-02-22
Opal Tower Investigation Final Report 2018-02-22
Opal Tower Investigation Final Report 2018-02-22
OPAL
TOWER
INVESTIGATION
FINAL
REPORT
Independent
Advice
to
NSW
Minister
for
Planning
and
Housing
19
February
2019
Opal Tower Investigation – Final Report
Contents
Executive
Summary
.........................................................................................................................................
1
TOR
1
–
Causes
of
damage
.......................................................................................................................
1
TOR
2
–
Making
the
Opal
Tower
safe
for
occupancy
....................................................................
1
TOR
3
–
How
to
avoid
this
type
of
incident
in
the
future
...........................................................
2
Introduction
........................................................................................................................................................
3
Terms
of
Reference
..........................................................................................................................................
3
Building
Structure
............................................................................................................................................
4
Investigation
Activities
...................................................................................................................................
4
Observed
Damage
.............................................................................................................................................
5
Consequences
of
Damage
..............................................................................................................................
6
Cause(s)
of
Damage
.........................................................................................................................................
7
Environment
..................................................................................................................................................
7
Materials
..........................................................................................................................................................
7
Foundations
...................................................................................................................................................
7
Construction
...................................................................................................................................................
8
Structural
design
..........................................................................................................................................
9
Damage
at
Level
4
–
Grid
Line
A
.................................................................................................................
9
Damage
at
Level
10
–
Grid
Line
C
...........................................................................................................
11
Investigations
by
Others
.............................................................................................................................
12
Proposed
Rectification
................................................................................................................................
12
The
Future
........................................................................................................................................................
13
Conclusions
......................................................................................................................................................
16
i
February 2019
Opal Tower Investigation – Final Report
Executive
Summary
At
the
request
of
the
Hon.
Anthony
Roberts,
Minister
for
Planning
and
Housing,
an
investigation
was
carried
out
into
the
cause
or
causes
of
structural
damage
to
the
Opal
Tower
at
Sydney
Olympic
Park,
which
was
first
observed
at
Christmas
2018.
In
addition,
the
investigation
reviewed
possible
remedial
action
to
repair
the
damage
to
the
building.
The
terms
of
reference
also
included
a
request
to
consider
any
recommendations
for
the
future,
with
the
intended
purpose
of
assisting
in
avoiding
problems
with
high-‐rise
construction
such
as
those
addressed
in
this
report.
Based
on
all
available
information,
the
following
opinions,
recommendations
and
findings
of
the
investigation
are
presented.
These
are
listed
below
under
each
term
of
reference
(TOR)
provided
by
the
Secretary
of
the
NSW
Department
of
Planning.
stated
otherwise
2
‘Design’
refers
to
structural
design
in
this
report,
unless
stated
otherwise.
1
February 2019
Opal Tower Investigation – Final Report
8. Other
hob
beam
/
panel
elements
of
similar
as-‐constructed,
structural
design
may
not
comply
with
the
NCC
and
AS3600-‐2009
and,
if
so,
will
require
rectification
works.
We
also
recommend
checking
of
the
forces
in
other
structural
elements
adjacent
to
the
hob
beams,
such
as
the
columns.
9. We
agree
in
principle
with
the
rectification
works
planned
to
date,
noting
that
these
have
advanced
considerably
since
our
interim
report
was
released
but
have
yet
to
be
agreed
by
all
parties
and
independently
certified.
10. We
recommended
that
a
detailed
analysis
be
undertaken
of
the
potential
redistribution
of
loads
from
the
damaged
elements
to
ensure
that
other
newly
loaded
building
elements,
before
and
after
rectification
works,
have
suitable
capacity
and
to
avoid
future
damage.
A
preliminary
analysis
has
been
carried
out
and
indicated
structural
loads
satisfied
the
NCC
in
the
non-‐damaged
parts
of
the
building
structure.
Nevertheless,
this
finding
should
be
robustly
and
independently
verified.
11. We
recommend
that
all
designs
and
construction
associated
with
the
rectification
works
be
checked
and
certified
as
safe
for
building
occupancy
by
qualified
independent
structural
engineers.
12. The
viability
of
residents
re-‐entering
the
building
extends
beyond
the
structural
issues
considered
here
and
hence
beyond
the
scope
of
this
investigation.
Nevertheless,
we
would
recommend
that
items
9-‐11
listed
above
be
completed
prior
to
re-‐occupation.
TOR
3
–
How
to
avoid
this
type
of
incident
in
the
future
We
recommend
the
following
should
be
implemented:
13. The
creation
of
a
government
Registered
Engineers
database
developed
in
partnership
with
an
appropriate
professional
body.
14. Independent
third
party
checking
and
certification
of
engineering
designs
and
subsequent
changes
to
the
design
of
critical
elements
by
a
Registered
Engineer,
including
confirmation
of
what
are
the
critical
elements
for
all
major
construction
projects.
15. Critical
stage,
on-‐site
checking
and
certification
by
a
Registered
Engineer
that
construction
is
as
per
the
design
for
all
major
construction
projects.
All
changes
to
identified
critical
structural
elements
that
are
proposed
and
made
during
construction
should
also
be
certified
by
an
independent
Registered
Engineer.
16. An
online
database
be
created,
where
all
certifications
may
be
viewed
by
a
broad
range
of
stakeholders
including
owners
and
prospective
owners;
before,
during
and
after
construction.
The
aim
is
to
increase
transparency
of
the
approval
and
certification
process.
17. A
Building
Structure
Review
Board
be
formed,
with
the
major
purpose
being
to
establish
and
publish
the
facts
relating
to
structural
damage
of
buildings
arising
from
design
and
construction,
investigate
their
causes
and
to
recommend
changes
to
Codes
and
Regulations
where
appropriate.
