ITEM UNIT

DESCRIPTION UNIT QTY AMOUNT


NO. RATE

BILL OF QUANTITIES FOR PROPOSED


BUILDING & CIVIL WORKS

1 Preliminaries

Allow for a temporary site office adequate to


A accomondate six persons,notice board, shelves and, ITEM 1 2,000,000 2,000,000
store for materials and tools storage.

B Allow for clean water for the works ITEM 1 500,000 500,000

Allow for temporary sign post for the proposed


C ITEM 1 300,000 300,000
works and permanent sign post as described.

Allow for security and insurance for the proposed


D ITEM 1 800,000 800,000
works
Allow for supply for substation with water
including all NWSC charges, sub main pipes and all
E ITEM 1 800,000 800,000
connections, testing and commissioning of all the
plumbing works.

TO SUMMARY PAGE 4,400,000


ITEM UNIT
DESCRIPTION UNIT QTY AMOUNT
NO. RATE

BUILDING WORKS
CONTROL ROOM

Clear site of small trees, shrubs and the like, grub up


A SM 48 1,500 72,000
the roots and clear away from the site.

Excavate to reduce levels average depth 200mm


B from striipped level, deposit in temporary spoil SM 48 1,500 72,000
heaps on site.

Excavate strip foundation commencing from


C CM 11 7,000 75,600
stripped level but not exceeding 1.5m deep.

D Ditto but cable trenches, column bases CM 14 7,000 98,000


Extra over excavation for excavation in rock for all
E CM 1 30,000 30,000
classes at any

F Allow for all necessary planking and strutting. ITEM 1 500,000 500,000

Allow for keeping excavation free from general


G ITEM 1 500,000 500,000
water.
Sawn formwork to: -
H sides of strip foundation LM 20 7,500 150,000
I Ditto but cable trench SM 6 25,000 160,000
J Ditto but column bases and footing SM 40 25,000 1,008,000
Concrete.
Mass Concrete Class as described.
Plain concrete (1:4:8-20mm aggregates) in 50mm
L SM 1 450,000 450,000
thick blinding for strip foundation
M Ditto to column bases SM 1 450,000 450,000
N Ditto to cable trenches SM 1 450,000 450,000
Vibrated reinforced concrete class 20/20 (1:2:4/25)
as described in
O Strip foundation CM 3 600,000 1,800,000
P Cable trenches CM 1 600,000 600,000
Q Column bases CM 10 600,000 6,000,000
R Columns footings/stubs CM 1 600,000 600,000
S concrete door ramp CM 0.5 600,000 300,000

High yield mild steel reinforcement from 8mm to


12mm including cutting, bending, spacers, tying
wire and fixing to BS 4449 in, strip foundation,
column base, footing and cable trenches.

T Y 12 KG 50 5,500 275,000
U Y 10 KG 635 5,500 3,492,500
V Y8 KG 30 5,500 165,000
17,248,100
ITEM UNIT
DESCRIPTION UNIT QTY AMOUNT
NO. RATE

Substructure natural Burnt clay brick walling in


cement sand mortar (1:4) including and reinforced
with 20 SWG Hoop iron in every alternative course

A 200mm thick wall. SM 16 5,500 88,000


FILLING
Return, fill and ram approved imported and selected
B CM 19 4,000 76,000
material around foundations.
Load cart away surplus excavated materials and
C CM 6 5,000 30,000
dispose in areas designated by council
Selected hardcore filling, compacted in layers of
D 150mm thick to make up levels to satisfaction of SM 18 18,000 324,000
client
50mm thick approved sand blinding on hardcore
E SM 18 3,000 54,000
fill.
Insecticide.
Prepare and apply "Premise 200 SC " or equal and
F approved insecticide to surfaces of blinding as per SM 101 1,000 101,000
manufacturer's written
Damp Proofing.
1000 gauge polythene DPM laid on top of blinding
G SM 20 2,000 40,000
including 200mm side and end lap
Mild steel bar to BS 4449;
Double BRC mesh reference No. A142 weighing
2.22kg per square meter including 150mm
H SM 23 12,500 287,500
minimum end and side lap, bends, tying wires and
spacer blocks.
Vibrated reinforced concrete class 20/20 (1:2:4/25)
I
as described in
J 150mm thick ground floor slab. SM 23 90,000 2,070,000
Sawn formwork to;
K Sides of ground floor slab 100-150mm high LM 20 3,750 75,000
Superstructures
Damp Proof Course.
200mm wide dump proof course (DPC) laid with
L LM 27 2,500 67,500
1:3mix cement sand mortar.
Block Walling
walling in cement sand mortar (1:3) including and
reinforced with 20 SWG hoop iron in every two
alternating course.
200mm thick smooth approved concrete blocks
M including making horizontal keys on external wall SM 69 80,000 5,520,000
surface.

