P343 16 PDF
P343 16 PDF
P343 16 PDF
IM-P343-16
CH Issue 3
1. Safety information
2. Introduction
3. Installation
4. Commissioning
5. Maintenance
6. Spare parts
7. Fault finding
IM-P343-16
Printed in the CH
UK Issue 3 1
© Copyright 2007
2 IM-P343-16 CH Issue 3
1. Safety information
Safe operation of these products can only be guaranteed if they are properly
installed, commissioned, used and maintained by qualified personnel (see
Section 1.11) in compliance with the operating instructions. General installation and
safety instructions for pipeline and plant construction, as well as the proper use of
tools and safety equipment must also be complied with.
1.2 Access
Ensure safe access and if necessary a safe working platform (suitably guarded)
before attempting to work on the product. Arrange suitable lifting gear if required.
1.3 Lighting
Ensure adequate lighting, particularly where detailed or intricate work is required.
IM-P343-16 CH Issue 3 3
1.6 The system
Consider the effect on the complete system of the work proposed. Will any proposed
action (e.g. closing isolation valves, electrical isolation) put any other part of the
system or any personnel at risk?
Dangers might include isolation of vents or protective devices or the rendering
ineffective of controls or alarms. Ensure isolation valves are turned on and off in a
gradual way to avoid system shocks.
1.8 Temperature
Allow time for temperature to normalise after isolation to avoid danger of burns.
1.12 Handling
Manual handling of large and/or heavy products may present a risk of injury. Lifting,
pushing, pulling, carrying or supporting a load by bodily force can cause injury
particularly to the back. You are advised to assess the risks taking into account the
task, the individual, the load and the working environment and use the appropriate
handling method depending on the circumstances of the work being done.
4 IM-P343-16 CH Issue 3
1.13 Residual hazards
In normal use the external surface of the product may be very hot. If used at the
maximum permitted operating conditions the surface temperature of some products
may reach temperatures of 90°C (194°F).
Many products are not self-draining. Take due care when dismantling or removing
the product from an installation (refer to 'Maintenance instructions').
1.14 Freezing
Provision must be made to protect products which are not self-draining against
frost damage in environments where they may be exposed to temperatures below
freezing point.
1.15 Disposal
Unless otherwise stated in the Installation and Maintenance Instructions, this
product is recyclable and no ecological hazard is anticipated with its disposal
providing due care is taken.
IM-P343-16 CH Issue 3 5
2. Introduction
2.1 Introduction
The EP5 is a 2 wire loop powered positioner requiring a 4-20 mA control signal, and is
designed for use with linear pneumatic valve actuators. The positioner compares the
electrical signal from a controller with the actual valve position and varies a pneumatic output
signal to the actuator accordingly. The desired valve position is therefore maintained for any
control signal and the effects of varying differential pressure, stem friction and hysterisis
are overcome. A mounting kit is supplied to suit all NAMUR standard columns or yokes.
Note: A 0-10 Vdc input signal and an intrinsically safe version ISP5 are also available.
A = Control signal
I = I / P converter output
S = Air supply
O = Positioner output
U1 = Increase action nozzle
U2 = Decrease action nozzle 3
4
O
S
2
I
+
- A
Fig. 1
6 IM-P343-16 CH Issue 3
3. Installation
Note: Before starting any installation observe the 'Safety information' in Section 1.
This publication is provided as a guide and it is recommended that it is read thoroughly prior
to installation. Also refer to the separate Installation and Maintenance Instructions for the
control valve and actuator.
3.1 Location
The positioner should be mounted in sufficient space to allow removal of the cover and provide
access to connections. When fitting to an actuator, ensure the positioner will not be exposed
to an ambient temperature outside the range -15°C to +65°C. The positioner enclosure is rated
to IP54 see BS EN 60534-6-1 1998.
Connection of air supply pressure (1.4 to 6 bar g) and control signal (4-20 mA or 0-10 Vdc)
should be considered prior to choice of location.
- The distance between the axes of the valve/actuator stem and the positioner slide pin.
- When attaching an EP5 to any Spirax Sarco valve actuator, ignore Step 3.
IM-P343-16 CH Issue 3 7
Step 2 For attachment to Spirax Sarco actuators
Using the 2 off M6 pan head screws, securely attach the 'T' shaped sliding pin holder to
the valve actuator coupling block (Figure 2). Apply Loctite to the sliding pin and screw into
hole 'Y' (as shown) on the sliding pin holder and tighten.
Valve X Y
actuator
coupling
block
'T' shaped
sliding pin holder
Z
Fig. 2
Close-up of
sliding pin
holder fitted to
valve coupling.
Using the 2 off M8 x 15 hex head screws and 8 mm spring washers, attach the mounting plate
to the back of the positioner, utilising holes No. 2 in the bracket (Figure 3). Take care not to
over-tighten these screws and strip the threads.
Positioner 4 3 2 1
Mounting plate
Fig. 3
Using the 2 off M8 x 15 hex head screws and 8 mm spring washers, attach the mounting
plate to the back of the positioner. The correct fixing hole may be determined by reference to
Figure 3, Table 2 and Figure 4. Take care not to over-tighten these screws and strip the threads.