2
February 2019
Opal Tower Investigation – Final Report
Introduction
The
Opal
Tower
is
a
high-‐rise
residential
building
located
in
Sydney
Olympic
Park,
NSW.
It
consists
of
36
storeys
above
ground
and
3
basement
levels
below
ground.
Construction
of
the
building
was
completed
in
2018
and
occupation
of
the
392
residential
apartments
commenced
in
the
second
half
of
2018.
A
photograph
of
the
Opal
Tower
is
shown
in
Figure
1.
The
building
is
characterised
by
its
overall
triangular
prismatic
shape,
with
a
number
of
insets
in
the
three
external
faces
of
the
building
(see
Figures
1
and
2).
These
architectural
features
are
referred
to
as
“slots”
on
some
design
drawings.
On
Christmas
Eve
2018,
residents
of
the
Opal
Tower
reported
loud
noises,
including
a
loud
“bang”,
reportedly
of
internal
origin,
and
presumably
associated
with
the
structure
of
the
building.
Early
investigations
of
the
source
of
these
loud
noises
identified
cracks
in
a
load-‐bearing
panel
on
Level
10
of
the
building,
forming
one
of
the
exterior
walls
at
the
base
of
one
of
the
inset
slots.
Later
investigations
revealed
further
cracking
of
the
hob
beam
supporting
the
cracked
load-‐bearing
panel.
Subsequent
investigations
also
identified
other
cracked
concrete
structural
members
at
Level
4
of
the
building,
again
at
the
base
of
an
inset
slot
feature.
Because
of
safety
concerns,
residents
of
the
building
were
evacuated,
first
on
Christmas
Eve
2018.
They
were
subsequently
allowed
to
re-‐enter
and
then
asked
again
to
depart
the
building
on
27
December
2018,
following
more
detailed
checking
of
structural
elements
and
specifically
the
identification
of
the
additional
structural
damage
on
Level
4
of
the
building.
On
27
December
2018,
the
NSW
Department
of
Planning
and
Environment
(DPE)
engaged
Professors
John
Carter
and
Mark
Hoffman
to
investigate
a
number
of
matters
related
to
the
cracking
of
the
concrete
structural
members
in
the
building,
including
the
likely
causes
of
the
observed
cracking.
Following
initial
investigations,
Professor
Stephen
Foster
was
also
engaged
to
assist
in
the
investigations,
on
the
recommendation
of
Professors
Carter
and
Hoffman.
This
report
contains
a
description
of
the
investigations
carried
out
and
presents
the
findings,
recommendations
and
opinions
of
the
investigators.
3
February 2019
Opal Tower Investigation – Final Report
Building
Structure
The
Opal
Tower
is
a
reinforced
concrete
building
with
post-‐tensioned
concrete
floor
slabs.
It
has
a
reinforced
concrete
central
core
structure,
which
houses
the
lifts
and
fire
stairs.
The
floors
of
the
building
are
supported
by
the
core
walls
and
reinforced
concrete
columns
and
precast
concrete
elements.
A
particular
feature
of
the
building
is
the
inset
slots
located
on
each
external
face
of
the
building
(see
Figures
1
and
2).
The
walls
of
these
inset
slot
sections
are
constructed
largely
from
precast
reinforced
concrete
panels
(with
some
cast
in
situ
panels).
The
walls
composed
of
these
panels
have
been
designed
to
carry
gravity
loading,
effectively
acting
as
columns,
transmitting
vertical
loads
(from
floors
above
the
inset
slots
and
from
floors
intersecting
them)
to
the
individual
supporting
columns
below
each
inset
slot
feature.
The
columns
of
the
building
are
founded
on
individual
pad
footings
and
the
central
core
is
supported
on
shallow
spread
footings.
All
footings
are
founded
on
shale
bedrock.
The
major
structural
design
of
the
building
was
carried
out
by
WSP,
an
international
engineering
services
company.
The
design
of
the
post-‐tensioned
concrete
floors
was
carried
out
by
Australasian
Prestressing
Services
(APS).
The
precast
wall
panels
were
fabricated
by
Evolution
Precast
Systems
(Evolution).
The
building
was
constructed
by
Icon
Co,
an
Australian
building
contractor
and
part
of
the
Kajima
Corporation
of
Japan
(Icon).
Investigation
Activities
Our
investigations
included
the
following
activities:
1. Multiple
visits
to
the
Opal
Tower
site
and
inspection
of
the
damaged
structural
members
in
the
building,
and
members
in
similar
locations;
2. Review
of
the
design
of
relevant
sections
of
the
building
and
related
documentation;
3. Review
of
construction
records
and
quality
control
records;
4. Review
of
defect
notice
No.
84;
5. Viewing
of
a
security
camera
recording
of
the
garden
area
in
the
slot
on
Level
10
where
damage
to
the
panel
was
first
observed;
6. Inspection
and
review
of
elements
of
the
structure
repaired
during
initial
construction
(Columns
C1
on
Level
6,
C38
on
Level
7,
and
C21
on
Level
8
as
well
as
the
Level
13
floor
slab);
7. Discussions
with
representatives
of
the
building’s
structural
designer
(WSP),
floor
slab
designer
(APS)
and
builder
(Icon);
8. Discussions
with
the
engineering
representative
of
the
Opal
Tower
Strata
Committee
(Cardno);
9. Discussions
with
the
Executive
of
the
Opal
Tower
Strata
Committee;
10. Discussions
with
senior
figures
associated
with
the
building
industry
nationally
and
in
NSW;
and
11. Consideration
of
unsolicited
advice
and
information
provided
by
members
of
the
engineering
profession
and
the
public.
Activities
1
to
6
listed
above
were
focused
on
various
structural
elements
in
sections
of
the
building
located
on
Levels
3,
4,
6,
7,
8,
9,
10,
13,
16
and
26,
as
well
as
the
basement
level
B3.
