Capital Improvements
Plan Update
2 0 1 9 - 2 0 2 4
Memo
To: Mayor and Board of Commissioners
Attached for your review is the above referenced CIP. The plan identifies needs in the
amount of $324.2 million over the next five years with an estimated operating impact of
$36.6 million. Many of the projects identified will require funding through grants, bond
referendums, installment purchase agreements and general fund revenues.
For the upcoming fiscal year (2019 – 2020) the funding request is $22.6 million. As you look
specifically at the year one requests, you will notice that most of the Level A projects
continue to focus on maintenance of our current assets along with the Downtown
Streetscape improvements.
At your retreat on February 1, we discussed some of the projects within the CIP in the
context of a future bond referendum. If the Board approves moving forward with this
initiative, some of the projects may shift based on direction and prioritization.
As you begin to review this document, please remember needs over the next five years and
beyond are identified. After year one, it becomes more difficult to project cost estimates,
which is why we update the plan annually. Although the rankings are based on a
prioritization system, some have been adjusted based on management recommendations.
However, it is important to note the Board has final authority in the rankings of the projects.
Typically, we have funded approximately $3 million annually for our CIP program. The final
numbers for year one will be presented within the Town Manager’s proposed budget for
2019 – 2020.
Page 1 of 2
Staff will be present at your CIP work session on March 5 to provide a general overview of the
proposed year one projects, as well as answer any questions. I would like to express my
appreciation to Aileen Staples, Ben Blevins, Antwan Morrison and Department Directors for their
efforts in compiling this year’s CIP update. Please let me know if you have any questions. Thanks.
Page 2 of 2
TOWN OF WAKE FOREST
TABLE OF CONTENTS
Page
INTRODUCTION 1
Definition
Process
Function
Fiscal Policy Excerpt
Public Art Ordinance
Update
PRIORITIZATION SYSTEM 4
Prioritization Matrix
Criteria Categories
Level of Funding
DEFINITION: The Capital Improvements Plan (CIP) is a five year plan identifying the Town’s capital
improvement needs. As a long range plan, the CIP reflects the Town’s policy regarding long range physical
and economic development. By providing a planned schedule of public improvements, the CIP outlines
present and future public needs and priorities. A capital improvement is defined as any expenditure for
equipment, buildings, infrastructure, land acquisition, plan or project in which the cost exceeds $25,000
and the estimated useful life is greater than 1 year.
CAPITAL IMPROVEMENT PLAN PROCESS: Capital project planning is an ongoing process. Each
year the CIP document is updated. The need or idea for capital improvements can originate from the Mayor,
Board, Citizens, or Town staff. These items are compiled into this document and presented to the Board of
Commissioners on an annual basis. Through the annual planning retreat and work session(s), the Board
focuses on prioritizing the first year’s expenditures. Once the CIP is approved, it outlines the Town’s
official commitment to funding these expenditures in the upcoming budget. During the annual budget
process in the spring, the first year projects are refined and a financing plan is put into place within the
budget to fund those expenditures.
Assess Departments
Community Submit
Needs Requests
Plan Submitted to
Management
Town Board for
Reviews
Inclusion in
Request
Budget/Plan
Management
Meets with
Departments
FUNCTIONS OF THE CIP: A CIP must be updated each year. Adopting a CIP does not end with the
first year. Changing needs and priorities, emergencies, cost changes, mandates and changes in technology
all require the CIP to be updated annually. The Town’s public facilities, streets, parks, infrastructure,
equipment, etc., are constantly in need of repair, replacement or expansion. A growing population will
require additional or new facilities. These reasons require that the CIP be updated to maintain the financial
solidity of the Town. The Town of Wake Forest’s staff has updated the CIP each year since adopting the
first document in 1985. The CIP achieves the following objectives as a component of the Town’s budget
and financial planning process:
1|Page
• Reduces the need for “crash programs” to finance the construction of Town facilities
• Focuses attention on community goals, needs and capabilities
• Achieves optimum use of taxpayer dollars
• Guides future community growth and development
• Advance planning ensures that projects are well thought out in advance of construction
• Provides for the orderly replacement of capital items
• Encourages a more efficient governmental administration as well as maintains a sound and
stable financial program
• The Town will prioritize all capital improvements in accordance with an adopted Capital
Improvement Plan (CIP).
• The Town will develop a five-year plan for capital improvements and review capital
• improvements and review and update annually.
• The Town will coordinate development of the capital improvements program with
development of the operating budget.
• The Town will use intergovernmental assistance to finance only those capital
improvements that are consistent with the capital improvement plan and Town priorities.
• The Town will maintain all its assets at a level adequate to protect the Town’s capital
investment and to minimize future maintenance and replacement costs.
• The Town will identify the estimated costs and potential funding sources for each capital
project proposal before it is submitted for approval.
• The Town will attempt to determine the least costly and most flexible method for all new
projects.
• Additional information on the CIP will be highlighted within the Capital Improvements section
of the annual budget document.
PUBLIC ART ORDINANCE – OVERVIEW: The Town of Wake Forest recognizes the
importance of facilitating the creation and installation of art for public spaces that evokes social and
aesthetic interaction. It is intended that works of Public Art will enliven public space, promote community
identity and sense of place, and contribute to a vibrant and engaging Town. The goal for the Public Art
Program is a transparent and directed public process for commissioning and acquiring art for public
spaces that will contribute to the Town’s cultural and economic vitality. The allocation will be calculated
at one percent (1%) of the total eligible project cost. Eligible projects under this ordinance include
architectural and engineering fees, site work, direct construction costs and contingency allowances for a
Capital Project, but shall exclude land or building acquisitions, taxes, legal fees, insurance costs, costs of
compliance with regulatory requirements, and other costs unrelated to actual construction; and shall also
exclude the cost of subsequent changes to the project unless any single subsequent changes exceeds
fifteen (15%) percent of the initial budgeted cost of the Capital Project.
2|Page
MAINTENANCE OF TOWN ASSETS: Capital assets include major government facilities,
infrastructure, equipment and networks that enable the delivery of public sector services. The
performance and continued use of these capital assets is essential to the health, safety, economic
development and quality of life of those receiving services.
Budgetary pressures often impede capital program expenditures or investments for maintenance and
replacement, making it increasingly difficult to sustain the asset in a condition necessary to provide
expected service levels. Ultimately, deferring essential maintenance or asset replacement could reduce the
organizations ability to provide services and could threaten public health, safety and overall quality of life.
In addition, as the physical condition of the asset declines, deferring maintenance and/or replacement could
increase long-term costs and liabilities.
It is with this in mind that the town staff has implemented an “Asset Maintenance” section. This section
is used to present planned maintenance projects that bear significant financial implications, which will
allow management to better plan for the town’s future needs. The overall CIP document is used to
account for upcoming projects, expansion of those currently and major financial purchases. However, as
the town continues to sufficiently manage the operating costs the need to maintain our aging assets
remains.
VEHICLE REPLACEMENT: In addition to the other capital improvement projects included in the CIP
Update, there are other major types of vehicles and equipment which are a substantial financial investment
and need to be handled in the most economic manner. Therefore, the Town chooses to incorporate these
items into the CIP update. Vehicles and/or equipment are evaluated primarily based on age, mileage
operation & maintenance cost. There are, however, several additional factors which must be considered in
determining these replacements: fuel costs, condition, safety, life of equipment, etc.
THE CIP UPDATE: The document that follows is the update to the CIP and covers the (5) fiscal years
2019-20 through 2023-24. This document contains capital expenditure requests from
each department/division for items that cost over $25,000 and generally have a useful life of five (5)
years or more.
This section of the CIP includes a description of the prioritization system, a summary by funding level for
the fiscal year 2019-20 and a summary by department/division and fund for each of the five fiscal years.
The remainder of the document contains summary information for each department/division with the
supporting information on capital project request forms.
3|Page
PRIORITIZATION SYSTEM
PRIORITIZATION MATRIX: The priority system includes a matrix shown below. This system was developed
to assist in the setting of priorities for capital expenditures because not all requests can be funded in any given
year due to budgetary constraints.
Priority
High Medium Low
1 Level A
Criteria
2
Level B
Level C
4
The matrix contains a measure of priority on the horizontal axis and a determination of criteria category on
the vertical axis. Priorities of the capital projects are measured as high, medium or low as follows:
CRITERIA CATEGORIES:
I. Health/Safety/Welfare - projects that protect the health, safety and welfare of the community and
the employees serving it.
II. Maintenance/Replacement - projects that provide for the maintenance of existing systems and
equipment.
III. Expansion of Existing Programs - projects which enhance the existing systems and programs
allowing for expansion of existing services.
IV. Expansion of New Programs - projects that allow for expansion into new programs and services.
Beyond 2024
DIVISION DESCRIPTION PRIOR 2019-2020 2020-2021 2021-2022 2022-2023 2023-2024 TOTALS Memo Only
USES:
GENERAL FUND
General Government $ 2,875,100 $ 5,289,200 $ 1,173,500 $ 4,108,800 $ 4,060,400 $ 4,259,400 $ 21,766,400 $ 24,002,000
Information Technology 650,000 2,595,000 230,000 230,000 2,080,000 185,000 5,970,000 -
Public Facilities 200,000 280,200 4,948,300 676,200 160,000 50,000 6,314,700 38,806,900
Public Safety - - 390,000 600,000 875,000 - 1,865,000 -
Transportation 13,350,900 8,221,700 708,900 10,001,200 7,480,400 18,008,900 57,772,000 78,491,700
Parks and Recreation 175,000 552,500 542,500 869,000 565,000 475,000 3,179,000 33,285,500
Streets Division 80,000 150,000 365,000 400,000 100,000 100,000 1,195,000 260,000
Fleet Division - - - 155,000 90,000 - 245,000 -
Environmental Services 65,600 125,000 825,000 625,000 205,000 - 1,845,600 2,000,000
Asset Maintenance 3,457,930 945,000 1,382,000 2,768,800 3,569,500 2,730,200 14,853,430 8,126,400
Vehicle/Equipment Replacements - 2,109,500 1,422,500 1,380,500 1,354,500 1,070,000 7,337,000 4,504,800
20,854,530 20,268,100 11,987,700 21,814,500 20,539,800 26,878,500 122,343,130 189,477,300
ELECTRIC FUND
Electric/Tree Trimming $ 1,200,000 $ 1,600,000 $ 2,102,500 $ 1,465,000 $ 1,787,500 $ 1,400,000 $ 9,555,000 $ -
Vehicle/Equipment Replacements - 761,500 361,500 40,500 471,500 70,000 1,705,000 1,168,000
TOTAL USES $ 22,054,530 $ 22,629,600 $ 14,451,700 $ 23,320,000 $ 22,798,800 $ 28,348,500 $ 133,603,130 $ 190,645,300
SOURCES:
GENERAL FUND
Current G.O. Referendum - Issued 1,136,000 - - - - - 1,136,000 -
Current G.O. Referendum - Not Yet Issued 3,584,000 172,000 - - - - 3,756,000 -
Future G.O. Referendum - Estimated - FY 2020 1,796,600 1,622,700 1,428,100 7,563,900 2,758,650 1,120,700 16,290,650 21,798,860
Future G.O. Referendum - Estimated - FY 2024 - - - 1,217,000 2,198,900 10,434,350 13,850,250 36,456,550
Future Installment Purchase - Other 6,461,100 5,480,200 5,612,600 4,058,800 310,400 1,059,400 22,982,500 38,520,100
Future Installment Purchase - Vehicles/Equipment - 2,352,000 2,615,000 1,630,500 2,369,500 1,070,000 10,037,000 5,069,800
Grant Funds - Awarded 5,913,600 5,291,400 93,700 1,081,300 - - 12,380,000 -
Grant Funds - Future Application/Application Submitted - 684,700 150,600 2,771,200 4,657,050 7,534,150 15,797,700 59,604,790
Capital Reserve Funds 247,000 1,233,000 85,900 - 420,000 200,000 2,185,900 4,213,000
Downtown Municipal Service Districts - 125,000 - - - - 125,000 -
Pay As You Go - User Fees/Other Revenues/Reserves - - 20,900 - - - 20,900 -
Special Obligation Bonds - - - - 3,000,000 3,000,000 6,000,000 19,000,000
Other Available Sources (Timing & Amounts TBD) 1,716,230 3,257,100 1,930,900 3,441,800 4,825,300 2,459,900 17,631,230 4,814,200
ELECTRIC FUND
Vehicles/Equipment Installment Purchase 400,000 761,500 361,500 205,500 546,500 70,000 2,345,000 1,168,000
Pay As You Go - User Fees/Other Revenues/Reserves 800,000 1,650,000 2,152,500 1,350,000 1,712,500 1,400,000 9,065,000 -
TOTAL SOURCES $ 22,054,530 $ 22,629,600 $ 14,451,700 $ 23,320,000 $ 22,798,800 $ 28,348,500 $ 133,603,130 $ 190,645,300
5|Page
Reconcile 2014 G.O. Bond Referendum
Issued Unissued Total
CIP Update 2018 - Upcoming Projects $ 1,136,000 $ 3,756,000 $ 4,892,000
Active Projects:
Smith and Sanford Creek Greenway 1,581,000 - 1,581,000
Priority Pedestrian Corridors 325,000 480,000 805,000
Dunn Creek Downtown Connector 115,500 - 115,500
Dunn Creek Boardwalk Rehab - 200,000 200,000
Passive/Active 430,625 34,000 464,625
Burlington Mills Road Landscape 86,500 - 86,500
W Oak Avenue & Forestville Road Underpass 168,000 - 168,000
Forestville Road Underpass 67,000 - 67,000
Traffic Signals 90,000 - 90,000
Hedrick Property 301,775 - 301,775
Richland Creek Greenway 28,600 - 28,600
Ligon Mill Underpass - 250,000 250,000
Smith Creek Stream Bank Repair - 200,000 200,000
Joyner Park 11,100,000 - 11,100,000
Northern Wake Senior Center 3,100,000 - 3,100,000
Rogers Road 1,650,000 - 1,650,000
5|Page
Downtown
GO Bond Special Municipal
Electric Installment Installment GO Bond Current - GO Bond Grants - Grants Obligation Capital Futures Service Department
Function General Fund Revenues Purchase Vehicles Purchase Other Current-Issued Not Issued Future Awarded Application Bonds Reserve Fund District Other Total
General Government $ 336,300 $ - $ 40,000 $ 12,952,600 $ - $ - $ 800,000 $ 364,100 $ - $ 25,000,000 $ 4,913,000 $ - $ 125,000 $ 1,237,400 $ 45,768,400
Information Technology 2,900,000 - - 2,750,000 - - - - - - 320,000 - - - 5,970,000
Public Facilities 2,122,200 - 70,000 42,450,000 - - 479,400 - - - - - - - 45,121,600
Public Safety 750,000 - 1,115,000 - - - - - - - - - - - 1,865,000
GTP 2,641,600 - - 950,000 844,000 3,581,000 45,185,610 11,999,000 70,192,490 - 365,900 - - 504,100 136,263,700
PRCR 762,100 - 910,000 - - 175,000 32,817,400 - 1,000,000 - 800,000 - - - 36,464,500
Electric - 8,915,000 640,000 - - - - - - - - - - - 9,555,000
Environmental Services 440,600 - 405,000 - - - 3,000,000 - - - - - - - 3,845,600
Fleet Maintenance 245,000 - - - - - - - - - - - - - 245,000
Streets 580,000 150,000 725,000 - - - - - - - - - - - 1,455,000
Asset Maintenance 7,702,030 - - 2,400,000 292,000 - 6,113,900 16,900 4,210,000 - - - - 2,245,000 22,979,830
Vehicle Replacements - - 14,714,800 - - - - - - - - - - - 14,714,800
$ 18,479,830 $ 9,065,000 $ 18,619,800 $ 61,502,600 $ 1,136,000 $ 3,756,000 $ 88,396,310 $ 12,380,000 $ 75,402,490 $ 25,000,000 $ 6,398,900 $ - $ 125,000 $ 3,986,500 $ 324,248,430
Millions
Street and Sidewalk Improvements $80
Greenways $-
Current -…
Obligation…
Municipal…
Revenues
GO Bond
General Fund
Purchase Vehicles
Purchase Other
GO Bond
Grants - Awarded
Grants Application
Downtown
Futures
Other
Current-Issued
Reserve
Capital
Electric
Future
Fund
Special
Installment
Smith and Sanford Creek Greenway
GO Bond
Installment
1,581,000 -
Dunn Creek Greenway - Boardwalk Rehab
- 200,000
Dunn Creek Greenway - Greenway Connector
115,500 -
Passive/Active Greenways
430,625 34,000
Smith Creek Greenway Stream Repair
- 200,000
Richland Creek Greenway
28,600 -
Hedrick Property 301,775 -
$ 20,180,000 $ 4,920,000
1ST YEAR
PRIORITY CAPITAL EXTERNAL FISCALLY
PAGE DEPARTMENT/Division PROJECT DESCRIPTION TYPE COST FUNDING CONSTRAINED
LEVEL A
GG-2 General Government Downtown Streetscape Improvements H-2 $ 3,830,200 $ 3,830,200 $ -
GG-3 General Government Construction of Fire Station #6 and Apparatus H-1 1,200,000 1,200,000 -
PF-2 Public Facilities ADA Improvements for Compliance H-1 25,000 - 25,000
ES-1 Environmental Services North White Street Landfill H-1 125,000 - 125,000
AM-4 Asset Maintenance Town Hall H-2 100,000 - 100,000
7IPage
Capital Improvement Plan
FUNDING LEVEL SUMMARY
FISCAL YEAR 2019-2020
1ST YEAR
PRIORITY CAPITAL EXTERNAL FISCALLY
PAGE DEPARTMENT/Division PROJECT DESCRIPTION TYPE COST FUNDING CONSTRAINED
LEVEL C:
- - -
TOTAL LEVEL C - - -
*External funding represents ONLY amounts that have been secured or officially awarded to the Town (i.e. Grants Awarded
and Authorized Bond Funding). Projects with bond authorization funding will be presented until the debt is actually issued.
8IPage
FY 2019 – 2024 Capital Improvements Plan Update
An important factor to consider when developing a capital improvements plan is the financial impact that the
proposed projects will have on the Town’s operating budget. While some projects will have little to no
staffing or operating impact, others may bear significant additional annual costs. These costs include, but are
not limited to: debt service (principal and interest), additional staffing, fuel, maintenance and repair, utility
services, contract/service agreements and supplies. It is, however, important to keep in mind that while
some projects add to the cost of operations, there are projects which will provide a cost savings benefit to
the town (i.e. energy efficiency). In developing these projections town staff have taken both of these into
consideration.
FUNCTION 2019-2020 2020-2021 2021-2022 2022-2023 2023-2024 Total
General Government 988,500 1,365,750 1,663,500 2,001,500 2,250,250 8,269,500
Information Technology 697,750 698,000 698,250 698,000 698,000 3,490,000
Public Facilities 9,300 25,300 729,300 1,437,300 1,423,300 3,624,500
Public Safety 1,250 581,250 697,500 1,361,250 1,452,500 4,093,750
Greenway, Transportation and Pedestrian Access 153,000 568,000 1,458,000 2,388,000 2,638,000 7,205,000
Parks, Recreation and Cultural Resources - 208,750 387,500 440,000 358,750 1,395,000
Public Works 75,000 185,500 185,500 296,000 296,000 1,038,000
Electric 125,000 616,000 732,500 833,500 1,183,500 3,490,500
Streets - - 85,000 185,000 95,000 365,000
Asset Maintenance 500,000 577,500 837,500 925,000 835,000 3,675,000
-
$ 2,549,800 $ 4,826,050 $ 7,474,550 $ 10,565,550 $ 11,230,300 $ 36,646,250
Electric
0%
Public Works
Public Safety 2%
26%
General Government
7%
Information
Public Facilities Technology
7% 10%
The data above displays the projected additional cost of operations over the next five years related to the
current capital improvement submissions. The majority of the impact on operations is for the additional debt
service which is related to the current bond authorization, as well potential future bond referendums and
other debt issuance (i.e. installment purchase agreements).
9|Page
Town of Wake Forest
Debt Overview
As of: December 31, 2018
General Fund
Installment Purchase $ 11,277,819 Outstanding Debt by Type of Issue
General Obligation Bonds 29,117,000
Total Tax-Supported Debt 40,394,819
Installment
Electric Fund Notes
28%
Revenue Bonds 1,551,740 GO
Installment Purchase 549,807 Bonds
68%
Revenue
Total Debt Outstanding $42,496,365 Bonds
4%
8.00%
7.00%
6.00%
5.00%
4.00%
FY 2019 = $102,149,845
3.00%
2.00%
FY 2019 =
1.00% $39,081,189
0.00%
2014 2015* 2016* 2017* 2018* 2019 est*
10 | P a g e
Capital Improvement Plan
GENERAL GOVERNMENT SUMMARY - BY PROJECT
Note: Wake Forest Fire Department funding is determined by the Board of Commissioners, which explains reporting in General Government.