8 IM-P343-16 CH Issue 3
Actuator pillar Actuator
or yoke spindle
100%
50%
0%
D
➤
➤
Step 4 Temporarily apply adequate air pressure directly into the actuator so that the
valve is at 50% of travel (Figure 5).
Step 5 Engage the slide pin into the positioner lever (see Figure 5, noting the position of
the spring, above the pin) and loosely fix the positioner to the actuator. For yoke actuators
use the single elongated screw hole with the M8 x 20 screw and spring washer, for pillars
use the U-clamps.
Important: Slide positioner vertically up or down the yoke/pillars so the positioner lever is
horizontal at 50% travel, and the indicator at LHS is aligned (Figure 5). Secure the tightening
screws/nuts.
Fig. 5
IM-P343-16 CH Issue 3 9
Step 6 Fit the angled protection plate to the rear of the positioner using the 2 off captive
M3 pan head screws. Access to these captive screws is from inside the positioner.
Step 7 Adjust the air supply pressure to stroke the actuator from 0% to 100% and ensure
the positioner lever rotates freely. Remove the temporary air supply from the actuator.
3.3 Connecting up
10 IM-P343-16 CH Issue 3
3.3.2 Electrical connections
Cabling should be installed in accordance with BS 6739 - Instrumentation in Process Control
Systems: Installation design and practice or local equivalent.
The EP5 only requires a 4 - 20 mA (standard) or 2 - 10 Vdc (if requested) signal. Remove the
front cover and locate the terminal block and earth terminal post (Figure 6).
Note: Ensure resistance from earth post to local earth (e.g. pipework) is less than 1 .
Connection to the unit is through the Pg 13.5 cable gland (as supplied), which when used
with suitable cable will ensure the IP54 protection rating. Appropriate conduit connections
may be used instead.
Connect conductors (0.5 to 2 mm²) to the terminal block and earth post (3 mm²) noting the
polarity +/- shown in Figure 6.
In hazardous areas use model ISP5 with intrinsic protection (type EEx ia llC T6, T5,T4) ensuring
the power supply from adjoining equipment is certified in accordance with EN 50.014 and
EN 50.020 standards, in respect of the limits of electric features shown at approval stage.
Refer to approval certificate supplied with each ISP5 product.
Earth
terminal
Cable post
gland I
Terminal
block
-
+ S
Fig. 6
IM-P343-16 CH Issue 3 11
4. Commissioning
Once the positioner has been mounted and connected up, proceeed as follows.
b. Setting the slider in the upper or lower portion of the crescent shaped sector lever (Figure 8).
Connection
to nozzle U2
Connection
to nozzle U1
Fig. 7
U1 = Increase action = With increasing electrical control signal the air pressure to the
actuator will increase.
U2 = Decrease action = With increasing electrical control signal the air pressure to the
actuator will decrease.
12 IM-P343-16 CH Issue 3
To change the slider location:
Refer to Figure 8 to determine the correct portion. To change the slider slacken the screw
and slide it into the correct portion of the arm.
I
* U1 nozzle
S
O
* U1 nozzle
I
S
O
Lower
sector
* U2 nozzle
I
S
O Lower
sector
Upper
sector
I
S
O
* U2 nozzle
* The arrow shows the stem movement direction when the input control signal increases.
IM-P343-16 CH Issue 3 13
Step 2 Set sensitivity
The positioner sensitivity is adjusted using the sensitivity screw (Xp %, see Figure 10). It is
set depending on air supply pressure. Before the commissioning stage it is essential to set
the sensitivity within a proportional band of (3% to 6%). Use Figure 10 to adjust the sensitivity
screw by firstly fully closing the screw (clockwise), then reopen the screw:-
1.4 bar
Supply pressure
Opening degree
¾
½
¼ 4.0 bar
1
/8 6.0 bar
0 3 6 (Xp %)
➤
➤
Fig. 9 Xp correct value
To increase positioner sensitivity close the adjusting screw, to decrease sensitivity open the
screw. Do not open the screw beyond the mechanical lock.
Sensitivity screw
Fig. 10
Note: Adjustment of the Xp % screw causes a change of positioner 'zero' point, and it is
therefore important to repeat the zeroing and travel setting procedures (Steps 4 and 5) after
any changes.
14 IM-P343-16 CH Issue 3
Step 3 Set damping
The final adjustment of damping screw should be performed with plant in operation, in order
to limit, if necessary, the actuation speed. During the commissioning set the damp screw flush
with the body see Figure 11.
Damp screw
Fig. 11
The reduction of air flowrate capacity to the actuator will slow down the valve movement to limit
the effect of cycling hunting. Closing the screw (clockwise) increases damping, and vice versa.
Zero point
adjustment screw
Central locking screw
Sector lever
Fig. 12
Note: Positioners fitted with a gauge block have the benefit of anticipating valve movement
by indicating increases of output air pressure.