All
areas
of
known
structural
damage,
both
major
and
minor,
were
inspected.
In
particular,
we
inspected
all
inset
slot
regions
of
the
building
focusing
on
the
4
February 2019
Opal Tower Investigation – Final Report
structural
panel
walls
and
their
supporting
hob
beams,
and
the
floor
plates
adjacent
to
damaged
hob
beams.
The
discussions
listed
as
activities
7
to
10
above
aided
our
understanding
of
the
technical
design
and
construction
issues
relating
to
the
Opal
Tower
as
well
as
providing
useful
background
information
pertaining
to
the
building
industry
and
current
building
practices.
Activity
11
listed
above
was
necessary
to
provide
due
consideration
to
the
concerns
expressed
by
individuals
and
to
reflect
on
the
unsolicited
information
provided.
It
was
not
possible
to
individually
acknowledge
these
contributions
to
our
investigation,
but
we
take
the
opportunity
to
do
so
collectively
now.
We
were
also
assisted
in
these
various
tasks
by
staff
of
the
NSW
Department
of
Planning
and
Environment.
We
wish
to
thank
the
Department
for
this
assistance.
We
note
that
the
opinions
and
findings
expressed
here
are
our
own
and
not
necessarily
those
of
any
other
party,
including
the
Department.
We
wish
to
thank
all
parties
who
provided
information
and
advice
to
this
investigation.
Their
cooperation
and
assistance
were
invaluable.
Observed
Damage
During
the
numerous
visits
to
the
site
of
the
Opal
Tower,
we
inspected
and
re-‐
inspected
a
number
of
locations
where
significant
damage
had
occurred
to
load
bearing
concrete
members.
The
areas
of
significant
structural
damage
are
located
on
Levels
4
and
10
of
the
Opal
Tower.
The
approximate
locations
of
these
damaged
regions
are
shown
in
Figures
3
and
4.
Photographs
of
some
of
the
damaged
concrete
structural
members
are
shown
in
Figures
5
to
12.
Specifically:
On
Level
10:
1. A
hob
beam
spanning
between
columns
C21
and
C38
(along
grid
line
C
shown
in
Figure
4)
and
the
Panel
A
resting
on
it
–
see
Figures
5
to
8.
Cracking
was
also
observed
in
the
floor
plate
adjacent
to
column
C21
–
see
Figure
9.
This
was
the
damage
observed
on
Christmas
Eve
and
is
considered
to
be
major
damage.
On
Level
4:
2. A
hob
beam
spanning
between
columns
C16
and
C34
(along
grid
line
A
shown
in
Figure
3)
–
see
Figure
10.
This
also
appears
to
be
major
damage.
3. A
hob
beam
spanning
between
columns
C2
and
C22
(along
grid
line
B
show
in
Figure
3).
These
cracks
could
be
considered
minor
at
this
stage
–
see
Figure
11.
4. Cracking
was
also
observed
in
the
floor
plate
between
Levels
3
and
4
–
see
Figure
12.
This
was
considered
to
be
major
damage.
It
is
noted
that
the
vertical
load
lines
along
which
the
observed
major
damage
occurred
are
different
and
hence
these
areas
of
damage
are
likely
to
be
unrelated
to
each
other.
From
the
security
camera
footage
referred
to
previously,
we
observed
cracking
in
the
bottom
corners
of
the
bottom
panel
(Panel
A)
on
Level
10.
The
time
stamp
on
this
5
February 2019
Opal Tower Investigation – Final Report
video
recording
indicated
that
the
cracking
of
the
panel
commenced
at
approximately
2.16
pm
on
Monday
24
December
2018
and
continued
for
approximately
8
seconds.
6
February 2019
Opal Tower Investigation – Final Report
Environment
In
particular,
the
environmental
factors
were
considered
to
be
highly
unlikely
to
have
contributed
to
the
damage
because
the
meteorological
records
for
the
few
months
preceding
the
failure,
and
particularly
in
the
period
immediately
prior
to
and
on
24
December
2018,
show
no
extreme
or
adverse
conditions.
The
rainfall
records
show
some
significant
downpours
in
the
months
leading
up
to
Christmas,
but
they
were
considered
not
to
be
unusual.
Materials
In
our
interim
report,
dated
14
January
2018,
we
indicated
that
there
was
no
evidence
in
the
documentation
we
had
reviewed
to
that
date
to
indicate
that
the
materials
used
in
construction
were
inferior
in
quality
or
did
not
meet
the
specifications
required.
Further
test
records
of
materials
used
in
construction,
received
by
us
after
our
Interim
Report
was
issued,
revealed
at
least
one
case
where
concrete
used
in
a
hob
beam
may
not
have
reached
its
specified
28
day
strength.
This
instance
is
described
in
greater
detail
later
in
this
report,
when
the
possible
causes
of
damage
are
addressed
(see
discussion
under
the
heading
‘Damage
at
Level
4
–
Grid
Line
A’).
The
reason
for
not
being
definitive
in
the
previous
statement,
is
that
there
was,
and
remains,
some
uncertainty
about
what
strength
concrete
was
actually
specified
for
the
hob
beams,
as
explained
in
more
detail
later.
Foundations
In
general,
differential
settlement
of
the
footings
of
a
building
can
occur
for
a
variety
of
reasons.
For
example,
neighbouring
columns
may
experience
large
differences
in
their
compressive
loading
or
the
ground
beneath
neighbouring
footings
may
vary
markedly
in
terms
of
stiffness
and
strength.
Differential
settlement
is
also
likely
if
the
ground
beneath
some
footings,
but
not
others,
softens
over
time,
perhaps
due
to
local
wetting
of
the
ground
beneath
the
footing
causing
softening
of
the
foundation
material.