LEVEL B
PROJECT DESCRIPTION
The Ailey Young House is a designated historic landmark owned by the Town of Wake Forest. The building is in need
of stabilization and rehabilitation. The Senior Planner with the Wake Forest Historic Preservation Commission has
developed a Preservation Plan for the building which includes a phased approach to the stabilization and
rehabilitation. The total project is expected to take five to ten years. The product will be a rare African American
historic resource that provides the community with important historical information about Wake Forest's African
American Community from 1875 as well as the history of the locally significant Young family. Although the
department priority is low, staff asks to consider elevating the priority because over 30 % of the estimated
construction cost has been invested in stabilizing the structure in preparation for a roof. Failure to provide a roof will
ultimately cause damage to the work that has been done and loss of the investment made in the last 24 months.
JUSTIFICATION
The Ailey Young House is a historic landmark owned by the Town of Wake Forest. The house is significant
Insert Photo
architecturally as a rare extant example of African American Housing during the Reconstruction period. It is also
significant as the home of Ailey Young, who raised her children in the house including her eldest, Allen. Allen Young
would grow up to be the founder of the first school in Wake Forest for African American children. The Young school is
no longer extant. Allen's daughter, Ailey Mae went on to become the first African American woman Commissioner
for the Town of Wake Forest. This building is a testament to the legacy of the Young family. It has the potential to
educate present and future generations about African American life during reconstruction and the important work of
the Young family through the generations. Rehabilitating the house to the standards of the Joyner Park buildings
provides tangible evidence as to the era in Wake Forest history.
Prior to Future
CAPITAL COST BREAKDOWN July 2019 2019-20 2020-21 2021-22 2022-23 2023-24 Years
Construction $ 131,800 $ 110,000 $ - $ - $ - $ - $ -
Equipment 3,200 12,000 - - - - -
Planning & Engineering 23,000 12,000 - - - - -
Other 11,500 - - - - - -
Total Project Costs $ 169,500 $ 134,000 $ - $ - $ - $ - $ -
Prior to Future
FUNDING SOURCE(S) July 2019 2019-20 2020-21 2021-22 2022-23 2023-24 Years
General Fund $ 2,300 $ 134,000 $ - $ - $ - $ -
Historic Preservation Commission 24,600 - - - - - -
Grants - CLG Awarded 19,600 - - - - - -
Grants - NCDCR Awarded 100,000 - - - - - -
In Kind Donation* 2,700 - - - - - -
Donations** 20,300 - - - - -
Total Funding Sources $ 169,500 $ 134,000 $ - $ - $ - $ - $ -
GG - 1
Strategic Plan Goal 1 - Economic Development LEVEL A
TOWN OF WAKE FOREST
CAPITAL IMPROVEMENTS PROGRAM
CIP UPDATE FY 2019-2024
PROJECT DESCRIPTION
Project will include widened sidewalks, ADA accessability with ramps, tree pits and soil
amendments, street trees and furniture, and architectural pedestrian scaled lighting.
1) S. White Street, 2) E. Owen Avenue, 3) E. Jones Avenue, 4) Wait Avenue,
5) Brooks Street 6) N. White Street, 7) Front Street Intersection
JUSTIFICATION
Insert image
This project is one of the recommended projects in the Renaissance Plan for Downtown Wake
Forest (2016) and the Strategic Plan Update (2017-2022). This supports the shopping
environment in downtown Wake Forest and preserve small town character with wide and
accessible sidewalks to accommodate sidewalk cafes, strollers, disabled, and elderly patrons.
Improvements on these streets will continue the cohesive look of the Renaissance Area, as well
as serve to increase the economic vitality of these areas.
Prior to Future
CAPITAL COST BREAKDOWN July 2019 2019-20 2020-21 2021-22 2022-23 2023-24 Years
Planning & Engineering $ 685,000 $ - $ 758,800 $ - $ 218,400 $ - $ 187,200
Purchase 135,000 - 140,000 - 20,000 - 25,000
Construction 1,594,500 3,526,600 - 3,793,800 - 979,800 935,700
Contingency -- CEI 265,700 265,700 224,800 224,800 69,100 69,100 128,600
Other - PAC 1% 25,400 37,900 9,900 40,200 2,900 10,500 12,500
Total Project Costs $ 2,705,600 $ 3,830,200 $ 1,133,500 $ 4,058,800 $ 310,400 $ 1,059,400 $ 1,289,000
Prior to Future
FUNDING SOURCE(S) July 2019 2019-20 2020-21 2021-22 2022-23 2023-24 Years
GG - 2
Strategic Goal 2 - Safe and Connected Community LEVEL A
TOWN OF WAKE FOREST
CAPITAL IMPROVEMENTS PROGRAM
CIP UPDATE FY 2019-2024
PROJECT DESCRIPTION
Plans are to put a second staffed ladder company within the Town limits in FY 2020. Based on
growth trends in population and buildings, we will need to construct an additional station (#6)
and add a staffed Engine Company approximately FY 2024 -2026.
JUSTIFICATION
Based on a recent ISO classification, we have a need for additional ladder companies because of
the amount of tall buildings within the Town limits. The station that the ladder will be located is
already in place. We are evaluating growth trends and response times throughout the Town and
based on those trends it will be necessary to add an additional Station on the North/East or East
side of the Town. As part of our evaluation process we will be able to determine the best
location and timing of when the station will need to be constructed.
Prior to Future
CAPITAL COST BREAKDOWN July 2019 2019-20 2020-21 2021-22 2022-23 2023-24 Years
Planning & Engineering $ - $ - $ - $ - $ - $ - $ 200,000
Construction - - - - - - 2,900,000
Equipment - 1,200,000 - - - - 613,000
Total Project Costs $ - $ 1,200,000 $ - $ - $ - $ - $ 3,713,000
Prior to Future
FUNDING SOURCE(S) July 2019 2019-20 2020-21 2021-22 2022-23 2023-24 Years
Fire Impact Fees $ - $ 1,200,000 $ - $ - $ - $ - $ 3,713,000
Total Funding Sources $ - $ 1,200,000 $ - $ - $ - $ - $ 3,713,000
GG - 3
Strategic Goal 1 - Economic Development LEVEL B
TOWN OF WAKE FOREST
CAPITAL IMPROVEMENTS PROGRAM
CIP UPDATE FY 2019-2024
PROJECT DESCRIPTION
Close Wait Avenue between Brooks and Roosevelt to create a larger block for either parking or
redevelopment.
JUSTIFICATION
This project is identified in the Renaissance Plan Update (2016) as a " Top 10 in 5 Years" project. Insert image
The current street has very little traffic and is not advantageous to the downtown street
network. Closing of this portion of Wait Avenue would allow for a positive use of this area.
Prior to Future
CAPITAL COST BREAKDOWN July 2019 2019-20 2020-21 2021-22 2022-23 2023-2024 Years
Construction $ - $ 75,000 $ - $ - $ - $ - $ -
Total Project Costs $ - $ 75,000 $ - $ - $ - $ - $ -
Prior to Future
FUNDING SOURCE(S) July 2019 2019-20 2020-21 2021-22 2022-23 2023-2024 Years
DMSD $ - $ 75,000 $ - $ - $ - $ - $ -
Total Funding Sources $ - $ 75,000 $ - $ - $ - $ - $ -
GG - 4
Strategic Goal 1 - Economic Development LEVEL B
TOWN OF WAKE FOREST
CAPITAL IMPROVEMENTS PROGRAM
CIP UPDATE FY 2019-2024
PROJECT DESCRIPTION
Layer the downtown environment incrementally with additional furnishings, lighting and
landscaping.
JUSTIFICATION
This project is identified in the Renaissance Plan Update (2016) as a general downtown practice. Insert image
Benches, lighting, planters, and other furnishings make the area pedestrian friendly and assist in
attracting visitors which will increase the economic vitality of the Renaissance Area.
Prior to Future
CAPITAL COST BREAKDOWN July 2019 2019-20 2020-21 2021-22 2022-2023 2023-2024 Years
Purchase $ - $ 50,000 $ - $ - $ - $ - $ -
Total Project Costs $ - $ 50,000 $ - $ - $ - $ - $ -
Prior to Future
FUNDING SOURCE(S) July 2019 2019-20 2020-21 2021-22 2022-2023 2023-2024 Years
DMSD $ - $ 50,000 $ - $ - $ - $ - $ -
Total Funding Sources $ - $ 50,000 $ - $ - $ - $ - $ -
GG - 5
LEVEL B
TOWN OF WAKE FOREST
CAPITAL IMPROVEMENTS PROGRAM
CIP UPDATE FY 2019-2024
PROJECT DESCRIPTION
The Community Development Department has one vehicle currently. When the Town hired a
full-time Zoning Compliance Officer, the vehicle was assigned to that position.
JUSTIFICATION
With an increased need for Community Development staff to monitor projects in the field Insert image
(private and public) an additional vehicle is needed to be used primarily by Transportation
Planning and Development Services staff. The vehicle is expected to be regularly used by
Transportation Planning as they monitor LAPP Projects, attend meetings at NCDOT offices,
attend CAMPO meetings, and visit sites under construction.
Prior to Future
CAPITAL COST BREAKDOWN July 2019 2019-20 2020-21 2021-22 2022-23 2023-24 Years
Purchase $ - $ - $ 40,000 $ - $ - $ - $ -
Total Project Costs $ - $ - $ 40,000 $ - $ - $ - $ -
Prior to Future
FUNDING SOURCE(S) July 2019 2019-20 2020-21 2021-22 2022-23 2023-24 Years
Installment Purchase $ - $ - $ 40,000 $ - $ - $ - $ -
Total Funding Sources $ - $ - $ 40,000 $ - $ - $ - $ -
GG - 6
Strategic Plan Goal 1 - Economic Development LEVEL B
TOWN OF WAKE FOREST
CAPITAL IMPROVEMENTS PROGRAM
CIP UPDATE FY 2019-2024
PROJECT DESCRIPTION
Identify and implement an interactive civic space in Downtown Wake Forest that attracts families
through play and water.
JUSTIFICATION
This project is identified in the Renaissance Plan Update (2016) as one of the "Top 10 projects in 5 Insert image
Years". Attracting families to downtown with spaces designed for children will be key in Wake Forest's
continued evolution into a vibrant place and will increase the economic vitality of the Renaissance
Area.
Prior to Future
CAPITAL COST BREAKDOWN July 2019 2019-20 2020-21 2021-22 2022-23 2023-2024 Years
Planning & Engineering $ - $ - $ - $ 50,000 $ - $ - $ -
Construction - - - - 750,000 - -
Total Project Costs $ - $ - $ - $ 50,000 $ 750,000 $ - $ -
Prior to Future
FUNDING SOURCE(S) July 2019 2019-20 2020-21 2021-22 2022-23 2023-2024 Years
GO Bond - Future Referendum FY 2024 $ - $ - $ - $ 50,000 $ 750,000 $ - $ -
Total Funding Sources $ - $ - $ - $ 50,000 $ 750,000 $ - $ -
GG - 7
Strategic Goal 1 - Economic Development LEVEL B
TOWN OF WAKE FOREST
CAPITAL IMPROVEMENTS PROGRAM
CIP UPDATE FY 2019-2024
PROJECT DESCRIPTION
Identify funds for potential economic development opportunities as they arise.
JUSTIFICATION
One of the key goals in the town's strategic plan is to stimulate economic development. This
function transitioned to the Town from the Wake Forest Chamber of Commerce during fiscal No Image Available
year 2015-2016. A 501 c (3) has been formed to facilitate potential deals with property owners
to foster economic growth in Wake Forest. Over the next few years estimated amounts have
been projected to include land acquistion costs along with infrastructure improvements.
Prior to Future
CAPITAL COST BREAKDOWN July 2019 2019-20 2020-21 2021-22 2022-23 2023-24 Years
Other* $ - $ - $ - $ - $ 3,000,000 $ 3,000,000 $ 19,000,000
Total Project Costs $ - $ - $ - $ - $ 3,000,000 $ 3,000,000 $ 19,000,000
Prior to Future
FUNDING SOURCE(S) July 2019 2019-20 2020-21 2021-22 2022-23 2023-24 Years
Special Obligation Bonds $ - $ - $ - $ - $ 3,000,000 $ 3,000,000 $ 19,000,000
Total Funding Sources $ - $ - $ - $ - $ 3,000,000 $ 3,000,000 $ 19,000,000
GG - 8
LEVEL B
Strategic Goal 1 - Economic Development
TOWN OF WAKE FOREST
CAPITAL IMPROVEMENTS PROGRAM
CIP UPDATE FY 2019-2024
PROJECT DESCRIPTION
Continue downtown branding by adding the "Wake Forest Downtown" logo to the water tower
located at the corner of S. White Street and Holding Avenue. This would be completed in
conjunction with painting of the water tower by the City of Raleigh.
Prior to Future
CAPITAL COST BREAKDOWN July 2019 2019-20 2020-21 2021-22 2022-23 2023-24 Years
Planning & Engineering $ - $ - $ - $ - $ - $ 10,000 $ -
Construction - - - - - 190,000 -
Total Project Costs $ - $ - $ - $ - $ - $ 200,000 $ -
Prior to Future
FUNDING SOURCE(S) July 2019 2019-20 2020-21 2021-22 2022-23 2023-24 Years
General Fund $ - $ - $ - $ - $ - $ 200,000 $ -
Total Funding Sources $ - $ - $ - $ - $ - $ 200,000 $ -
GG - 9
Capital Improvement Plan
INFORMATION TECHNOLOGY SUMMARY - BY PROJECT
PROJECT DESCRIPTION
Interconnect Town sites with a fiber network infrastructure.
JUSTIFICATION
1. Increased demand for higher speed connectivity.
2. Increases efficiencies and reliability for Town run systems and processes.
3. Business Continuity: Fiber infrastructure can provide redundant connectivity for physical locations.
Insert image
4. Provide enhanced services to the community.
5. Enhanced security for Town sites.
6. Better position the Town for the digital age.
7. Increased opportunity for economic development.
8. Long term cost benefits compared to leasing or third party service provided solutions.
Prior to Future
CAPITAL COST BREAKDOWN July 2019 2019-20 2020-21 2021-22 2022-23 2023-24 Years
Planning & Engineering $ 650,000 $ 110,000 $ 115,000 $ 115,000 $ 115,000 $ 115,000 $ -
Construction - 2,100,000 - - - - -
Contingency - - - - - - -
Other - - - - - - -
Total Project Costs $ 650,000 $ 2,210,000 $ 115,000 $ 115,000 $ 115,000 $ 115,000 $ -
Prior to Future
FUNDING SOURCE(S) July 2019 2019-20 2020-21 2021-22 2022-23 2023-24 Years
General Fund $ - $ 110,000 $ 115,000 $ 115,000 $ 115,000 $ 115,000 $ -
Installment Purchase Agreement 650,000 2,100,000 - - - - -
Total Funding Sources $ 650,000 $ 2,210,000 $ 115,000 $ 115,000 $ 115,000 $ 115,000 $ -
IT - 1
Strategic Goal 2 - Safe and Connected Community LEVEL B
Strategic Goal 3 - Organizational Culture that Embraces/Reflects Our Core Values
Strategic Goal 4 - Fiscal Strength
TOWN OF WAKE FOREST
CAPITAL IMPROVEMENTS PROGRAM
CIP UPDATE FY 2019-2024
DEPARTMENT PROJECT MANAGER DEPARTMENTAL PRIORITY
Information Technology Tom LaBarge Medium
PROJECT DESCRIPTION
1) Upgrades - purchase enhanced software modules as released to coincide with fully integrated
software system. FY 19-20 - $75,000; FY 20-21 - $75,000; FY 21-22 - $75,000; FY 23-24 - $25,000.
2) Integrated Enterprise Software - procurement of new fully integrated enterprise software.
FY 22-23 - $1,570,000.
3) Allow for software upgrades and license fees for new officers.
FY 19-20 - $35,000; FY 20-21 - $40,000; FY 21-22 - $40,000; FY 22-23 - $45,000; FY 23-24 - $45,000.
4) Refresh existing Communications 911 System, OSSI System Hardware and Finger Print System.
FY 22-23 - $400,000.
JUSTIFICATION
1) Periodically New World Systems releases enhancements and new modules. Staff would like to be able
to purchase these as they become available to further advance our efficiency.
2) Per Town standards, software maintains a useful life of ten (10) years. The Town went live with our Insert image
current software application in FY 2008. This integration facilitates sufficient fiscal oversight, monitoring
and built-in audit controls.
3) As software improves and new features are added, the new features could enhance and improve our
current system. New Licenses will need to be purchased as employees are added.
4) Communication Center 911 Systems Refresh: A) 5 year life cycle replacement of OSSI system, audio
recording system and finger print system; B) Business Continuity: As equipment ages, reliability, stability
and performance will become and issue; C) As hardware failure would have an immediate impact on the
employee productivity and public safety; D) Upgrade of hardware and operating system will add new
features and increase performance over current system.
Prior to Future
CAPITAL COST BREAKDOWN July 2019 2019-20 2020-21 2021-22 2022-23 2023-24 Years
Purchase $ - $ 110,000 $ 115,000 $ 115,000 $ 1,545,000 $ 70,000 $ -
Equipment - - - - 420,000 - -
Total Project Costs $ - $ 110,000 $ 115,000 $ 115,000 $ 1,965,000 $ 70,000 $ -
Prior to Future
FUNDING SOURCE(S) July 2019 2019-20 2020-21 2021-22 2022-23 2023-24 Years
General Fund $ - $ 110,000 $ 115,000 $ 115,000 $ 1,645,000 $ 70,000 $ -
Capital Reserve - - - - 320,000 - -
Total Funding Sources $ - $ 110,000 $ 115,000 $ 115,000 $ 1,965,000 $ 70,000 $ -
IT - 2
Strategic Goal 2 - Safe Connected Community LEVEL B
Strategic Goal 4 - Fiscal Strength TOWN OF WAKE FOREST
CAPITAL IMPROVEMENTS PROGRAM
CIP UPDATE FY 2019-2024
PROJECT DESCRIPTION
Implementation of a virtualized Hyper-Converged Infrastructure (HCI).
JUSTIFICATION
1. Continued consolidation of stand-alone virtualized servers.
2. Maximizes server hardware resources. Insert image
3. Centralized management of host and guest operating systems.
4. Allows for hardware and software maintenance without interruption to services.
5. Lower cost of ownership.
Prior to Future
CAPITAL COST BREAKDOWN July 2019 2019-20 2020-21 2021-22 2022-23 2023-24 Years
Purchase $ - $ 275,000 $ - $ - $ - $ - $ -
Other - - - - - - -
Total Project Costs $ - $ 275,000 $ - $ - $ - $ - $ -
Prior to Future
FUNDING SOURCE(S) July 2019 2019-20 2020-21 2021-22 2022-23 2023-24 Years
General Fund $ - $ 275,000 $ - $ - $ - $ - $ -
- - - - - - -
Total Funding Sources $ - $ 275,000 $ - $ - $ - $ - $ -
IT - 3
Capital Improvement Plan
PUBLIC FACILITIES SUMMARY - BY PROJECT
PROJECT DESCRIPTION
Renovation/Upgrade - PW Operations Center
JUSTIFICATION
The town completed a feasibility study for the Operations Center expansion/relocation a few
years ago. In 2018, the town purchased 5031 Unicon Drive to relocate the Electric Division, Insert image
which includes 26 staff, vehicles and equipment along with essential inventory items. This
transition will be complete by Spring 2019. Reqest includes funding for renovating existing
facility to accomodate growth in Public Works staff (Streets, Engineering, Environmental
Services and PWA).
Prior to Future
CAPITAL COST BREAKDOWN July 2019 2019-20 2020-21 2021-22 2022-23 2023-24 Years
Planning & Engineering $ 200,000 $ 25,000 $ 35,000 $ - $ - $ - $ 200,000
Purchase - - - - - - -
Construction - 150,000 - 400,000 100,000 - 15,000,000
Total Project Costs $ 200,000 $ 175,000 $ 35,000 $ 400,000 $ 100,000 $ - $ 15,200,000
Prior to Future
FUNDING SOURCE(S) July 2019 2019-20 2020-21 2021-22 2022-23 2023-24 Years
General Fund $ 200,000 $ 175,000 $ 35,000 $ 400,000 $ 100,000 $ - $ -
Installment Purchase - - - - - - 15,200,000
Total Funding Sources $ 200,000 $ 175,000 $ 35,000 $ 400,000 $ 100,000 $ - $ 15,200,000
PF - 1
LEVEL A
TOWN OF WAKE FOREST
CAPITAL IMPROVEMENTS PROGRAM
CIP UPDATE FY 2019-2024
PROJECT DESCRIPTION
ADA Compliance
JUSTIFICATION
Title II of the 2010 Standards require local governments to have accessibility in all programs,
media, and facility access. The Transition Plan has been completed for Parks and Recreation. Insert image
Public Rights of Ways and remainder of buildings will be added to the CIP in FY 2020-2021. The
dollar amounts, excluding $150,000 of Future Years funds are for the items currently included in
the Transition Plan.