IM-P343-16 CH Issue 3 15
Step 5 Set travel
Increase the electrical control signal to the upper value (normally 20 mA or 10 V, but this
depends on the application) and now check the travel of the valve. If required, slacken the
central locking screw (see Figure 12) and adjust the slider up or down the upper or lower portion
of the crescent shaped sector lever. Moving the slider away from the pivot will reduce the
travel, and vice versa. Normally, except with 3-port valves, the fully open position is achieved
before the valve plug hits the upper mechanical stop of the valve/actuator. Avoid settings of
the positioner that allow contact with this mechanical stop. Vary the electrical control signal
around the upper value to verify the travel setting, and if necessary repeat the adjustment of
the slider until the required travel occurs at the upper value.
Important: Zero and travel settings on EP5 are not independent of each other, so re-check
the zero setting as described in Step 4. It may prove necessary to repeat Steps 4 and 5
several times until acceptable zero and travel settings are achieved. For fine adjustment of
the travel, the potentiometer shown in Figure 13 can be used. This should only be used for
final adjustment of +/- 5%.
When complete, lock both zero and travel adjustments.
Travel adjustment
potentiometer
Fig. 13
16 IM-P343-16 CH Issue 3
5. Maintenance
5.1 Regular maintenance
1. Drain any build-up within the air supply filter set as impurities such as oil, water and dirt
will cause inconsistent operation.
2. Ensure air supply is at the correct pressure (see Section 3.3.2 and refer to actuator TI).
3. Make visual checks to ensure the valve is operating correctly.
Fig. 14
- Refit the lock to touch the adjuster top and secure with lock-nut.
- Set sensitivity see Step 2, Section 4, Commissioning.
- Reset zero and span if required.
IM-P343-16 CH Issue 3 17
5.2.2 Removal and cleaning of capillary orifice (see Figure 15):
- Loosen locking plate screw.
- Rotate locking plate to expose capillary orifice.
- Using supplied extractor/cleaner pull the orifice from the body.
- Clean the small orifice and cross drilling using only the special cleaning wire supplied.
- Reassemble the orifice ensuring both 'O' rings are in place and the lock plate covers the orifice.
Extractor/cleaner
Fig. 15
Damping faces
Locking plate
Capillary orifice
Fig. 16
Capillary extractor / cleaner
18 IM-P343-16 CH Issue 3
6. Spare parts
Available spares
Gauge block (without gauges) 1
Gauge 0 - 2 bar 2
Gauge 0 - 4 bar 3
Gauge 0 - 7 bar 4
Springs and tubes 5
Set of gaskets, diaphragms and orifice 6
Amplifying relay set 7
6 7 5 1
TAG number
3 or 4
Fig. 17
Alternatively, please return any items to your local Spirax Sarco branch.
Please ensure all items are suitably packed for transit (preferably in the original cartons).
IM-P343-16 CH Issue 3 19
7. Fault finding
Output pressure too low or zero
Cause Remedy
a. No control signal a. Restore mA signal
b. Low air supply pressure b. Verify actuator air pressure requirement
c. Clogged or dirty sensitivity adjuster c. Clean adjuster see Section 5.2.1
d. Clogged or dirty capillary orifice d. Clean orifice see Section 5.2.2
e. Incorrect set-up e. Recalibrate see Section 4, Steps 1 to 5
f. Damaged pneumatic actuator or piping f. Verify replace as necessary
g. Port I not blanked or leaking g. Insert ¼" NPT blank in port I
Output pressure too high
Cause Remedy
a. Sensitivity adjuster open too far a. Recalibrate see Section 4, Step 2
Actuator movement too slow
Cause Remedy
a. Low air supply capacity a. Check supply capacity and pipe sizes
b. Damping screw closed too far or clogged b. Recalibrate see Section 4, Step 3
Actuator failing to close
Cause Remedy
a. Output pressure too low a. Refer to previous fault
b. Incorrect zero point b. Recalibrate see Section 4, Step 4
c. Damping screw closed or clogged c. Clean screw and recalibrate see Section 4, Step 3
d. Valve / actuator coupling incorrect d. Reset (refer to valve/actuator IMIs)
e. Actuator too small e. Fit correct actuator
Actuator failing to fully open valve
Cause Remedy
a. Output pressure too low a. Refer to previous fault
b. Incorrect travel adjustment b. Recalibrate see Section 4, Step 5
c. Damping screw closed or clogged c. Clean screw and recalibrate see Section 4, Step 3
d. Valve / actuator coupling incorrect d. Reset (refer to valve/ actuator IMIs)
e. Actuator too small e. Fit correct actuator
Hunting
Cause Remedy
a. Incorrect controller set up (P, I, and D) a. Verify and adjust according to process requirement
b. Sensitivity orifice closed too far b. Adjust by opening sensitivity screw
see Section 4, Step 2
c. Excessive valve friction c. Verify and maintain as valve IMI
d. Control valve over-sizing d. Verify operating conditions against valve capacity.
Note: The effects of hunting caused by valve over-sizing or unstable process conditions can be
reduced by adjustment of damping screw see Section 4, Step 3.
20 IM-P343-16 CH Issue 3