7
February 2019
Opal Tower Investigation – Final Report
The
records
we
inspected
reveal
that
all
column
footings
for
the
Opal
Tower
structure
were
founded
on
shale
of
low
to
medium
strength,
with
the
majority
being
medium
strength.
The
records
we
reviewed
indicate
that
the
spread
footings
supporting
the
tower
core
and
all
but
two
of
the
40
individual
pad
footings
supporting
the
tower
columns
were
inspected
by
a
geotechnical
engineer
prior
to
the
pouring
of
concrete
to
form
the
footings.
All
inspected
footings
were
certified
by
the
geotechnical
engineer
as
suitable
to
carry
a
maximum
allowable
bearing
pressure
of
3.5
MPa.
We
could
not
find
inspection
records
for
columns
designated
as
C8
and
C40
(see
Structural
Drawing
4419
S02.051
A
for
column
designations
and
locations).
However,
if
differential
footing
settlements
had
been
a
contributing
cause
of
damage
to
the
building,
and
specifically
the
damage
observed
on
Levels
4
and
10,
we
would
have
expected
to
observe
cracking
in
the
floor
slabs
and
at
floor-‐column
connections
in
the
lower
levels
of
the
building.
Our
inspections
of
these
areas
of
the
building
indicated
no
such
damage.
So
on
the
basis
of
this
observation
and
the
documentary
evidence
of
the
condition
of
the
shale
foundation
at
the
time
the
footings
were
poured,
we
concluded
that
differential
settlement
of
the
column
footings
is
unlikely
to
be
a
contributing
factor
to
the
structural
damage
observed
on
Levels
4
and
10
of
the
Opal
Tower.
Construction
There
are
a
number
of
points
noted
where
construction
differed
from
the
design
and
/
or
Standards:
(a) Grouting:
design
drawings
indicate
that
full
grout
coverage
was
expected
between
the
panel
and
the
hob
beam.
However,
during
construction
only
the
inner
surfaces
of
approximately
50-‐70%
of
the
joint
width
appear
to
have
been
grouted,
consistent
with
the
shop
drawings
which
show
the
grout
extending
over
only
the
inner
portion
of
the
hob
beam
to
panel
connection.
Furthermore,
coring
of
the
Level
4
hob
beam
revealed
incomplete
grout
coverage
in
some
places.
This
partial
grout
coverage
led
to
an
eccentric
bearing
load
and
elevated
bearing
and
bursting
stresses
on
the
hob
beams;
(b) Inadequate
cover
concrete,
specifically
in
the
hob
beam
spanning
columns
C21
and
C38
on
Level
10,
the
location
of
some
reinforcing
steel
in
the
vicinity
of
the
hob
to
column
connection,
the
encroachment
of
discontinued
(anchored)
column
bars
into
the
cover
zone,
and
the
placement
of
an
electrical
conduit
within
the
cover
zone
in
this
area;
(c) A
dowel
bar
between
the
hob
beam
and
the
panel
on
Level
10
was
observed
to
be
incomplete,
possibly
cut
during
construction;
(d) The
original
design
drawings
of
the
building
indicate
precast
concrete
panels
of
a
thickness
corresponding
to
the
width
of
the
hob
beam
upon
which
they
rest.
However,
the
panels
were
manufactured
to
be
20
mm
thicker
and
erected
so
that
they
overhang
the
inside
face
of
the
hob
beam.
For
example,
on
Level
10
the
panel
was
originally
designed
to
be
manufactured
180
mm
thick
to
correspond
to
the
hob
beam
width,
but
was
constructed
to
be
200
mm
thick
and
overhang
the
inner
face
of
the
hob
beam
by
approximately
20
mm;
(e) Potentially
inadequate
tensile
capacity
in
the
horizontal
direction
in
the
bottom
region
of
Panel
A
on
that
rests
on
the
hob
beam
spanning
columns
C21
and
C38
on
Level
10.
There
is
compelling
evidence
indicating
that
the
wrong
size
reinforcing
bars
were
placed
in
this
area
during
manufacture
of
this
particular
8
February 2019
Opal Tower Investigation – Final Report
panel
–
20
mm
diameter
bars
were
used
instead
of
28
mm
diameter
bars
(see
Figure
8);
and
(f) We
could
find
no
evidence,
during
our
site
inspections
and
in
the
construction
photos
and
photographs
of
damaged
hobs,
that
reinforcement
cross-‐ties
were
incorporated
in
those
hobs
to
resist
bursting
forces.
In
regard
to
the
timing
of
the
observation
of
damage,
it
is
likely
that
the
damage
occurred
after
progressive
build-‐up
of
load
on
the
structure
as
apartments
became
occupied,
culminating
with
the
observed
damage
at
Level
10
on
24
December.
It
is
unclear
when
the
observed
damage
on
Level
4
occurred.
The
architectural
design
where
the
major
damage
to
the
hob
beam
has
been
observed
on
Level
4
is
quite
different
to
that
of
the
damaged
hob
beam
on
Level
10.
The
cause
of
the
damage
observed
on
Level
4
and
Level
10
is
considered
in
greater
detail
in
following
sections
of
this
report.
Structural
design
Our
investigations
have
identified
at
least
two
areas
of
the
as-‐built
structure,
which,
in
our
opinion,
do
not
meet
all
requirements
of
the
relevant
Australian
Standard,
AS3600
Concrete
Structures
and
therefore
do
not
meet
the
requirements
of
the
National
Construction
Code
Volume
1
(NCC).
The
specific
areas
of
the
building
coincide
with
the
locations
of
the
most
serious
damage
observed
to
the
concrete
structure.
