Outstanding Issues: Project Control
Outstanding Issues: Project Control
Outstanding Issues: Project Control
###
Raised by Item Outstanding Issues Team in Charge Status / Plan Remark
Structural steel is under fabrication and will reach site next week.
GC Office - Dispatch & Receiving of 1,2 - Structural Steel(7/24)
Project Control Dispatching & Receiving of Material Construction Upto now no impact considering FDN is delayed. Procurement team
JV Office - Dispatch & Receiving of 1,2 - Structural Steel(7/19)
has be to request to follow up agency for material.
Letter for Consent to establishment was issued to Mahashtra
Application of NOC Administration
pollution control board from MMRDA on July-17
Specification and Quantity for pile test & next 3 months to be MR already issued. But MR will be reissued for qt'y of
RCD Pile test Construction
provided to procurement team test pile and next 3month pile.
Construction
Manpower mobilization plan and the hiring status to be checked
HR
Application of NOC to INSA: Need to check with the agency to find out
the reason of objection from 2 Local owner of barge
Heavy Equipment
Mobilization of Floating Barge Plan for the arrangement of supplying Aggregate, Sand and Cement
QA/QC
is required to be submitted to GC for getting final approval on floating
BP from HAJU.
Raised by Item Outstanding Issues Team in Charge Status / Plan Remark
Pipeline Interference Set-up Way-out plan Design Plan were received from Ramboll and JFE. Under review
Quantity Variation Report to H.O Report by end of July Design BOQ received from Ramboll on 27 Jul.
DBR of Temporary Bridge Awaiting approval from GC Design past 33 days pending
Fishing Boat Channel Awaiting approval from GC Design past 33 days pending
Temporary Bridge- Material Platform Awaiting approval from GC Design past 33 days pending
Diesel Storage tank design capacity of tank / foundation designs pending Site Execution/Equipment Site execution will furnish details and based on that design can start
Tower crane capacity and model at material platform Design of supporting structure(Details awaited) Construction
Many IRF's are still open. Need to close IRF's on weekly basis and
Closing of open IRF's & responsibilities of Construction, maintain log of open and close IRF's. Need to define responsibility
QA/QC Construction / Design
Project control & QA/QC dept matrix for raising, closing maintaining closed IRF's
Status of open and close IRF's is not known
Construction of foundation and prefab structure for QA/QC lab not yet
Delay in commencement of Main QA/QC lab Construction
started. Status of commencement date and end date unknown.
Bi-directional Load Test Finalization of Technical Parameters for Bi-directional PIle Load Test Design
The 2nd unit is already ready for dispatch at vendor factory. Already
Heavy Equipment Clearance for dispatch of 2nd Batching plant unit discussed with execution team and next week onwards dispatch Construction
instruction will be given.
Both 1000 cfm & 330 cfm air compressor are ready for dispatch at
Clearance for dispatch of 1000 cfm & 330 cfm air vendor factory. Already discussed with execution team and
Construction
compressor accordingly instruction to be given to the manufacturer for dispatch
form 1st of August onwards.
Administration Accommodation NRI Complex Maintenance Administration Still going on(will be completed by Agency) : Mr. Pramod CHOI
Access Control at Site Immediately need Installation of Security Cabin at project office gate Administration Enquiry floated Shaji
Container Cabin needed so that medicals can be done at site for sub-
OHC Centre SCM Container cabin ordered, awaiting deliver for further action
contractor workmen.
Installation of Security Cabin project office gate. Enquiry floated, MR
Security Cabin and Access Control at Site Administration Pramod M
to be raised
Need to shift one guest house to another location and take that
Office space needed More people are joining who would be. Administration Pramod M
space for office. Awaiting added info from other stake holders
Application made partially. Need a meeting with Dy. Labour
Labour Licence Application for obtaining labour licence Administration Expected on Monday
commissioner. Awaiting appointment.