Prior to Future
CAPITAL COST BREAKDOWN July 2019 2019-20 2020-21 2021-22 2022-23 2023-24 Years
Construction $ - $ 25,000 $ 50,000 $ 50,000 $ 60,000 $ 50,000 $ 150,000
Contingency - - - - - - -
Other - - - - - - -
Total Project Costs $ - $ 25,000 $ 50,000 $ 50,000 $ 60,000 $ 50,000 $ 150,000
Prior to Future
FUNDING SOURCE(S) July 2019 2019-20 2020-21 2021-22 2022-23 2023-24 Years
General Fund $ - $ 25,000 $ 50,000 $ 50,000 $ 60,000 $ 50,000 $ 150,000
Total Funding Sources $ - $ 25,000 $ 50,000 $ 50,000 $ 60,000 $ 50,000 $ 150,000
PF - 2
LEVEL B
TOWN OF WAKE FOREST
CAPITAL IMPROVEMENTS PROGRAM
CIP UPDATE FY 2019-2024
PROJECT DESCRIPTION
Purchase SUV (FY 2020) and a Service Truck (FY 2021)
JUSTIFICATION
This request is to add a vehicle for the Public Facilities Director. He is currently using a truck
that was replaced by the Police Department. An SUV would allow the department to travel as a
group as needed. In addition, this would allow plans to be transported to construction sites,
remain dry and without damage. A basic set of tools would also remain in the vehicle for use by
the manager. These tools would be used to make repairs when remaining staff are working on Insert image
other assignments.
In order for the department to keep up with the growth and demand of the town, the director
anticipates making a request for an additional staff member in FY 2020. If approved, a service
truck will be needed. An additional position is being requested to focus on the Downtown
Municipal Service District. The existing pickup will suffice for expected duties.
Prior to Future
CAPITAL COST BREAKDOWN July 2019 2019-20 2020-21 2021-22 2022-23 2023-24 Years
Purchase $ - $ 30,000 $ 40,000 $ - $ - $ - $ -
Other - - - - - - -
Total Project Costs $ - $ 30,000 $ 40,000 $ - $ - $ - $ -
Prior to Future
FUNDING SOURCE(S) July 2019 2019-20 2020-21 2021-22 2022-23 2023-24 Years
Installment Purchase $ - $ 30,000 $ 40,000 $ - $ - $ - $ -
- - - - - - -
Total Funding Sources $ - $ 30,000 $ 40,000 $ - $ - $ - $ -
PF - 3
LEVEL B
TOWN OF WAKE FOREST
CAPITAL IMPROVEMENTS PROGRAM
CIP UPDATE FY 2019-2024
PROJECT DESCRIPTION
Construct approximately 900 square feet to the north end of the police department to be used
as an evidence room.
JUSTIFICATION
Due to regulation changes and the need to keep evidence longer the department is out growing Insert image
the current evidence room.
Prior to Future
CAPITAL COST BREAKDOWN July 2019 2019-20 2020-21 2021-22 2022-23 2023-24 Years
Planning & Engineering $ - $ 15,000 $ - $ - $ - $ - $ -
Construction - - 250,000 - - - -
Equipment - - 25,000 - - - -
Contingency - - 20,000 - - - -
Other - 200 3,000 - - - -
Total Project Costs $ - $ 15,200 $ 298,000 $ - $ - $ - $ -
Prior to Future
FUNDING SOURCE(S) July 2019 2019-20 2020-21 2021-22 2022-23 2023-24 Years
General Fund $ - $ 15,200 $ 298,000 $ - $ - $ - $ -
Total Funding Sources $ - $ 15,200 $ 298,000 $ - $ - $ - $ -
PF - 4
LEVEL B
TOWN OF WAKE FOREST
CAPITAL IMPROVEMENTS PROGRAM
CIP UPDATE FY 2019-2024
PURPOSE
Install a generator at the Public Facilities Building for events that require staff to stay overnight
and there is a chance of loosing power.
JUSTIFICATION
When the Facilities building was renovated a full kitchen, shower, locker room, conference Insert image
room, and air mattress was put in place for emergencies that require employees to stay
overnight. The building has room for facilities staff as well as others to stay if needed and has
been used by the Electric Department as well as Parks and Recreation Maintenance Staff but if
power is lost the building is useless in emergencies. During the last hurricane event a temporary
generator was brought in on the day prior to the storm arriving.
Prior to Future
CAPITAL COST BREAKDOWN July 2019 2019-20 2020-21 2021-22 2022-23 2023-24 Years
Equipment $ - $ 35,000 $ - $ - $ - $ - $ -
Contingency - - - - - - -
Other - - - - - - -
Total Project Costs $ - $ 35,000 $ - $ - $ - $ - $ -
Prior to Future
FUNDING SOURCE(S) July 2019 2019-20 2020-21 2021-22 2022-23 2023-24 Years
General Fund $ - $ 35,000 $ - $ - $ - $ - $ -
Total Funding Sources $ - $ 35,000 $ - $ - $ - $ - $ -
PF - 5
LEVEL B
TOWN OF WAKE FOREST
CAPITAL IMPROVEMENTS PROGRAM
CIP UPDATE FY 2019-2024
PROJECT DESCRIPTION
Design and construct approximately 1,000 square feet of office space for future staffing needs
at Flaherty Community Center.
JUSTIFICATION
Parks and Recreation plans to convert two part time positions to one full time. This would be Insert image
used as an office for that employee. The center currently has one reception and office
combination.
Prior to Future
CAPITAL COST BREAKDOWN July 2019 2019-20 2020-21 2021-22 2022-23 2023-24 Years
Planning & Engineering $ - $ - $ 25,000 $ - $ - $ - $ -
Construction - - - 200,000 - - -
Equipment - - - 4,000 - - -
Contingency - - - 20,000 - - -
Other - - 300 2,200 - - -
Total Project Costs $ - $ - $ 25,300 $ 226,200 $ - $ - $ -
Prior to Future
FUNDING SOURCE(S) July 2019 2019-20 2020-21 2021-22 2022-23 2023-24 Years
General Fund $ - $ - $ 25,300 $ 226,200 $ - $ - $ -
Total Funding Sources $ - $ - $ 25,300 $ 226,200 $ - $ - $ -
PF - 6
LEVEL B
TOWN OF WAKE FOREST
CAPITAL IMPROVEMENTS PROGRAM
CIP UPDATE FY 2019-2024
PROJECT DESCRIPTION
New police station including design, engineering, and construction.
JUSTIFICATION
The town contracted with an architectural firm to do a space analysis of a new police station.
This was done in conjunction with a master plan to accommodate the needs of perspective Insert image
departments that would be housed on town hall campus. The project will include preliminary
plans, construction documents, technology, furniture, and contingency funds. Tarlton Park
could be purchased and extend the need to build the new station to later.
Prior to Future
CAPITAL COST BREAKDOWN July 2019 2019-20 2020-21 2021-22 2022-23 2023-24 Years
Planning & Engineering $ - $ - $ - $ - $ - $ - $ 1,750,000
Purchase - - 4,500,000 - - - 1,200,000
Construction - - - - - - 18,000,000
Contingency - - - - - - 1,800,000
Other - - - - - - 227,500
Total Project Costs $ - $ - $ 4,500,000 $ - $ - $ - $ 22,977,500
Prior to Future
FUNDING SOURCE(S) July 2019 2019-20 2020-21 2021-22 2022-23 2023-24 Years
General Fund $ - $ - $ - $ - $ - $ - $ 227,500
Installment Purchase - - 4,500,000 - - - 22,750,000
Total Funding Sources $ - $ - $ 4,500,000 $ - $ - $ - $ 22,977,500
PF - 7
LEVEL B
TOWN OF WAKE FOREST
CAPITAL IMPROVEMENTS PROGRAM
CIP UPDATE FY 2019-2024
PROJECT DESCRIPTION
Satellite location for maintenance.
JUSTIFICATION
With additional greenways, staff, and equipment being added space is needed to accommodate.
This location would be on the south side of town to reduce daily travel. This building would be Insert image
located by a greenway and will include a public restroom with an exterior entrance. A fenced yard
would be included for future equipment. The building would be approximately 3000 square feet
and a gravel lot. The intent for this building is to be located at the Smith Creek Trailhead near the
Raleigh Waste Water Treatment Plant.
Prior to Future
CAPITAL COST BREAKDOWN July 2019 2019-20 2020-21 2021-22 2022-23 2023-24 Years
Planning & Engineering $ - $ - $ - $ - $ - $ - $ 35,000
Construction - - - - - - 400,000
Equipment - - - - - - -
Contingency - - - - - - 40,000
Other-PAC - - - - - - 4,400
Total Project Costs $ - $ - $ - $ - $ - $ - $ 479,400
Prior to Future
FUNDING SOURCE(S) July 2019 2019-20 2020-21 2021-22 2022-23 2023-24 Years
GO Bonds - FY 2024 Referendum - - - - - - 479,400
Total Funding Sources $ - $ - $ - $ - $ - $ - $ 479,400
PF - 8
Capital Improvement Plan
PUBLIC SAFETY SUMMARY - BY PROJECT
PROJECT DESCRIPTION
Purchase new vehicles per state contract specifications for requested additional positions.
JUSTIFICATION
Population and call volume are continuing to increase, as the town is still developing both
commercially and residentially at a fast pace. The increased territory and the time to patrol has Insert image
increased. To keep pace with this growth new personnel will be needed to maintain the current
level of service. These vehicles reduce the geographical areas of responsibility and adds to ancillary
functions that assist in targeting high crime areas and answering calls for service.
Prior to Future
CAPITAL COST BREAKDOWN July 2019 2019-20 2020-21 2021-22 2022-23 2023-24 Years
Purchase $ - $ - $ 390,000 $ - $ 400,000 $ - $ -
Equipment - - - - - - -
Other - - - - - - -
Total Project Costs $ - $ - $ 390,000 $ - $ 400,000 $ - $ -
Prior to Future
FUNDING SOURCE(S) July 2019 2019-20 2020-21 2021-22 2022-23 2023-24 Years
Installment Purchase $ - $ - $ 390,000 $ - $ 400,000 $ - $ -
- - - - - - -
Total Funding Sources $ - $ - $ 390,000 $ - $ 400,000 $ - $ -
PS - 1
Strategic Goal 2 - Safe Connected Community LEVEL C
TOWN OF WAKE FOREST
CAPITAL IMPROVEMENTS PROGRAM
CIP UPDATE FY 2019-2024
PROJECT DESCRIPTION
Obtain a mobile command vehicle to provide a back-up
communication and operational function for the Police
Department and town.
JUSTIFICATION
A mobile command vehicle would provide the Police
Department and town with a versatile asset to continue service
in a mobile platform. This vehicle could be used as a command Insert image
post at major crime scenes, natural disasters, and town events
by providing conference rooms, communications capabilities,
video capabilities, and exterior lighting. Mobile command
vehicles allow for a quick response and transferability of
services at a moment’s notice.
Prior to Future
CAPITAL COST BREAKDOWN July 2019 2019-20 2020-21 2021-22 2022-23 2023-24 Years
Purchase $ - $ - $ - $ - $ 325,000 $ - $ -
Other - - - - - - -
Total Project Costs $ - $ - $ - $ - $ 325,000 $ - $ -
Prior to Future
FUNDING SOURCE(S) July 2019 2019-20 2020-21 2021-22 2022-23 2023-24 Years
Installment Purchase $ - $ - $ - $ - $ 325,000 $ - $ -
- - - - - - -
Total Funding Sources $ - $ - $ - $ - $ 325,000 $ - $ -
PS - 2
Strategic Goal 2 - Safe Connected Community LEVEL B
TOWN OF WAKE FOREST
CAPITAL IMPROVEMENTS PROGRAM
CIP UPDATE FY 2019-2024
PROJECT DESCRIPTION
Provide a Back-up Communications Center in case the current one becomes inoperable or
unsafe.
JUSTIFICATION
To ensure the continuity of services, a back-up plan is needed in the event the current
communications center were to be shut down, temporarily or permanently. There have been
cases when the operations of communications should have been evacuated for safety reasons, Insert image
but we had to continue running it because we had no where to move the operations. Reasons
for a back-up plan can be: man made problems, power outages, natural disasters or in major
incidents it provides the Town with more capacity. With the increasing size of the Police
Department we can not afford to take the risk of losing communications. This request includes
radio system, furniture, software and installation. The center will also include an emergency
operations room.
Prior to Future
CAPITAL COST BREAKDOWN July 2019 2019-20 2020-21 2021-22 2022-23 2023-24 Years
Purchase $ - $ - $ - $ 600,000 $ - $ - $ -
Other - - - - - - -
Total Project Costs $ - $ - $ - $ 600,000 $ - $ - $ -
Prior to Future
FUNDING SOURCE(S) July 2019 2019-20 2020-21 2021-22 2022-23 2023-24 Years
General Fund $ - $ - $ - $ 600,000 $ - $ - $ -
Asset Foreiture Funds* - - - - - - -
Total Funding Sources $ - $ - $ - $ 600,000 $ - $ - $ -
PS - 3
LEVEL B
TOWN OF WAKE FOREST
CAPITAL IMPROVEMENTS PROGRAM
CIP UPDATE FY 2019-2024
Insert image
Prior to Future
CAPITAL COST BREAKDOWN July 2019 2019-20 2020-21 2021-22 2022-23 2023-24 Years
Purchase $ - $ - $ - $ - $ 150,000 $ - $ -
Other - - - - - - -
Total Project Costs $ - $ - $ - $ - $ 150,000 $ - $ -
Prior to Future
FUNDING SOURCE(S) July 2019 2019-20 2020-21 2021-22 2022-23 2023-24 Years
General Fund $ - $ - $ - $ - $ 150,000 $ - $ -
Grants - - - - - - -
Total Funding Sources $ - $ - $ - $ - $ 150,000 $ - $ -
PS - 4
Capital Improvement Plan
GREENWAYS, TRANSPORTATION AND PEDESTRIAN ACCESS (GTP) - BY PROJECT
Note 1: This section is used to account for the design, construction and improvements to greenways, trails, bike paths and pedestrian access throughout the town.
Pu
rn
e ll
Rd
¾
n
"
) 18
Transportation Planning Projects
CIP 2019-2024
W
all Rd
d
Je E Carroll
Bl v
nk Joyner
i ns Park
1A
St
al
R d (
/
pit
te
b
¾
hi
Ca
d
W
15
R
"
) N
b
¾ JB
ll
Mi
2
"
) Flaherty
Park
on
1 14
(
/ 1 "
) "
) St
17 "
)
ps
21
"
)
Thom
St
ad
b
¾ ¾
n
22
Rd
iu
m
"
)
ai n
P
Dr
¾ 14 E J u niper
¾n
n "
) Oak
h
NM
rc P Grove Chu
b
¾ ¾n
lvd
u rc h R d
Ch b ve
A
¾
B
n
o
de
Durha
¾
ni
6
"
) mR
U
an
d
;
Ä
e
27
"
)
ak
Gr
13
"
) )¾nb
25 24 ¾
" 24
" 24 "
)
W
98 ) )")b 98 "
)27
tions
¾ 20
"
) n
14 "
) "
) 25 24
" ¾
;
Ä P
¾n
"
) 11 "
) 2
Wake Forest
di
Reservoir
98 19
Tr a
"
)
b ¾ P
14
"¾¾
)b n
98
b
¾ Wait Ave
Dr Calvin Jones
98 16
"
)29
14
Hw y
"
) 12
¾n P
"
) "
)
He
10
"
) 25
n
St rita
g "
)
ai
e L
23
"
) 26
S
M
"
)
a ke R
P Jo
1A
¾n n es
¾
n
¾ /
b ( 14
Da
i
d
n"
¾) ¾n
ry
P b
¾ Ch
¾
Rd
n a
9
"
) 3 "
) Ro gers Rd
¾
n
lk
Rd
¾
n
¾
n
d
e Rd
eus
ll R
¾
n fN 27
"
)
Mi
ll so
Fa 4
"
)
on
¾
n Ro
Li g
ge
b
¾ 12
rs
"
) Rd
28 7
"
) "
)
Capital Blvd
b
¾
Fo
Town of Rolesville's
res
LEGEND
5
8
"
) Greenway Project Streets
¾
n
"
) "
)
G1
Greenways
)
"
R1 Roadway Project
Major Streams
)
"
S1 Pedestrian Project
1 Major Water Bodies
(
/ n ¾ P
Burlin gto n Mil
ls R d
b
¾ Parks
Open Space 401 ( ¾
n
P
¾
n Private School
/
¾
n Park
¾
n Public School
School
P
University
.
¾
n ¾ Town Limits
Other Jurisdictions
Li
go
Riv
27
"
)
Mill
er
0 0.25 0.5 1
Rd
PROJECT DESCRIPTION
Construction to implement a Complete Streets vision along Stadium Drive (SR1930) from Capital Blvd (US-1) to N. Wingate St.
(SR 1954). This project would extend the center turn lane, add curb and gutter, and pave wider shoulders on both sides of the
road. A roundabout is planned at the intersection of Stadium Drive and N. Wingate Street. Additional turn lanes would be
marked at intersections and driveways where needed. Pedestrian and bicycle improvements from Glencoe Drive to the
bridge over Richland Creek include a 10-foot wide multi-use path on the south side and a 5-foot wide sidewalk on the north
side. From the bridge to N. Wingate Street there will be sidewalks on both sides of the road. Shared-lane bicycle markings
(called “sharrows”) will be added to the travel lanes along the entire corridor. The project also will include two pedestrian
refuge islands, high visibility crosswalks, and accessible transit stops.
JUSTIFICATION
insert photo
Implementation of the adopted Transportation, Bicycle & Pedestrian Plans for the Town of Wake Forest. The Town received
Locally Administered Projects Program (LAPP) funding to complete preliminary engineering (design & environmental
documentation) during FY2013-14. Federal authorization for preliminary engineering was approved in the amount of
$293,000 ($234,400 federal; $58,600 local). Staff pursued 6,466,750 federal; $3,885,750 local). Project is under construction
with plans to be completed in June 2020. Debt will be issued soon for this project.
T-1
Strategic Goal 2 - Safe Connected Community LEVEL B
PROJECT DESCRIPTION
TIP No. U-5118BA. Design and ROW complete. Construction to implement a Complete Streets
and Operational Improvements along Ligon Mill Road (SR 2044) from US 1 Alt (South Main
Street) to the Walmart driveway, approximately 500 feet north of Brimfield Springs Lane. The
project length is 0.371 miles. The typical section includes a four lane divided roadway with
curb and gutter, 4' wide bike lanes and 5-ft+ wide sidewalks on both sides of the roadway. and
high visibility crosswalks & ramps. Access to the Smith Creek Greenway will be included.
Funding through LAPP. The project is currently under construction and debt will be be issued
soon for the project. Construction is expected to completed by June 2019 and the project
completion is expected to be June 2020.
JUSTIFICATION
Implementation of the adopted Transportation, Bicycle & Pedestrian Plans for the Town of
Wake Forest.
T-2
Strategic Goal 2 - Safe Connected Community LEVEL B
PROJECT DESCRIPTION
Roadway connections.
JUSTIFICATION
Connect roadway as part of the Transportation Plan, which will allow for faster response time
for Fire and EMS in case of an emergency. As well as an alternate route for traffic. Projects
added per BOC recommendation. Foundation Drive design to be in conjunction with the Parks &
Recreation Department Master Plan for 94 acres.
Prior to Future
CAPITAL COST BREAKDOWN July 2019 2019-20 2020-21 2021-22 2022-23 2023-24 Years
Planning & Engineering $ 171,500 $ 25,000 $ - $ - $ - $ - $ -
Purchase - - - 50,000 - - -
Construction 845,500 275,000 - - - 7,891,000 -
Contingency - - - - - - -
Total Project Costs $ 1,017,000 $ 300,000 $ - $ 50,000 $ - $ 7,891,000 $ -
Prior to Future
FUNDING SOURCE(S) July 2018 2019-20 2020-21 2021-22 2022-23 2023-24 Years
General Fund $ - $ 267,000 $ - $ 50,000 $ - $ - $ -
Installment Purchase 950,000 - - - - - -
GO Bonds - Future Referendum FY 2024 - - - - - 7,891,000 -
Capital Reserve 67,000 33,000 - - - - -
Total Funding Sources $ 1,017,000 $ 300,000 $ - $ 50,000 $ - $ 7,891,000 $ -
T-3
Strategic Goal 2 - Safe Connected Community LEVEL B
PROJECT DESCRIPTION
Preliminary engineering, NEPA documentation, ROW, and construction to implement a Complete Streets vision along Durham Road (NC 98
Bus) from Retail Drive to Tyler Run Drive in Wake Forest. The lanes within the existing project area vary from 6-lanes from Retail Drive to
NB US1 Ramp to 2-lanes from NB US1 Ramp to Tyler Run Drive. Improvements from Retail Drive to Cloverleaf Drive include adding sidewalk
to both sides of Durham Road behind existing curb & gutter. From Cloverleaf Drive to the US NB Ramp, improvements involve adding a
dedicated sidewalk section through the interchange along the south side of Durham Road, inclusive of the addition of curb & gutter and
the adjustment of existing concrete barrier rail and guardrail through the overpass. East of US 1 NB Ramps, the improvements include a
three-lane curb & gutter section from St. John’s Episcopal Church driveway to just east of Richland Drive, sidewalk on the north side and
multi-use path on the south side . The multi-use path would continue on the south side of Durham Road (NC 98 BUS) and Tyler RunDrive.
This project would extend the center turn lane for the full length of the corridor. The proposed pedestrian connections would eliminate a
1.6 mile gap from Durham Road (NC98 Bus): Richland Creek Plaza multi-use path terminus to Tyler Run Drive. A sidewalk extension from
Durham Road along Cloverleaf Drive, will be included. The proposed project includes design for 969 lf multi-use path, and 6,983 lf sidewalk.