8,733,000
ITEM UNIT
DESCRIPTION UNIT QTY AMOUNT
NO. RATE

Sawn formwork to;


A Vertical sides of ring beam SM 50 25,000 1,250,000
B Ditto but soffit SM 4 25,000 90,000
C Ditto but soffit of roof slab SM 23 25,000 575,000
D Sides of roof slab 100-150mm high LM 20 3,750 75,000
Vibrated reinforced concrete class
20/20 (1:2:4/25) as described in:
D Columns CM 1 600,000 600,000
E Ring beam CM 2 600,000 1,200,000
F 150mm thick roof slab SM 23 90,000 2,070,000

Steel reinforcement bars including cutting, bending,


spacer blocks, tying wires and fixing. High tensile
bars to BS 4461: 8mm to 12mm bars to:

G Y8 KG 68 5,500 374,000
H Y 10 KG 86 5,500 473,000
I Y 12 KG 200 5,500 1,100,000

Finishes
Internal Finishes ( Walling)

13mm thick cement sand plaster (1:4) to walling


J SM 99 13,000 1,287,000
mixed with lime smooth finish to receive paint

13mm cement sand mortar(1:4) on the gable surface


K SM 57 15,000 855,000
externally.
Prepare and apply three coats of 1st silk vily matt
L SM 156 12,500 1,950,000
on wall plastered surfaces
Flooring
20mm thick cement sand (1:3) screed for floor to
M SM 18 13,000 234,000
receive terrazzo

N 30mm thick well polished terrazzo floor finish SM 18 100,000 1,800,000

13,933,000
COLLECTION
Page 1 17,248,100

Page 2 8,733,000

Page 3 13,933,000

39,914,100
ITEM UNIT
DESCRIPTION UNIT QTY AMOUNT
NO. RATE

GUARD HOUSE
SUBSTRUCTURES
Excavation

Site excavate to reduce levels commencing from existing


A SM 20 1,500 30,000
ground level;150mm deep and Not exceeding 1.5m deep;

Excavate for strip foundation trench, commencing


B CM 8 1,500 11,340
reduced level; Not exceeding 1.5m deep

Return, fill and ram approved imported and selected


C CM 10 4,000 40,000
material around foundations.
Load cart away surplus excavated materials and dispose in
D CM 13 5,000 65,000
areas designated by council
Mass concrete mix (1:4:8) in
E 50mm thick blinding under strip foundations SM 8 450,000 3,780,000

Vibrated reinforced insitu concrete class 20/20; with mini


mum cube crushing strength of 20N/mm2 at 28 days; in

F 150mm thick ground floor slab CM 1 600,000 810,000


G Strip foundations CM 2 600,000 1,008,000
Mesh fabric reinforcement
Mesh reinforcement NO. A142 size 200 x 200mm
I weighing 2.22 kg per square meter; in floor slab; including SM 9 13,000 117,000
all necessary supports
Sawn formwork to:
J Edges: slabs 75 - 150mm girth LM 13 3,750 48,750
K Vertical sides; strip footing; 200mm high SM 6 25,000 140,000
Plinth Walls

200mm thick foundation walls; bedded and jointed in


L cement and sand (1:4) mortar; reinforced with 20SWG SM 8 55,000 462,000
Hoop Iron in every alternate course

Hardcore

300mm thick hardcore of approved inert material; well


M SM 7 18,000 126,000
compacted in 150mm thick (maximum) layers

6,638,090
ITEM UNIT
DESCRIPTION UNIT QTY AMOUNT
NO. RATE

Blinding
50mm thick approved quality murram blinding to surfaces
A SM 7 3,000 21,000
of hardcore
Anti-termite treatment

Approved anti-termite chemical treatment; applied by


approved professional pest control specialist; applied
B SM 41 1,000 40,600
strictly in accordance with the manufacturers' instructions;
ten(10) year guarantee

DPM
C Guage 1000 polythene damp proof membrane SM 7 2,000 14,000
25mm thick cement/sand (1:4) rendering; on concrete or
stonework; wood float finished to
D Plinths ; externally SM 6 15,000 84,000

Prepare surfaces and apply undercoat and two finishing


coats black bitumastic or other equal approved water
resistant paint on rendered surfaces to:

