STEEL WORKS
1.0 Materials. Roof framing
2.0 Labor
Particulars Quantity No. Of days Rate Amount
Welder 4 10 450.00 18,000.00
Helper 4 10 358.00 14,320.00
Total 32,320.00
II. FALSEWORKS
Total = 234.31 𝒎𝟐
1.0 Materials
Particulars Quantity Unit Unit cost Amount
2"x2"x12' Gmelina Lumber 3,000 bd ft. 25.00 72,000.00
5mmx1.2mx2.4m ordinary plywood 100 Pcs 260.00 35,500.00
C.W nails # 4" (40kg/box) 4 Boxes 1,760.00 7,040.00
C.W nails # 3" (40kg/box) 3 Boxes 1,760.00 5,280.00
C.W nails # 2.5" (40kg/box) 2 Boxes 1,760.00 3,520.00
C.W nails # 1" (40kg/box) 1 Boxes 1,760.00 1,760.00
Total 125,100.00
III. TINSMITHRY
1.0 Materials
Unit
Particulars Quantity Unit cost Amount
0.40 mm x 1110 m effective length rib type pre-painted
color roofing long span (brown) 98 L.m. 490.00 48,020.00
0.40 mm x 2.40 m pre-painted spanish gutter (brown) 10 L.m. 490.00 4,900.00
Tekscrew for C-purlins 2240 Pcs 2.00 4,480.00
Blind rivets 1/8" x 1/2" (1000pcs/box) 3 Boxes 350.00 1,050.00
Total 58,450.00
2.0 Labor
Particulars Quantity No. Of days Rate Amount
Tinsmither/carpenter 5 12 450 27,000.00
Helper 5 12 358 21,480.00
Total 48,480.00
TOTAL COST OF MATERIAL = 292,760.00
TOTAL = 411,340.00
COST ESTIMATE OF THE PROPOSED TWO-STOREY BUILDING
CE 82 CONSTRUCTION COST ENGINEERING
DECEMBER 2018