ROW plans for easement and/or land acquisition will be required.
JUSTIFICATION
insert photo
Implementation of the adopted Open Space & Greenways, Transportation, Bicycle & Pedestrian Plans for the Town of Wake Forest. In
addition to improving traffic flow, this project would fill a 1.6 mile gap on Durham Road by installing a combination of multi-use path and
sidewalk to link with existing pedestrian facilities on Durham Rd. Many of these sidewalk sections are critical missing pieces needed for
efficient and safe pedestrian access to schools and work places. In many cases, there are footworn paths indicating many pedestrians are
striving to walk in a hostile environment which presents several safefty concerns. Shared-lane bicycle markings (called “sharrows”) will be
added to the travel lanes in designated areas along the corridor. Sharrows increase a driver’s awareness of the presence of bicyclists and
reduce the likelihood of bicycling in the wrong direction. Many commuters are traveling to/from downtown Wake Forest to Durham Rd in
order to shop and dine at the local commercial businesses, reach other destinations such as work sites, schools and residential areas. Staff
pursued a FFY2017 Locally Administered Projects Program (LAPP) funding to support right-of-way acquisition and construction.
T-4
Strategic Goal 2: Enhance and Promote a Safe and Connected Community LEVEL B
PROJECT DESCRIPTION
Engineering Design, ROW acquisition, and construction of approximately 0.8 miles of greenway trail. This
segment will extend the recently constructed Smith & Sanford Creek Greenways from south of Heritage
High School to Ligon Mill Road.
JUSTIFICATION
Implementation of the adopted Open Space & Greenways, Transportation, Bicycle & Pedestrian Plans
for the Town of Wake Forest. To connect residents with each other and to important destinations,
providing for conservation of natural resources, recreation, and bicycle/pedestrian transportation
opportunities while preserving greenspaces in Wake Forest. Safer bike/pedestrian facilities and crossings
are needed along Burlington Mills and Ligon Mills Rds. Wake Forest will create major bike/pedestrian
insert photo
commuter connections along the Smith Creek corridor, thus linking the residential areas along Burlington
Mills and Ligon Mill Rds, Heritage Elementary, Middle, and High schools, and Heritage Park via greenway.
Wake Forest recieved a 2016 Clean Water Management Trust Fund (CWMTF) grant for additional funding
of $513,581 to support ROW for phase 2 and phase 3.
T-5
LEVEL B
PROJECT DESCRIPTION
Engineering Design, ROW acquisition, and construction of approximately 1.1 miles of greenway trail and trailhead. This
segment will provide a connection from Ligon Mill Road to Burlington Mills Road and ultimately to Raleigh's Neuse River
Greenway via the Wake Forest Connector bridge. The design of the 40 parking spaces trailhead on Ligon Mill Road is
designed under this project but constructed by NCDOT with B-5318 - Ligon Mill Road Underpass.
JUSTIFICATION
Implementation of the adopted Open Space & Greenways, Transportation, Bicycle & Pedestrian Plans for the Town of
Wake Forest. To connect residents with each other and to important destinations, providing for conservation of natural
resources, recreation, and bicycle/pedestrian transportation opportunities while preserving greenspaces in Wake Forest.
insert photo
Safer bike/pedestrian facilities and crossings are needed along Burlington Mills and Ligon Mills Rds. Wake Forest will
create major bike/pedestrian commuter connections along the Smith Creek corridor, thus linking the residential areas
along Burlington Mills and Ligon Mill Rds, Heritage Elementary, Middle, and High schools, and Heritage Park via
greenway. Staff pursued a Wake County Open Space Program grant during March/April 2014. Wake Forest has recieved
$941,000 for design and construction from the Wake Co. grant in support of the greenway project and a 2016 Clean
Water Management Trust Fund (CWMTF) grant for additional funding of $513,581 to support ROW for phase 2 and
phase 3.
T-6
Strategic Goal 2 - Safe Connected Community LEVEL B
PROJECT DESCRIPTION
Multiyear project. Add sidewalk to the north side of W. Holding Avenue from S.
Main Street to west end. Project consists of narrowing the roadway width by
resetting the curb and gutter and storm drain facilities. Traffic calming
measures will be included. Construction work will be done by Town Street
Division. Phase 1 will extend from Elmwoon Ct to St. Catherines Church,
approximately 650 lf.
JUSTIFICATION
W. Holding Avenue is a residential collector street. Current policy requires NO IMAGE PROVIDED
sidewalks on both sides. Concerns with speeding from neighborhood residents
allows traffic calming measures to be included.
T-7
Strategic Goal 2 - Safe Connected Community LEVEL B
PROJECT DESCRIPTION
Preliminary engineering, ROW acquisition, and construction of Dunn Creek Greenway: Town Property to NC 98
Business(Wait Avenue) to E Juniper Ave . This project includes a 1.9 mile trail connection to Ailey Young Park within the
Northeast Neighborhood. There are approximately nine pedestrian bridge crossings proposed for this project.
JUSTIFICATION
Implementation of the adopted Open Space & Greenways, Transportation, Bicycle & Pedestrian Plans for the Town of
Wake Forest. Dunn Creek is key north/south corridor that connects the Neuse River. Once completed, the segment will
provide access to dowtown Wake Forest, residential subdivisions, commercial developments, schools, Ailey Young Park on INSERT PHOTO
E. Juniper Avenue (Northeast End), Wake Forest Reservoir, and Smith Creek Soccer Center. The benefits that a greenway
can bring to this area include: stormwater capacity, that can balance increased impervious surfaces, recreation
opportunities, buffers, and a route for pedestrian and bicycle tranpsortation. The Town is paying for Design and Right-of-
Way. Staff will also pursue a LAPP grant during the FFY2021 call for projects to support the cost of construction for the
Dunn Creek Greenway, Phase 3 project. The Federal Fiscal Year (FFY) for 2021 is October 1, 2020 through September 30,
2021.
T-8
Strategic Goal 2 - Safe and Connected Community LEVEL B
PROJECT DESCRIPTION
Design, ROW acquisition, and construction to complete the Northside Loop: North White Street to
North Main Street. The typical section includes two lane divided road with curb & gutter and multi-
use path on both sides of the road.
JUSTIFICATION
Implementation of the adopted Transportation, Bicycle & Pedestrian Plans for the Town of Wake
Forest. Staff will pursue a LAPP grant and other funding options to support this effort.
insert photo
General Fund $ - $ - $ - $ - $ - $ - $ -
GO Bonds - Current Referendum (2014) - Unissued 50,000 100,000 - - - - -
GO Bonds - Future Referendum FY 2020 - - - - - - 2,700,000
Grants - Future Application - - - - - - 6,205,000
Grants - CSX Contribution - Future Application - - - - - - 5,000,000
Total Funding Sources $ 50,000 $ 100,000 $ - $ - $ - $ - $ 13,905,000
T-9
Strategic Goal 2 - Safe Connected Community LEVEL B
PROJECT DESCRIPTION
Addition of traffics when warranted.
JUSTIFICATION
Signal light is needed at intersection due to increased volume of
residental development, safety concerns for motorists and
pedestrians utilizing trail, soccer center and shopping nearby.
Signal warrants have been met at Heritage Lake/Friendship
Chapel and Forestville Road/Song Sparrow. Adjacent
neighborhoods to contribute upgrades (Steel Poles and
Pedestrian Heads) along with NCDOT and Town funding.
Intersections:
Prior to Future
CAPITAL COST BREAKDOWN July 2019 2019-20 2020-21 2021-2022 2022-2023 2023-2024 Years
Planning & Engineering $ - $ - $ 20,000 $ 40,000 $ - $ - $ 30,000
Construction - 75,000 125,000 400,000 - - 300,000
Other - - 50,000 50,000 - - -
Total Project Costs $ - $ 75,000 $ 195,000 $ 490,000 $ - $ - $ 330,000
Prior to Future
FUNDING SOURCE(S) July 2019 2019-20 2020-21 2021-2022 2022-2023 2023-2024 Years
General Fund $ - $ 35,000 $ 70,000 $ 160,000 $ - $ - $ 132,000
Grants - NCDOT - Future Application - 40,000 100,000 330,000 - - 198,000
Other - Heritage Homeowners Association - - 25,000 - - - -
Total Funding Sources $ - $ 75,000 $ 195,000 $ 490,000 $ - $ - $ 330,000
T - 10
Strategic Goal 2: Enhance and Promote a Safe and Connected Community LEVEL B
PROJECT DESCRIPTION
Installation of Bus shelters, benches, trash cans, lighting and amenities at bus
stops along the Wake Forest Loop. The following are the first phase of bus stops
in which bus shelters will be installed:
JUSTIFICATION
Building supporting infrastructure for our transportation service is vital for the
success of our system. Better bike and pedestrian facilities in combination with
high quality passenger waiting shelters will result in more ridership and better
return on investment on the service hours we operate. The Town will continue
to work to add bus shelters and bus stop amenities like benches, lighting and
litter receptacles to our system every year.
T - 11
Strategic Goal 2 - Safe Connected Community LEVEL B
PROJECT DESCRIPTION
TIP No. P-5707 Rogers Road (SR 2052) The project will construct a bridge on
Rogers Road (S.R. 2052) over the CSX S-line railroad in the same location as
the existing at-grade crossing. Current plans include an on-site detour during
construction. The project includes a 5-Land Curb & Gutter. The Town will
reimburse NCDOT to complete the improvements of Heritage Branch from
the end of their project to the intersection of Boulder Pointe Drive.
JUSTIFICATION
Improvements to project P-5707 requested by the Town to include
additional sidewalk, vinyl coated fence on top of the retaining walls and
vinyl coated fence on bridge, and a turn lane for Grandmark Street.
T - 12
Strategic Goal 2 - Safe Connected Community LEVEL B
PROJECT DESCRIPTION
Design, ROW, and construction of a 10' multi-use path
approximately 2.2 miles of NC 98 (Dr. Calvin Jones Highway) from
Heritage Lake Road (SR 5144) to US 1A (South Main Street).
JUSTIFICATION
The project is consistent with the adopted Wake Forest Open Space
and Greenway Plan and the Wake County Greenway System Plan. NO IMAGE PROVIDED
This greenway will provide an east-west connection between major
corridors for the Town.
T - 13
Strategic Goal 2 - Safe Connected Community LEVEL B
PROJECT DESCRIPTION
Design, ROW and construction for Richland Creek Greenway Phase 1 from Harris
Road (SR 1931) to Stadium Drive. The path woud start at Harris Road (SR 1931)
and continue at the underpass (access built) then follow Richland Creek to the
the Cougar Trail soft trail and end at Stadium Drive. The portion of the Cougar
Trail that continues west to Joyner park will convert to paved trail and a 10' wide
bridge, 35’ long is to be constructed. The bridge will be rated for an H-5 load.
Approximately 1.1 miles of paved greenway.
T - 14
Strategic Goal 2 - Safe Connected Community LEVEL B
PROJECT DESCRIPTION
Design, ROW and construction for Richland Creek Greenway: north of existing
end to Town Limits. This greenway will provide neighborhood connections to the
following streets: Fulworth Avenue & Chamberwell Ave (Richland Hills) and
Houndsditch Circle (Twin Creeks at Olde Mill Stream). Approximately 1.3 miles of
greenway. There are approximately seven greenway bridge crossings proposed
for this project. Design for Phase 1 and Phase 2 combined, ROW and
Construction separate.
JUSTIFICATION
INSERT IMAGE
The project is consistent with the adopted Open Space and Greenway Plan and
Parks & Recreation Master Plan. Prefabricated or concrete pedestrian bridges
are recommended as they will provide a longer service life. Implementation of
the Open Space & Greenways, Transportation, Bicycle & Pedestrian Plans for the
Town of Wake Forest. Staff will pursue a LAPP grant and other funding options to
support this project.
T - 15
Strategic Goal 2: Enhance and Promote a Safe and Connected Community LEVEL B
PROJECT DESCRIPTION
Design, ROW acquisition and construction to extend Ligon Mill Road from Dr. Calvin Jones Hwy (NC 98)
to NC 98 BUS (Durham Road).The typical section includes a 4-lane divided boulevard with a sidewalks
and bike lanes, high visiblity crosswalks & ramps where needed. This phase is approximately 1 mile.
JUSTIFICATION
Implementation of the adopted Transportation, Bicycle & Pedestrian Plans for the Town of Wake
Forest. Staff will apply for Locally Administered Projects Program (LAPP) funding to complete Right of
Way aquisition and Construction in future years.
T - 16
Strategic Goal 2: Enhance and Promote a Safe and Connected Community
LEVEL B
PROJECT DESCRIPTION
Design, ROW and construction for Richland Creek Greenway: Stadium Drive to
US 1. Approximatley 2.3 miles of greenway. A pedestrian underpass currently
exists at NC 98 Bypass (Dr. Calvin Jones Hwy). A crosswalk is needed a NC 98 Bus
(Durham Rd) as well as Wayfinding along the corridor.
JUSTIFICATION
The project is consistent with the adopted Open Space and Greenway Plan and
Parks & Recreation Master Plan. Prefabricated or concrete pedestrian bridges
are recommended as they will provide a longer service life. Implementation of INSERT IMAGE
the Open Space & Greenways, Transportation, Bicycle & Pedestrian Plans for the
Town of Wake Forest. Staff will pursue a LAPP grant and other funding options
to support this project.
T - 17
Strategic Goal 2 - Safe Connected Community LEVEL B
PROJECT DESCRIPTION
Construction of Sharrows/Shared Lanes pavement markings on
the following downtown streets:
1. US 1A S. Main St: South Ave to W Sycamore Ave
2. Elm Ave: S. Main St to S. Franklin St
3. Roosevelt/Wait Ave: Front St to Franklin St
4. S. White St: Elm Ave to Roosevelt Ave
5. S. Taylor St: Elm Ave to Wait Ave
6. W. Sycamore Ave: S Main St to S. Wingate St
7. S Wingate St: South Ave to Kinvara Ct
JUSTIFICATION
Implementation of the adopted Transportation, Bicycle &
Pedestrian Plans for the Town of Wake Forest. Sharrows are
markings applied directly to the pavement to direct cyclists to
ride in the proper direction and raise motorist awareness of the
potential presence of cyclists
T - 18
Strategic Goal 2: Enhance and Promote a Safe and Connected Community LEVEL B
PROJECT DESCRIPTION
Design, ROW acquisition and construction to extend Ligon Mill Road from NC 98 BUS (Durham Road) to Stadium
Drive.The typical section includes a 4-lane divided boulevard with a sidewalks and bike lanes, high visiblity crosswalks &
ramps where needed. This phase is approximately 0.75 mile.
JUSTIFICATION
Implementation of the adopted Transportation, Bicycle & Pedestrian Plans for the Town of Wake Forest. Staff will
apply for Locally Administered Projects Program (LAPP) funding to complete Right of Way aquisition and Construction
in future years.
T - 19
Strategic Goal 2: Enhance and Promote a Safe and Connected Community LEVEL B
PROJECT DESCRIPTION
Design, ROW acquisition and construction to complete pedestrian sidewalk
connections along:
T - 20
Strategic Goal 2 - Safe Connected Community LEVEL B
JUSTIFICATION
This project will complete the US-1A Bicycle Lanes Incidental
Project R-3600. Design work is complete. The bicycle lanes will
connect to Wake Forest Middle School.
T - 21
Strategic Goal 2 - Safe and Connected Community LEVEL B
PROJECT DESCRIPTION
Preliminary engineering, ROW acquisition, and construction of Dunn Creek Greenway: North of
Traditions Grande Blvd to Flaherty Park and Sedgefield Subdivision. Approximately .28 miles of
greenway. Per the Parks, Recreation, and Cultural Resources Master Plan Update a 10' wide
asphalt greenway trail will be added to provide a loop around the sports fields at Flaherty Park.
JUSTIFICATION
Implementation of the adopted Open Space & Greenways, Transportation, Bicycle &
Pedestrian Plans and Parks, Recreation, and Cultural Resources Master Plan Update for the
Town of Wake Forest. Staff will pursue LAPP/SPOT funding opportunities to support the
INSERT PHOTO
preliminary enginering, ROW and construction of the .28 mile greenway connection. The
developer of Traditions is constructing approximately 1.3 miles of this greenway which includes
Wildflower Ridge Rd to the greenway phase 4 gap and from the phase 4 gap to the county line.
T - 22
Strategic Goal 2 - Safe Connected Community
LEVEL B
PROJECT DESCRIPTION
Preliminary engineering, environmental, ROW acquisition, and construction for passvie/active park greenway
connections.
JUSTIFICATION
Implementation of the adopted Open Space & Greenways, Transportation, Bicycle & Pedestrian Plans for the
Town of Wake Forest. Identify open space land where citizens can enjoy minamally improved amenities for
active use. Such as: environmental study, primitive camping, non-motorized boating, hiking, mountain biking,
and equestrian trails. Other amenities include trailheads, educational/information kiosk, parking and restrooms.
The following locations were identified by the Greenways Advisory Board and ranked in order of priority: INSERT PHOTO
Reservoir, 80-acre tract behind Heritage schools, Neuse River and Falls Lake.
T - 23
Strategic Goal 2 - Safe Connected Community LEVEL B
PROJECT DESCRIPTION
Design, ROW acquisition and construction to implement a Complete Streets
vision along Ligon Mill Road (S R2044) from from US 1 Alt (South Main Street) to
Song Sparrow Drive (SR 4428). The typical section includes three lanes with curb
and gutter, left-turn lanes at intersections and driveways, 4' wide bike lanes on
both sides of the roadway, 5-ft wide sidewalks on both sides of the roadway, and
high visibility crosswalks & ramps. Access to the Smith Creek Greenway will be
included.
JUSTIFICATION
Implementation of the adopted Transportation, Bicycle & Pedestrian Plans for
the Town of Wake Forest. Staff will also pursue a LAPP grant during a future call
for projects to support the cost of design, right-of-way and construction for the
Ligon Mill Road Complete Streets project.
T - 24
Strategic Goal 2 - Safe and Connected Community LEVEL B
PROJECT DESCRIPTION
Design, ROW, and construction of a 10' multi-use path approximately 4.6
miles and pedestrian overpass on NC 98 (Dr. Calvin Jones Highway) from
US 1A (South Main Street) to NC 98 Business (Durham Road).
JUSTIFICATION
The project is consistent with the adopted Wake Forest Open Space and
Greenway Plan and the Wake County Greenway System Plan. This
greenway will provide an east-west connection between major corridors NO IMAGE PROVIDED
for the Town.
T - 25
Strategic Goal 2 - Safe Connected Community LEVEL B
PROJECT DESCRIPTION
Preliminary engineering, ROW acquisition, construction for greenway trail:
Basley Street to Cottonbrook Drive (Bowling Green) with an access point at
Landen Drive (Willowdee) and Basley Street to Jones Dairy Road (Heritage
Hills) bridge pedestrian underpass. A spur to from Jones Dairy Rd to Friendship
Chapel Rd. Approximately 2.5 miles of trail.
JUSTIFICATION
Implementation of the adopted Open Space & Greenways, Transportation,
Bicycle & Pedestrian Plans for the Town of Wake Forest. Staff will pursue
LAPP Funds to support the preliminary enginering, ROW and construction of insert photo
this project; $3.5M.
T - 26
Capital Improvement Plan
PARKS, RECREATION AND CULTURAL RESOURCES SUMMARY - BY PROJECT
PROJECT DESCRIPTION
This project consists of building sand-based grass infield (replacing dirt infield),
grading and installation of hybrid sod on field 3, mirroring the work that has
been completed on field 2.
JUSTIFICATION
Building of grass infields would be to accommodate program needs and the
sand-based structure with corrugated draining would allow for appropriate
water drainage for the high-use infield area. Building of a permanent baseball
mound would be much safer than continuing to use portables. Aesthetics of
these fields will increase dramatically.
INSERT PHOTO
Prior to Future
CAPITAL COST BREAKDOWN July 2019 2019-20 2020-21 2021-22 2022-23 2023-24 Years
Construction $ - $ 115,000 $ - $ - $ - $ - $ -
Other - - - - - - -
Total Project Costs $ - $ 115,000 $ - $ - $ - $ - $ -
Prior to Future
FUNDING SOURCE(S) July 2019 2019-20 2020-21 2021-22 2022-23 2023-24 Years
General Fund $ - $ 115,000 $ - $ - $ - $ - $ -
- - - - - - -
Total Funding Sources $ - $ 115,000 $ - $ - $ - $ - $ -
PROJECT DESCRIPTION
1) Heavy Duty Truck (FY 2020)
2) Crew Cab - Light Duty Truck (FY 2021)
3) Department Staff Vehicle (FY 2021)
4) 4x4 Extended Cab/Tow Package - 2 Medium Duty Trucks (FY 2020) & (FY 2023)
JUSTIFICATION
Insert image
Prior to Future
CAPITAL COST BREAKDOWN July 2019 2019-20 2020-21 2021-22 2022-23 2023-24 Years
Purchase $ - $ 90,000 $ 47,500 $ - $ 35,000 $ - $ -
Other - - - - - - -
Total Project Costs $ - $ 90,000 $ 47,500 $ - $ 35,000 $ - $ -
Prior to Future
FUNDING SOURCE(S) July 2019 2019-20 2020-21 2021-22 2022-23 2023-24 Years
General Fund $ - $ - $ - $ - $ - $ - $ -
Installment Purchase - 90,000 47,500 - 35,000 - -
Total Funding Sources $ - $ 90,000 $ 47,500 $ - $ 35,000 $ - $ -
PRCR - 2
Strategic Goal 2 - Safe Connected Community LEVEL B
PROJECT DESCRIPTION
Skid Steer Loader
JUSTIFICATION
Machine has the capacity for various attachments that will help improve landscaping and
increase efficiency of tasks, including: brush cutter, broom, excavator. In addition, it would
suffice the park maintenance divisions need to:
-Load/Unload bulk and palleted materials
-Grading and culvert work
-Move heavy materials such as rip rap and boards, in repair of greenway bridges INSERT PHOTO
-Repair greenway shoulders
-Snow removal in parking lots and driveways, while doing a better job than snow plows
-Remove dead trees and large fallen limbs
-Will allow for portions of larger projects to be removed from contracted services and
performed in-house(sports field infield grading, dog park grading), saving money.