Our
specific
findings
are:
(a) At
Level
4
of
the
building
–
inadequate
bursting
(or
splitting)
resistance
of
the
hob
located
immediately
above
column
C34;
and
(b) At
Level
10
of
the
building
-‐
inadequate
bursting
(or
splitting)
and
/
or
bearing
resistance
of
the
hob
at
the
locations
of
its
connections
to
columns
C21
and
C38.
These
findings
are
described
in
greater
detail
below,
together
with
the
reasons
that
support
our
opinions
expressed
here.
9
February 2019
Opal Tower Investigation – Final Report
deformation.
In
particular,
a
focus
of
these
studies
was
ascertaining
whether
bearing
and
/
or
bursting
of
the
hob
were
possible
causes
of
the
observed
damage.
The
hand
calculations
considered
the
capability
of
the
hob
in
both
bearing
and
bursting.
The
axial
forces
passing
through
the
pre-‐cast
wall
panel
to
the
hob
beam
connection,
and
then
into
the
columns,
were
addressed.
Some
of
these
calculations
adopted
the
‘strut
and
tie
model’
describing
equilibrium
of
forces
in
the
hob
beam
(Figure
14).
This
hand
calculation
method
followed
the
approach
specified
in
AS3600.
The
finite
element
analysis
(Figure
13),
albeit
preliminary,
indicated
significant
splitting
forces
in
the
column
adjacent
to
the
hob
beam.
It
would
be
prudent
to
undertake
a
more
detailed
analysis
of
this
feature
and
to
confirm
if
appropriate
bursting
reinforcement
is
in
place.
Rectification
works
may
be
necessary
pending
the
outcome
of
the
abovementioned
detailed
analysis.
The
damage
observed
in
the
hob
beam
above
Column
C34
at
Level
4
is
shown
in
Figure
15.
This
image
indicates
bowing
of
the
reinforcement
steel
outwards
from
the
beam
and
opening
of
the
stirrup.
Also
noticeable
is
a
lack
of
cross-‐tie
reinforcement
to
guard
against
splitting
failure..
It
is
notable
that
the
observed
damage
was
constrained
to
the
inside
facing
of
the
hob
beam;
the
outside
of
the
hob
beam
at
the
critical
section
was
supported
by
a
lateral
garden
bed
wall
(Figure
16)
built
integrally
with
the
slab
and
against
the
hob
beam.
This
wall
likely
provided
support
to
the
outer
side
of
the
hob
beam
forcing
the
damage
inward
where
such
support
was
lacking.
This
damage
remained
“hidden”
until
exposed
on
27
December
2018
after
removal
of
an
internal
wall
in
the
adjacent
apartment.
It
is
not
known
when
this
damage
occurred.
The
site
observations
of
the
damaged
beam
are
consistent
with
a
bursting
failure.
There
are
contradicting
views
and
documentation
as
to
the
design
strength
of
the
hob
beam
concrete
on
Level
4.
Notwithstanding,
65
MPa
concrete
was
understood
to
have
been
poured
during
construction
as
it
was
specified
for
the
puddle
pours
in
the
slab
around
the
columns
and
it
was
considered
expedient
to
use
the
same
batch
of
concrete
when
pouring
the
hob.
During
our
investigations,
and
subsequent
to
the
issue
of
our
interim
report,
records
of
strength
for
the
concrete
used
to
construct
the
hob
beam
were
provided
to
us.
These
reveal
28
day
strengths
of
these
concrete
samples
as
50
MPa,
where
65
MPa
concrete
was
ordered
for
supply,
indicating
that
the
concrete
in
the
hob
may
also
have
been
of
a
lower
strength.
Our
independent
analysis
of
concrete
core
testing
samples,
extracted
and
tested
in
January
2019
by
Mahaffey
Associates,
did
not
contradict
this
observation.
Clearly,
this
mis-‐match
in
design
strengths
points
to
a
possible
and
unfortunate
ambiguity
in
the
interpretation
of
the
design
documentation.
We
have
drawn
conclusions
from
our
numerical
analyses
of
the
as-‐built
design,
combined
with
hand
calculations
and
field
observations
of
the
damaged
hob
beam
at
Level
4
–
Grid
Line
A.
In
our
opinion,
these
are
as
follows:
1. With
the
design
loads
assumed,
the
strength
of
the
Level
4
hob
beam
spanning
columns
C16
and
C34
does
not
meet
the
requirements
of
AS3600–2009
(which
was
the
operative
version
of
the
code
at
the
time
the
structure
was
designed);
10
February 2019
Opal Tower Investigation – Final Report
2. The
observed
spalling
of
the
hob
beam
cover
concrete
above
and
adjacent
to
column
C34
implies
that
the
beam
is
in
a
state
of
high
stress;
3. The
strength
of
the
concrete
in
the
“as
constructed”
hob
beam
was
lower
than
that
assumed
in
the
design;
4. Splitting
forces
are
significant
and
the
tie-‐reinforcement
provided
was
inadequate
to
resist
these
forces;
and
5. The
cause
of
the
damage
to
the
hob
was
by
bursting
(also
known
as
splitting)
of
the
concrete
in
the
hob
beam
section.
11
February 2019
Opal Tower Investigation – Final Report
the
cover
concrete
in
a
zone
of
high
stress
immediately
above
column
C38
and
a
patch
repair
of
the
wall
panel,
again
in
a
high
stress
region;
and
5. Construction
issues
observed
in
the
Level
10
C
hob
beam
to
precast
panel
connection
that,
in
our
opinion,
were
not
influential
on
the
failure
include
a
cut
dowel
bar
and
inadequate
anchorage
of
hob
beam
shear
fitments
(90
degree
hooks
located
within
50
mm
of
the
concrete
surface
–
refer
AS3600–2009
Clause
8.2.12.4).