E Plinths: externally SM 6 30,000 180,000


R.C SUPERSTRUCTURE
Sawn formwork to
F Sides and soffits beams SM 28 25,000 700,000
G Bench slab SM 2 25,000 52,500
Supply and fix square twisted steel bars in structural concrete w
ork including cutting, bending, hoisting, tie wire, spacer blocks
and supporting all in position
H 8mm bars kg 25 5,500 137,500
I 12mm bars kg 45 5,500 247,500
Vibrated reinforced insitu concrete class 20/20; with minimum
cube crushing strength of 20N/mm2 at 28 days; in

J Ring beam CM 1 600,000 336,000


K Bench slab CM 1 600,000 600,000
WALLS

Walling bedded in cement/sand mortar (1:4) reinforced with


20SWG Hoop Iron in every alternate course

L 200mm thick walls SM 38 80,000 3,012,000


Bituminous felt or other equal approved damp proof course; in
cement/sand (1:3) mortar
M 200mm wide SM 4 2,000 7,000

5,432,100
ITEM UNIT
DESCRIPTION UNIT QTY AMOUNT
NO. RATE
ROOF
SAWN PRESSURE IMPREGNATED CYPRESS GRADE
S50
A 100 x 75mm Wall Plate secured to concrete beam at 1200mm
centres with and including 6mm diameter mild steel round bar
one side cast in beam (m.s) other fixed to wall plate with tack LM 12 6,500 78,000
nails.
B 150x 50mm Tie Beam LM 10 9,000 90,000
C 150x 50mm Rafters LM 15 9,000 135,000
F 100 x 50mm Strurts and Ties LM 25 6,500 162,500
G 100 x 50mm purlins LM 35 6,500 228,800
H 200 x 50mm Ridge board. LM 5 12,500 62,500
ROOF COVERING
I Guage 26 versatile iron sheets roof covering fixed to timber
purlins (measured separately) at 900mm centres with and
including roofing nails complete with rubber washers. SM 15 45,000 675,000

J Ridge capping ditto. LM 4.5 5,000 22,500


WROT HARDWOOD, selected, treated and kept clean

L 225mm x 25mm wrought cypress fascia board nailed to


LM 10 12,500 125,000
rafters.
Prepare surfaces; apply three coats first grade oss paint to
approval; on timber surfaces to
M 200mm girth; on fascia board SM 3 4,000 12,000
OPENINGS
Windows

Mild steel casement windows; fixed panes; custom made;


sections to drawings and with approved ironmongery; sections
divided with 25 x25 x 3mm thick RHS welded onto main frame
40 x 25 x 3mm RHS;

N Ditto but 1000 x 1200mm high NO 1 450,000 450,000


Window Cill
Supply and fix clay window cills; bedded and jointed in
O cement/sand (1:3) mortar; pointed in matching coloured LM 1 18,000 21,600
cement to windows
DOORS
Mild steel door size 750 x 2100 mm complete with all iron
P NO 2 700,000 1,400,000
mongery as per drawing
Iron mongery
Supply and fix "Assa Abloy" or equal approved iron
mongery; matching screws; locks to include a set of 3
keys; available from their authorised local dealers to
approval
3,462,900
ITEM UNIT
DESCRIPTION UNIT QTY AMOUNT
NO. RATE

A 100mm mild steel butt hinges Pairs 3 15,000 45,000


B 3 lever steel casement rebated door lock with handles NO 2 70,000 140,000

Prepare surfaces, three coats gloss oil paint to metal surfac


es
C Doors internally and Externally SM 6 15,000 94,500
FINISHES
FLOOR FINISHES
Screed; cement/sand (1:3) on concrete
D 30mm thick to receive floor tiles SM 7 15,000 105,000

Supply and fix coloured ceramic floor tiles on screed; joint


s pointed in matching cement grout to approval

E 300 x300 x 10mm thick tiles SM 7 70,000 490,000


WALLING
Backing: 10mm cement/sand (1:4); on masonry or concret
e ; wood float finished to
F Walls to receive ceramic tiles SM 8 13,000 97,500

Supply and fix coloured glazed ceramic wall tiles; on backi


ng; joints pointed in matching cement grout

G 300 x 300 x 10mm thick tiles SM 8 40,000 320,000


H Supply and fix matching pvc tile strip to tile edges LM 5 8,000 40,000

Plaster; 13mm cement/lime putty/sand; wood float; on m


asonry and concrete to
I Walls and concrete surfaces; externally SM 76 15,000 1,140,000

Prepare surfaces; apply three coats First grade vinyl emulsi


on
paint or other equal approved; on wood float plaster to:

J Walls and concrete surfaces SM 76 12,000 912,000


WATER SUPPLY
GENERAL WORKS

Connect piped water using 1''G.I.class B pipe to the


substation by liaising with the relevant water body;
K ITEM 1 500,000 500,000
including excavation of water pipe water trench,
backfilling, all connections and accessories.