Prior to Future
CAPITAL COST BREAKDOWN July 2019 2019-20 2020-21 2021-22 2022-23 2023-24 Years
Equipment $ - $ 60,000 $ - $ - $ - $ - $ -
Other - - - - - - -
Total Project Costs $ - $ 60,000 $ - $ - $ - $ - $ -
Prior to Future
FUNDING SOURCE(S) July 2019 2019-20 2020-21 2021-22 2022-23 2023-24 Years
General Fund $ - $ - $ - $ - $ - $ - $ -
Installment Purchase - 60,000 - - - - -
Total Funding Sources $ - $ 60,000 $ - $ - $ - $ - $ -
PRCR - 3
Strategic Goal 2 - Safe Connected Community LEVEL B
PROJECT DESCRIPTION
Precision Cut Mower
JUSTIFICATION
This equipment will allow us to do more with less, almost doubling
productivity at more than 8 feet cutting width. This unit will be used at
Smith Creek Soccer Center.
INSERT PHOTO
Prior to Future
CAPITAL COST BREAKDOWN July 2019 2019-20 2020-21 2021-22 2022-23 2023-24 Years
Equipment $ - $ 62,500 $ - $ - $ 50,000 $ - $ -
Other - - - - - - -
Total Project Costs $ - $ 62,500 $ - $ - $ 50,000 $ - $ -
Prior to Future
FUNDING SOURCE(S) July 2019 2019-20 2020-21 2021-22 2022-23 2023-24 Years
General Fund $ - $ - $ - $ - $ - $ - $ -
Installment Purchase - 62,500 - - 50,000 - -
Total Funding Sources $ - $ 62,500 $ - $ - $ 50,000 $ - $ -
PRCR - 4
Strategic Goal 2 - Safe Connected Community LEVEL B
PROJECT DESCRIPTION
Expansion and re-configuration of the existing dog park at Flaherty Park while adding a picnic shelter,
amenities, fencing, and agility obstacles. This will divide the current dog park in to three sections: Large dogs,
small dogs, all-weather-all-dogs.
JUSTIFICATION
The master plan calls for a landscape plan and amenities. Re-configuration would allow the landscape to be INSERT PHOTO
better maintained. The all-weather-all-dogs section, contained of wood chips, will allow dogs to be off-leash
during wet weather conditions to avoid mud. Also, this area would be predominantly used in cooler months
to allow the other areas to be closed at staff's discretion to preserve or re-establish turf.
Prior to Future
CAPITAL COST BREAKDOWN July 2019 2019-20 2020-21 2021-22 2022-23 2023-24 Years
Construction $ - $ 225,000 $ - $ - $ - $ - $ -
Other - - - - - - -
Total Project Costs $ - $ 225,000 $ - $ - $ - $ - $ -
Prior to Future
FUNDING SOURCE(S) July 2019 2019-20 2020-21 2021-22 2022-23 2023-24 Years
General Fund $ - $ 225,000 $ - $ - $ - $ - $ -
- - - - - - -
Total Funding Sources $ - $ 225,000 $ - $ - $ - $ - $ -
PRCR - 5
Strategic Goal 2 - Safe Connected Community LEVEL B
PROJECT DESCRIPTION
The activity bus can accommodate up to 21 passengers and can be equipped
with a wheelchair lift to meet ADA requirements.
JUSTIFICATION
One of the major barriers we face is the lack of transportation we have to
provide additional opportunities for program participants to visit our parks,
aquatic center, sprayground or other facilities where programs are based. An
addition of two accessible buses would provide for the maximum number of
participants currently in our full day camp program. The buses will also be
INSERT PHOTO
used to transport participants in various programs including special needs
social club, active older adult trips and teen trips. This will reduce amount of
charter shuttles needed for July 3rd Celebration.
Prior to Future
CAPITAL COST BREAKDOWN July 2019 2019-20 2020-21 2021-22 2022-23 2023-24 Years
Purchase $ - $ - $ 150,000 $ - $ - $ - $ -
Other - - - - - - -
Total Project Costs $ - $ - $ 150,000 $ - $ - $ - $ -
Prior to Future
FUNDING SOURCE(S) July 2019 2019-20 2020-21 2021-22 2022-23 2023-24 Years
General Fund $ - $ - $ - $ - $ - $ -
Installment Purchase - - 150,000 - - - -
Total Funding Sources $ - $ - $ 150,000 $ - $ - $ -
PRCR - 6
LEVEL B
TOWN OF WAKE FOREST
CAPITAL IMPROVEMENTS PROGRAM
CIP UPDATE FY 2019-2024
PROJECT DESCRIPTION
Replacement plan/program for lighting at athletic fields.
JUSTIFICATION
Existing systems are reaching the end of the expected lifespan. Replacement/installation of systems
with remote monitoring and operation will avoid large expenditures for repair of outdated systems
and reduce ongoing maintenance costs. The fixtures and bulbs in use currently are being phased out
and replacement of bulbs, ballasts, and fixtures will become increasingly difficult and more expensive
in the future. The goal of the department is to upgrade and replace lighting systems before they
create a safety hazard that will cause fields to be deemed unsafe/unplayable after sunset. Due to the
continued growth, installation of systems at Ailey Young Park and Tyler Run Park will provide
additional playing time and space without the cost of land purchase/development.
Prior to Future
CAPITAL COST BREAKDOWN July 2019 2019-20 2020-21 2021-22 2022-23 2023-24 Years
Purchase - - $ 235,000 $ 250,000 $ 300,000 $ 275,000 750,000
Other - - - - - - -
Total Project Costs $ - $ - $ 235,000 $ 250,000 $ 300,000 $ 275,000 $ 750,000
Prior to Future
FUNDING SOURCE(S) July 2019 2019-20 2020-21 2021-22 2022-23 2023-24 Years
General Fund $ - $ - $ - $ - $ - $ - $ -
GO Bonds - Future Referendum FY 2020 - - 235,000 250,000 300,000 275,000 750,000
Total Funding Sources $ - $ - $ 235,000 $ 250,000 $ 300,000 $ 275,000 $ 750,000
PRCR- 7
LEVEL B
PROJECT DESCRIPTION
Muti-Use Tractor
JUSTIFICATION
Mult-Use tractor to be applied in maintenance of the WF Reservoir, having
the ability to mow the dam. Has attachments with the ability to use this in
Debris/Snow Removal, Soil/Site Prep/Turf Maintenance, Special
INSERT PHOTO
Prior to Future
CAPITAL COST BREAKDOWN July 2019 2019-20 2020-21 2021-22 2022-23 2023-24 Years
Equipment $ - $ - $ 35,000 $ - $ - $ - $ -
Other - - - - - - -
Total Project Costs $ - $ - $ 35,000 $ - $ - $ - $ -
Prior to Future
FUNDING SOURCE(S) July 2019 2019-20 2020-21 2021-22 2022-23 2023-24 Years
General Fund $ - $ - $ - $ - $ - $ - $ -
Installment Purchase - - 35,000 - - - -
Total Funding Sources $ - $ - $ 35,000 $ - $ - $ - $ -
PRCR - 8
Safe Connected Community LEVEL B
PROJECT DESCRIPTION
Utility Tractor, Approx. 60 hp.
JUSTIFICATION
In order to better maintain greenway corridors, the plan is to purchase a large
three-point-hitch rotary mower, aerification machine, and boom mower which
needs a larger tractor. Cab would be for safety while operating the boom
mower. Utilize larger implements, such as aerification implement and bush INSERT PHOTO
hog.
Prior to Future
CAPITAL COST BREAKDOWN July 2019 2019-20 2020-21 2021-22 2022-23 2023-24 Years
Purchase $ - $ - $ 40,000 $ - $ - $ - $ -
Other - - - - - - -
Total Project Costs $ - $ - $ 40,000 $ - $ - $ - $ -
Prior to Future
FUNDING SOURCE(S) July 2019 2019-20 2020-21 2021-22 2022-23 2023-24 Years
General Fund $ - $ - $ - $ - $ - $ - $ -
Installment Purchase - - 40,000 - - - -
Total Funding Sources $ - $ - $ 40,000 $ - $ - $ - $ -
PRCR - 9
Strategic Goal 2 - Safe Connected Community LEVEL B
PROJECT DESCRIPTION
Aerification Machine
JUSTIFICATION
Purchasing this equipment would eliminate $12,000 annually that is paid to
a contractor to have this done one time each year. Our athletic fields need
this practice performed at least 3 times each year to promote water
drainage and root systems. This would cause fewer athletic program rain- INSERT PHOTO
outs, safer playing surfaces, and better field performance during dry
weather conditions.
Prior to Future
CAPITAL COST BREAKDOWN July 2019 2019-20 2020-21 2021-22 2022-23 2023-24 Years
Equipment $ - $ - $ 35,000 $ - $ - $ - $ -
Contingency - - - - - - -
Other - - - - - - -
Total Project Costs $ - $ - $ 35,000 $ - $ - $ - $ -
Prior to Future
FUNDING SOURCE(S) July 2019 2019-20 2020-21 2021-22 2022-23 2023-24 Years
General Fund $ - $ - $ - $ - $ - $ - $ -
Installment Purchase - - 35,000 - - - -
Total Funding Sources $ - $ - $ 35,000 $ - $ - $ - $ -
PRCR - 10
Strategic Goal 2 - Safe Connected Community LEVEL B
PROJECT DESCRIPTION
Irrigation is currently installed in the Walker and Performance Gardens. This
project would extend the irrigation in the turf portion of the amphitheater,
surround the restrooms, and the community center.
JUSTIFICATION
With the upcoming project at Joyner Park we anticipate a significant increase in
activity and visitors. Installing irrigation in the amphitheater will allow for
better aesthetics in summer months, but also allow for better maintenance,
giving us a better product to present to the public. This installation will allow
the turf to look great, regardless of the weather. INSERT PHOTO
*Picture on top is result of dry weather in the summer.
Prior to Future
CAPITAL COST BREAKDOWN July 2019 2019-20 2020-21 2021-22 2022-23 2023-24 Years
Construction $ - $ - $ - $ 45,000 $ - $ - $ -
Other - - - - - - -
Total Project Costs $ - $ - $ - $ 45,000 $ - $ - $ -
Prior to Future
FUNDING SOURCE(S) July 2019 2019-20 2020-21 2021-22 2022-23 2023-24 Years
General Fund $ - $ - $ - $ 45,000 $ - $ - $ -
- - - - - - -
Total Funding Sources $ - $ - $ - $ 45,000 $ - $ - $ -
PROJECT DESCRIPTION
Installation of concrete pads surrounding the backstop, connecting sidewalks to
bleachers and dugouts, installation of ADA bleacher sets, and metal dugouts.
JUSTIFICATION
This project is a step toward making our parks fully accessible and replace
wooden dugouts that are rotting. The concrete pads will provide an
aesthetically pleasing area for spectators, while keeping them out of dirt and
mud that currently surrounds the bleachers and scorer's tables.
INSERT PHOTO
Prior to Future
CAPITAL COST BREAKDOWN July 2019 2019-20 2020-21 2021-22 2022-23 2023-24 Years
Construction $ - $ - $ - $ 170,000 $ 80,000 $ - $ -
Other - - - - - - -
Total Project Costs $ - $ - $ - $ 170,000 $ 80,000 $ - $ -
Prior to Future
FUNDING SOURCE(S) July 2019 2019-20 2020-21 2021-22 2022-23 2023-24 Years
General Fund $ - $ - $ - $ 170,000 $ 80,000 $ - $ -
- - - - - - -
Total Funding Sources $ - $ - $ - $ 170,000 $ 80,000 $ - $ -
INSERT PHOTO
Prior to Future
CAPITAL COST BREAKDOWN July 2019 2019-20 2020-21 2021-22 2022-23 2023-24 Years
Planning & Engineering $ - $ - $ - $ - $ - $ - $ -
Construction - - - 400,000 - - -
Equipment - - - - - - -
Other - PAC 1% - - - 4,000 - - -
Total Project Costs $ - $ - $ - $ 404,000 $ - $ - $ -
Prior to Future
FUNDING SOURCE(S) July 2019 2019-20 2020-21 2021-22 2022-23 2023-24 Years
General Fund $ - $ - $ - $ - $ - $ - $ -
GO Bond - Future Referendum FY 2020 - - - 404,000 - - -
Total Funding Sources $ - $ - $ - $ 404,000 $ - $ - $ -
PRCR - 13
LEVEL B
PROJECT DESCRIPTION
Park Sidewalk Connections
JUSTIFICATION
Many of our park features are not connected to each or the street
sidewalk. This project aims to accomplish this task.
Prior to Future
CAPITAL COST BREAKDOWN July 2019 2019-20 2020-21 2021-22 2022-23 2023-24 Years
Purchase $ - $ - $ - $ - $ - $ - $ -
Construction - - - - 100,000 - -
Total Project Costs $ - $ - $ - $ - $ 100,000 $ - $ -
Prior to Future
FUNDING SOURCE(S) July 2019 2019-20 2020-21 2021-22 2022-23 2023-24 Years
General Fund $ - $ - $ - $ - $ - $ - $ -
Recreation Impact Fees - - - - 100,000 - -
Total Funding Sources $ - $ - $ - $ - $ 100,000 $ - $ -
PRCR -14
Strategic Goal 2 - Safe Connected Community LEVEL B
PROJECT DESCRIPTION
Complete 0.25 mile walking path around the perimeter of Tyler Run Park,
providing walking loop.
JUSTIFICATION
The department's master plan recommended that some parks could use better
circulation systems within them, particularly paved walkways and loop walks. INSERT PHOTO
This would accomplish that while adding to our greenway system.
Prior to Future
CAPITAL COST BREAKDOWN July 2019 2019-20 2020-21 2021-22 2022-23 2023-24 Years
Planning & Engineering $ - $ - $ - $ - $ - $ - $ -
Construction - - - - - 200,000 -
Other - - - - - - -
Total Project Costs $ - $ - $ - $ - $ - $ 200,000 $ -
Prior to Future
FUNDING SOURCE(S) July 2019 2019-20 2020-21 2021-22 2022-23 2023-24 Years
General Fund $ - $ - $ - $ - $ - $ - $ -
Recreation Impact Fees - - - - - 200,000 -
Total Funding Sources $ - $ - $ - $ - $ - $ 200,000 $ -
PRCR - 15
Strategic Goal 2 - Safe Connected Community LEVEL C
TOWN OF WAKE FOREST
CAPITAL IMPROVEMENTS PROGRAM
CIP UPDATE FY 2019-2024
PROJECT DESCRIPTION
As the Town's population continues to grow, this facility would serve citizens South of NC 98 across Capital
Blvd. The past two Master Plans have noted a lack of services in this area. Proposed uses include: community
center, playgrounds, picnic areas and trails.
Prior to Future
CAPITAL COST BREAKDOWN July 2019 2019-20 2020-21 2021-22 2022-23 2023-24 Years
Planning & Engineering $ - $ - $ - $ - $ - $ - 650,000
Construction - - - - - - $ 6,100,000
Contingency - - - - - - -
Other - PAC - - - - - - 67,500
Total Project Costs $ - $ - $ - $ - $ - $ - $ 6,817,500
Prior to Future
FUNDING SOURCE(S) July 2019 2019-20 2020-21 2021-22 2022-23 2023-24 Years
General Fund $ - $ - $ - $ - $ - $ - $ -
GO Bonds - Future Referendum FY 2020 - - - - - - 6,317,500
Grants - Future Application - PARTF - - - - - - 500,000
- - - - - - -
Total Funding Sources $ - $ - $ - $ - $ - $ - $ 6,817,500
PRCR - 16
Strategic Goal 2 - Safe Connected Community LEVEL B
PROJECT DESCRIPTION
Preliminary engineering, environmental, and construction to improve the facilities at Ailey Young Park. The
improvements will provide universal accessibility (including updated basketball courts, updated playground
and updated picnic shelter and amenities) and increase capacity for current uses (parking, expanded
bathrooms). Construction for Dunn Creek Greenway Phase 3 spur from Juniper Avenue to the baseball field is
also included in this project.
JUSTIFICATION
Implementation of the adopted Parks, Recreation & Cultural Resources and Open Space & Greenways Plans
for the Town of Wake Forest. Identify open space land where citizens can enjoy minamally improved amenities INSERT PHOTO
for active use. Such as: environmental study, primitive camping, non-motorized boating, hiking, mountain
biking, and equestrian trails. Other amenities include trailheads, educational/information kiosk, parking and
restrooms.
PRCR - 17
Strategic Goal 2 - Safe Connected Community LEVEL B
PROJECT DESCRIPTION
The department Master Plan was updated in 2015. As the Town continues to
grow the need to provide additional services for recreational opportunities will
continue to grow as well. Additional equipment will be needed to main the area
as well.
JUSTIFICATION
The 2015 Master Plan sited the need for facilities to be developed and
constructed, include appropriate spaces for wellness/fitness, INSERT PHOTO
cultural, special needs, and aquatic opportunities. . As the population increases
in the Town, the demand for additional parks and recreational facilities has also
increased, which makes the development of this park an essential project that is
critical to enhancing the quality of life for our citizens. Elements to be included
walking trails, nature center, bike trails, ropes course, dic-golf,
playground, restrooms and picnic shelters. Cost and equipmenet needed will be
adjusted once the master plan is completed.
Prior to Future
CAPITAL COST BREAKDOWN July 2019 2019-20 2020-21 2021-22 2022-23 2023-24 Years
Purchase $ - $ - $ - $ - $ - $ - $ 10,000,000
Equipment - - - - - - 90,000
Other - PAC 1% - - - - - - 100,000
Total Project Costs $ - $ - $ - $ - $ - $ - $ 10,190,000
Prior to Future
FUNDING SOURCE(S) July 2019 2019-20 2020-21 2021-22 2022-23 2023-24 Years
General Fund $ - $ - $ - $ - $ - $ - $ -
GO Bonds - Future Referendum FY 2024 - - - - - - 10,100,000
Installment Purchase - - - - - - 90,000
Total Funding Sources $ - $ - $ - $ - $ - $ - $ 10,190,000
PRCR -18
Strategic Goal 2 - Safe Connected Community LEVEL B
PROJECT DESCRIPTION
Add permanent restrooms to parks.
JUSTIFICATION
Currently several of our parks do not have restrooms. We are using port-
a-johns which are not ADA accessible. Adding permanent restroom
facilities would meet these requirements, permanent restrooms would be
more sanitary and cost efficient over time. INSERT PHOTO
Locations: Rank
1. Smith Creek
2. Tyler Run Park
3. Miller Park
4. Ailey Young
5. Flaherty Tennis Courts
Prior to Future
CAPITAL COST BREAKDOWN July 2019 2019-20 2020-21 2021-22 2022-23 2023-24 Years
Equipment $ - $ - $ - $ - $ - $ - $ 1,200,000
Other - PAC 1% - - - - - - 12,000
Total Project Costs $ - $ - $ - $ - $ - $ - $ 1,212,000
Prior to Future
FUNDING SOURCE(S) July 2019 2019-20 2020-21 2021-22 2022-23 2023-24 Years
General Fund $ - $ - $ - $ - $ - $ - $ -
GO Bonds - Bond Referendum FY 2020 - - - - - - 1,212,000
Total Funding Sources $ - $ - $ - $ - $ - $ - $ 1,212,000
PRCR -19
Strategic Goal 2 - Safe Connected Community LEVEL B
TOWN OF WAKE FOREST
CAPITAL IMPROVEMENTS PROGRAM
CIP UPDATE FY 2019-2024
PROJECT DESCRIPTION
The Town has completed the Master Plan for the development of this 118 acre park. Phase II includes the
community center, playground and cover over the amphitheater which is scheduled to be completed in 2019.
Phase III
Phase III will complete the development of the park. Additional office space, shelter enclosure, parking and
equipment will be added: Truck, Two mowers, utility vehicle, drag machine, and sprayer.
JUSTIFICATION
Joyner Park serves as the metro park for the western quadrant. As the population increases in the Town, the
Insert image
demand for additional parks and recreational facilities has also increased, which makes the development of
this park an essential project that is critical to enhancing the quality of life for our citizens. The amphitheater is
a vital part of this park. It is currently used for concerts, weddings and other family functions. It is, however,
not used to it's full potential due to the lack of a cover. During the Six Sunday's Concert Series the performers
request to be moved due to the heat. They have also voiced concerns about the damage to instruments due to
the heat. The cover would greatly enhance the potential usage of the facility. In addition, equipment will be
needed to maintain the area as Phase III is built.