Proposed
Rectification
As
previously
mentioned,
soon
after
the
structural
damage
to
the
building
was
observed,
WSP
instigated
a
program
of
installing
props
under
the
damaged
areas,
as
a
temporary
measure,
to
ensure
the
safety
of
these
areas
of
the
building.
12
February 2019
Opal Tower Investigation – Final Report
Icon
and
WSP
have
briefed
us
on
the
structural
principles
behind
their
proposal
for
permanent
repair
of
the
damage
observed
on
Levels
4
and
10
and
strengthening
of
the
associated
structural
members,
viz.,
the
hob
beam
and
lowest
panel
at
these
locations.
We
also
understand
that,
as
advised
for
consideration
in
our
interim
report,
rectification
works
to
bolster
other
hob
beam
/
panel
elements
on
Levels
4,
10
and
16
are
being
undertaken,
and
considered
for
Level
26.
We
understand
that
this
bolstering
will
include
a
combination
of
grouting
of
the
hob
to
panel
joints,
the
provision
of
cast
in
situ
sandwich
panels
enclosing
the
hob
and
the
panel
that
sits
immediately
upon
it,
and
the
addition
of
exterior
columns
adjacent
to
some
pre-‐cast
panel
walls.
We
understand
that
the
joint
between
all
hob
beam
/
panel
elements
has
now
been
retrospectively
fully
grouted
and
we
support
this
as
a
preliminary
measure.
It
is
our
opinion
that
the
structural
principles
behind
the
proposal
for
rectification
are
sound,
as
stated
in
our
interim
report,
and
considerable
progress
has
been
made
in
this
regard.
However,
we
have
not
received
complete
details
of
a
structural
analysis
of
the
proposed
rectifications.
We
recommend
that
detailed
plans
for
the
proposed
rectification
works
should
be
checked
by
an
independent
qualified
structural
engineering
organisation.
As
mentioned
previously,
the
observed
damage
on
Levels
4
and
10
will
have
caused
load,
designed
to
be
taken
by
the
damaged
elements,
to
be
redistributed
to
other
parts
of
the
structure.
A
preliminary
analysis
has
been
carried
out
indicating
an
increase
in
some
column
loads
above
the
original
design
load
but
to
levels
that
would
not
exceed
the
requirements
of
the
NCC.
We
advise
that
this
analysis
should
be
verified
by
a
qualified
independent
structural
engineer.
In
addition
to
restoration
works
for
the
hob
beam
and
wall
panels
on
Levels
4,
10,
16
and
possibly
26,
it
is
recommended
that
the
following
additional
structural
elements
should
be
checked
for
adequacy
with
respect
to
their
load
carrying
capacity
and
rectification
work
be
undertaken,
if
needed:
1. All
hob
beams
and
connecting
wall
panels
in
the
building
of
similar
design;
2. Other
components
that
may
be
subjected
to
splitting
forces,
such
as
columns
supporting
hob
beams;
and
3. The
longitudinal
tension
force
that
may
derive
in
the
hob
beam
connecting
columns
C16
and
C34
at
Level
4
resulting
from
discontinuation
of
the
panels
at
the
expansion
joint.
We
remain
available
to
provide
further
advice
to
government
once
the
full
details
of
the
proposed
rectification
scheme
have
been
determined.
It
is
also
our
opinion
that
appropriate
rectification
works
can
address
any
deficiencies
in
the
original,
as-‐constructed,
design
and
should
ensure
the
building
is
compliant
with
the
NCC.
The
Future
Our
third
term
of
reference
asked
us
to
make
any
other
recommendations
on
what
needs
to
happen
to
avoid
future
incidents
such
as
the
one
discussed
in
this
report.
Our
investigations
of
this
rare
but
concerning
case
of
structural
damage
in
a
relatively
new
13
February 2019
Opal Tower Investigation – Final Report
high-‐rise
apartment
block,
have
provided
us
with
relevant,
important
and
unique
insights.
Australia
enjoys
a
strong
regulatory
environment
in
construction,
especially
in
regards
to
building
structural
safety,
through
the
National
Construction
Code
and
associated
mechanisms,
including
in
New
South
Wales.
This
has
provided
Australia
with
an
excellent
record
in
terms
of
building
structural
safety
with
few
if
any
of
the
catastrophic
incidents
recorded
in
many
other
international
jurisdictions.
Standards
and
Codes
are
generally
built
into
our
regulatory
systems
to
specify
minimum
safety
criteria,
which
must
be
attained.
Australia
is
also
home
to
some
of
the
world’s
best
architects,
design
engineers
and
construction
companies
who
enjoy
high
international
reputations
for
their
work
globally,
including
the
firms
associated
with
the
design
and
construction
of
the
Opal
Tower.
However,
community
and
consumer
expectations
rise
far
higher
than
just
overall
building
structural
safety,
with
a
reasonable
belief
that
all
components
of
a
building
should
be
structurally
sound
and
stable.
In
the
case
of
the
Opal
Tower,
this
expectation
was
clearly
not
satisfied.
Structural
design
and
construction
codes
in
Australia
are
based
upon
the
principle
of
performance
pathways,
which
focus
on
overall
building
performance
requirements
rather
than
specifying
how
it
is
to
be
constructed.
This
approach
enables
innovation
and
evolution
in
terms
of
architectural
appearance
and
construction
techniques,
and
has
become
a
celebrated
feature
of
the
Australian
built
environment.
This
includes
not
only
Performance
Solutions
under
the
NCC
but
also
performance-‐based
design
and
construction
in
accordance
with
Australian
Standards.
Performance-‐based
design
and
construction
enables
the
creation
of
attractive
novel
architectural
and
structural
design
solutions
with
increasing
efficiencies,
countering
the
architectural
‘sameness’
and
higher
construction
costs
that
can
arise
from
highly
prescriptive
construction
procedures.
