Boq Floor Tiling Works

Download as pdf or txt
Download as pdf or txt
You are on page 1of 1

ZOAR CONSTRUCTION COMPANY LIMITED

P.O. BOX
NAIROBI, KENYA.

QUOTATION FOR PROPOSED RENOVATION TO FLOOR FOR CHURCH

Item No. Description Unit Quantity Rate Amount

Excavations including maintaining and supporting sides


and keeping free from water, mud and fallen material

A Excavate for foundations not exceeding 1.00 metre, starting from


ground level CM 210 550.00 115,500.00

Disposal

B Return, fill and ram selected excavated material around foundations. CM 150 250.00 37,500.00

C Load, wheel and deposit surplus excavated material from site CM 60 450.00 27,000.00

Plain concrete class 15 in:

D 50mm thick blinding under foundations SM 210 750.00 157,500.00

Reinforced concrete class (20) as described, in:-

E Ground floor slab SM 210 1,275.00 267,750.00

Mesh fabric reinforcement to B.S 4483 and setting in concrete with


300mm side and end laps (measured nett-allow for laps).

F Fabric ref. A142 in surface SM 210 450.00 94,500.00

Hardcore fill

G 300mm thick well compacted hardcore filling blinded with 50mm thick
quarry dust layer to receive surface bed SM 210 500 105,000.00

Murram fill

H Provide, place, water process and compact in accordance


with the specification natural gravel material n.e. 300mm thick SM 210 550 115,500.00

Sawn formwork, as described, to:-

I Vertical sides of floor slab n.e. 150mm high LM 75 150.00 11,250.00

Floor finish

Cement and sand (1:4 )backings etc

J 12mm backing finished to receive ceramic wall tiles (ms) SM 210 400.00 84,000.00

K Supply of ceramic floor tiles, fix on prepared bed (m.s) with


proprietary adhesive; jointed and pointed in matching SM 210 1,250.00 262,500.00
coloured proprietary grouting

TOTAL AMOUNT TO FORM OF TENDER 1,278,000.00

You might also like