Prior to Future
CAPITAL COST BREAKDOWN July 2019 2019-20 2020-21 2021-22 2022-23 2023-24 Years
Planning & Engineering $ - $ - $ - $ - $ - $ - $ 1,023,300
Purchase - - - - - - 215,000
Construction - - - - - - 9,353,500
Contingency - - - - - - -
Other - PAC - - - - - - 103,800
Total Project Costs $ - $ - $ - $ - $ - $ - $ 10,695,600
Prior to Future
FUNDING SOURCE(S) July 2019 2019-20 2020-21 2021-22 2022-23 2023-24 Years
General Fund $ - $ - $ - $ - $ - $ - $ 127,100
Installment Purchase - - - - - - 215,000
GO Bonds - Future Referendum FY 2024 - - - - - - 9,853,500
Capital Reserve - Impact Fees - - - - - - 500,000
Total Funding Sources $ - $ - $ - $ - $ - $ - $ 10,695,600
PRCR - 20
Capital Improvement Plan
ENVIRONMENTAL SERVICES SUMMARY - BY PROJECT
Insert image
Prior to Future
CAPITAL COST BREAKDOWN July 2019 2019-20 2020-21 2021-22 2022-23 2023-24 Years
Planning & Engineering $ 65,600 $ 125,000 $ 125,000 $ 125,000 $ - $ - $ -
Purchase - - - - - -
Construction - - 500,000 500,000 - - 2,000,000
Equipment - - - - - - -
Contingency - - - - - - -
Other - - - - - - -
Total Project Costs $ 65,600 $ 125,000 $ 625,000 $ 625,000 $ - $ -
Prior to Future
FUNDING SOURCE(S) July 2019 2019-20 2020-21 2021-22 2022-23 2023-24 Years
General Fund $ 65,600 $ 125,000 $ 125,000 $ 125,000 $ - $ - $ -
GO Bonds - Future Referendum FY 2020 - - 500,000 500,000 - - -
GO Bonds - Future Referendum FY 2024 - - - - - - 2,000,000
Grants - - - - - -
- - - - - - -
- - - - - -
Total Funding Sources $ 65,600 $ 125,000 $ 625,000 $ 625,000 $ - $ - $ 2,000,000
ES - 1
LEVEL B
JUSTIFICATION
Due to the continued growth, these trucks will be needed in order
to provide the service level expected of our residents.
Prior to Future
CAPITAL COST BREAKDOWN July 2019 2019-20 2020-21 2021-22 2022-23 2023-2024 Years
Purchase $ - $ - $ 200,000 $ - $ 205,000 $ - $ -
Other - - - - - - -
Total Project Costs $ - $ - $ 200,000 $ - $ 205,000 $ - $ -
Prior to Future
FUNDING SOURCE(S) July 2019 2019-20 2020-21 2021-22 2022-23 2023-2024 Years
General Fund $ - $ - $ - $ - $ - $ - $ -
Installment Purchase - - 200,000 - 205,000 - -
- - - - - - -
Total Funding Sources $ - $ - $ 200,000 $ - $ 205,000 $ - $ -
ES - 2
Capital Improvement Plan
FLEET SUMMARY - BY PROJECT
INSERT PHOTO
Prior to Future
CAPITAL COST BREAKDOWN July 2019 2019-20 2020-21 2021-22 2022-23 2023-24 Years
Equipment $ - $ - $ 155,000 $ - $ - $ -
Contingency - - - - - - -
Total Project Costs $ - $ - $ - $ 155,000 $ - $ - $ -
Prior to Future
FUNDING SOURCE(S) July 2019 2019-20 2020-21 2021-22 2022-23 2023-24 Years
General Fund $ - $ - $ - $ 155,000 $ - $ - $ -
- - - - - - -
Total Funding Sources $ - $ - $ - $ 155,000 $ - $ - $ -
FM - 1
LEVEL B
TOWN OF WAKE FOREST
CAPITAL IMPROVEMENTS PROGRAM
CIP UPDATE FY 2019-2024
PROJECT DESCRIPTION
Current work order system to track and monitor fleet maintenance within all Town
Departments.
JUSTIFICATION
Current software is outdated and may become incapatable with current practices. Insert image
Prior to Future
CAPITAL COST BREAKDOWN July 2019 2019-20 2020-21 2021-22 2022-23 2023-24 Years
Purchase $ - $ - $ - $ - $ 90,000 $ - $ -
Other - - - - - - -
Total Project Costs $ - $ - $ - $ - $ 90,000 $ - $ -
Prior to Future
FUNDING SOURCE(S) July 2019 2019-20 2020-21 2021-22 2022-23 2023-24 Years
General Fund $ - $ - $ - $ - $ 90,000 $ - $ -
- - - - - - -
Total Funding Sources $ - $ - $ - $ - $ 90,000 $ - $ -
FM - 2
Capital Improvement Plan
STREETS SUMMARY - BY PROJECT
PROJECT DESCRIPTION
Lighting Town roadways according to NCDOT and ASHTO standards.
JUSTIFICATION
For the safety of our citizens as well as the traveling public, it would be advisable to light the
roadways of Wake Forest. This project is for lighting along town owned roads not in the Wake
Power service district. It is general policy of the Town to light all streets within Town limits.
Other areas for lighting include but are not limited to: NO IMAGE AVAILABLE
1) Jones Dairy Rd. - from NC 98 ByPass to Friendship Chapel Rd. (Wake Forest Power & Wake
Electric).
Also included is changing out existing HPS fixtures with LED Fixtures in areas around Town.
Prior to Future
CAPITAL COST BREAKDOWN July 2019 2019-20 2020-21 2021-22 2022-23 2023-24 Years
Planning & Engineering $ - $ - $ - $ - $ - $ - $ -
Construction - 50,000 50,000 50,000 - - -
Other - - - - - - -
Total Project Costs $ - $ 50,000 $ 50,000 $ 50,000 $ - $ - $ -
Prior to Future
FUNDING SOURCE(S) July 2019 2019-20 2020-21 2021-22 2022-23 2023-24 Years
General Fund $ - $ - $ - $ - $ - $ - $ -
Electric Fund - 50,000 50,000 50,000 - - -
Total Funding Sources $ - $ 50,000 $ 50,000 $ 50,000 $ - $ - $ -
S-1
LEVEL B
TOWN OF WAKE FOREST
CAPITAL IMPROVEMENTS PROGRAM
CIP UPDATE FY 2019 - 2024
PROJECT DESCRIPTION
Continued construction of approved sidewalk plan.
JUSTIFICATION
Construction of sidewalks is consistent with town policy and is mandated by the
Zoning Ordinance for new development. The amounts reflect todays costs as
identified in the transportation plan. Originally set to begin in FY2017-18, through
2020-21, expanded thru 2023-24 to reflect consistent growth throughout the Town.
NO IMAGE AVAILABLE
PRIORITIES
Durham Road- Capital to North Wingate
North White Street- Roosevelt to Flaherty
North Avenue- Start to End
Roosevelt- Front Street to Wait Ave
Rogers Road- Forestville to South Main
Prior to Future
CAPITAL COST BREAKDOWN July 2019 2019-20 2020-21 2021-22 2022-23 2023-24 Years
Planning & Engineering $ 5,000 $ 5,000 $ 5,000 $ 5,000 $ 5,000 $ 5,000 $ -
Construction 75,000 95,000 95,000 95,000 95,000 95,000 -
Other - - - - - - -
Total Project Costs $ 80,000 $ 100,000 $ 100,000 $ 100,000 $ 100,000 $ 100,000 $ -
Prior to Future
FUNDING SOURCE(S) July 2019 2019-20 2020-21 2021-22 2022-23 2023-24 Years
General Fund $ 80,000 $ 100,000 $ 100,000 $ 100,000 $ 100,000 $ 100,000 $ -
- - - - - - -
Total Funding Sources $ 80,000 $ 100,000 $ 100,000 $ 100,000 $ 100,000 $ 100,000 $ -
S-2
LEVEL B
TOWN OF WAKE FOREST
CAPITAL IMPROVEMENTS PROGRAM
CIP UPDATE FY 2019-2024
PROJECT DESCRIPTION
Single Axle Dump Truck -Addition
JUSTIFICATION
The purchase of this dump truck will allow the crews within the Streets Division to
each have access to a dump truck instead of waiting for one to become available.
As major projects continue to come on line, the division will be better prepared to
perform these projects and to work more efficiently. Insert image
The purchase of this truck may need to be moved up in the CIP process according to
workloads. Currently set for FY 2020-21.
Prior to Future
CAPITAL COST BREAKDOWN July 2019 2019-20 2020-21 2021-22 2022-23 2023-24 Years
Purchase $ - $ - $ 215,000 $ - $ - $ - $ -
Other - - - - - - -
Total Project Costs $ - $ - $ 215,000 $ - $ - $ - $ -
Prior to Future
FUNDING SOURCE(S) July 2019 2019-20 2020-21 2021-22 2022-23 2023-24 Years
General Fund $ - $ - $ - $ - $ - $ - $ -
Installment Purchase - - 215,000 - - - -
Total Funding Sources $ - $ - $ 215,000 $ - $ - $ - $ -
S-3
LEVEL B
TOWN OF WAKE FOREST
CAPITAL IMPROVEMENTS PROGRAM
CIP UPDATE FY 2019-2024
PROJECT DESCRIPTION
Hot Patch Machine
JUSTIFICATION
The purchase of this machine will allow Town
Street Crews to perform more complexpatching
operations. As major projects come forward,
the Division will be better prepared to perform
this work more efficiently. Insert image
Prior to Future
CAPITAL COST BREAKDOWN July 2019 2019-20 2020-21 2021-22 2022-23 2023-2024 Years
Purchase $ - $ - $ - $ 250,000 $ - $ - $ -
Other - - - - - - -
Total Project Costs $ - $ - $ - $ 250,000 $ - $ - $ -
Prior to Future
FUNDING SOURCE(S) July 2019 2019-20 2020-21 2021-22 2022-23 2023-2024 Years
General Fund $ - $ - $ - $ - $ - $ - $ -
Installment Purchase - - - 250,000 - - -
Total Funding Sources $ - $ - $ - $ 250,000 $ - $ - $ -
S-4
LEVEL B
TOWN OF WAKE FOREST
CAPITAL IMPROVEMENTS PROGRAM
CIP UPDATE FY 2019-2024
PROJECT DESCRIPTION
Asphalt Paving Machine
JUSTIFICATION
The purchase of this machine will allow Town
Street Crews to perform more complex paving
operations and also allow for Greenway
maintenance, repair and construction. As major
projects come forward, the Division will be Insert image
better prepared to perform this work more
efficiently.
Prior to Future
CAPITAL COST BREAKDOWN July 2019 2019-20 2020-21 2021-22 2022-23 2023-2024 Years
Purchase $ - $ - $ - $ - $ - $ - $ 260,000
Other - - - - - - -
Total Project Costs $ - $ - $ - $ - $ - $ - $ 260,000
Prior to Future
FUNDING SOURCE(S) July 2019 2019-20 2020-21 2021-22 2022-23 2023-2024 Years
General Fund $ - $ - $ - $ - $ - $ - $ -
Installment Purchase - - - - - - 260,000
Total Funding Sources $ - $ - $ - $ - $ - $ - $ 260,000
S-5
Capital Improvement Plan
ELECTRIC SUMMARY - BY PROJECT
PROJECT DESCRIPTION
New Electric Division Building including building remodel and construction retrofitting
JUSTIFICATION
The town contracted with an architectural firm to do a space analysis for Public Works. The
findings were a recommended building costing $32 million. To save money, an existing Insert image
warehouse was purchased for $3.2 million that would result in Public Works and Electric
operating out of two buildings, rather than six and four addresses. The project will include
construction documents, construction, technology, furniture and contingency funds.
Prior to Future
CAPITAL COST BREAKDOWN July 2019 2019-20 2020-21 2021-22 2022-23 2023-24 Years
Planning & Engineering $ 60,000 $ 500,000 $ 500,000 $ - $ - $ - $ -
Purchase - - - - - - -
Construction 340,000 - - - - - -
Equipment - - - - - - -
Contingency - - - - - - -
Other - - - - - - -
Total Project Costs $ 400,000 $ 500,000 $ 500,000 $ - $ - $ - $ -
Prior to Future
FUNDING SOURCE(S) July 2019 2019-20 2020-21 2021-22 2022-23 2023-24 Years
Installment Purchase $ 400,000 $ - $ - $ - $ - $ - $ -
Electric Fund - 500,000 500,000 - - - -
Total Funding Sources $ 400,000 $ 500,000 $ 500,000 $ - $ - $ - $ -
E-1
LEVEL B
TOWN OF WAKE FOREST
CAPITAL IMPROVEMENTS PROGRAM
CIP UPDATE FY 2019-2024
PROJECT DESCRIPTION
Provide funds to extend and upgrade the Electrical Distribution System.
JUSTIFICATION
Current economic conditions have begun to show improvement in new multi-family residential and
commercial loads that require service which our distribution sytem will need to be prepared for. Upgrades
Insert image
on existing distribution system in the older sections of the system need attention and extension of service
to new development will still be required. The amount budgeted varies from year to year and is adjusted
accordingly during the annual budget process contingent upon what projects (commercial or residential)
are projected for the upcoming year.
Prior to Future
CAPITAL COST BREAKDOWN July 2019 2019-20 2020-21 2021-22 2022-23 2023-24 Years
Planning & Engineering $ 50,000 $ 100,000 $ 100,000 $ 100,000 $ 100,000 $ 100,000 $ -
Purchase - - - - - - -
Construction 750,000 1,000,000 1,100,000 1,200,000 1,300,000 1,300,000 -
Total Project Costs $ 800,000 $ 1,100,000 $ 1,200,000 $ 1,300,000 $ 1,400,000 $ 1,400,000 $ -
Prior to Future
FUNDING SOURCE(S) July 2019 2019-20 2020-21 2021-22 2022-23 2023-24 Years
Electric User Fees/Other Revenues $ 800,000 $ 1,100,000 $ 1,200,000 $ 1,300,000 $ 1,400,000 $ 1,400,000 $ -
- - - - - - -
Total Funding Sources $ 800,000 $ 1,100,000 $ 1,200,000 $ 1,300,000 $ 1,400,000 $ 1,400,000 $ -
E-2
LEVEL A
TOWN OF WAKE FOREST
CAPITAL IMPROVEMENTS PROGRAM
CIP UPDATE FY 2019-2024
PROJECT DESCRIPTION
Convert the Town's street lights from high pressure sodium to energy efficient LED.
JUSTIFICATION
LED's are more energy efficient than traditional bulbs saving on energy costs. The LED's last longer which
saves money in manpower. The Town has also commited to having all street lights changed to LED by
2024.
Prior to Future
CAPITAL COST BREAKDOWN July 2019 2019-20 2020-21 2021-22 2022-23 2023-24 Years
Planning & Engineering $ - $ - $ - $ - $ - $ - $ -
Purchase - - 312,500 - 312,500 -
Construction - - - - - - -
Equipment - - - - - - -
Contingency - - - - - - -
Other - - - - - - -
Total Project Costs $ - $ - $ 312,500 $ - $ 312,500 $ - $ -
Prior to Future
FUNDING SOURCE(S) July 2019 2019-20 2020-21 2021-22 2022-23 2023-24 Years
General Fund $ - $ - $ - $ - $ - $ - $ -
Electric User Fees & Other Revenues - - 312,500 - 312,500 - -
Total Funding Sources $ - $ - $ 312,500 $ - $ 312,500 $ - $ -
E-3
LEVEL B
TOWN OF WAKE FOREST
CAPITAL IMPROVEMENTS PROGRAM
CIP UPDATE FY 2019-2024
PROJECT DESCRIPTION
Replacement of existing test equipment due to age and technology changes.
JUSTIFICATION
This test board will be replacing the existing test board and be installed in the new Meter Shop in the
proposed new Operation Center. Due to constant changes in technology, we hope to have the most up Insert image
to date equipment available to perform the required testing of our meters.
Prior to Future
CAPITAL COST BREAKDOWN July 2019 2019-20 2020-21 2021-22 2022-23 2023-24 Years
Purchase $ - $ - $ - $ - $ - $ - $ -
Equipment - - 90,000 - - - -
Total Project Costs $ - $ - $ 90,000 $ - $ - $ - $ -
Prior to Future
FUNDING SOURCE(S) July 2019 2019-20 2020-21 2021-22 2022-23 2023-24 Years
Electric User Fees & Other Revenues $ - $ - $ 90,000 $ - $ - $ - $ -
- - - - - - -
Total Funding Sources $ - $ - $ 90,000 $ - $ - $ - $ -
E-4
LEVEL B
TOWN OF WAKE FOREST
CAPITAL IMPROVEMENTS PROGRAM
CIP UPDATE FY 2019-2024
PROJECT DESCRIPTION
New Back Property Digger Derrick
JUSTIFICATION
This machine allows for easy, safe access into back property easements.
Allowing for maintenance and repair with minimal impact on residents
yards and faster restoration time after storms.
Prior to Future
CAPITAL COST BREAKDOWN July 2019 2019-20 2020-21 2021-22 2022-23 2023-24 Years
Purchase $ - $ - $ - $ 165,000 $ - $ - $ -
Other - - - - - - -
Total Project Costs $ - $ - $ - $ 165,000 $ - $ - $ -
Prior to Future
FUNDING SOURCE(S) July 2019 2019-20 2020-21 2021-22 2022-23 2023-24 Years
Electric User Fees & Other Revenues $ - $ - $ - $ - $ - $ - $ -
Installment Purchase - - - 165,000 - - -
Total Funding Sources $ - $ - $ - $ 165,000 $ - $ - $ -
E-5
LEVEL B
TOWN OF WAKE FOREST
CAPITAL IMPROVEMENTS PROGRAM
CIP UPDATE FY 2019-2024
PROJECT DESCRIPTION
PIck-Up Truck- Additional Vechicle
JUSTIFICATION
With future growth of the town expected, both residentialy and commercialy, new employess will be
needed to meet the work load. Any new crews to the town will need a work vechicle. Insert image
Prior to Future
CAPITAL COST BREAKDOWN July 2019 2019-20 2020-21 2021-22 2022-23 2023-24 Years
Purchase $ - $ - $ - $ - $ 75,000 $ - $ -
Other - - - - - - -
Total Project Costs $ - $ - $ - $ - $ 75,000 $ - $ -
Prior to Future
FUNDING SOURCE(S) July 2019 2019-20 2020-21 2021-22 2022-23 2023-24 Years
Electric User Fees & Other Revenues $ - $ - $ - $ - $ - $ - $ -
Installment Purchase - - - - 75,000 - -
Total Funding Sources $ - $ - $ - $ - $ 75,000 $ - $ -
E-6
Capital Improvement Plan
ASSET MAINTENANCE SUMMARY - BY PROJECT
Note 1: The November 2014 approved bond referendum included $4.6M of funds allocated for Greenway Improvements. Projects that have been completely funded are not reported in this update. The remaining projects
include: 1) Wake Forest Reservoir Improvements
LEVEL B
TOWN OF WAKE FOREST
CAPITAL IMPROVEMENTS PROGRAM
CIP UPDATE FY 2019 - 2024
PROJECT DESCRIPTION
Continued construction of approved sidewalk plan to replace
deteriorated, broken and/or uneven sidewalks which can create
tripping hazards. To be done on an area by area basis.
JUSTIFICATION
Construction of sidewalks is consistent with town policy and is NO IMAGE AVAILABLE
mandated by the zoning ordinance for new development.
Prior to Future
CAPITAL COST BREAKDOWN July 2019 2019-20 2020-21 2021-22 2022-23 2023-24 Years
Planning & Engineering $ - $ - $ - $ - $ - $ - $ -
Construction - 100,000 100,000 100,000 100,000 100,000 -
Contingency - - - - - - -
Other - - - - - - -
Total Project Costs $ - $ 100,000 $ 100,000 $ 100,000 $ 100,000 $ 100,000 $ -
Prior to Future
FUNDING SOURCE(S) July 2019 2019-20 2020-21 2021-22 2022-23 2023-24 Years
General Fund $ - $ 100,000 $ 100,000 $ 100,000 $ 100,000 $ 100,000 $ -
- - - - - - -
Total Funding Sources $ - $ 100,000 $ 100,000 $ 100,000 $ 100,000 $ 100,000 $ -
AM - 1
LEVEL B
PROJECT DESCRIPTION
Pavement rehabilitation and maintenance of accepted roadways owned and maintained by the Town of
Wake Forest. Work to be conducted by outside contractor.
JUSTIFICATION
Maintenance projects as identified in the 2014 Summit Design pavement analysis report, ranked based on Insert image
need/prioritization. The last analysis was performed in 2000. In FY 2017-2018, $2.4 million was used to
complete several reconnections along with resurfacing/rehabilitating streets identified in report. With the
number of town owned streets added over the years, this is an ongoing project. Staff is recommending
to allocate a portion of 2020 Bond referendum for additional street resurfacing and maintenance.