Supply and install 600 litres an approved plastic water


tank, approved 3/4'' water tap and concrete
L ITEM 1 800,000 800,000
platform including all necessary required fittings and
connections
4,684,000
ITEM UNIT
DESCRIPTION UNIT QTY AMOUNT
NO. RATE
INTERNAL WATER SUPPLY AND DISTRIBUTION

All Water piping shall be PPR pipe PN20. Complete with


Tees, Sockets, Elbows, Threaded adapters,Threaded
elbows,Reducers and all associated fittings.

PPR Pipes PN20


A 20mm LM 7 20,000 140,000
B 25mm LM 4 25,000 100,000
Isolating Valves
C 20mm NO 3 60,000 180,000
D 25mm NO 4 72,000 288,000
E 15mm(1/2") flexible tubing 450mm long NO 1 30,000 30,000

INTERNAL DRAINAGE
Supply and Install the following including clamps/
brackets for supporting pipes, builders works which
involves making good to any openings made in floor slabs
and chiselling of walls

uPVC Pipes PN6


F 50mm Complete with Tees, Bends, Reducers, Access
plugs, necessary fittings and accessories. LM 6 25,000 150,000
G 110mm Complete with Tees, Bends, Reducers, Access
plugs, necessary fittings and accessories. LM 10 35,000 350,000
H 110 x 50mm PVC Floor trap NO 1 65,000 65,000
I Stainless steel grating 150x 150 NO 1 120,000 120,000
J 110mm Straight WC connector NO 1 65,000 65,000
SANITARY FITTINGS
Supply and install the following sanitary fittings including
all necessary fittings and accessories
WC Suite
K Squating Pan as Hindware in vitreous china, in white
colour, P&S-trap, with vertical outlet and fixing kit,outlet
connector, Cistern complete with 6 Litre flushing fittings NO 1 850,000 850,000
with pull handle all to the engineers satisfaction,

Shower Head/Arm
L Traditional fixed Shower head as Vado westbury WG-
16204-C/P rigid riser with 6" (150mm) shower head and
arm, hand shower and diverter chrome finish,1/2" x NO 1 150,000 150,000
10mm threaded inlet.
M Concealed 1/2" FxF Stop Cock with Tricorn handle as
PEX-760 NO 1 65,000 65,000
2,553,000
ITEM UNIT
DESCRIPTION UNIT QTY AMOUNT
NO. RATE

A Lever Arm Bib Tap chrome plated 1/2" as PEX 708-1/2.


NO 1 55,000 55,000
Wash Hand Basin
B Wash hand fixed on wall as Ideal standard Rugiada
complete with one center tap hole,white colour, 32mm
chrome plated bottle trap, complete with 1/2" basin pillar NO 1 650,000 650,000
tap as Vado Astra AST-106-CP with contract handle.

Wall Mirrors
C Wall mirrors 600 x 400mm with bevelled edges polished
with chrome plated dome shaped screws NO 1 195,000 195,000
D Toilet roll holder as Vado Eclipse ECL-180-C/P NO 1 75,000 75,000
E Towel Rail as Vado Eclipse 24"(600mm) ECL -184-C/P
NO 1 65,000 65,000
GENERAL WORKS

Connect piped water using 1''G.I.class B pipe to the


substation by liaising with the relevant water body;
F ITEM 1 500,000 500,000
including excavation of water pipe water trench,
backfilling, all connections and accessories.