While
it
was
not
within
the
scope
of
our
review
to
look
closely
at
the
certifications
that
took
place
on
the
Opal
Tower,
we
found
no
evidence
that
the
building
certifiers
had
been
deficient
in
regards
to
statutory
expectations.
Nevertheless,
there
was
a
range
of
construction
issues
that
occurred
which
were
not
compliant
with
Australian
standards,
and
aspects
of
the
design
which
led
to
structurally
inadequate
sections
of
the
Opal
Tower.
While
no
evidence
has
been
found
that
those
responsible
for
certifying
work
did
not
conform
with
requirements,
it
is
evident
that
a
number
of
checks
for
compliance
were
not
undertaken
or
undertaken
with
insufficient
rigour.
Through
the
course
of
the
investigation
of
the
Opal
Tower,
it
has
become
evident
that
tensions
between
the
application
of
performance-‐based
design
and
construction
and
the
regulatory
environment
and
processes
have
led
to
deficiencies
where
community
expectations
of
building
quality
have
not
been
met.
We
believe
that
these
can
be
resolved
with
improvements
to
the
regulatory
environment
without
altering
the
benefits
of
the
current
overarching
approaches
to
design
and
construction
in
New
South
Wales
and
Australia.
From
the
outcomes
of
our
investigation
we
make
the
following
recommendations.
The
first
three
recommendations,
if
they
had
been
in
place,
would
have
significantly
reduced
the
likelihood
of,
or
avoided,
the
Opal
Tower
damage.
The
last
two
are
put
14
February 2019
Opal Tower Investigation – Final Report
forward
as
mechanisms
to
raise
the
overall
standards
of
building
design
and
construction
and
community
confidence.
1. Creation
of
a
Registry
of
Engineers.
Registered
engineers
should
have
a
high
level
of
competency
including
recognised
qualifications
benchmarked
to
international
education
standards,
minimum
level
of
professional
practice
and
currency
of
continuing
technical
professional
development
(particularly
important
in
an
evolving
field
such
as
building
design
and
construction).
The
Registry
should
be
managed
by
government
in
partnership
with
an
appropriate
professional
body.
Certifications
and
approvals
associated
with
the
design
and
construction
of
a
building
should
then
only
be
undertaken
by
Registered
Engineers
in
their
specialised
area
of
expertise.
2. Independent
third
party
certification
of
engineering
designs.
All
engineering
designs
for
major
projects
should
require
checking
and
certification
by
a
Registered
Engineer.
For
identified
critical
elements
of
a
design,
certification
should
be
by
a
third
party
Registered
Engineer,
fully
independent
from
the
original
designer.
This
requirement
should
also
extend
to
all
changes
to
critical
elements
that
occur
up
until
the
completion
of
construction,
and
essentially
to
any
alternations
that
may
subsequently
occur
during
the
operational
life
of
a
structure.
Major
projects
are
those
that
are
clearly
significant;
a
detailed
definition
should
be
developed
with
all
stakeholders.
3. Regime
of
critical
stage,
on-‐site
inspections
by
an
independent
Registered
Engineer.
A
mandated
regime
for
inspections
on
major
projects
should
be
developed
for
critical
stages
of
construction
and
for
identified
critical
elements
to
ensure
that
construction
is
according
to
certified
designs.
Furthermore,
these
inspections
should
be
undertaken
by
an
engineer
who
is
registered
and
present
on-‐site.
Recommendations
for
what
constitute
the
‘critical
stages
of
construction’
should
be
made
by
the
structural
designer,
and
independently
verified
as
a
part
of
the
design
certification
process.
It
would
also
be
preferable
to
have
a
Registered
Engineer
on
site
who
certifies
that
all
elements
of
a
building
are
as
per
the
approved
design.
4. Raise
transparency
through
the
creation
of
an
open
repository
for
all
certifications.
This
repository
may
be
accessed
by
a
broad
range
of
stakeholders
including
owners
and
prospective
owners;
before,
during
and
after
construction.
This
is
intended
to
raise
the
accountability
of
certification
processes
and
simultaneously
provide
confidence
to
the
community
that
appropriate
certifications
are
being
undertaken,
confirming
the
integrity
of
all
aspects
of
design
and
construction.
For
the
current
investigation,
we
have
been
provided
with
all
available
information
requested.
As
independent
expert
reviewers,
however,
we
have
noted
that
the
time
taken
to
obtain
documentation
and
its
curation
and
completeness
was
at
times
challenging.
We
do
not
believe
that
this
is
an
ideal
situation
and
that
the
community
would
benefit
from
increased
transparency.
15
February 2019
Opal Tower Investigation – Final Report
5. Creation
of
a
Building
Structure
Review
Board.
This
Board
would
consist
of
independent
experts
whose
role
would
be
to
review
major
incidents
of
design
and
construction
related
structural
damage
to
buildings.
The
Board’s
role
would
be
to
assess
the
causes
of
such
incidents
and
to
consider
and
recommend
changes
to
codes
and
regulations
arising
from
their
findings.
This
would
provide
community
confidence
that
expert
independent
consideration
was
being
undertaken
of
serious
incidents
of
damage
and
a
mechanism
for
prompt
and
efficient
adaption
of
codes
and
regulations
in
a
performance-‐based
design
and
construction
environment.
Conclusions
This
report
has
documented
our
investigations
of
the
structural
damage
to
the
Opal
Tower
at
Sydney
Olympic
Park,
which
first
became
apparent
on
Christmas
Eve
2018.
We
have
considered
all
evidence
put
before
us
and
have
concluded
that
the
causes
of
the
observed
damage
were
related
to
a
combination
of
design
and
construction
matters,
in
particular
changes
made
after
the
original
design
and
exacerbated
by
construction
issues.
The
details
of
these
causes
and
the
reasoning
behind
our
conclusions
have
been
provided
in
the
body
of
this
report.