Prior to Future
CAPITAL COST BREAKDOWN July 2019 2019-20 2020-21 2021-22 2022-23 2023-24 Years
Planning & Engineering $ 375,000 $ 100,000 $ - - $ 50,000 $ 50,000 $ -
Construction 2,269,530 - 500,000 1,500,000 835,000 835,000 -
Contingency - - - - - - -
Total Project Costs $ 2,644,530 $ 100,000 $ 500,000 $ 1,500,000 $ 885,000 $ 885,000 $ -
Prior to Future
FUNDING SOURCE(S) July 2019 2019-20 2020-21 2021-22 2022-23 2023-24 Years
General Fund $ 244,530 $ 100,000 $ - $ - $ - $ - $ -
Installment Purchase 2,400,000 - - - - - -
GO Bonds - Future Referendum FY 2020 - - 500,000 1,500,000 - - -
Powell Bill - - - - 885,000 885,000 -
Total Funding Sources $ 2,644,530 $ 100,000 $ 500,000 $ 1,500,000 $ 885,000 $ 885,000 $ -
AM - 2
LEVEL B
PROJECT DESCRIPTION
Continual maintenance of Town owned and maintained stormwater infrastructure by
the Town of Wake Forest. Work to be conducted by both Town staff and outside
contractor. Specific areas will be identified as operating budget is prepared.
Insert image
JUSTIFICATION
Maintenance projects as identified by Town staff as stormwater infrastructure
continues to age.
Prior to Future
CAPITAL COST BREAKDOWN July 2019 2019-20 2020-21 2021-22 2022-23 2023-24 Years
Planning & Engineering $ - $ 10,000 $ 10,000 $ 10,000 $ 10,000 $ 10,000 $ -
Purchase - - - - - - -
Construction 90,000 290,000 290,000 290,000 290,000 290,000 600,000
Total Project Costs $ 90,000 $ 300,000 $ 300,000 $ 300,000 $ 300,000 $ 300,000 $ 600,000
Prior to Future
FUNDING SOURCE(S) July 2019 2019-20 2020-21 2021-22 2022-23 2023-24 Years
General Fund $ 90,000 $ 300,000 $ 300,000 $ 300,000 $ 300,000 $ 300,000 $ 600,000
- - - - - - -
Total Funding Sources $ 90,000 $ 300,000 $ 300,000 $ 300,000 $ 300,000 $ 300,000 $ 600,000
AM - 3
LEVEL A
TOWN OF WAKE FOREST
CAPITAL IMPROVEMENTS PROGRAM
CIP UPDATE FY 2019-2024
PROJECT DESCRIPTION
1. Replace Eaton Lighting controls with Enlightened Lighting Controls.
2. Replace Carpet FY2021
3. Space reconfiguration
4. AHU replacement FY2025, Chiller Replacement FY2030, and VAV Box Replacement FY2030
5. JUSTIFICATION
As Town Hall ages, needs arise for upkeep and maintenance of several areas such as lighting and
carpet. The lighting controls are now obsolete and some parts can not be ordered for repairs. Parts
are not being made by Eaton or any other after-market company. Over the past several years the
town has continued to evolve and grow, which has necessitated additional staff and office space. This
provides funding for small reconfigurations as the need arises. Insert image
Prior to Future
CAPITAL COST BREAKDOWN July 2019 2019-20 2020-21 2021-22 2022-23 2023-24 Years
Purchase 70,000 100,000 100,000 175,000 100,000 100,000 230,000
Equipment - - - - - - -
Other - - - - - - -
Total Project Costs $ 70,000 $ 100,000 $ 100,000 $ 175,000 $ 100,000 $ 100,000 $ 230,000
Prior to Future
FUNDING SOURCE(S) July 2019 2019-20 2020-21 2021-22 2022-23 2023-24 Years
General Fund $ 70,000 $ 100,000 $ 100,000 $ 175,000 $ 100,000 $ 100,000 $ 230,000
- - - - - - -
Total Funding Sources $ 70,000 $ 100,000 $ 100,000 $ 175,000 $ 100,000 $ 100,000 $ 230,000
AM - 4
Strategic Goal 2 - Safe Connected Community LEVEL B
PROJECT DESCRIPTION
Repair low areas in the outfield of Forrest Field.
JUSTIFICATION
Approximately 0.25 acres of the playing surface at Forrest Field remains
constantly wet because of drainage issues. They have recently gotten worse
because of the conditions of the slopes caused by the ramp that leads to Wake INSERT PHOTO
Forest Elementary School.
Prior to Future
CAPITAL COST BREAKDOWN July 2019 2019-20 2020-21 2021-22 2022-23 2023-24 Years
Planning & Engineering $ - $ 60,000 $ - $ - $ - $ - $ -
Other - - - - - -
Total Project Costs $ - $ - $ - $ - $ - $ - $ -
Prior to Future
FUNDING SOURCE(S) July 2019 2019-20 2020-21 2021-22 2022-23 2023-24 Years
General Fund $ - $ 60,000 $ - $ - $ - $ - $ -
- - - - - - -
Total Funding Sources $ - $ - $ - $ - $ - $ - $ -
AM - 5
LEVEL B
PROJECT DESCRIPTION
Athletic Court Reconstruction
JUSTIFICATION
Re-surfacing courts should be on a 5-year cycle. Reconstruction should be on a 10-year cycle. The courts
in the first phase of this project will be 15 years old.
INSERT PHOTO
Athletic Courts Construction:
Dubois Baketball Courts(19-20) -$85,000
Flaherty Tennis Courts 1-4 (20-21) - $185,000
Flaherty Tennis Courts 5-8 (21-22) - $185,000
Holding Park basketball - $40,000
Prior to Future
CAPITAL COST BREAKDOWN July 2019 2019-20 2020-21 2021-22 2022-23 2023-24 Years
Construction - 85,000 185,000 185,000 - - 40,000
Other - - - - - -
Total Project Costs $ - $ 85,000 $ 185,000 $ 185,000 $ - $ - $ 40,000
Prior to Future
FUNDING SOURCE(S) July 2019 2019-20 2020-21 2021-22 2022-23 2023-24 Years
General Fund $ - $ 85,000 $ 185,000 $ 185,000 $ - $ - $ 40,000
Total Funding Sources $ - $ 85,000 $ 185,000 $ 185,000 $ - $ - $ 40,000
AM - 6
LEVEL B
TOWN OF WAKE FOREST
CAPITAL IMPROVEMENTS PROGRAM
CIP UPDATE FY 2019-2024
PROJECT DESCRIPTION
Replacement plan/program of fencing at athletic fields.
JUSTIFICATION
The current fencing is showing signs of wear, and repairs can be more time-consuming and costly that
replacement. The goal of the department is to upgrade and replace fencing systematically before it Insert image
becomes a safety hazard that may cause fields to be deemed unsafe/unplayable.
Prior to Future
CAPITAL COST BREAKDOWN July 2019 2019-20 2020-21 2021-22 2022-23 2023-24 Years
Purchase $ - $ 150,000 $ 150,000 $ - $ - $ - $ -
Other - - - - - - -
Total Project Costs $ - $ 150,000 $ 150,000 $ - $ - $ - $ -
Prior to Future
FUNDING SOURCE(S) July 2019 2019-20 2020-21 2021-22 2022-23 2023-24 Years
General Fund $ - $ 150,000 $ 150,000 $ - $ - $ - $ -
Total Funding Sources $ - $ 150,000 $ 150,000 $ - $ - $ - $ -
AM - 7
LEVEL B
TOWN OF WAKE FOREST
CAPITAL IMPROVEMENTS PROGRAM
CIP UPDATE FY 2019-2024
PROJECT DESCRIPTION
1. Replace metal roof only at Police Department at 225 S. Taylor Street FY2019-2020.
2. Replace HVAC, Exhaust Fans, and TPO Roof FY2031-2032.
JUSTIFICATION
The metal roof has been leaking. Staff has searched for the leaks, in addition to two independent Insert image
vendors and the leaks can't be found. Staff has made attempts to seal the joints and other areas,
however, the leaks have continued. THe TPO Roof, exhaust fans, and HVAC equipment will be at
the end of their life expectancy FY2031-2032.
Prior to Future
CAPITAL COST BREAKDOWN July 2019 2019-20 2020-21 2021-22 2022-23 2023-24 Years
Planning & Engineering $ - $ - $ - $ - $ - $ - $ -
Purchase - - - - - - 55,000
Construction - 50,000 - - - - 100,000
Total Project Costs $ - $ 50,000 $ - $ - $ - $ - $ 155,000
Prior to Future
FUNDING SOURCE(S) July 2019 2019-20 2020-21 2021-22 2022-23 2023-24 Years
General Fund $ - $ 50,000 $ - $ - $ - $ - $ 155,000
- - - - - - -
Total Funding Sources $ - $ 50,000 $ - $ - $ - $ - $ 155,000
AM - 8
Strategic Goal 2 - Safe Connected Community LEVEL B
TOWN OF WAKE FOREST
CAPITAL IMPROVEMENTS PROGRAM
CIP UPDATE FY 2019-2024
PROJECT DESCRIPTION
Update existing audio visual, camera and sound system in the Board chambers for televising
meetings.
JUSTIFICATION
Existing system is nine (9) years old. Some of the components were actually brought over from
the old town hall and incorporated. Three cameras have gone down and have been replaced in
current fiscal year. Phase I of the upgrade was pushed out to FY 2018-2019 and is scheduled to
be completed sometime in February or March.
Prior to Future
CAPITAL COST BREAKDOWN July 2019 2019-20 2020-21 2021-22 2022-23 2023-24 Years
Equipment $ 113,200 $ - $ 31,500 $ 52,000 $ - $ - $ 50,000
Other (Installation) - - 15,500 13,500 - - 15,000
Total Project Costs $ 113,200 $ - $ 47,000 $ 65,500 $ - $ - $ 65,000
Prior to Future
FUNDING SOURCE(S) July 2019 2019-20 2020-21 2021-22 2022-23 2023-24 Years
General Fund $ 113,200 $ - $ 47,000 $ 65,500 $ - $ - $ 65,000
Total Funding Sources $ 113,200 $ - $ 47,000 $ 65,500 $ - $ - $ 65,000
AM - 9
Strategic Goal 2 - Safe Connected Community LEVEL B
PROJECT DESCRIPTION
Replace engineered wood fiber playground surface with pour-in-place surface for accessibility
and ease of maintenance.
JUSTIFICATION
This is another step to making our parks ADA accessible this will also decrease maintenance
needs and cost. Also adding a couple of ADA accessbile features, as the existing ones are not.
INSERT PHOTO
Prior to Future
CAPITAL COST BREAKDOWN July 2019 2019-20 2020-21 2021-22 2022-23 2023-24 Years
Planning & Engineering $ - $ - $ - $ - $ - $ - $ -
Construction - - - 125,000 100,000 75,000 -
Other - - - - - - -
Total Project Costs $ - $ - $ - $ 125,000 $ 100,000 $ 75,000 $ -
Prior to Future
FUNDING SOURCE(S) July 2019 2019-20 2020-21 2021-22 2022-23 2023-24 Years
General Fund $ - $ - $ - $ 125,000 $ 100,000 $ 75,000 $ -
Installment Purchase - - - - - - -
Total Funding Sources $ - $ - $ - $ 125,000 $ 100,000 $ 75,000 $ -
PROJECT DESCRIPTION
Rehab of Wake Forest Reservoir property with paved parking, new boat ramp,
dock, new bridge, continuation of soft trail on east side, two additional bridges,
facilites, and consession amenities.
Prior to Future
CAPITAL COST BREAKDOWN July 2019 2019-20 2020-21 2021-22 2022-23 2023-24 Years
Planning & Engineering $ 292,000 $ - $ - $ 380,000 $ - $ - $ 250,000
Purchase - - - - - - -
Construction* - - - - 1,900,000 515,000 1,100,000
Contingency - - - - - - -
Other- Public Art - - - 3,800 19,000 5,200 13,500
Total Project Costs $ 292,000 $ - $ - $ 383,800 $ 1,919,000 $ 520,200 $ 1,363,500
Prior to Future
FUNDING SOURCE(S) July 2019 2019-20 2020-21 2021-22 2022-23 2023-24 Years
General Fund $ - $ - $ - $ 3,800 $ 19,000 $ 5,200 $ 13,500
GO Bond - Current Referendum - Issued 292,000 - - - - - -
GO Bond - Future Referendum FY 2020 - - - 380,000 190,000 515,000 850,000
Grants - PARTF - Future Application - - - - - - 500,000
Other - City of Raleigh - Cost Share 50/50 - - - - 475,000 - -
WINN Act Grant (future application)-65/35 * - - - - 1,235,000 - -
Total Funding Sources $ 292,000 $ - $ - $ 383,800 $ 1,919,000 $ 520,200 $ 1,363,500
AM - 11
LEVEL A
PROJECT DESCRIPTION
Relocate and replace failing stormwater pipe and box between North
Main St., N. College St. and N. Wingate St. Upgrade existing boxes on
North Main Street (US1A) to current standards with hood and grade,
re granite curb as needed, and resurface street to minimize flooding.
JUSTIFICATION
Pipe failure located at 527 North Main has caused sinkhole near Phase 1
corner of home. North Main Street (US 1A) in both the northbound
and southbound lanes are in need of repair from Oak Ave to Roosevelt
Ave. After multiple NCDOT resurfacings, the additional asphalt has Insert image
created a safety hazard to motorists, pedestrians and bicyclists by
having only 1-2" of reveal on the existing granite curb in lieu of 4-6". In
addition, the outdated stormwater boxes have lost thier capacity to
accept larger flow volumes per design (1-2" instead of 4-6") causing
flooding and ponding water.
Phase 2
Prior to Future
CAPITAL COST BREAKDOWN July 2019 2019-20 2020-21 2021-22 2022-23 2023-24 Years
Planning & Engineering $ - $ - $ - $ - $ 100,000 $ - $ -
Construction - - - - - 750,000 -
Contingency - - - - - - -
Total Project Costs $ - $ - $ - $ - $ 100,000 $ 750,000 $ -
Prior to Future
FUNDING SOURCE(S) July 2019 2019-20 2020-21 2021-22 2022-23 2023-24 Years
General Fund $ - $ - $ - $ - $ 100,000 $ 250,000 $ -
Grants - Future Application - NCDOT - - - - - 500,000 -
- - - - - - -
Total Funding Sources $ - $ - $ - $ - $ 100,000 $ 750,000 $ -
AM - 12
Strategic Plan Goal 2 - Safe Connected Community LEVEL A
TOWN OF WAKE FOREST
CAPITAL IMPROVEMENTS PROGRAM
CIP UPDATE FY 2019-2024
PROJECT DESCRIPTION
Rehabilitate upper dam with proper emergency spillway, reslope fill to 3:1, repave greenway trail with
spillway crossing. Future Flaherty Park Masterplan for additional park amenities, Dunn Creek Greenway trail Upper Pond
JUSTIFICATION
As identified in the Structural and Dam Inventory in 2014 preformed by Kimley-Horn and a Full Inspection
and Evaluation by Freese and Nichols in 2017, Flaherty Park Dam- Upper Pond and Lower Pond dams are in
need of minor repair due to tree growth and erosion on the downstream side of the existing spillway slopes. Lower Pond
The Upper Pond Dam evaluation identified wet areas with aquatic plants just south-east of the fill slope
indicating a minor seepage or leak. If left unchecked, the Upper Pond Dam slope could become unstable Upper Pond
creating a dam failure, potential loss of the pond/recreational fishing area, failure of the greenway
connection, and increased risk for citizen safety. The Upper Pond Dam reconstruction and repair would take
approximately 6-8 months to complete. The project would remove trees from the dam, install a sand filter
drain to alleviate soil pressure, flatten the downstream dam slope to a 4H:1V making it much safer, widen
the greenway trail connection to ten feet wide and eliminate the need for a fence. The existing 18" concrete
pipe located in the Upper Pond's southern corner would also be replaced with a 2' x 3' box culvert which
would decrease the risk of debris blockage and overtopping. The constuction is expected to take 6-8 months
to complete.
Prior to Future
CAPITAL COST BREAKDOWN July 2019 2019-20 2020-21 2021-22 2022-23 2023-24 Years
Planning & Engineering $ 131,300 $ - $ - $ - $ - $ - $ 60,000
Purchase - - - - - - -
Construction - - - - - - 653,500
Equipment - - - - - - 100,000
Contingency - 10% - - - - - - 65,400
Total Project Costs $ 131,300 $ - $ - $ - $ - $ - $ 878,900
Prior to Future
FUNDING SOURCE(S) July 2019 2019-20 2020-21 2021-22 2022-23 2023-24 Years
General Fund $ 131,300 $ - $ - $ - $ - $ - $ -
GO Bond - Future Referendum FY 2024 - - - - - - 778,900
Grants - Future Application - PARTF - - - - - - 100,000
Total Funding Sources $ 131,300 $ - $ - $ - $ - $ - $ 878,900
AM - 13
Strategic Plan Goal 2 - Safe Connected Community LEVEL B
PROJECT DESCRIPTION
Identify and repair existing Richland Creek Greenway due to stream bank erosion, tree fall and age.
JUSTIFICATION
Flooding, erosion and wet soil conditions have lead to the degredatation of the greenway trail. Stabilize
stream banks with restoration, remove tree root trip hazards, cracking pavement and overlay with 2" new Insert image
asphalt surface.
Prior to Future
CAPITAL COST BREAKDOWN July 2019 2019-20 2020-21 2021-22 2022-23 2023-24 Years
Planning & Engineering $ 30,000 $ - $ - $ - $ - $ - $ 150,000
Purchase - - - - - - -
Construction 86,900 - - - - - 75,000
Equipment - - - - - - -
Contingency - - - - - - -
Other - - - - - - -
Total Project Costs $ 116,900 $ - $ - $ - $ - $ - $ 225,000
Prior to Future
FUNDING SOURCE(S) July 2019 2019-20 2020-21 2021-22 2022-23 2023-24 Years
General Fund $ 100,000 $ - $ - $ - $ - $ - $ 75,000
GO Bonds -Future Referendum FY 2020 - - - - - - -
Grants - Awarded (FEMA) 16,900 - - - - - -
Grants - Future Application - - - - - - 150,000
Total Funding Sources $ 116,900 $ - $ - $ - $ - $ - $ 225,000
AM - 14
Strategic Goal 2 - Safe Connected Community LEVEL B
PROJECT DESCRIPTION
Maintenance of existing boardwalk per the strucutral inventory assessment recommendations
conducted in 2014. Recommend full replacement with a permatrak type system and full redesign
based on flooding and structural condition of existing system.
JUSTIFICATION
Continued maintenance of existing boardwalks due to location. These items were identified as Insert image
priority 1,2 and 3 based on need and severity and safety of parks and greenway users. Recommend
full replacement as opposed to minor repairs over the next five to ten years due to intracate
reconstruction annually and time greenway trail is closed. Future boardwalk should be replaced with
a Permatrak concrete deck as opposed to wood due to location within 5 years.
Prior to Future
CAPITAL COST BREAKDOWN July 2019 2019-20 2020-21 2021-22 2022-23 2023-24 Years
Planning & Engineering $ - $ - $ - $ - $ - $ - $ 375,000
Purchase - - - - - - -
Construction - - - - - - 1,500,000
Equipment - - - - - - -
Contingency - - - - - - -
Other- Public Art - - - - - - 18,800
Total Project Costs $ - $ - $ - $ - $ - $ - $ 1,893,800
Prior to Future
FUNDING SOURCE(S) July 2019 2019-20 2020-21 2021-22 2022-23 2023-24 Years
General Fund $ - $ - $ - $ - $ - $ - $ 393,800
GO Bonds-Future Referendum 2020 - - - - - - 1,400,000
PARTF (future application) - - - - - - 100,000
Total Funding Sources $ - $ - $ - $ - $ - $ - $ 1,893,800
AM - 15
Strategic Plan Goal 2 - Safe Connected Community LEVEL B
PROJECT DESCRIPTION
Improvement of Smith Creek Soccer Center with addition of restroom facilities, repave/revise layout of
parking lot, add greenway loop around fields on east side, add large trees, plantings and landscape
beds around perimeter, and upgrade playground facilities to meet ADA, use and volume. Incorporate
environmental education stations and hands on activities showcasing the stream restoration,
floodplain, greenways, and habitat.
Insert image
JUSTIFICATION
Smith Creek Soccer Center is heavily used for NCFC (CASL) soccer, greenways and general recreation.
The current site has two port-a-johns, three fields, and a leg of Smith Creek Greenway. Revisions to the
floodplain map will allow restrooms near the shelter. Addition of a full loop for users, ADA playground,
resurface/revise parking lot, add large trees for shade, shade sails, public art, and picnic tables and/or
shelters.
Prior to Future
CAPITAL COST BREAKDOWN July 2019 2019-20 2020-21 2021-22 2022-23 2023-24 Years
Planning & Engineering $ - $ - $ - $ - $ - $ - $ 190,000
Construction - - - - - - 1,050,000
Other - Public Art - - - - - - 12,400
Total Project Costs $ - $ - $ - $ - $ - $ - $ 1,252,400
Prior to Future
FUNDING SOURCE(S) July 2019 2019-20 2020-21 2021-22 2022-23 2023-24 Years
General Fund $ - $ - $ - $ - $ - $ - $ 552,400
NCFC - Future Contribution - - - - - - 200,000
Grants - PARTF - Future Application - - - - - - 500,000
AM - 16
LEVEL B
TOWN OF WAKE FOREST
CAPITAL IMPROVEMENTS PROGRAM
CIP UPDATE FY 2019-2024
PURPOSE
Replace AHU (Hybrid), Gas Water Heaters, Storage Tank, Condenser Unit, Hydroponic Heaters,
and Solar Panels FY2026-2027.