Finance Statement of Final Accounts Closing of Monthly & Quarterly : Updated JV & TPL/Daewoo Finance Input the data in TPL/Daewoo(Mr.Paras & Choi) Bala/Choi
SAP A/C System Keep on Excel File Finance End of SEP. will be Updated SAP(Mr.Paras) Bala
Safety
Raised by Item Outstanding Issues
Design to submit the plan as how many submission will be done which can
1st Financial Milestone be considered for billing
Project Control Minimum Stock Minimum Stock items to be given to store / SCM so that they'll maintain the
minimum stock
Controlled Permeability
Details awaited from Design
Membrane
Construction :
Super-Str Drain and Road sections to be finalized
Super-Str
Raised by Item Outstanding Issues
Supplier, Agency Selection, P/O Permissions for Diesel dispenser pump and agency confirmation
Access from Barge to Pile Jacket ( Ladders to have steps instead of flat
Access from Barge to Pile Jacket surface with anti -skid arrangement ( with rebar).
Raised by Item Outstanding Issues
Hand railing for working barges (AF180 & San 40 partly completed ,Spud
Hand railing for working Barges barge Yuvaan, KM 180 and Saradhi-1 to be done)
Safety
Waste Disposal Oil soaked cotton wastes , used oil & Waste oil to be disposed by 11.02.2019
Raised by Item Outstanding Issues
Inputs for M60 Grade Concrete Need Inputs like Early Strength requirement, Method of Concrete
for Precast Segments placement, Retention time, Slump/flow to start Mix design trials
Finalisation of Aggregate source Its difficult to achieve required values of durability tests using
for M45 & M60 grade concrete aggregates from existing source (TIPL) for M45 & M60 grade
QA/QC
Contractors/Vendors for
fabrication and Permanent Copy of PO issued to Vendor/Contractor shall be marked to QA/QC
construction activities
Outstanding Issues - 09 feb 19
Project Controls / Billing R A Bill No-7 amounting of INR 142 Cr as per the sheet 15-Feb-19
circulated
Project Controls / Billing Project Control to circulate the list by 14 Feb as what items to 28-Feb-19
be considered in R A Bill No 8
Quality
control/Environment
Construction
Team in Charge Status / Plan Target date
Design
Design 11-Feb-19
PJC / SCM
Heavy Equipment
Design 12-Feb-19
Team in Charge Status / Plan Target date
Design
SCM
Planning
Planning
Team in Charge Status / Plan Target date
Planning 14-Feb-19
Planning
SCM
Delivery on end of
SCM February
SCM
PJC Order Placed for Canteen Furniture Next Week
PJC
HR/ Admin HR / Admin to confirm the date as this is long due item Immediate
15-Feb-19
Team in Charge Status / Plan Target date
13-Feb-19
18-Feb-19
15-Feb-19
JV office area PCC Done. Labour camp & Belapur jetty by 19-Feb-19
19.02.2018
Design/ Construction Mix design trials for M60 grade concrete for precast Immediate
Super Stucture segments could not commence
Remark
- Completed
-
Remark
18-Feb-19
-Hose- Recieved
'-Winch problem- Need to final
Naval Architect (NA) is of the opinion that present configuration is best from
stability point of view. Had further discussion with NA on 16.02.2019. Naval
Architect will give alternatee options on 18-feb-19
3572 Nos received and balance 3078 Nos will be received by 20th Feb 2019
Partly resolved
- completed
Expected-21-Feb-2019
Revised target-20-feb-19
Detailed Plan (With Target, Support Reqd & Responsibility) by USN: 26.02.19
30 KLD at JV Office and 300 kld at Camp. Detailed Plan by USN by 21.02.2019
Construction :
Sub-Str
Raised by Item Outstanding Issues
Construction :
Super-Str
Raised by Item Outstanding Issues
Store
Access from Barge to Pile Jacket ( Ladders to have steps instead of flat
Access from Barge to Pile Jacket surface with anti -skid arrangement ( with rebar).
Raised by Item Outstanding Issues
Hand railing for working barges (AF180 & San 40 partly completed ,Spud
Hand railing for working Barges barge Yuvaan, KM 180 and Saradhi-1 to be done)
Safety
Aviation lights Aviation light for Cranes
Safe walkway on marshy land at Walk way by providing with SAND BAGS in Marshy Land in the MP 240
Nhava NHAVA.
Environment
Raised by Item Outstanding Issues
Environment
Waste Disposal Oil soaked cotton wastes , used oil & Waste oil to be disposed by 11.02.2019
Raised by Item Outstanding Issues
Outstanding Issues - 09 feb 19
Team in Charge
Team in Charge
Team in Charge
Design
Design
Design
Design
Team in Charge
Team in Charge
Team in Charge
Team in Charge