0% found this document useful (0 votes)
160 views1 page

ITR C (Mecanical)

This document is an Inspection Test Record for a pig trap system. It outlines 9 reliability test steps to check the installation and operation of the pig trap, including verifying previous inspection records, inspecting instrumentation hookups, pressurizing the vessel, conducting endurance and performance tests according to operating manuals while logging parameter readings, and compiling as-built drawings and outstanding work lists for handover to operations.

Uploaded by

Momo Itachi
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
160 views1 page

ITR C (Mecanical)

This document is an Inspection Test Record for a pig trap system. It outlines 9 reliability test steps to check the installation and operation of the pig trap, including verifying previous inspection records, inspecting instrumentation hookups, pressurizing the vessel, conducting endurance and performance tests according to operating manuals while logging parameter readings, and compiling as-built drawings and outstanding work lists for handover to operations.

Uploaded by

Momo Itachi
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

INSPECTION TEST RECORD (ITR) - C

Pig Trap M46-C


Project No.
Project Title
Facilities
GENERAL INFORMATION
Tag no. System no./Sub-system No.
Make & Model Reference drawing
Serial No Location
RELIABILITY TEST OK N/A P/L No
1 Verify ITR-B is complete and signed off by relevant parties
2 Check/ inspect installation and hook-up of all associated instruments in the
system and ensure all shutdown valves are locked closed.
3 Ensure that all tie-ins or open flanges are blinded.
if spectacle blind are required for isolation of the pig trap from the pipeline, the
spectacle blinds shall be located on the pig trap side of the pig trap valve, kicker
4
valve, isolation valve on the pressurising line (if fitted) and on any vent and drain
lines which are connected to other facilities.
5 Open the isolation valve and introduce medium into the pig trap; pressurize up
the vessel according to operating condition.
6 Refer to the Operation Procedure & Manual (OPM) for detailed Endurance and
Performance Test run.
Attach the logging parameters such as gauges and analyzers’ reading. On-site
7 readings shall be cross-referenced to P&ID and DCS for analysis and performance
assessment.
8 Print copy or snapshots from DCS as proof for acceptance.
Compile Handover Certificates, as-built drawings (P & ID) and
9 outstanding work list for the system (if any) and issue to Operations for
acceptance.
COMMENT(S) AND ADDITIONAL INFORMATION

COMPLETED BY VERIFIED BY ACCEPTED BY


Designation
Company
Name
Signature
Date