We
have
not
sought
to
indicate
who
was
responsible
for
any
of
the
causes,
but
rather
to
establish
their
structural
basis.
We
have
noted
that,
at
times,
documentation
has
been
unclear
in
this
regard.
We
have
also
addressed
the
issue
of
remediation
of
the
structural
damage
to
the
Opal
Tower.
Although
full
details
of
the
remediation
measures
are
yet
to
be
determined,
we
have
agreed
in
principle
with
the
proposal
for
remediation
that
was
put
before
us.
We
have
also
responded
to
the
terms
of
reference
of
our
investigation
by
making
five
separate
recommendations
for
future
actions
by
government
and
regulatory
bodies.
These
were
aimed
at
avoiding
situations
like
the
one
encountered
with
the
Opal
Tower
and
at
improving
the
robustness
of
structural
designs
and
the
implementation
of
those
designs
during
construction.
These
recommendations
are
also
intended
to
improve
the
transparency
and
public
accountability
of
the
regulatory
systems
relating
to
the
built
environment
in
New
South
Wales
and
Australia.
John
Carter,
Mark
Hoffman
and
Stephen
Foster
Date:
19
February
2019
16
February 2019
Opal Tower Investigation – Final Report
17
February 2019
Opal Tower Investigation – Final Report
C34
Figure 3. Plan view indicating locations of damage observed on Level 4
Figure 4. Plan view indicating locations of damage observed on Level 10
18
February 2019
Opal Tower Investigation – Final Report
19
February 2019
Opal Tower Investigation – Final Report
Figure
6.
Damaged
precast
Panel
A
at
Level
10
above
column
C38,
after
some
broken
sections
of
concrete
removed.
20
February 2019
Opal Tower Investigation – Final Report
Figure
7.
Photographs
of
the
hob
beam
in
the
vicinity
of
column
38
at
level
10,
prior
to
pouring
concrete
(top
photo),
inside
the
building
on
8
January
2019
after
cracked
concrete
cover
removed
(middle),
and
outside
on
8
January
2019
after
the
garden
and
waterproof
covering
removed
(bottom).
Note
the
positioning
of
the
reinforcing
bars,
the
encroachment
of
the
column
bars
into
the
cover
zone,
the
lack
of
anchorage
of
some
horizontal
bars,
and
the
encroachment
of
a
conduit
into
the
concrete
cover
zone.
The
vertical
dowel
bars
that
engage
with
the
precast
concrete
panels
can
also
be
seen
in
the
top
photograph.
21
February 2019
Opal Tower Investigation – Final Report
Figure
8.
Photographs
of
the
outside
(top)
and
inside
(bottom)
of
panel
A
at
Level
10
just
above
hob
beam
adjacent
to
column
21,
indicating
N20
reinforcing
bars
at
100
mm
centres
in
the
lower
portion
of
the
precast
panel.
Note
the
exposed
grout
between
panel
A
and
the
hob
beam
and
the
black
plastic
sheath
for
the
joining
dowel
(top
photo,
right
of
tape
measure).
22
February 2019
Opal Tower Investigation – Final Report
Figure
9.
Photographs
of
the
damaged
floor
slab
adjacent
to
column
C21
on
Level
10.
23
February 2019
Opal Tower Investigation – Final Report
Figure
10.
Photographs
of
the
damaged
hob
beam
on
Level
4
near
column
C34
before
(top)
and
after
(bottom)
cracked
concrete
removed.
24
February 2019
Opal Tower Investigation – Final Report
Figure
11.
Photograph
of
the
hob
beam
and
panel
on
Level
4
near
column
C2
with
red
lines
indicating
minor
cracking.
25
February 2019
Opal Tower Investigation – Final Report
Figure
12.
Photograph
of
a
crack
in
the
floor
plate
between
Levels
3
and
4.
26
February 2019
Opal Tower Investigation – Final Report
Figure
13.
Typical
distributions
of
axial
stresses
acting
on
the
hob-‐beam
(left)
and
tensile
bursting
stresses
(right)
–
Level
4
Grid
Line
A.
27
February 2019
Opal Tower Investigation – Final Report
P
P/2 P/2
Precast wall
w1
w2 z
w2 w1 Grout Tb
Hob-beam
P
P/2 P/2
Figure
14.
Schematic
representation
of
axial
forces
and
stresses
passing
through
the
wall
panel
to
hob-‐beam
grouted
connection
(left),
and
strut-‐and-‐tie
model
describing
bursting
forces
that
result
from
the
disturbance
caused
by
the
joint’s
geometry
(right).
28
February 2019
Opal Tower Investigation – Final Report
Bowing
of
reinforcement
and
opening
of
stirrup
Figure
15.
Damage
in
hob
beam
at
Level
4
above
column
C34
showing
bowing
of
reinforcement
and
opening
of
stirrup.
29
February 2019
Opal Tower Investigation – Final Report
30
February 2019
Opal Tower Investigation – Final Report
Figure
17.
Hob
beam
at
Level
10
in
the
vicinity
of
column
C34
(outside)
showing
splitting
along
shear
compression
crack
band
lines.
31
February 2019
Opal Tower Investigation – Final Report
32
February 2019
Opal Tower Investigation – Final Report
Figure
19.
Drawing
of
the
underside
of
Wall
10C-‐14.5
(Level
10
grid
line
C)
documenting
a
splitting
crack
in
the
floor
slab
between
columns
C21
and
at
C38.
33
February 2019
Opal Tower Investigation – Final Report
Figure
20.
Hob-‐beam
and
precast
wall
panel
at
Level
10
in
the
vicinity
of
column
C21
(apartment
side)
showing
splitting
of
the
precast
panel
and
the
damaged
hob
beam.
34
February 2019