East Halmahera Ferronickel Development Project (P3Fh Project)
East Halmahera Ferronickel Development Project (P3Fh Project)
LV Panel 1006LVP01
Status Status During Energize
No. Feeder
Pre-Condition Step 1 Step 2A Step 2B Step 2C
1 Incoming from 1006TRF01 Open Close Close Close Close
2 Outgoing to 1702LCP01-04 Open Open Open Open Open
3 Outgoing to 1006MCC01 Open Open Close Close Open
4 Outgoing to 1006MCC02 Open Open Open Open Close
5 Spare Open Open Open Open Open
6 Outgoing to LDP13 Open Open Open Open Open
7 Outgoing to 1007MCC01 Open Open Open Open Open
Note :
1 Before Energize panel, Busbar must be finished Insulation Test
2 Before Energize panel, Incoming Breaker Setting must be checked first
3 Before Energize panel, Transformer signal for Trip/Alarm must be checked
4 All Feeder that not energized must be racked out
5 a. Blue highlight is general sequence
b. Brown highlight is sequence for Energize 1006UPS01
c. Yellow highlight is sequence for Energize 4001UPS01
d. Green highlight is sequence for Energize 1006UPS02
OF ENERGIZING LSS-13