Supply and install 600 litres an approved plastic water


tank, approved 3/4'' water tap and concrete
G ITEM 1 800,000 800,000
platform including all necessary required fittings and
connections

2,340,000

Collection

Page 1 6,638,090

Page 2 5,432,100

Page 3 3,462,900

Page 4 4,684,000

Page 5 2,553,000

Page 6 2,340,000

25,110,090
ITEM UNIT
DESCRIPTION UNIT QTY AMOUNT
NO. RATE

External Works
Vibrated reinforced concrete class 20/20 (1:2:4/20)
in;
A concrete ramps at the doors SM 2 105,000 210,000
Mild steel bar to BS 4449;
Double BRC mesh reference No. A142 weighing
2.22kg per square metre including 150mm
B SM 2 13,000 26,000
minimum end and side lap, bends, tying wires and
spacer blocks

Pallisade Fencing

Aluminium Pallisade fence consisting of 50x5mm


Rolled Trident Pale 50x40x2.5, 3.0mm Angle Iron
Crossbar 100x10x1.5 Square Tube Post, 3mm Post
C LM 60 800,000 48,000,000
Bracket, M8 Anti-vandal nut & round headed bolt,
M8 Anti-vandal nut & round headed bolt, 17 pales
@ 165 centres, 115mm gap between pales

Vibrated reinforced concrete class


20/20 (1:2:4/25) as described in:
D Foundation pads size 900x450x450 CM 5 600,000 2,952,450
Razor Wire

Supply and fix Razor Wire at the top of boundary wall


conforming to the following specifications.
Coil size-450mm diameter, Blade profile-ripper
razor wire, Stretch factor-maximum of 10m per coil
E LM 60 300,000 18,000,000
and secured to wall with galvanised steel
25x25x4mm square tube bar 600mm long anchored

69,188,450
ITEM UNIT
DESCRIPTION UNIT QTY AMOUNT
NO. RATE

ELECTRICAL INSTALLATIONS WORKS

Allow for supply and installation of electrical


installations to be as per electrical drawing to
comprise the following;

Supply and Installation of an outdoor Security


NO 1 1,200,000 1,200,000
Light

Supply and Installation of a bunker Meter Box NO 1 100,000 100,000

Supply and Installation of interior florescent tubes,


NO 6 150,000 900,000
lights and switch
Supply, installation, commissioning of Generator
10kVA plus exhaust pipe extension outside the NO 1 15,000,000 15,000,000
bunker
Supply, installation and commissioning of 48V
NO 1 2,000,000 2,000,000
600Ah deep cycle battery bank system
Supply, installation and commissioning of
NO 1 800,000 800,000
Distribution board
Supply and installation of Electrical
interconnections and Automatic Voltage Regulator NO 1 500,000 500,000
(AVR)
Design, supply and installation of medium voltage
powerline 11kv to the nearest UMEME facility (100
LM 100 15,000 1,500,000
metres) with all accessories terminating in the meter
Box.
Supply and Installation of Automatic Transfer
NO 1 1,300,000 1,300,000
Switch, ATS.
Bunker and equipment Earthing should be
separated from the mast Earthing measuring < 4 LM 50 8,000 400,000
Ohms
Supply and onstallation of of the complete site
LM 150 15,000 2,250,000
ducting (100m and 50mm PVC pipes.)
3 CABLE TRENCH
Trench (600x600mm deep) length approx.4metres at
various
Excavate for trench from reduced level not
F CM 1 7,000 10,080
exceeding 1.5 metres deep and cart away
Fill in and ram selected excavated materials around
G CM 1 5,000 5,000
trench walls

5,465,080
ITEM UNIT
DESCRIPTION UNIT QTY AMOUNT
NO. RATE
3.1 Trench bed
50mm plain concrete(1:4:8) blinding on cable
H SM 0.5 450,000 225,000
trench
Vibrated reinforced concrete class 20/20 1:2:4 as de
scribed in;
I 150mm thick trench base CM 0.5 450,000 225,000
J 150mm thick trench walls with fair face finish CM 0.5 450,000 225,000

Supply and lay 100mm diameter medium gauge


K LM 8 -
PVC ducts
L Ditto but bends N0 2 -
Smooth formwork to
M Sides of trench wall SM 25,000 -
Steel reinforcement bars including tying bending
spacer blocks tying wires and fixing high tensile
bars to BS 4461 -
N Y8 mm at 150 centres in cable trench KG 5,500 -
Polymer Resin covers to trench covers
Supply and fix approx. precast concrete covers size
O NO 10 -
600x600mm
Cable trays

Supply and fix heavy duty galvanized steel


P perforated cable trays, 400mm wide, firmly fixed LM 15 75,000 1,125,000
from below and raised 200mm above trench bed.

1,800,000

Collection

Page 1 5,465,080

Page 2 1,800,000

7,265,080
SUMMARY PAGE

PRELIMINARIES 4,400,000

CONTROL ROOM 39,914,100

GUARD ROOM 25,110,090

EXTERNAL WORKS 69,188,450

ELECTRICALS 7,265,080

TOTAL PROJECT COST 145,877,720