JUSTIFICATION
These units were installed in FY2010 and will be at the end of their life expectancy FY 2026. This Insert image
equipment work together to provide heat for the building as well as hot water and air condition.
The building is rented regularly and we need to avoid equipment failure and possible cancelled
rentals.
Prior to Future
CAPITAL COST BREAKDOWN July 2019 2019-20 2020-21 2021-22 2022-23 2023-24 Years
Purchase $ - $ - $ - $ - $ - $ - $ 100,000
Other - - - - - - -
Total Project Costs $ - $ - $ - $ - $ - $ - $ 100,000
Prior to Future
FUNDING SOURCE(S) July 2019 2019-20 2020-21 2021-22 2022-23 2023-24 Years
General Fund $ - $ - $ - $ - $ - $ - $ 100,000
- - - - - - -
Total Funding Sources $ - $ - $ - $ - $ - $ - $ 100,000
AM - 17
LEVEL B
TOWN OF WAKE FOREST
CAPITAL IMPROVEMENTS PROGRAM
CIP UPDATE FY 2019-2024
PURPOSE
1. Replace HVAC due to age and life expectancy FY 2027.
2. Roof Replacement Due to age FY 2032.
JUSTIFICATION
The Alston Massenburg Center was renovated in FY 2012. The building and components are Insert image
holding up well and the information included is based on expected life of the HVAC and Roof.
These items should be replaced at the end of life expectancy to prevent downtime due to
unexpected failures.
Prior to Future
CAPITAL COST BREAKDOWN July 2019 2019-20 2020-21 2021-22 2022-23 2023-24 Years
Purchase $ - $ - $ - $ - $ - $ - $ 90,000
Other - - - - - - -
Total Project Costs $ - $ - $ - $ - $ - $ - $ 90,000
Prior to Future
FUNDING SOURCE(S) July 2019 2019-20 2020-21 2021-22 2022-23 2023-24 Years
General Fund $ - $ - $ - $ - $ - $ - $ 90,000
- - - - - - -
Total Funding Sources $ - $ - $ - $ - $ - $ - $ 90,000
AM - 18
Strategic Plan Goal #2 - Enhance and Promote a Safe and Connected Community LEVEL B
PROJECT DESCRIPTION
Stream restoration and bank stabilization of Miller Park from Wait Ave/Taylor Street to Elm/Franklin Street. Replant
banks with riparian trees and shrubs. Rehab park trails, incorporate nature/sensory play into park (music, sounds,
touch tables, etc), repave trails to meet current 10 foot standards, and include natural playground that is ADA
accessible. Possible garden or planting space.
JUSTIFICATION
Structural inventory identified excessive scour at Bridge B in Miller Park in 2014. Unnamed Tributary to Spring
Branch within park continues to have high erosive velocities and is degrading causing stream instability and Insert image
potential bridge failure. Wake EMC is also concerned over loss of stream bank in excess of 10 feet laterally moving
towards new parking lot. In addition, stream is piped north of Wait Ave without any stormwater BMP treatment.
Project will add an attractive bioretention area to downtown to treat approximately 100 acres of drainage area. H.
L. Miller Park trail system is aging an in need of repairs. Project to rehab all trails within park and extend trail
connection to Taylor Street. Excellent pocket park for hands on education and sensory play due to location and
surrounding environmental features.
Prior to Future
CAPITAL COST BREAKDOWN July 2019 2019-20 2020-21 2021-22 2022-23 2023-24 Years
Planning & Engineering $ - $ - $ - $ - $ - $ - $ 59,000
Purchase - - - - - - 454,000
Construction - - - - - - 717,000
Equipment - - - - - - 1,500
Contingency - - - - - - -
Other- Public Art - - - - - - 1,300
Total Project Costs $ - $ - $ - $ - $ - $ - $ 1,232,800
Prior to Future
FUNDING SOURCE(S) July 2019 2019-20 2020-21 2021-22 2022-23 2023-24 Years
General Fund $ - $ - $ - $ - $ - $ - $ 307,800
Grants - Future Application - CWMTF,
NCDEQ WRD,NCDEQ 319, PARTF - - - - - - 925,000
Total Funding Sources $ - $ - $ - $ - $ - $ - $ 1,232,800
AM - 19
Capital Improvement Plan
VEHICLE/EQUIPMENT REPLACEMENT SUMMARY BY DEPARTMENT/DIVISION
TOTAL GENERAL FUND $ 2,109,500 $ 1,422,500 $ 1,380,500 $ 1,354,500 $ 1,070,000 $ 7,337,000 $ 4,504,800
TOTAL PROPRIETARY FUNDS $ 761,500 $ 361,500 $ 40,500 $ 471,500 $ 70,000 $ 1,705,000 $ 1,168,000
Finance Department
Replacement
Vehicles 2019-2024
Recommended Current
Year of Year of Age Useful Life Estimated cost Miles or
Asset # Acquisition replacement (Years) (Years) to replace Unit # Year Make Model Hours FY 19-20 FY 20-21 FY 21-22 FY 22-23 FY 23-24
D32277 2014 2024 5 10 $ 27,000 4301 2014 Escape SUV 13,180 - - - - 27,000
$ 27,000 - - - - 27,000
Human Resources
Replacement Vehicles
2019-2024
Replacement Current Estimated
Year of Year Age Useful Life Cost to Mileage or
Asset # Acquisition per Policy (Years) (Years) Replace Unit # Year Make Model Hours FY 19-20 FY 20-21 FY 21-22 FY 22-23 FY 23-24
A44095 2008 2018 11 10 $ 38,500 4811 2008 FORD EXPEDITION 54,261 - 38,500 - - -
E42974 2010 2020 9 10 39,500 4801 2010 FORD EXPEDITION 32,924 - - 39,500 - -
C15854 2011 2021 8 10 41,000 4803 2011 FORD F150 CLUB CAB 4X4 51,263 - - - 41,000 -
2013 2023 6 10 41,000 4805 2013 FORD F-150 EXT CAB P/U 36,038 - - - - 41,000
C76067
Inspections
Replacement
Vehicles 2019-2024
Estimated
Year of Replacement Year Current Age Useful Life Cost to Vehicle Mileage or
Asset # Acquisition per Policy (Years) (Years) Replace # Year Make Model Item Description Hours FY 19-20 FY 20-21 FY 21-22 FY 22-23 FY 23-24
JOHN
- - - -
620254 2005 2013 14 8 $ 42,500 6212 2005 DEERE 4500 Tractor 1,755 42,500
10 - - - -
D47459 2006 2016 13 38,500 6201 2006 FORD F250 4X4 EXT CAB Truck 101,577 38,500
- - - -
N/A 2009 2013 10 5 13,500 6223 2009 TORO WALK BEHIND MOWER 48" Mower 36 13,500
- - - -
110067 2013 2018 6 5 13,500 6228 2013 HUSTLER Super Z Mower Lawnmower 1,539 13,500
- - - -
2650 2014 2019 5 5 13,500 6231 2014 HUSTLER Super Z Mower Lawnmower 1,247 13,500
- - - -
2567 2012 2017 7 5 13,500 6202 2012 HUSTLER X-ONE Lawnmower 831 13,500
- - - -
2732 2015 2020 4 5 14,000 6234 2015 HUSTLER Super Z Mower Lawnmower 1,319 14,000
- - - -
2731 2015 2020 4 5 35,000 6235 2015 HUSTLER Super Z Mower Lawnmower 1,474 35,000
- - - -
2733 2015 2020 4 5 14,000 6236 2015 HUSTLER Super Z Mower Lawnmower 1,158 14,000
- - - -
15601 2013 2021 6 8 13,500 6227 2013 John Deere XUV550 S4 ATV ATV 1,328 13,500
- - -
51799 2017 2022 2 5 65,000 6242 2017 John Deere Z960M Zero Turn Mower 531 65,000 -
10 - -
B85533 2012 2017 14 64,500 6226 2012 FORD F350 CREW CAB 4X4 XL Truck 54,534 - 64,500 -
Police
Replacement Vehicles
2019 - 2024
Replacement Estimated
Year of Year per Current Age Useful Life Replacement Department Mileage or
Vehicle Status Asset # Acquisition Policy (Years) (Years) Cost Requested Unit # Year Make Model Hours FY 19-20 FY 20-21 FY 21-22 FY 22-23 FY 23-24
Patrol 225175 2017 2022 2 5 45,000 2023 251 2017 CHEVROLET TAHOE 19,778 - - - 45,000 -
Patrol 226257 2017 2022 2 5 45,000 2023 252 2017 CHEVROLET TAHOE 24,773 - - - 45,000 -
Patrol 227648 2017 2022 2 5 46,000 2024 253 2017 CHEVROLET TAHOE 16,380 - - - - 46,000
Patrol 538512 2017 2022 2 5 45,000 2023 254 2017 DODGE CHARGER 22,864 - - - 45,000 -
Patrol 538149 2017 2022 2 5 42,000 2024 255 2017 DODGE CHARGER 19,102 - - - - 42,000
Patrol 538148 2017 2022 2 5 45,000 2022 256 2017 DODGE CHARGER 31,481 - - 45,000 - -
Patrol 538147 2017 2022 2 5 42,000 2024 258 2017 DODGE CHARGER 25,630 - - - - 42,000
Patrol 538150 2017 2022 2 5 45,000 2023 259 2017 DODGE CHARGER 29,754 - - - 45,000 -
Spare 258048 2008 2018 11 10 38,000 2020 168 2008 CHEVROLET Impala 63,986 38,000 - - - -
Spare 247900 2012 2017 7 5 39,000 2021 105 2012 DODGE Charger 59,226 - 39,000 - - -
Spare 247899 2012 2017 7 5 39,000 2021 133 2012 DODGE Charger 55,655 - 39,000 - - -
Spare 247903 2012 2017 7 5 39,000 2021 139 2012 DODGE Charger 58,875 - 39,000 - - -
Spare 247901 2012 2017 7 5 39,000 2021 146 2012 DODGE Charger 50,617 - 39,000 - - -
Spare 275816 2013 2023 6 10 43,000 2021 208 2013 CHEVROLET Tahoe 53,705 - 43,000 - - -
Truck 260756 2014 2024 5 10 45,000 2022 225 2014 DODGE RAM 2500 TK 34,292 - - 45,000 - -
Patrol Motorcycle 192650 2015 2025 4 10 45,000 2023 135 2015 BMW MOTORCYCLE 11,163 - - - 45,000 -
Investigations 114460 2016 2021 3 5 42,000 2024 149 2016 FORD Taurus Interceptor 16,592 - - - - 42,000
Patrol Motorcycle W23242 2017 2027 5 10 45,000 2024 260 2014 BMW MOTORCYCLE 10,056 - - - - 45,000
Patrol 610626 2017 2022 2 5 42,000 2024 262 2017 DODGE CHARGER 10,383 - - - - 42,000
Spare 629438 2012 N/A 7 6 38,000 2018 201 2013 DODGE Charger 61,126 38,000 - - - -
Spare 629439 2013 N/A 6 6 38,000 2019 202 2013 DODGE Charger 60,119 38,000 - - - -
Training 134153 2009 N/A 10 10 45,000 2018 131 2009 FORD Crown Victoria 61,911 - - - 45,000 -
Training 145483 2006 N/A 13 10 45,000 2018 156 2006 FORD Crown Victoria 57,070 - - - 45,000 -
Training 261192 2008 N/A 11 10 45,000 2018 170 2008 CHEVROLET Impala 57,433 - - - 45,000 -
Training 550705 2011 N/A 8 10 45,000 2019 192 2011 DODGE Charger 53,413 - - - 45,000 -
Police
Replacement Vehicles
2019 - 2024
Replacement Year Current Age Useful Life Estimated Cost Unit Mileage or
Asset # Year of Acquisition per Policy (Years) (Years) to Replace # Year Make Model Hours FY 19-20 FY 20-21 FY 21-22 FY 22-23 FY 23-24
C11758 2009 2019 10 10 $ 30,000 5402 2009 Ford Escape XLT 4WD 43,127 30,000 - - - -
F40366 2012 2022 7 10 36,500 5406 2012 Ford Expedition XL 52,406 - - - 36,500 -
Engineering
Replacement Vehicles
2019-2024
Asset # Year of Replacement Year Current Age Useful Life Estimated cost Unit # Year Make Model Mileage or
acquisition per Policy (Years) (Years) of replacement Hours FY 19-20 FY 20-21 FY 21-22 FY 22-23 FY 23-24
A02030 2007 2017 12 10 $ 38,000 5501 2007 FORD F350 4X4 XL SUPER DUTY 46,253 38,000 - - - -
C63642 2011 2021 8 10 55,000 5505 2011 FORD F350 4X4 SUPER DUTY 16,965 - 55,000 - - -
$93,000 38,000 55,000 - - -
Fleet Maintenance
Replacement Vehicles
2019-2024
Replacement Estimated
Year of Year Current Age Useful Life Cost of Mileage or
Asset # Acquisition per Policy (Years) (Years) Replacement Unit # Year Make Model Item Description Hours FY 19-20 FY 20-21 FY 21-22 FY 22-23 FY 23-24
2342 2004 2012 15 7 $ 21,500 5637 2004 LAY-MOR SWEEPER TRACTOR 827 21,500 - - - -
404106 2007 2017 12 10 175,000 5613 2007 INTERNATIONAL 4200 SBA 4X2 DUMP TRUCK 6,641 175,000 - - - -
A43484 2008 2018 11 10 60,000 5609 2008 FORD F350 4X4 CREW CAB TRUCK 55,661 60,000 - - - -
2340 2008 2018 11 10 125,000 5610 2008 JCB 3C BACKHOE 4,909 125,000 - - - -
C31011 2008 2018 11 10 60,000 5615 2008 FORD F350 4X4 CREW CAB TRUCK 63,115 60,000 - - - -
A19112 2008 2018 11 10 60,000 5632 2008 FORD F350 4X4 CREW CAB TRUCK 70,969 60,000 - - - -
14059 2014 2019 5 5 13,500 5649 2014 John Deere Z930M LAWN MOWER 1,499 13,500 - - - -
14060 2014 2019 5 5 13,500 5612 2014 John Deere Z930M LAWN MOWER 936 13,500 - - - -
2051 2005 2013 14 8 101,500 5627 2005 JOHN DEERE 6420 TRACTOR TRACTOR 996 - 101,500 - - -
B22038 2009 2019 10 10 60,000 5638 2009 FORD F250 4X4 EXT CAB TRUCK 65,739 60,000 - - -
STREET
FA2115 2012 2019 7 7 215,000 5646 2013 FREIGHTLINER STREET SWEEPER SWEEPER 3,034 215,000 - - -
PAVEMENT
2467 2010 2020 9 10 72,000 5605 2010 HAMM HAMM HD 13 VV ROLLER 595 - 72,000 - - -
2429 2010 2020 9 10 192,000 5622 2010 LINKBELT LINKBELT EXCAVATOR EXCAVATOR 1,520 - 192,000 - -
Sewer jet &
394144 2006 2021 13 15 98,000 5617 2006 PIPEHUNTER 7834G SEWER JET Trailer are one 589 - - 98,000 - -
Sewer Vacuum &
394143 2006 2021 13 15 88,500 5620 2006 PIPEHUNTER Sewer vacuum Trailer are one 499 - - 88,500 - -
3085 2016 2021 3 5 13,500 5660 2016 Hustler X-One LAWN MOWER 546 - - 13,500 - -
2339 2008 2018 11 10 182,500 5619 2008 CHAMPION C86C MOTOR GRADER 1,094 - - - 182,500 -
A08604 2012 2022 7 10 60,000 5641 2012 FORD F350 4X4 CREW CAB TRUCK 32,775 - - - 60,000 -
2541 2012 2022 7 10 80,000 5642 2012 HYUNDAI ROBEX60CR-9 EXCAVATOR EXCAVATOR 2,440 - - - 80,000 -
C33244 2012 2022 7 10 60,000 5645 2012 FORD F350 CREW CAB 4X4 XL TRUCK 33,218 - - - 60,000 -
2341 2008 2016 11 8 9,500 5636 N/A ANDERS TACK SPRAYER Tack Sprayer 546 - - - - 9,500
GR7124 2016 2023 3 7 255,000 5661 2016 FREIGHTLINER JOHNSTON 655 MKII SWEEPER 797 - - - - 255,000
N/A 2018 2023 1 5 11,500 5670 2018 Hustler X-One 52" Mower Zero Turn Mower 9 - - - - 11,500
Streets
Replacement Vehicles
2019-2024
Replacement Estimated
Year of Year Current Age Useful Life Cost to Mileage or
Asset # acquisition per Policy (Years) (Years) Replace Unit # Year Make Model Item Description Hours FY 19-20 FY 20-21 FY 21-22 FY 22-23 FY 23-24
$ 171,000 2013 FREIGHTLINER M2106 Leaf Truck 5,268 171,000 - - - -
FB6894 2013 2020 6 7 5805
190,000 199,000
FG4363 2013 2020 6 7 5813 2013 FREIGHTLINER 108SD GARBAGE TRUCK 6,274 - - -
130,000
AU6827 2010 2018 9 8 130,000 5810 2010 FREIGHTLINER M2 KNUCKLEBOOM 5,435 - - -
Leaf Vacuum - Tow
168221 2013 2020 6 7 42,000 5801 2013 ODB SCL800 TM25 73 - 42,000 - - -
Behind
Leaf Vacuum - Tow
168222 2013 2020 6 7 42,000 5812 2013 ODB SCL800 TM25 122 - 42,000 - - -
Behind
GH3874 2014 2022 5 8 138,000 5814 2015 FREIGHTLINER M2106 KNUCKLEBOOM 3,997 - - 138,000 - -
Environmental Services
Replacement Vehicles
2019-2024
Replacement Estimated
Year of Year Current Age Useful Life Cost to Mileage or
Asset # Acquisition per Policy (Years) (Years) Replace Unit # Year Make Model Plate # Hours FY 19-20 FY 20-21 FY 21-22 FY 22-23 FY 23-24
A63336 2009 2019 10 10 $ 40,000 5001 2009 FORD E150 CARGO VAN 78514T 53,668 40,000 - - -
$ 40,000 40,000 - - - -
Public Facilities
Replacement Vehicles
2019-2024
Replacement
Year of Year Current Age Useful Life Estimated Cost of Mileage or
Asset # Acquisition per Policy (Years) (Years) Replacement Unit # Year Make Model Item Description Hours FY 19-20 FY 20-21 FY 21-22 FY 22-23 FY 23-24
2057 2006 2014 13 8 23,000 8546 2006 BOBCAT 2200D ATV 4X4 ATV 378 - 23,000 - - -
428141 2007 2017 12 10 158,000 8537 2007 INTERNATIONAL 4200 SBA 4X2 DUMP BED 1,075 158,000 - - -
436364 2007 2017 12 10 204,000 8543 2007 INTERNATIONAL 4300 SBA 4X2 BUCKET TRUCK 3,445 204,000 - - - -
436362 2007 2017 12 10 204,000 8549 2007 INTERNATIONAL 4300 SBA 4X2 BUCKET TRUCK 3,861 204,000 - - - -
2308 2008 2018 11 10 125,000 8522 2008 YANMAR Vi075-A EXCAVATOR 1,909 125,000 - - - -
083478 2009 2019 10 10 190,500 8531 2009 INTERNATIONAL 4200 BUCKET TRUCK 8,289 190,500 - - - -
2481 2010 2020 9 10 47,500 8561 2010 WACKER NEUSON RTSC2 TRENCH ROLLER 45 - 47,500 - - -
2482 2010 2020 9 10 47,500 8562 2010 WACKER NEUSON RTSC2 TRENCH ROLLER 62 - 47,500 - - -
A25617 2011 2021 8 10 40,500 8523 2011 FORD E250 CARGO VAN VAN 49,848 - - 40,500 - -
2012 2022 7 10 93,500 8512 2012 TAKEUCHI TL240CR SKID STEER 627 - - - 93,500 -
2552
2012 2022 76,500 8514 2012 FORD F550 4X4 CREW CAB TRUCK 41,795 76,500
7 10 - - - -
B85573 TOOL BO
2012 2022 76,500 8529 2012 FORD F550 4X4 CREW CAB TRUCK 46,220 76,500
7 10 - - - -
B85572 TOOL BO
2004 2014 15 10 38,000 8570 2004 Ford F350 Crew Cab Pickup Truck 67,731 38,000 - - - -
C78568
Electric - Operations
Replacement Vehicles
2019-2024
Estimated
Year of Replacement Year Current Age Useful Life Cost to Mileage
Asset # Acqusition per Policy (Years) (Years) Replace Unit # Year Make Model Item Description or Hours FY 19-20 FY 20-21 FY 21-22 FY 22-23 FY 23-24
2551 2012 2020 7 8 $ 85,500 8607 2012 VERMEER BC1800XL CHIPPER 2,516 - 85,500 - - -
2730 2015 2023 4 8 70,000 8609 2015 BANDIT 2650T STUMP GRINDER 249 - - - - 70,000
Tree Trimming
Replacement Vehicles
2019-2024